Академический Документы
Профессиональный Документы
Культура Документы
Building area
Location
Owner
Subject
:
:
:
:
:
Activities/Item
Unit
Quantity
Unit cost
1 Foundation works.
cu.m
100.75
4,500.00
pc.
134.00
1,584.00
pc.
110.00
1,983.00
pc.
52.00
2,379.00
kg.
90.00
70.00
bag
910.00
190.00
pc.
189.00
1,584.00
pc.
640.00
1,013.55
pc.
192.00
649.00
pc.
500.00
253.45
kg.
150.00
70.00
pc.
105.00
800.00
pc.
800.00
75.00
kg.
20.00
70.00
kg.
50.00
70.00
kg.
200.00
70.00
gal.
10.00
60.00
bag
1,900.00
190.00
pc.
170.00
1,584.00
pc.
790.00
1,013.55
pc.
258.00
649.00
pc.
1,240.00
253.45
kg.
300.00
70.00
pc.
455.00
800.00
pc.
3,660.00
90.00
pc.
3,978.00
75.00
kg.
92.00
70.00
kg.
185.00
70.00
kg.
123.00
70.00
gal.
31.00
60.00
sub-total 1
2 Column works.
Portland Cement
D.S.B. 25mm x 6m
D.S.B. 20mm x 6m
D.S.B. 16mm x 6m
D.S.B. 10mm x 6m
G.I. tie wire #16
Formply 1/2" x 4' x 8'
Coco lumber 2" x 2" x8'
C.W.Nail #3
C.W.Nail #2
C.W.Nail #4
Use oil
sub-total 2
3 Beam works.
Portland Cement
D.S.B. 25mm x 6m
D.S.B. 20mm x 6m
D.S.B. 16mm x 6m
D.S.B. 10mm x 6m
G.I. tie wire #16
Formply 1/2" x 4' x 8'
Coco lumber 2" x 3" x8'
Coco lumber 2" x 2" x8'
C.W.Nail #3
C.W.Nail #2
C.W.Nail #4
Use oil
sub-total 3
4 Slab works
Portland Cement
D.S.B. 9mm x 6m
welded wire mesh 4mm dia,2'X2'
G.I. tie wire #16
T-Joist 3.5m
bag
1,100.00
190.00
pc.
490.00
253.45
sht
790.00
650.00
kg.
220.00
70.00
pc.
578.00
1,600.00
bag
117.14
190.00
cu.m
8.93
680.00
cu.m
17.85
750.00
pc.
50.00
365.15
pc.
180.00
253.45
kg.
34.00
70.00
pc.
45.00
800.00
bag
1,630.00
190.00
cu.m
240.00
680.00
pc.
276.00
253.45
kg.
79.00
70.00
pc.
345.00
253.45
pc.
24,432.00
7.50
pcs
16,288.00
9.50
bag
1,955.00
190.00
cu.m
232.00
680.00
sub-total 4
5 Stair works
Portland Cement
Sand S-1
Gravel G-1
D.S.B. 12mm x 6m
D.S.B. 10mm x 6m
G.I. tie wire #16
Formply 1/2" x 4' x 8'
sub-total 5
6 C.H.B. Works
Portland Cement
Sand S-1
D.S.B. 10mm x 6m
G.I. tie wire #16
D.S.B. 9mm x 6m
C.H.B. 4" ordinary
C.H.B. 5" ordinary
sub-total 6
7 Plastering works
Portland Cement
White Sand
sub-total 7
pc.
40.00
1,100.00
pc.
16.00
1,100.00
set
40.00
1,300.00
5,500.00
pc.
40.00
Hinges
pc.
120.00
20.00
Door knob
pc.
96.00
350.00
pc.
16.00
5,500.00
pc.
40.00
4,200.00
pc.
16.00
1,200.00
pc.
40.00
400.00
pc.
16.00
1,000.00
pc.
16.00
12,000.00
pc.
18,178.00
35.00
pc.
3,024.00
25.00
pc.
530.00
30.00
pc.
1,050.00
25.00
pc.
2,600.00
25.00
sub-total 8
9 Tile works.
pc.
1,820.00
25.00
Portland Cement
bag
476.00
190.00
Tile grout
kg.
224.00
7.50
56.00
600.00
pc.
160.00
55.00
pc.
3,020.00
160.00
White Sand
cu.m
Tile trim
sub-total 9
10 Ceiling works.
pc.
770.00
450.00
Hardinails
kg.
140.00
120.00
kg.
28.00
110.00
C.W. Nail #3
kg.
78.40
70.00
C.W.Nail #2
kg.
112.00
70.00
pc.
480.00
320.00
214.20
950.00
45.00
450.00
11 Steel Railings.
Stair & balcony railings
Stair handrail 2"x4"x10'
sq.m.
pc.
sub-total 15
12 Painting works.
Flat latex paint
gal
375.00
450.00
Semi-gloss latex
gal
300.00
600.00
Gloss latex
gal
190.00
750.00
Patching compound
kg.
