Akashi-Kaikyo Bridge
kiandFuruya
Nobuaki
The Akashi-Kaikyo Bridge, whichis under
construction hy the HonshuShikoku
Bridge Authority, and has a scheduled
completion date in 1998, is the world's
longest suspension bridge, witha main
span of1990 m. It is noteworthy that the
bridge is not only large interms of the
span length but is being constructed
under verydifficult conditions: a deep soft
layer that has to be penetrated for
an
anchorage foundation (the bottom of
foundation = -61 m); water depth (45 m)
and tidalcurrent speed (4.0 m/s) at the
main pier sites; strong wind (about80 m/s)
for the design of the superstructure; and
so on. In order to overcome the difG
culties, many technical developments
have been tested and actually employed: a
unique construction method for bigand
deep foundations; the development of
highly workableconcrete with low-heat
cement; thedevelopment of high-strength
(hreaking strength = 1.8 GPa) wires for
the main cables; the construction of a
large wind tunnel (effective width for
test = 40 m) anda full-bridge modeltest in
it; and so on. In this Paper, the way in
which the basic scheme of the bridgewas
determined andthe basic concept underlying the technical innovations will be discussed.
Introduction
The Akashi-Kaikyo Bridge, shown in Figs 1
and 2 (Fig. 2 was taken in December 1993 from
the Honshu.side) is a three-span truss-stiffened
suspension bridge for a six-lane highway.' Its
main span length of 1990 m exceeds the UK's
Humber Bridge, which, at 1410 m. is currently
by a margin of
the longest bridge in the world,
41%. The Akashi-Kaikyo Bridge is a part
of
the Kobe-Naruto route of the Honshu-Shikoku
Highway system (in total, three routes (Fig.
3)),
which represents an important direct link
between the Japanese archipelago.The
southern half of the Kobe-Naruto expressway
has been in service since 1985 when the
Ohnaruto Bridge, witha main span of 876 m,
was completed.
2. Originally, the Akashi-Kaikyo Bridge
was designed forboth highway and railway,
with a main spanof 1780 m. However, the
financial deteriorationof the Japan National
Railways in the 1970s and 1980s made it impossible to plan the bridge for dual purpose, and
Structurol and
Building Boord
Structurol Panel
Poper 10434
~~
Written discussion
closes 18 October 1994
Nobuoki Furuyo,
Monoger of
Planning Diuision.
Second
Operation Bureau,
(Ex-deputy
General
Manager, Torumi
Construction Office),
Honshu-Shikoku
Bridge Authority,
Japan
Masooki Tatsumi.
Director of
Construction
Department,
Third Construction
Bureau, (Ex-director,
Torumi
Construction Office).
Honshu-Shikoku
Bridge Authority,
Japan
FURUYA AND
TATSUMI
MeM sea bwl d ToXyo s t y
N H W L Nea3y hghw high watw ltnsl
TP
?A
2P
Side view
3P
4A
Prane view
Fig. 1. AkashiKaikyoBridge:
general drawing
(dimensionsinm)
1993
286
AKASHI-KAIKYO
BRIDGE
length of the side span. The side span length
was therefore determined tobe 960 m.
10. The deck of the bridge has been
designed to be truss-stiffened in order to secure
the safety of the structurewhich inevitably has
a very low natural frequency, againstwind
action, and in order to facilitate theerection of
the deck on the
Alternative
designs
in which the deck was stiffened with a streamlined mono-box girder, such asin the case of
the Humber or Severn Bridge in the UK, did not
satisfy the requirement with regard to a flutter
Ocean Pacific
Sea
Japan
wind speed of not less than 78 m/s, unless the
bridge was designed intentionally with thicker
Kobe
steel plates than the truss-stiffenedone to raise
and the bridge
torsional stiffness. In other words, it wasfound
Kojima
that the designs incorporating a streamlined
\
mono-box girder, whose cross-section was
Tokyo
designed against ordinary stress (bylive load
or wind load), began to have bending-torsional
coupled flutter at 55-61 m/s, a speed
which
was far lower than the requiredone. Also, as
was proven in wind tunnel tests, the designs
showed significant buffetinga s well as vortexinduced oscillation, whichwere both not conlmabari
sidered negligible in respect of fatigue damage
OKINAWA
and serviceability of the bridge.
