Вы находитесь на странице: 1из 20

REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


PROJECT MANAGEMENT OFFICE - BUREAU OF DESIGN
MANILA, PHILIPPINES

VARIOUS DPWH PROPOSED PROJECTS


(DETAILED ENGINEERING DESIGN AND/OR SPECIAL STUDIES)
STANDARD THREE-STOREY
SCHOOL BUILDING
(3 & 6 - CLASSROOMS)

REVIEWED:

RECOMMENDING APPROVAL:

APPROVED :

CONCURRED :

MARIANO C. DEL CASTILLO

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

ARMIN A. LUISTRO

OIC, BUILDINGS DIVISION, BOD

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

SECRETARY
DEPARTMENT OF EDUCATION

GENERAL

BILL OF QUANTITIES
SIX-CLASSROOMS

A.
I.

Mobilization / Demobilization

II.

Temporary Facilities

III.

Safety and Health

IV.

VII.

Masonry Works

VIII.

Fabricated Materials and Hardwares

Earthworks

V.

Termite Control Works

VI.

Concrete Works

QUANTITY ENGINEER

JOVEN T. SANTOS

DOMICIANO B. LUSICA

COST ENGINEER

PROJECT MANAGER

OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

BOD
BILL OF QUANTITIES

G-1

1
36

BILL OF QUANTITIES
XIV.

Plumbing / Sanitary Works

IX. Finishing Works

X. Carpentry Works

XI. Roof and Framing Works

XII. Painting Works

XIII. Electrical Works

QUANTITY ENGINEER

JOVEN T. SANTOS

DOMICIANO B. LUSICA

COST ENGINEER

PROJECT MANAGER

OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

BOD
BILL OF QUANTITIES

G-2

2
36

ARCHITECTURAL

TABLE OF CONTENTS
GENERAL
G-1
G-2
G-3
G-4

BILL OF QUANTITIES
BILL OF QUANTITIES
BILL OF QUANTITIES
BILL OF QUANTITIES

STRUCTURAL

ARCHITECTURAL
A-1

S-1

A-2

KEY PLAN

S-2

GENERAL NOTES

A-3

GROUND FLOOR PLAN, SECOND FLOOR & THIRD FLOOR PLAN,


FRONT ELEVATION, SCHEDULE OF FINISH

S-3

FOUNDATION PLAN, 2nd & 3rd FLOOR FRAMING PLAN

S-4
A-4

REAR ELEVATION, LEFT & RIGHT ELEVATION,


LONGITUDINAL SECTION & CROSS SECTION

COLUMN SCHEDULE, SCHEDULE OF FOOTING,


SCHEDULE FOOTING BEAMS, TYPICAL FOOTING
DETAIL, ELEVATION OF COLUMN & DETAIL OF WALL
FOOTINGS

A-5

GROUND FLOOR, SECOND FLOOR & THIRD FLOOR REFLECTED


CEILING PLAN, ROOF PLAN

A-6

SCHEDULE OF DOORS & WINDOWS, DETAIL PLAN,


ELEVATIONS & SECTION OF RAMP, SPOT DETAILS

A-7

SECTION DETAIL OF EAVES, SPOT DETAIL CORNER CEILING,


CONCRETE SUN BREAKER DETAIL, PERSPECTIVE, SECTION &
SPOT DETAIL OF CEILING, PLAN & SECTION OF VENTILATION

A-8

STAIR DETAILS

A-9

BAY SECTIONS, DOOR FRAME TYPICAL PLAN &


SECTION, JALOUSIE DETAILS & FIRE ESCAPE DETAILS

A - 10

DETAIL PLAN OF TOILET & SECTION,


DETAIL OF COUNTER SINK, URINAL SECTION & DETAIL

A - 11

S-5

GENERAL NOTES

PLAN FOOTING F-3, ELEVATION FOOTING F-3,


PLAN FOOTING CF-1 & TYPICAL ELEVATION OF
MICRO-PILE

S-6

SCHEDULE MAIN BEAMS, SCHEDULE OF SECONDARY


BEAMS, SCHEDULE OF SLABS, TYPICAL SLAB
ELEVATION, TYPICAL BEAM ELEVATION &
TYPE OF STIRRUPS

S-7

DETAIL OF STAIR, RAMP DETAIL,


DETAIL OF DC-1, DETAIL OF STAIR ON GRADE &
DETAIL OF WALL ON FTB

S-8

ROOF FRAMING PLAN

S-9

ELEVATION OF END WALL FRAME,


DETAIL SECTION OF PC-1,
CONNECTION OF PURLINS TO RG-4,
CONCRETE SUN BREAKER DETAIL

DETAILS OF BLACKBOARD

S - 10
S - 11

ELECTRICAL

PLUMBING

PERSPECTIVE, TABLE OF CONTENTS

P-1

GROUND FLOOR, TYPICAL SECOND & THIRD


FLOOR PLUMBING LAYOUT,
GROUND FLOOR, TYPICAL SECOND & THIRD
FLOOR WATER LINE LAYOUT

EE - 1

P-2

ISOMETRIC DRAINAGE LINE LAYOUT,


ROOF DRAINAGE LAYOUT,
DETAIL SECTION OF DRAIN PIPE
AND SPOT DETAIL

EE - 2

POWER LAYOUT AND LIGHTING LAYOUT ( 3-CL )