190.00
20.00
Stupa cloth
pc.
100.00
1.50
Mesh Tape
roll
175.00
110.00
Varnish
gal
35.00
500.00
QDE paint
gal
100.00
750.00
Paint thinner
gal
30.00
250.00
Masking tape
pc.
150.00
15.00
pc.
210.00
12.00
pc.
210.00
12.00
Accessories
set
1.00
7,500.00
set
1.00
312,000.00
sub-total 17
13 Roofing works.
Roof framing and trusses
set
1.00
266,799.50
Total cost
Remarks
7.64%
453,375.00
212,256.00
218,130.00
123,708.00
6,300.00
1,013,769.00
11.66%
172,900.00
299,376.00
648,672.00
124,608.00
126,725.00
10,500.00
84,000.00
60,000.00
1,400.00
3,500.00
14,000.00
600.00
1,546,281.00
22.28%
361,000.00
269,280.00
800,704.50
167,442.00
314,278.00
21,000.00
364,000.00
329,400.00
298,350.00
6,440.00
12,950.00
8,610.00
1,860.00
2,955,314.50
13.47%
209,000.00
124,190.50
513,500.00
15,400.00
924,800.00
1,786,890.50
1.09%
22,256.72
6,069.00
13,387.50
18,257.50
45,621.00
2,380.00
36,000.00
143,971.72
7.34%
309,700.00
163,200.00
69,952.20
5,530.00
87,440.25
183,240.00
154,736.00
973,798.45
3.99%
371,450.00
157,760.00
529,210.00
6.55%
44,000.00
17,600.00
52,000.00
220,000.00
2,400.00
33,600.00
88,000.00
168,000.00
19,200.00
16,000.00
16,000.00
192,000.00
868,800.00
7.53%
636,230.00
75,600.00
15,900.00
26,250.00
65,000.00
45,500.00
90,440.00
1,680.00
33,600.00
8,800.00
999,000.00
7.66%
483,200.00
346,500.00
16,800.00
3,080.00
5,488.00
7,840.00
153,600.00
1,016,508.00
1.69%
203,490.00
20,250.00
223,740.00
4.74%
168,750.00
180,000.00
142,500.00
3,800.00
150.00
19,250.00
17,500.00
75,000.00
7,500.00
2,250.00
2,520.00
2,520.00
7,500.00
629,240.00
4.36%
312,000.00
266,799.50
578,799.50
100.00%
13,265,322.67
5,040,822.61
18,306,145.28
18,306,145
#VALUE!
#REF!
PROJECT:
OWNER:
LOCATION:
SCOPE:
BUILDING AREA
sq.m
UNIT COST
ITEM NO.
DESCRIPTION
QTY
UNIT
MATERIALS
LABOR
TOTAL
TOTAL
AMOUNT
A. SITE WORKS
1. Excavation ( footings and wall footings)
418.50 m
280.00
280.00
117,180.00
2. Backfilling
418.50 m
175.00
175.00
73,237.50
3. Lean concrete
160.00
75.00
235.00
916.70
1,035.80
1,952.50
85.00
45.00
130.00
1.00
280.00
281.00
5 Vapor barrier
6 Bulk excavation
subtotal =
B. FORMWORKS
190,417.50
-
6.01 m
550.55
280.00
830.55
4,993.68
2. wall footing
6.30 m
653.65
302.40
956.05
6,020.72
653.65
302.40
956.05
1.23 m
581.80
302.40
884.20
3 ground beams
4 ground slabs
5 suspended slab
1,085.91
12.42 m
354.00
280.00
634.00
7,875.47
6 columns
105.40 m
354.00
280.00
634.00
66,823.60
198.06 m
354.00
280.00
634.00
125,569.25
354.00
280.00
634.00
6.27 m
354.00
280.00
634.00
8 concrete gutter
9 stairs
subtotal =
C. CONCRETE
3,976.77
216,345.40
-
1. column footing
100.75 m
4,168.55
557.75
4,726.30
476,174.73
30.23 m
4,168.55
557.75
4,726.30
142,876.05
4,168.55
557.75
4,726.30
92.25 m
4,168.55
557.75
4,726.30
436,001.18
5 suspended slab
338.57 m
4,168.55
557.75
4,726.30
1,600,183.39
6 column
230.52 m
4,168.55
557.75
4,726.30
1,089,506.68
7 beams
358.47 m
4,168.55
557.75
4,726.30
1,694,236.76
4,168.55
557.75
4,726.30
22.10 m
4,168.55
557.75
4,726.30
2. wall footing
3 ground beams
4 ground slabs
8 concrete gutter
9 stairs
total volume =
1,172.89 m
subtotal =
D. REINFORCING BARS
