S.No
Name (Abbreviation)
Formula
No.ofCommunicationChannels
n (n-1)/2
SchedulePerformanceIndex(SPI)
SPI = EV/PV
<1behindschedule,=1onschedule,>
1aheadofschedule
CostPerformanceIndex(CPI)
CPI = EV/AC
<1Overbudget,=1Onbudget,>1
Underbudget
ScheduleVariance(SV)
SV = EV PV
<0Behindschedule,=0Onschedule,>
0Aheadofschedule
CostVariance(CV)
CV = EV AC
<0Overbudget,=0Onbudget,>0
Withinbudget
EstimateatCompletion(EAC)if
originalisflawed
EAC = AC + New
ETC
iftheoriginalestimateisbasedonwrong
data/assumptionsorcircumstanceshave
changed
EstimateatCompletion(EAC)if
BACremainsthesame
EAC=AC + BAC
EV
thevarianceiscausedbyaonetimeevent
andisnotlikelytohappenagain
AC=ActualCost,BAC=Budgetatcompletion,EV=EarnedValue
EstimateatCompletion(EAC)if
CPIremainsthesame
EAC= BAC/CPI
iftheCPIwouldremainthesametillendof
project,i.e.theoriginalestimationisnot
accurate
BAC=Budgetatcompletion,CPI=Costperformanceindex
EstimateatCompletion(EAC)if
substandardperformance
continues
usewhenthequestiongivesallthevalues
(AC,BAC,EV,CPIandSPI),otherwise,this
formulaisnotlikelytobeused
AC=ActualCost,BAC=Budgetatcompletion,EV=EarnedValue,CPI
=CostPerformanceIndex,SPI=SchedulePerformanceIndex
Earned Value
Interpretation
Remarks
nshouldincludetheprojectmanager,n= e.g.iftheno.ofteammembersincreasefrom4to5,theincreasein
numberofmembersintheteam
communicationchannels:5(51)/24(41)/2=4
Page1of2
EV=EarnedValue,PV=PlannedValue
EV=EarnedValue,AC=ActualCost.sometimestheterm
cumulativeCPIwouldbeshown,whichactuallyistheCPIuptothat
moment
EV=EarnedValue,PV=PlannedValue
EV=EarnedValue,AC=ActualCost
AC=ActualCost,NewETC=NewEstimatetoCompletion
Name (Abbreviation)
Formula
ToCompletePerformanceIndex
(TCPI)
<1Underbudget,=1Onbudget,>1
Overbudget
Remarks
BAC=Budgetatcompletion,EV=Earnedvalue,AC=ActualCost
TCPI=Remaining
Work/Remaining
Funds
BAC=Budgetatcompletion,EV=Earnedvalue,CPI=Cost
performanceindex
EAC=EstimateatCompletion,AC=ActualCost
11
EstimatetoCompletion
12
VarianceatCompletion
13
PERTEstimation
14
StandardDeviation
<0Underbudget,=0Onbudget,>0
Overbudget
(P O)/6
BAC=Budgetatcompletion,EAC=EstimateatCompletion
O=Optimisticestimate,M=MostLikelyestimate,P=Pessimistic
estimate.
(O + 4M + P)/6
LS ES
15
Interpretation
thisisaroughestimateforthestandard
deviation
<0Behindschedule,=0Oncriticalpath
O=Optimisticestimate,P=Pessimisticestimate
LS=Latestart,ES=Earlystart
Float/Slack
LF EF
16
http://edwarddesigner.com/web/pmpcalculationformulae/
17
http://edwarddesigner.com/web/pmpearnedvaluequestionsexplanined/
Earned Value
LF=Latefinish,EF=Earlyfinish
Page2of2