Вы находитесь на странице: 1из 1

Sharourah Power Plant Ext.

Project
Saudi Electricity Company

Document Compliance Statement

Southern Operating Area

Doc No: Sharourah 51MW/BOP/033-I-001

Contract #
40721056/00

Doc Title: Instrument Installation Material List (BM


Bulk Material List) Rev-1
SEC Ref. /
Date

SEC Comments

A0621

Al-Fanar to note that the above mentioned document is


kept under information category. However Instruments
and Hook ups and tubing material were reviewed with
respect to the relevant engineering document. It is noted
that the estimated quantity is much less than the
required quantity as per the Instrument Hook up
Drawings, Rev - 3. Al-Fanar to clarify and revise the
document accordingly.

Alfanar Reply

As per our understanding estimated quantities for hook up


material is sufficient enough for instrument installation how,
ever in view point of your comment we have upgraded the
spare quantity of instrument Hookup and tubing from 10% to
25%.

Alfanar Construction : PO Box 301, Riyadh 11411 KSA T : + 966 1 275 5999 Ext. 4900 F: + 966 1 275 8811 Email : akbar@alfanar.com

11/29/2016

1/1

Resolution/ Status

Please refer to attach


updated revision of
Instrument Installation
Material List (BM Bulk
Material List), Rev 2