CONCRETE WORK
CW.1 MATERIALS
CW.1.1
General
Materials used in the works shall be of the qualities and kinds specified herein and equal
to approved samples. Delivery shall be made sufficiently in advance to enable samples to
be taken and tested if required. No materials shall be used until and unless approved and
materials not approved shall be immediately removed from the works at the Contractor's
expense.
Materials shall be transported, handled and stored on the site or elsewhere in such a
manner as to prevent damage, deterioration or contamination all to the satisfaction of the
RO. The RO reserves the right to inspect any materials to be used on the works at any
time and at any place of storage.
Unless otherwise specified or otherwise agreed to by the RO (Representative of Owner),
materials shall comply with the appropriate American Standards.
Where the
requirements of the relevant Standards are in conflict with this Specification then this
Specification shall take precedence.
If required, the Contractor shall supply to the RO the appropriate certificate of
compliance with the Standards. Notwithstanding the above, tests shall be carried out as
and when directed by the RO in accordance with the relevant Standards. Materials for
tests shall be provided and delivered by the Contractor at his cost, to an approved
laboratory.
Cutting of structural members shall not be permitted without prior approval from the RO.
The work includes all miscellaneous concrete work as indicated in Drawings and
specified under any trades and Nominated sub-contractor.
The Contractor shall be fully conversant with all contract drawings and other information
on works including mechanical, electrical and utility drawings and specifications to be
carried out by sub-contractors and specialist contractors.
The main contractor shall co-ordinate and make necessary provisions for the built-in
work and embedded pipes or conduits by all Nominated sub-contractors and specialist
contractors.
CW.1.2
Cement
cement brand unless he has specific reasons to do so and permission in writing shall be
obtained from the RO.
High alumina cement shall not be used for any concrete work.
All cement shall be delivered to site in sealed and branded bags of the manufacturer or in
properly designed bulk containers.
All cement shall be stored in a weather proof dry shed with raised boarded floor, or in
properly designed bulk storage tanks.
Cement of different manufacture and of different types shall be kept separately and shall
not be used in the same mix.
Cement that becomes lumpy or otherwise deteriorated in transit or storage shall not be
used for concreting. All cement unfit for use shall be removed from site immediately.
Consignment of cement shall be used in the order of delivery.
The Contractor shall at the request of the RO, produce a certificate showing the date and
place of manufacture of the cement. As and when directed by the RO, samples of cement
shall be provided for testing. Any cement failing to comply with the requirements of the
relevant Standards shall be rejected.
CW.1.3
Aggregates
Coarse aggregates shall be 'granite' or other hard stone from a source approved by the RO
Limestone aggregates shall NOT be used unless otherwise specified.
CW.1.4
Quality
___________________________________________________________________________________
Technical Specification
When tested in accordance with the methods described in American Stanstard aggregates
are to have the following properties :
(i)
(ii)
Unless evidence of general performance is offered which is satisfactory to the RO, the
maximum quantities of clay, silt and fine dust, and of organic impurities, are not to
exceed the limits given in American Standard.
CW.1.5
Definitions
The term 'fine aggregate' 'coarse aggregate' and all-in aggregate', are as defined in
American Standard.
CW.1.6
Water
Water shall be obtained from a public supply. If water for the works is not available from
a public supply, approval shall be obtained regarding the source of water.
Water obtained from sources other than public supply shall be clean fresh water free from
chemical and organic impurities. When required by the RO, the Contractor shall arrange
for tests of the water to be carried out in accordance with American Standard before and
during the progress of the work.
CW.1.7
Admixture
Admixture shall not be used unless approved by the RO. The Contractor shall be required
to furnish the following to the RO prior to the approval for the use of admixture:
*
*
*
*
Admixture used shall generally comply with American Standard. Requests for
permission to use other types of admixtures not covered by these Standards may only be
considered when accompanied by full supporting information. Admixture containing
calcium chloride shall not be used.
General
Unless otherwise stated, concrete mix refers to "designed mix". However, "nominal mix"
may be used in place of "designed mix" provided:
___________________________________________________________________________________
Technical Specification
*
*
*
CW.2.2
In designed mixes, the strength shall be the main criterion specified, with compliance to
minimum and maximum cement content, and maximum water/cement ratio. The
workability of the mix shall be in accordance with American Standard. Mix design shall
be based on a target mean strength not less than the specified characteristic strength plus
7N/mm. The Contractor shall design the mix and shall be responsible to ensure that the
mix supplied will give the required properties including strength. Unless otherwise
specified for protection against aggressive soil conditions, designed concrete mixes shall
comply with the specifications in Table.
