Академический Документы
Профессиональный Документы
Культура Документы
EXPANSION PROJECT
ENGINEERING SPECIFICATION
FOR
INSTALLATION OF VESSEL & HEAT EXCHANGER
ES No.
D-303
Revision
PAGE 1 OF 1
DATE
Jul /24/2008
Oct/16/2008
DESCRIPTION
Newly Issued For Approval
(All)
(1.1)
(1.1)
Nov/07/2008
Dec/09/2008
ENGINEERING SPECIFICATION
FOR
INSTALLATION OF VESSEL & HEAT EXCHANGER
ES No.
D-303
Revision
PAGE 1 OF 7
*CONTENTS*
1. GENERAL................................................................................................................................................................2
1.1 Scope...............................................................................................................................................................2
1.2 Related Engineering Specifications..................................................................................................................2
2. INSTALLATION WORKS.........................................................................................................................................2
3. IN-PROCESS CHECK.............................................................................................................................................3
3.1 Preparation of Foundation................................................................................................................................3
3.2 Setting of Liners or Mortar Pad........................................................................................................................3
3.3 Anchor Bolts Setting.........................................................................................................................................3
3.4 Setting of Equipment........................................................................................................................................3
3.5 Grouting of Anchor Pocket...............................................................................................................................4
3.6 Alignment.........................................................................................................................................................4
3.7 Grouting of Base..............................................................................................................................................4
4. ALIGNMENT.............................................................................................................................................................4
4.1 Tolerance..........................................................................................................................................................4
4.2 Priority Criteria.................................................................................................................................................5
4.3 Alignment of Vertical Equipment......................................................................................................................5
4.4 Alignment of Skid-mounted Equipment............................................................................................................6
4.5 Alignment of Stacking-type Equipment............................................................................................................6
5. ASSEMBLING OF ACCESSORIES.........................................................................................................................6
5.1 Internal Parts....................................................................................................................................................6
5.2 Platform and Ladder.........................................................................................................................................7
5.3 Davit.................................................................................................................................................................7
ENGINEERING SPECIFICATION
FOR
INSTALLATION OF VESSEL & HEAT EXCHANGER
ES No.
D-303
Revision
PAGE 2 OF 7
1. GENERAL
1.1 Scope
1.1.1 This specification covers the general requirements for the installation and inspection of vessels and
heat exchangers (Hereinafter collectively referred to as equipment), which may be included in S-OIL
ONSAN REFINERY EXPANSION PROJECT to be constructed by S-OIL Corporation. (Hereinafter
referred to as S-OIL) at Onsan, Korea.
1.1.2 This specification covers the general requirements for other similar type of static equipment, such as
silencers, filters, etc.
1.1.3 Vessels, heat exchangers, or tanks to be fabricated at site are not covered by this specification.
2. INSTALLATION WORKS
Equipment shall be installed in correct position and orientation. Due care shall be paid to the following points
during the work.
(1) Prevention of damage to foundation, foundation bolts, equipment, adjacent structures, etc.
(2) Where the equipment having conical skirt or flat bottom support is directly placed on the foundation, the
vessel shall be installed without excessive concentrated force against bottom plate.
(3) For horizontal equipment which are subject to expansion/contraction, the relative position between foundation
bolts and bolt holes shall be set to allow free movement of the equipment in the correct direction of
expansion/contraction.
(4) Where sliding plates are used, no liners shall be applied between base plate and sliding plate. Contact
surfaces shall be cleaned and metal to metal coated with grease or graphite. After completion of installation
ENGINEERING SPECIFICATION
FOR
INSTALLATION OF VESSEL & HEAT EXCHANGER
ES No.
D-303
Revision
PAGE 3 OF 7
of the equipment and connection with piping, the nuts of the anchor bolts at sliding side shall be loosened to
give 1 to 2 mm of clearance, and then tightened with lock nuts leaving this clearance.
(5) Welding of liners shall be carried out after completion of final alignment inspection. In general, no welding
shall be permitted between base plate and liners.
(6) Where wooden pillows are used, setting and tightening of anchor bolts shall be in accordance with drawings
and manufacturer's installation manual.
3. IN-PROCESS CHECK
ENGINEERING SPECIFICATION
FOR
INSTALLATION OF VESSEL & HEAT EXCHANGER
ES No.
D-303
Revision
PAGE 4 OF 7
3.6 Alignment
(1) Elevation
(2) Position
(3) Perpendicularity or level
4. ALIGNMENT
4.1 Tolerance
Alignment of the equipment shall be carried out as follows, unless otherwise specified
Vertical
Horizontal
Elevation
3.0
Position
3.0
Perpendicularity
Level
0.8 / 1,000
(And not more than 19mm)
0.8 / 1,000
(And not more than 19mm)
ENGINEERING SPECIFICATION
FOR
INSTALLATION OF VESSEL & HEAT EXCHANGER
ES No.
D-303
Revision
PAGE 5 OF 7
(2) Elevation shall be measured on the basis of level marking on the foundation.
(3) Position shall be measured on the basis of center marking of the foundation.
4.2.1 When the criteria stipulated in Para. 4.1 above interfere each other, the following order of priority may
be given:
(a) Perpendicularity
(b) Position
(c) Elevation
(a) Horizontality
(b) Position
(c) Elevation
4.2.2 Regardless of the above priority, where an equipment is connected directly to special piping or another
equipment, relative position and elevation shall be given the priority.
In general, alignment of vertical equipment shall be performed on 3 points from top to bottom of each
orientation and at two orientation of right angle to each other.
ENGINEERING SPECIFICATION
FOR
INSTALLATION OF VESSEL & HEAT EXCHANGER
ES No.
D-303
Revision
PAGE 6 OF 7
Alignment of skid-mounted equipment shall be performed for horizontality, position and elevation of skid-base.
Alignment check for each component is not required.
4.5.1 Alignment of stacking-type equipment shall be performed based on relative position and elevation of
connecting nozzles, adjusting by placing shim plates between base plates of lower equipment and
upper equipment.
4.5.2 In the case of flange connection, applying paste on gaskets, inserting gaskets and bolt tightening shall
be confirmed.
5. ASSEMBLING OF ACCESSORIES
Installation of internal parts such as, main beam, distributor, demister, grating, etc. shall be performed in
accordance with drawing, with consideration of work sequence for catalyst/packing loading or tray assembly
work.
ENGINEERING SPECIFICATION
FOR
INSTALLATION OF VESSEL & HEAT EXCHANGER
ES No.
D-303
Revision
PAGE 7 OF 7
5.2.1 Platforms and ladders may be mounted any time before or after the installation of the equipment.
However, when mounted before installation, it shall be confirmed that those will not affect the erection
work of equipment.
5.2.2 When platforms and ladders are fixed to vertical towers and vessels subject to expansion/contraction,
slot holes of platforms, ladders, or lugs and loosening of nuts shall be confirmed.
5.2.4 When deformation of checker plates of platform floor is found, repair shall be carried out by heating or
reinforcing.
5.2.5 Welding slag of platform and ladders shall be completely removed by hammer.
5.2.6 When handrails are assembled by welding at site, the weld bead shall be finished flush by grinding.
5.2.7 Smooth movement and correct position of safety gate (bar) shall be checked.
5.3 Davit