For after construction is finished, the site will turned to commercial place.
Calculation (after construction):
Qpeak=
CiA
360
DETAILS:
C=0.90, i=100m/h (duration for 30 minutes),
A= 37.07 acers
1 acers= 0.405 hectare (ha)
A=37.07 x 0.405 = 15.01335 acers
Qpeak=
( 0.90 ) (100)(15.01335)
360
= 3.75 m3/s
SUGGESTED DESIGN:
To design the shape and calculate the normal depth, we assume the Qpeak to be larger than
3.75 m3/s, which is 4 m3/s.
SELECTION OF S0
S0 = 0.005 m
x
=0.005 m
1000
Gradient = 5
Gradient =
y0 y1
x0 x 1
Tan = 5
Tan-1 (5) =
= 78.69
The water is able to flow since the angle is greater than 10.
1+ z 2
A = By0 + zy02
P = B +2y0
A= 0.8y0 + 0.5y02
P = 0.8 + 2y0
P = 0.8 +
1+(0.5)2
5 y0
A
R= P
R=
0.8 y + 0.5 y
0.8+ 5 y
1
A R 3 S0
n
Q=
A R
2
3
Qn
S0
2
0.8 y+ 0.5 y
(0.8y0 + 0.5y02) ( 0.8+ 5 y )
2
( 4 )(0.018)
0.005
(0.8 y 0 +0.5 y 0) 3
2
2 3
0
(0.8 y 0 + 5 y )
= 1.018
Qn
S0
1
2
1.5
1.4
1.2
1.1
1.18
1.19
1.1905
0.7385
2.7915
1.5790
1.3827
1.0332
0.8790
1.001
1.017
1.018
Q=
1
A R 3 S0
n
(1.2)2
2
( 0.8 ) ( 1.2 )+ ( 0.5 ) (1.2 )
( 0.80 ) ( 1.2 )+(0.5)[
]
(
)
( 1.2 )
0.8+
5
Q=
0.30
Q=
1
( 1.68 ) 0.615 0.005
0.30
Q = 0.243 m3/s
Qbefore Qdesign
Thus, this channel will able to carry both flow, before and after construction. There will be no
spillways occur at the drain.
Tc = B + 2yz
Tc = 0.8 + (2)(0.5)z
Tc = 0.8 + yc
Using formula,
(0.8 y c + 0.5 y 2c )3
(0.8+ y c )
A 3c Q 2
=
Tc g
42
9.81
= 1.631
Q2
g
yc
1
1.1
1.08
1.084
1.221
1.724
1.612
1.634
yc 1.084 m
Q2
y0+
2
2gA
Q = 4m3/s
y0 = 1.19 m
A= By0 + zy02
A = (0.8)(1.19) + (0.5)(1.19)2
A=1.6605 m2
4
E0 = 1.19+ (2)(9.81)(1.6605)2
= 1.48576 m
Emin =
yc+
Q
2
2 g Ac
Q = 4 m3/s
yc = 1.084 m
A= Byc + zyc2
A = (0.8)(1.084) + (0.5)(1.084)2
A=1.4547 m2
2
4
Emin = 1.084+ (2)(9.81)(1.4547)2
= 1.4694 m
CALCULATION OF y1 and y2
H + Emin = E1,3
E1,3 = 1.4694 + 0.6
= 2.0694m
E1,3 =
Q
y 1,3 +
2
2 g A1,3
2.6094 =
y 1,3 +
4
2 2
(2)(9.81)( 0.8 y 1,3+ 0.5 y 1,3)
E3
1.483
2.063
2.154
2.072
2.070
y1
0.5
0.6
0.67
0.68
0.676
0.673
E1
3.459
2.472
2.080
2.037
2.054
2.070
y3 2.008 m
For y1:
y1 0.673 m
ESTIMATION OF COST
Assuming the length of the channel is 200m, the excavation cost is RM 4/m3 and lining cost is
RM5/m2.
Volume of excavation = Area channel x Length
= 1.68 m2 x 200
= 336 m3
Cost excavation = 336 x RM4 = RM1344
JUSTIFICATION OF DESIGN
Q=AV
Q= 4m3/s, A=1.66m2
V=2.41m/s
For recommended limit velocity, since we are using hard lined channel, the limit velocity is
4m/s
Vdesign<Vrecommended limit
Thus, the flow in the channel does not exceed the recommended limit.