EE - 1

GENERAL NOTES, LEGEND FLUORESCENT LIGHT


FIXTURE MOUNTING DETAIL, LOAD SCHEDULE,
PANEL BOARD DIAGRAM AND ELECTRICAL
RISER DIAGRAM ( 6-CL )

EE - 2

POWER LAYOUT AND LIGHTING LAYOUT ( 6-CL )

P-3

ISOMETRIC WATER LINE LAYOUT


AND SEWER LINE LAYOUT

P-4

PLAN OF SEPTIC TANK, LONGITUDINAL


SECTION, CROSS SECTION DETAIL,
MANHOLE COVER DETAIL, CATCH BASIN
DETAIL, LEGEND AND PLUMBING NOTES

GENERAL NOTES, LEGEND,


FLUORESCENT LIGHT FIXTURE MOUNTING
DETAIL, LOAD SCHEDULE, PANEL BOARD
DIAGRAM AND ELECTRICAL RISER DIAGRAM ( 3-CL )

TRUSS DETAILS & CONNECTION DETAILS


BASE PLATE DETAILS, ANCHOR BOLT DETAIL, ROOF
PANEL SIDE LAP DETAIL, J-BOLT TO PURLIN CONN.
DETAIL, J-BOLT SPACING, PURLIN CONN. DETAIL,
SECTION, TRUSS DETAIL AT GUTTER END

S - 12

FIRE ESCAPE ELEVATION

S - 13

FIRE ESCAPE DETAILS

NOTE :
OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

BOD
TABLE OF CONTENTS

A-1

5
36

( 3-CLASSROOMS )

THIRD FLOOR PLAN

( 3-CLASSROOMS )

( 3-CLASSROOMS )

GROUND FLOOR PLAN

K E Y

SECOND FLOOR PLAN

P L A N

NOTE :
OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 3-CLASSROOMS )

BOD
KEY PLAN

A-2

6
36

SECOND FLOOR PLAN

FRONT ELEVATION

GROUND FLOOR PLAN

SCHEDULE OF FINISH

THIRD FLOOR PLAN

NOTE :
OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

GROUND FLOOR PLAN,


SECOND FLOOR & THIRD FLOOR PLAN,
FRONT ELEVATION,
SCHEDULE OF FINISH

BOD

A-3

7
36

RIGHT SIDE ELEVATION

LEFT SIDE ELEVATION

CROSS SECTION

REAR ELEVATION

LONGITUDINAL SECTION

NOTE :
OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

REAR ELEVATION, LEFT & RIGHT


ELEVATION, LONGITUDINAL SECTION
& CROSS SECTION

BOD

A-4

8
36

SECOND FLOOR REFLECTED CEILING PLAN

ROOF PLAN

GROUND FLOOR REFLECTED CEILING PLAN

THIRD FLOOR REFLECTED CEILING PLAN

NOTE :
OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

GROUND FLOOR, SECOND FLOOR &


THIRD FLOOR REFLECTED CEILING
PLAN, ROOF PLAN

BOD

A-5

9
36

DETAIL ELEVATION OF RAMP

SPOT DETAIL
DETAIL SECTION OF RAMP
SPOT DETAIL

DETAIL SECTION

SCHEDULE OF DOORS AND WINDOWS

DETAIL PLAN OF RAMP

NOTE :
OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

SCHEDULE OF DOORS & WINDOWS,


DETAIL PLAN, DETAIL PLAN, ELEVATION
& SECTION OF RAMP, SPOT DETAILS

BOD

A-6

10
36

SECTION ( CEILING )

SECTION DETAIL (VENT.)

SPOT DETAIL
PERSPECTIVE ( CEILING )

SECTION DETAIL (EAVES)

CONCRETE
SUNBREAKER DETAIL

SPOT DETAIL (EAVES)

NOTE :
OIC, BUILDINGS DIVISION

DETAIL PLAN (VENT.)

SPOT DETAIL (CORNER CLG.)