TABLE SPECIFICATIONS FOR DESIGNED
Grade
Characteristic
Strength N/mm at 28 days
Minimum cement content in
kg/m of fully compacted
concrete
Maximum cement content in
kg/m of fully compacted
concrete
Maximum water/cement
ratio
55
55
50
50
45
45
40
40
35
35
CONCRETE MIX
30
30
25
25
20
20
300
550
0.55
0.6
0.5
0.5
15
15
0.7
10
-
0.8
Design of mix shall ensure no segregation, no excessive bleeding and ability to achieve
specified surface finish. Segregation and bleeding shall be determined by visual
inspection.
The total chloride content of the concrete mix when expressed as a percentage of chloride
ion by mass of cement shall not exceed the limits specified in Table .
TABLE - MAXIMUM TOTAL CHLORIDE CONTENT
Type of Concrete
Prestressed Concrete
Steam-cured Concrete
Other concrete
CW.2.3
Trial Mixes
The mix design shall be verified by preparation of trial mixes. Twelve cubes shall be
taken; six of which shall be tested at 7 days and the other six at 28 days. The average of
the six cubes tested at 28 days shall satisfy the above target mean strength in 6.2.2. Trial
___________________________________________________________________________________
Technical Specification
mixes need not be undertaken provided the supplier can furnish evidence of test results for
the proposed mix satisfactory to the RO.
No concrete shall be placed in the work until the results of the trial mix are approved by
the RO.
CW.2.4
The RO reserves the right to instruct the Contractor to modify and improve the mix
design from time to time during the progress of work as and when he considers necessary
to meet the requirements. This shall not entitle the Contractor to any extra payment.
CW.3
MIXING CONCRETE
Concrete shall be thoroughly mixed in a batch type mechanical mixer. The quantity
of material in each batch shall not exceed the rated capacity of the mixer.
Mixing shall continue until the concrete is uniform in colour and consistency.
The first batch of concrete fed into the drum or pan shall have an increase of an
appropriate amount of dry mortar similar in proportion to that of the concrete to be
mixed and of mixing water for coating the drum or pan.
The entire contents of the drum shall be discharged before the materials for the
succeeding batch are fed into the drum or pan. Mixers which have been out of use for
more than 30 minutes should be thoroughly cleaned before any fresh concrete is
mixed.
No concrete shall be mixed by hand except with the specific approval of the RO for a
small amount. Where such approval is granted, the Contractor shall at his own
expense increase the proportion of cement by 10%. Mixing shall be continued until
the concrete is of uniform colour and consistency.
CW.4
___________________________________________________________________________________
Technical Specification
CW.5
DISTRIBUTION OF CONCRETE
CW.5.1
General
The concrete shall be distributed from the mixer to the position of placing in the works by
approved means which do not cause segregation or otherwise impair the quality of the
concrete. Concrete which has in the opinion of the RO becomes unduly segregated shall
be remixed by hand before deposited in the work.
Details of any proposed pumping conveyor belt or chuting plant must be approved by the
RO before such plant is delivered to the site.
All distributing equipment shall be cleaned before commencing mixing and distribution
of the concrete and such equipment shall be kept free from set concrete.
CW.5.2
Foreign matter and unsuitable batch of concrete must be removed immediately from the
hopper before pumping is resumed.
When extra sections of pipe are to be added, each length or pipe must be thoroughly
wetted inside but no free water shall remain in the pipe.
When the pipeline is exposed to the sun, the line shall be protected against absorption of
heat by covering with damp sacking or staw mats during pumping.
___________________________________________________________________________________
Technical Specification
Vibration, with any type of vibrator, shall not be continued in any one spot to the extent
that pools of grout are formed. Care shall be taken to avoid any disturbance of concrete
which has become too stiff to regain plasticity when vibrated.
Vibration shall not be applied by way of the reinforcement. Where vibrators of the
immersion type are used, contact with reinforcement and all inserts shall be avoided so
far as is practicable.
Vibration shall not be used as a means of distributing heaped concrete into position.
After being compacted and finished, the concrete must be left absolutely undisturbed
while setting.
(a)
(b)
After thoroughly wetting, the concrete shall be covered with a layer of approved
water-proof paper or plastic membrane until the concrete has reached the age of 4
days.