104,451.23
5,543,430.01
-
1. column footing
grade 40
kg
36.45
8.00
44.45
grade 60
2,160.64 kg
37.45
8.00
45.45
98,201.09
-
2. Wall Footing
grade 40
kg
36.45
8.00
44.45
grade 60
1,417.18 kg
37.45
8.00
45.45
64,410.83
-
3. Ground slabs
grade 40
337.64 kg
36.45
8.00
44.45
15,008.10
grade 60
607.93 kg
37.45
8.00
45.45
27,630.42
-
4. Ground beams
grade 40
kg
36.45
8.00
44.45
grade 60
kg
37.45
8.00
45.45
5 Suspended slab
grade 40
3,068.04 kg
36.45
8.00
44.45
136,374.38
grade 60
5,365.78 kg
37.45
8.00
45.45
243,874.70
-
grade 40
5,063.36 kg
36.45
8.00
44.45
225,066.35
grade 60
7,034.78 kg
37.45
8.00
45.45
319,730.75
-
grade 40
7,115.42 kg
36.45
8.00
44.45
316,280.42
grade 60
9,258.56 kg
37.45
8.00
45.45
420,801.55
kg
36.45
8.00
44.45
876.90 kg
36.45
8.00
44.45
8 concrete gutter
9 stairs
Total mass =
42,306.23
subtotal =
38,978.21
1,906,356.79
E. MASONRY WORKS
Plastering (interior)
Plastering,(exterior)
CHB Laying 4"
CHB Laying 6"
Concrete topping (30mm- 50mm thick)
1,031.00 m
185.00
90.00
275.00
283,525.00
1,031.00 m
185.00
145.00
330.00
340,230.00
1,031.00 m
572.00
110.00
682.00
703,142.00
1,031.00 m
720.00
120.00
840.00
866,040.00
1,031.00 m
175.00
90.00
265.00
subtotal =
273,215.00
2,466,152.00
53.00 nos.
1,100.00
21.00
1,121.00
59,413.00
53.00 nos.
1,100.00
21.00
1,121.00
59,413.00
53.00 nos.
1,300.00
21.00
1,321.00
70,013.00
53.00 nos.
5,500.00
21.00
5,521.00
292,613.00
5 Hinges
53.00 nos.
20.00
21.00
41.00
2,173.00
6 Door knob
53.00 nos.
350.00
21.00
371.00
19,663.00
53.00 nos.
5,500.00
21.00
5,521.00
292,613.00
160.00 nos.
4,200.00
18.00
4,218.00
674,880.00
194,880.00
160.00 nos.
1,200.00
18.00
1,218.00
160.00 nos.
400.00
18.00
418.00
66,880.00
160.00 nos.
1,000.00
18.00
1,018.00
162,880.00
subtotal =
1,895,421.00
F. Painting works.
1 Flat latex paint
375.00
gal
450.00
15.00
465.00
174,375.00
2 Semi-gloss latex
300.00
gal
600.00
15.00
615.00
184,500.00
3 Gloss latex
190.00
gal
750.00
15.00
765.00
145,350.00
4 Patching compound
190.00
kg.
20.00
15.00
35.00
6,650.00
5 Stupa cloth
100.00
pc.
1.50
15.00
16.50
1,650.00
6 Mesh Tape
175.00
roll
110.00
15.00
125.00
21,875.00
7 Varnish
35.00
gal
500.00
15.00
515.00
18,025.00
100.00
gal
750.00
15.00
765.00
76,500.00
9 Paint thinner
30.00
gal
250.00
15.00
265.00
7,950.00
10 Masking tape
150.00
pc.
15.00
15.00
30.00
4,500.00
210.00
pc.
12.00
15.00
27.00
5,670.00
210.00
pc.
12.00
15.00
27.00
5,670.00
1.00
set
7,500.00
15.00
7,515.00
8 QDE paint
13 Accessories
subtotal =
G. ROOF FRAMING
1 L 65X65X5
7,515.00
660,230.00
-
2,254.49
54.00
24.00
78.00
175,850.22
L 50X50X6
2,055.49 kg
54.00
24.00
78.00
160,328.22
L 50X50X5
266.82 kg
54.00
24.00
78.00
20,811.96
2 L 50 X50X3
2,198.98 kg
54.00
24.00
78.00
171,520.44
3 LC 255 x 90 x 3.5
1,254.49 kg
54.00
24.00
78.00
97,850.22
73.92 kg
35.00
8.00
43.00
3,178.56
440.00 nos.
25.00
25.00
11,000.00
28.00 nos.
686.50
205.00
891.50
24,962.00
112.00 nos.
325.00
98.00
423.00
47,376.00
1.00 nos.
12,197.45
12,197.45
12,197.45
480.00 kgs
1.00 lot
54.00
117,867.30
24.00
-
78.00
37,440.00
117,867.30
117,867.30
subtotal =
880,382.37
13,758,735.07
14,914.62