The Activities information on a particular project is shown in the
table ..
Table .. Logic table for project activities A through F.
(i) Draw a Network Diagram showing the various logical activity relationships from this information. (ii) Perform a forward and backward pass to complete activity boxes. Arrange data within activity boxes as outlined in Figure below. EARLY START FLOAT LATE START
EARLY FINISH ACTIVITY NO.
DURATION LATE FINISH
Figure . Layout of Activity Box information.
(iii) b)
Highlight the critical path on your diagram.
It is suggested that the duration of the whole project could be shortened by 4 days by completing Activity B in 4 days rather than 8 days. Rework the Network Diagram and comment on whether this strategy would succeed. State the reasons for