(2)
(a)
After completion of the finishing process, all exposed surfaces shall be covered
with a layer of approved plastic sheeting until such time as the concrete has
hardened sufficiently to permit water curing. Water curing shall be effected
whenever possible by the continuous spraying of cool water for a period of 2
days. Particular care shall be taken to avoid terminal shock at the surface of the
concrete caused by the intermittent application of large quantities of cold water.
___________________________________________________________________________________
Technical Specification
Formwork to concrete walls and columns shall be kept cool by water sprays as
soon as the concrete has hardened sufficiently and until the formwork is removed,
then one of the curing methods as (1) (b) and (1) (c) shall be adopted until the
concrete has reached the age of 7 days.
(3)
No traffic shall be allowed over any part of the finished concrete until it has been
set and properly protected to the satisfaction of the RO.
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
No water in excess of the quantity required in the approved mix shall be allowed to be
added to the concrete to increase its workability affected by elapsed time and/or
temperature.
While it is not being discharged, the concrete in a transit truck/truck mixer/agitator shall
be kept continuously agitated.
The concrete shall be placed in its final position and left undisturbed within 2 hours from
the time when the cement was added to the mix.
General
All sampling, curing, testing and compliance of cubes shall be carried out in accordance
with CQHPs guideline. A sample shall be taken from a randomly selected batch of
concrete chosen by the RO The sample shall be obtained by taking a number of
___________________________________________________________________________________
Technical Specification
10
increments in accordance with CQHPs guideline, and whenever practicable, at the point
of discharge from the mixer or ready-mixed truck.
CW.12.2
Test Results
If the test result of any of the test is not satisfactory, at the RO's instruction, that part of
the works shall be rejected and reconstructed to comply with this Specification, or other
approved measures be taken to make the works secure, all at the Contractor's expense.
No extension of time shall be entertained in this connection.
___________________________________________________________________________________
Technical Specification
11
CW.13 REINFORCEMENT
CW.13.1 General
The reinforcement shall be complying to the CQHPs guideline.
Where the letter T is used in the structural detailing, it shall mean that such reinforcement
shall be high-yield bars having a minimum characteristic strength of 350N/mm unless
otherwise specified.
The letter R, where used, shall indicate that such reinforcement shall be mild steel bars
with a minimum characteristic strength of 250N/mm.
Reinforcement bar not designated by any letter shall be of high yield having a minimum
characteristic strength of 350N/mm.
Reinforcement shall be free from pitting, loose rust, mill scale, paint, oil, grease, adhering
earth or any other material which may impair the bond between the concrete and the
reinforcement or which may cause corrosion of the reinforcement or disintegration of the
concrete.
Neither the nominal size nor the length of a bar shall be less than the size or length shown
on the drawings.
The reinforcement shall be tested in accordance with the relevant American Standard.
Certificate of original and manufacturer's test certificates shall be produced if required.
Selection of test pieces shall be made by the RO. The Contractor shall bear all costs
involved in making these tests.
12
which they are intended to be in contact and shall be securely wired or if approved
welded thereto.
Before the inspection and approval by the RO, the Contractor or his competent
representative shall be required to examine the accuracy of the fixing, placing and
cleanliness of the steel reinforcement.
No concreting shall commence until the RO has inspected the reinforcement in position
and until his approval has been obtained. Reinforcements shall not be displaced from the
approved positions during concreting.
Reinforcement projecting from work being concreted or already concreted shall be
protected from deformation or other damage.
The cover shall be provided by means of distance pieces of cement mortar, concrete or
other approved material. The proportions of the mortar or concrete used for casting the
distance pieces shall not be inferior to those of the concrete in which they are embedded.
The vertical distances between successive layers of bars in beams of similar members
shall be maintained by the provision of steel spacer bar of the size of the largest bar in the
two successive layers to be kept separate or the maximum size of coarse aggregate plus
5mm, whichever is the greater. The spacer shall be inserted at such intervals that the
main bars do not perceptibly sag between adjacent spacer bars. A pair of bars in contact
or a bundle of three or four bars in contact shall be considered as a single bar of
equivalent area when considering size.
CW.13.4
Welding Reinforcement
(2)
Splices shall be staggered so that no more than half of the bars are
spliced at any cross section of the structural member.
(3)
___________________________________________________________________________________
Technical Specification
13
(4)
(5)
At least one sample for every 100 splices shall be tested. The RO may
order additional tests to be carried out to ensure the quality and
workmanship at all times.