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

SECTION DETAIL OF EAVES,


SPOT DETAIL CORNER CEILING,
CONCRETE SUNBREAKER DETAIL,
PERSPECTIVE, SECTION &
SPOT DETAIL OF CEILING,
PLAN & SECTION OF VENTILATION

BOD

A-7

11
36

CRASH RAILING
ELEVATION

DETAIL

BALCONY RAILING DETAIL

NOSING DETAIL

SPOT DETAIL
DETAIL SECTION OF STAIR

SPOT DETAIL

HANDRAIL DETAIL

(AT GROUND FLOOR )

(AT SECOND FLOOR)

(AT THIRD FLOOR)

DETAIL PLAN OF STAIR

DETAIL PLAN OF STAIR

DETAIL PLAN OF STAIR

NOTE :
OIC, BUILDINGS DIVISION

SECTION DETAIL

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

BOD
STAIR DETAIL

A-8

12
36

CLASSROOM

CORRIDOR

CORRIDOR
CLASSROOM

DOOR FRAME TYPICAL


PLAN & SECTION DETAIL

CORRIDOR

BAY SECTION

(ALONG TOILETS)
CLASSROOM

FIRE ESCAPE ELEVATION

GLASS JALOUSIE TYPICAL


DETAIL PLANS

CLASSROOM

BAY SECTION

(ALONG CORRIDORS)

2nd
FLOOR PLAN

GROUND
FLOOR PLAN

CORRIDOR

GLASS JALOUSIE TYPICAL


DETAIL SECTIONS

NOTE :
OIC, BUILDINGS DIVISION

3rd
FLOOR PLAN

FIRE ESCAPE PLAN

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

BAY SECTIONS, DOOR FRAME


TYPICAL PLAN & SECTION,
JALOUSIE DETAILS & FIRE
ESCAPE DETAILS

BOD

A-9

13
36

URINAL TROUGH
SECTION & DETAIL

DETAIL SECTION

DETAIL SECTION

DETAIL OF COUNTER SINK

DETAIL SECTION OF TOILET


( GROUND FLOOR )

( TYPICAL SECOND FLOOR & THIRD FLOOR )

DETAIL PLAN OF TOILET

DETAIL PLAN OF TOILET

NOTE :
OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

DETAIL PLAN OF TOILET & SECTION,


DETAIL OF COUNTER SINK,
URINAL SECTION & DETAIL

BOD

A-10

14
36

SECTION
CHALK DUST BOX DETAIL

SPOT DETAIL SECTION


EDGE FRAMING

BLACKBOARD DETAIL

CONNECTION SECTION DETAIL

NOTE :
OIC, BUILDINGS DIVISION

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

BLACKBOARD DETAIL,
CONNECTION SECTION DETAIL,SECTION,
SPOT DETAIL SECTION EDGE FRAMING,
CHALK DUST BOX DETAIL

BOD

A-11

15
36

STRUCTURAL

STRUCTURAL DESIGN
POSITION: STRUCTURAL ENGINEER
PRC No.: 32516
TIN No.: 107-915-002
PTR No.: 7653512

NELSON S. ANTONIO

DOMICIANO B. LUSICA

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

STRUCTURAL DESIGN
POSITION: STRUCTURAL ENGINEER
PRC No.: 14234
TIN No.: 178-384-258
PTR No.: 8108050

PROJECT MANAGER

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

OIC, BUILDINGS DIVISION

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

BOD
GENERAL NOTES

S-1

16
36

STRUCTURAL DESIGN
POSITION: STRUCTURAL ENGINEER
PRC No.: 32516
TIN No.: 107-915-002
PTR No.: 7653512

NELSON S. ANTONIO

DOMICIANO B. LUSICA

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

STRUCTURAL DESIGN
POSITION: STRUCTURAL ENGINEER
PRC No.: 14234
TIN No.: 178-384-258
PTR No.: 8108050

PROJECT MANAGER

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

OIC, BUILDINGS DIVISION

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

BOD
GENERAL NOTES

S-2

17
36

2nd FLOOR FRAMING PLAN

3rd FLOOR FRAMING PLAN

FOUNDATION PLAN

STRUCTURAL DESIGN
POSITION: STRUCTURAL ENGINEER
PRC No.: 32516
TIN No.: 107-915-002
PTR No.: 7653512

NELSON S. ANTONIO

DOMICIANO B. LUSICA

(SEE COVER SHEET)

(SEE COVER SHEET)

(SEE COVER SHEET)

STRUCTURAL DESIGN
POSITION: STRUCTURAL ENGINEER
PRC No.: 14234
TIN No.: 178-384-258
PTR No.: 8108050

PROJECT MANAGER

GILBERTO S. REYES

RAUL C. ASIS

ROGELIO L. SINGSON

DIRECTOR IV, BOD

UNDERSECRETARY

SECRETARY

OIC, BUILDINGS DIVISION

VARIOUS DPWH
PROPOSED PROJECTS

STANDARD THREE-STOREY
SCHOOL BUILDING
( 6-CLASSROOMS )

FOUNDATION PLAN, 2nd & 3rd FLOOR


FRAMING PLAN

BOD

S-3

18
36

Вам также может понравиться