Вы находитесь на странице: 1из 3

Well Control Drills and Exercises

Image not found


http://www.wipertrip.comimages/stories/articles/100/472_well_control.jpg
472
well control

Three types of drills are to be exercised, one while drilling with the kelly on the string, one normally while tripping without the

kelly on the string and one with the bit off bottom ie.:
Kick Drill While Drilling (pit drill)
Kick Drill While Tripping (trip drill)
Kick Drill While Bit Off Bottom (strip drill).

General Requirements
The following guidelines shall be followed for well control drills :
Well control drills shall be initiated by the contractor or the Drilling Supervisor and performed under the supervision of the Drilling Supervisor to
ensure that the crews are adequately trained and prepared to implement well control procedures correctly.
Well control drills shall only be conducted when they do not complicate ongoing operations. A kick should be simulated by manipulation of a
primary kick indicator such as the tank level indicator or the flowline indicator.
The drills described in the above section include the full sequence of shutting in a well. The critical reaction time shall be measured up to the point
when the well is closed in.
Trip drills shall only be conducted if the BHA is inside the casing shoe.
Out-of-hole drills may be conducted at any time when out of hole with no tools or wireline through the BOP stack.

Kick Drill While Drilling - Pit Drills Procedure


Before drilling out to any shoe, and at the discretion of the Drilling Supervisor, but not less than once every week per crew while normal drilling
operations are in progress.
1. INITIATE kick verbally or by raising a float (normally Drilling Supervisor or Toolpusher).
2. On initiation the crew leader is to ALERT the crew and STOP the rotary.
3. PULL kelly above the rotary table until the lower kelly cock is above the drilling floor, at same time SLOW DOWN the pump.
4. STOP the pumps.
5. CLOSE the annular preventer
6. OPEN the hydraulic operated valve in the side outlet from the BOP stack to the choke manifold (The inner valve is always open under normal
conditions).
Note : A diagram with all relevant measurement relating to tool joint position should be available to the driller at the BOP control panel.
7. TAKE readings of the closed-in annulus and drillpipe pressures.
8. MEASURE the gain in the active mud tank.
9. END drill, RETURN all settings to normal operating mode.

Kick Drill While Tripping Trip Drills Procedure


At the discretion of the Drilling Supervisor, but not less than once every two weeks per crew while normal drilling operations are in progress.
1. INITIATE kick verbally or by raising a float in the trip tank.
2. On initiation the crew leader (Driller/Assistant driller) is to ALERT the crew.
3. BRING tool joint to rotary level.
4. INSTALL stabbing valve in open position (hand tight).
5. CLOSE stabbing valve.
6. CLOSE the annular preventer.
7. OPEN hydraulic operated valve in the side outlet from the BOP stack to the choke manifold.
Note: A diagram with all relevant measurements relating to tool joint position shall be available to the driller at the BOP control panel.
8. INSTALL circulating head, MAKE UP correct torque, OPEN stabbing valve and TAKE readings of the closed-in annulus and drillpipe pressure.

9. READ gain in trip tank.


10. END drill, RETURN all settings to normal operating mode.

Volumetric Stripping Drill - Procedure

Strip Drills
A combined volumetric/stripping drill should preferably be performed once per week per crew. The drill shall only be conducted after a casing string
(ideally the 9 5/8" or Production string) has been cemented and pressure tested and prior to drilling out the shoe track.
Note: The Annular Preventer shall be pressure tested following the stripping drill.
1. HOLD a strip drill in the casing before drilling out the shoe track.
2. RIH to 1 000 ft above top cement.
3. HOLD a kick drill. CLOSE annular preventer
4. INSTALL inside BOP. OPEN stabbing valve.
5. APPLY 500 psi pressure on the annulus through the kill line
6. REDUCE closing pressure of the annular preventer to minimum avoiding leakage (make sure bushings are locked !).
7. OPEN valve to surge bottle in annular closing line.
8. CONNECT line from choke manifold to trip tank. Trip tank to be half full. CHECK if trip tank drains into strip tank.
9. SET UP flow line so that any fluid that leaks through annular preventer goes into trip tank.
10. MAKE UP next stand. (Have a good file on the floor to remove tong and slip marks on the pipe.)
11. STRIP stand in hole and MAINTAIN pressure on annulus constant by bleeding off through the choke. Run pipe slowly to avoid pressure surges.
Measure volume of mud bleed off and ensure total volume is equal to closed end volume of stand stripped into hole.
12. When complete stand is run in, CLOSE IN at choke manifold by closing valve behind the choke.
13. DRAIN closed end volume of one stand out of trip tank into stripping tank.
14. INSTALL next stand.
15. CONTINUE stripping until crew is familiar with operation.
Note : Check if all equipment is working properly and calibrations of tanks is correct. Ensure crews are fully aware that Kelly Cock has to be put on
before the inside BOP.

After Completing The Strip Drill


1. BLEED OFF annulus pressure through choke.
2. CLOSE valve to surge bottle in annular preventer closing line.
3. INCREASE annular pressure to normal operating pressure.
4. OPEN annular preventer.
5. CLOSE HCR. SET UP choke manifold for normal drilling.
6. PULL BACK to remove inside BOP and kelly cock.
7. CLOSE kelly cock (in case pressure trapped in below Inside BOP).
8. REMOVE inside BOP.
9. OPEN kelly cock carefully to check for pressure.
10. REMOVE kelly cock.
11. TEST bag type preventer prior to continuing operations.

Reporting
The Driller is to document the drill in the IADC report under remarks. The following shall be recorded.
Type of drill.
Time of drill.
Reaction time in seconds from the moment the kick is simulated until the well is closed in. The designated crew member is a member of the drill

crew who is present on the drill floor at the time of a BOP drill or well control situation. All drill crew members must be capable and able to react
correctly to the drill or real well control situation.
The total time taken for the drill. The time taken should be less than a pre-determined benchmark. If not, the drill shall be repeated.
The following shall be recorded on the DDR:
the reaction time from the moment the kick is simulated until the designated crew member is ready to start the closing procedure.
the total time it takes to complete the entire drill.
time drill was held (to determine which crew performed the drill).

Вам также может понравиться