(6)
Every batch of hot rolled steel bars delivered to Site shall be covered
by:
(a)
(2)
The above three items of (1)(a), (b) & (c) shall be submitted in
one lot for each batch delivered to site within 14 days after the
steel bars are delivered to site.
(3)
Ten (10) samples of each batch shall be tested. If the bar pattern of
the batch is acceptable by the Building Authority for abbreviated
testing, 3 samples shall be tested.
(4)
(5)
___________________________________________________________________________________
Technical Specification
14
(a)
(b)
(c)
(d)
(e)
(6)
measured mass;
calculated effective cross-sectional area;
yield stress;
tensile strength;
elongation; and
(7)
(a)
(b)
bar pattern;
(c)
(d)
(e)
(a)
(b) If one or more valid test results is less than 93% of the minimum
yield strength, the batch shall be deemed not to comply.
(8)
(c)
If one or more valid test results fails to meet any of the mass,
tensile strength, elongation, or bend test requirements, two
additional samples for each failure shall be taken from different
bars of the same batch and be subjected to the test(s) in which the
original sample failed. If any one of the additional samples fails,
the batch shall be deemed not to comply.
(d)
In the case of 3-sample test, if one or more valid test results has a
yield stress between the minimum yield strength and 93% of it, 7
additional samples shall be taken from different bars of the same
batch and be tested. The results of the total 10 samples shall be
judged as in (b) & (c) above.
Any batch if deemed not to comply shall be removed from Site totally
and all rebar are not allowed to use.
___________________________________________________________________________________
Technical Specification
15
16
concrete shall be filled with mortar and finished to the approval of the RO. Wire ties
passing through the concrete may be used only when approved and the ends of the wire
shall be concealed and measures taken to prevent rust stains on the concrete.
All rubbish, chippings, shavings etc shall be removed from the interior of formwork
immediately before concrete is placed, first by compressed air and then by a jet of water.
Temporary openings shall be formed for the inspection of the inside of the formwork and
for the escape of water used for washing. The Contractor may use approved form oil
which is compatible with the required finish to coat the faces of the formwork in contact
with the concrete. Such oils shall be insoluble in water, non-staining, not injurious to the
concrete and shall not become flaky or be removed by rain or wash water. Diesel oil and
liquids which retard the setting of the concrete shall not be used. The same approved
type of form oil shall be used throughout all works. The application of the form oil shall
be such that no reinforcement or prestressing tendons shall be coated by the oil and there
shall be no accumulation of the oil at the bottom of the formwork.
.
CW.14.4 Removal of Formwork
Formwork supporting cast-in-situ concrete shall not be removed unless:
i)
ii)
iii) the cube strength of the cast concrete is 10N/mm or twice the stress to
which it will then be subjected, whichever is higher.
In the absence of the cube test result and stress calculations, the minimum periods before
striking of the formwork for ordinary Portland cement concrete, as given in Table
In any event, no formwork or support shall be struck or removed without the RO's
consent in writing. Striking or removal of formwork shall be done only in the presence
of the RO's representative at site.
TABLE :MINIMUM PERIOD FOR STRIKING FORMWORK
Location
Sides of columns, walls and beams
Soffits of slabs (props left under)
Soffits of beams (props left under)
Props to slabs
Props to beams
___________________________________________________________________________________
Technical Specification
17
All formwork shall be removed without damage to the concrete. The Contractor shall be
responsible for any injury to the work and any consequential damage caused by or arising
from the method adopted for the striking or moving of the formwork or supports.
Immediately after the removal of the formwork, it is the Contractor's responsibility to
notify the RO for inspection and any remedial treatment required by the RO shall be
carried out without delay. Any remedial treatment which has been carried out before the
RO's inspection and approval shall render the member liable for rejection.
CW.15 FINISHES
CW.15.1 Concrete to Receive Applied Finish
When the concrete is to receive an applied finish, the form work shall be made of
closely jointed wrought boards. Alternatively, steel or other materials may also be
used, subject to the RO agreement. On removal of the form work and upon RO
inspection, defects shall be treated as provided in Section of Removal of Formwork.
The concrete face shall then be roughened by approved means to form a key before the
finish is applied.
CW.15.2 Slabs to Receive Topping
The top face of slab intended to receive topping shall be first spaded and then left
roughened with approved means.
Just prior to placing the topping, the base slab shall be thoroughly cleaned, prepared for
bond and wetted. No pools of water shall be left standing on the wetted surface. A thin
coat of neat cement grout shall be applied onto the surface of the slab for a short
distance ahead of the topping. The wearing surface shall be applied before the grout has
hardened.
