Академический Документы
Профессиональный Документы
Культура Документы
CAPM & PMBOK are registered trademarks of the Project Management Institute, Inc.
Objectives
After completing this
lesson, you will be able
to:
!
4
The iteration of processes within the phases is dependent on the scale of the projects. Small projects may
have only one iteration, while bigger projects may have multiple iterations before they enter a new phase.
Copyright 2014, Simplilearn, All rights reserved.
Exam Tips
6
Study the table to identify processes under project management and the knowledge area they
belong to.
Copyright 2014, Simplilearn, All rights reserved.
Initiating Process
Group
Planning Process
Group
Executing
Process Group
Monitoring and
Controlling
Process Group
Closing Process
Group
Inputs
Actions taken
The inputs and activities of initiating process group are important from the exam perspective.
Exam Tips
8
Inputs
Project charter
Requirements
Stakeholder register
Organizational process assets
Enterprise environmental factors
Resource calendars
Work performance information
Actions taken
Inputs
10
Actions taken
Inputs
Deliverables
Work performance data
Change requests
Organizational process assets
Project management plan and documents
Selected sellers
Actions taken
11
12
Actions taken
Quiz
13
QUIZ
1
A project manager is validating the scope. Which process group is the project manager working in?
a.
Planning
14
c.
Initiating
d.
Closing
QUIZ
1
A project manager is validating the scope. Which process group is the project manager working in?
a.
Planning
Initiating
d.
Closing
Answer: b.
Explanation: Monitoring and Controlling (see PMBOK Guide section 3.6). During project closure the
project manager reviews the acceptance documentation from scope validation to ensure that all project
requirements are completed.
15
QUIZ
2
a.
Project charter
16
c.
d.
Procurement documents
QUIZ
2
a.
Project charter
d.
Procurement documents
Answer: a.
Explanation: All other options are inputs to the initiating process group.
17
QUIZ
3
a.
Project manager
b. Functional manager
18
c.
Team members
d.
Stakeholders
QUIZ
3
a.
Project manager
b. Functional manager
c.
Team members
d.
Stakeholders
Answer: a.
Explanation: The project manager is in control of the project throughout the project life cycle.
19
QUIZ
4
The high level project schedule constraints have just been determined. Which process group is the
project in?
a.
Planning
b. Closing
20
c.
d.
Initiating
QUIZ
4
The high level project schedule constraints have just been determined. Which process group is the
project in?
a.
Planning
b. Closing
c.
d.
Initiating
Answer: d.
Explanation: The high level constraints of schedule and budget are determined during the initiating
process group. The detailed planning is done during the planning process group.
21
QUIZ
5
a.
22
b.
Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the
project draws to a close
Stakeholder influences are greatest towards the end of the project
c.
d.
QUIZ
5
a.
b.
Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the
project draws to a close
Stakeholder influences are greatest towards the end of the project
c.
d.
Answer: b.
Explanation: Stakeholder influences are greatest towards the beginning of the project.
23
QUIZ
6
a.
24
c.
d.
QUIZ
6
a.
d.
Answer: a.
Explanation: In every project, all five process groups must be included but the level of attention given to
each process group will be governed by the project manager depending on the project size and complexity.
25
Summary
Here is a quick recap of
what was covered in
this lesson:
26
Project life cycle addresses the question, What to do to get the work done? while
Project management process addresses the question, What to do to manage the
project?
There are 47 processes in project management grouped into ten knowledge areas, and
mapped to five Process Groups
Initiating Process Group defines a new project or phase. When the project charter is
approved, the project is officially authorized
Planning Process Group establishes the total scope of effort, objectives, and course of
action required to attain those objectives
Executing Process Group completes the work defined in the project management plan to
satisfy the project specifications
Monitoring and Controlling Process Group tracks, reviews, and regulates the progress
and performance of the project; identifies and initiates the changes to the plan when
required
Closing Process Group finalizes the activities across all Process Groups to formally
complete the project, phase, or contractual obligations
Thank You
CAPM & PMBOK are registered trademarks of the Project Management Institute, Inc.
27
Reference
[1] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 50.
[2] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 51.
28