When surface hardeners are required to be used, the Contractor shall submit for the RO
approval, the type, colour, composition, details of manufacture and the manufacturer's
method of use. Any hardener consisting of soluble alkaline compounds, rust and
materials designed to disguise rust shall not be allowed to be used. Upon approval of
the type, the application of the hardener shall be as specified by the manufacturer.
(1)
The Contractor shall check the actual positions, sizes and alignments of the
finished works. He shall report to the RO when any dimensional deviations
exceed the permissible values and shall carry out any rectification works,
including cutting out and rebuilding part or the whole of the finished works, as
directed by the RO
___________________________________________________________________________________
Technical Specification
18
(2)
When required by the RO, the Contractor shall furnish all necessary instruments
and labour for the use of the RO for checking the finished structure.
(3)
Permissible deviation
Position
External face of
structural member and
wall
Internal member and
opening
Internal beam and
external beam over
window frame
Beam
Slab
Column
Wall thickness
Corewall, lift enclosure
wall, internal panel
wall, and external face
of
structural member
3mm
Alignment
(vertically&
horizontally)
Level of floor
Internal faces of
column
General floor level
(with
due allowance for
rendering and finishes)
6mm
3mm
6mm
3mm
6mm
3mm
1 in 1000
1 in 500
3mm from specified
P.D. level
The provisions of this clause apply to water tanks, swimming pools and other
water retaining structures.
(2)
The minimum cement content shall be 325 kg/m3 for maximum size of aggregate
of 20 mm and the water/cement ratio shall not exceed 0.55. The maximum
cement content shall be 400 kg/m3 for reinforced concrete works and 500 kg/m3
for prestressed concrete works.
(3)
(4)
The Contractor shall ensure that, on completion of the work, it is free from any
evidence of seepage of water to the outside faces, and that the criteria of the water
tightness test in subclause (10) are satisfied.
(5)
Unless construction joints are specified on the Drawings, the position of the joints
shall be proposed by the Contractor and be submitted to the ROs.
(6)
Water stops shall be provided at all construction joints and movement joints
unless otherwise directed. Water stops shall be of an approved type and shall be
fixed in accordance with the manufacturer's written specification. Purpose-made
junction pieces shall be used at all intersections. Water stops shall be maintained
in correct position during concreting.
(7)
Kickers shall be cast monolithic with the base slab. Supports for kicker formwork
shall not penetrate through any water retaining elements.
(8)
Form ties which leave an open hole through the concrete shall not be used. All
recesses for form ties shall be plugged with 0.45:1:2 water-cement-sand dry-pack
mortar well rammed into place.
(9)
All pipes, sleeves, ducts, fittings, bolts and the like which are to be embedded in
or pass through the concrete shall be fitted with puddle flanges and be cast-in.
Boxing-out for such items, drilling or cutting the finished concrete shall not be
permitted.
(10)
A water tightness test for the water retaining structure shall be carried out after
the concrete has attained its specified grade strength and before any finishes are
applied. The procedures and criteria of acceptance shall be as follows:
(a)
The structure is cleaned and filled to the normal maximum level with
water.
(b)
The work is protected such that the water level is not affected by rainfall or
undue evaporation during the test.
(c)
When first filled, the water level is maintained by the addition of further
water for a stabilizing period. This stabilizing period is not less than 7
days.
(d)
After the stabilizing period, the level of the water surface is recorded at
24-hour intervals for a test period of 7 days.
(e)
During this 7-day test period, the total permissible drop in level shall be
1/500 of the average water depth and 10 mm, whichever is less.
(f)
The water retaining structure shall be deemed not water tight if the total
drop in water level during the 7-day test period exceeds the permissible
value, or if there is any evidence of seepage of water to the outside faces.
(g)
(h)
The Contractor shall inspect the concrete immediately after removing formwork
and report any honeycombing or other defects to the SO
(2)
(b)
the specified grade strength of the concrete are deemed not to be attained
and investigations by non-destructive tests, core tests or other tests as
directed by the SO have revealed that the finished concrete is
unacceptable;
that part of the works shall be cut out and properly reconstructed at the
Contractor's expense. Such cutting out shall extend to a position suitable
for a construction joint.
(3)
(4)
If the specified grade strength of the concrete in any part of the structure are
deemed not to be attained, the SO may stop concreting at other parts of the
structure which would otherwise affect or be affected by the defective part until
investigations and, if necessary, remedial works are complete.