0
200
400
11. Many other new concepts of aerodynamic stability proposed by Japanese engiScale of km
neers were examined in both structural
analysis and wind tunnel tests. However, the
conclusions were not favourable either because
Fig. 3. Location of
the deck became rather heavier than the truss- from beneaththeseasurfacewithcranes,
Honshu-Shikoku
stiffened one or because the many big slots and which isa common methodin the erection of
judged
Bridges
air gaps providedin the girder to improve the box-girdertypesuspensionbridges,is
to be inappropriate.
air-flow characteristic inevitablylowered the
stiffness and thus the natural frequency. Fig. 5
13. In the case of the truss type girder, an
is an examplewhich was tested andconsidered
advanced technology for erection has existed in
to be inappropriate on account of the difficulty
Japan since the 1970s:i.e. a successive fullyinvolved with its erection, but it was evaluated splicing cantilever erectionmethod with
as being better than the othersfrom the point of planely pre-assembled blocks, shownin Fig. 6,
view of aerodynamic performance.
was adopted in 1987 for the erection of the Seto
12. It should be borne in mind with regard
Bridges on the Kojima-Sakaide route. In this
to the erectionof the girder of the Akashimethod, truss members are assembled into
Kaikyo Bridge that the straits beneath the
plane blocks in a workshop (each one is usually
bridge have a rapid tidal current and
convey
two panels in length and weighs around 1 MN)
and are then transported to the site. The blocks
heavy sea traffic. This means that the direct
lift-up operation of pre-assembled girder blocks are hoisted to deck level at the main towers and
Ad
Kobe side
1A
AwajiIslandside
2P
4A
3P
I
+O m
E
a
-50 m
-100 m
-150 m
-200 m
m
m
[1777 Kobelayer
Granite
500
looo
I
Horizontal distance: m
Fig. 4. Geological
condition beneath
Akashi Straits
287
FURUYA AND
TATSUMI
,fl,
-
B-Box
F-EIox
.&.
Fig. 5. Example of
new conceptfor
suspended deck
(dimensions in m )
cantilever erection
method
288
F-Box
are transported to erection frontson the preerected and spliced deck, whereupon they are
connected to thepre-erected truss with full
bolts; hanger ropes are then attached to this
part while the tensionin the ropes is controlled
in order to avoid over-stress. This
method can
impose full stiffnessof the girderfrom the
beginning, a fact which contributes to an
increase in the stability against wind action
during erection, thereby avoiding the kind
of
mishap thatoccurred during the erectionof the
Forth Road Bridge, when truss members that
were not yet connected collidedin the wind and
sustained some damage.
14. In the design of a long span suspension
bridge, the sag/span ratio is one
of the most
important factors. In the caseof the AkashiKaikyo Bridge, the ratiohas been determined
as 1/10, following the developmentof highstrength wires witha breaking strength of
1.8 GPa. The allowable stress hasbeen deter.
AKASHI -KAIKYO
RRTDGE
TP + 52.0
dia. 85.0
Slurry wall
Fig. 7. Structure of
1A (Kobe-side
anchorage)
(dimensions in m)
289
Downloaded by [] on [17/11/16]. Copyright ICE Publishing, all rights reserved.
FURUYA AND
technical institution on behalf of the contractor cosity for the desegregation of the coarse
toaidthelatterstechnicalassessment
in
aggregate.Afterthreeyears
of researchand
respect of the future plan of the work. Fig. 9 is investigation, including tests with a full-size
an example of the monitoring result(a compari- test cast, a concrete with the following characson of the data from the shallow to the deep
teristics was developed.6
excavation stages).
( a ) The specific design strength at the age of
Body of anchorages
23. The body of the two anchorages located
AKASHI-KAIKYO
BRIDGE
kgflcm'
500 1500
1000
Measuring position
(Kgf/cm2 l 0 0 kPa)
2P
---
__
Outside
Inside
- - Estimation
kgflcm'
Tension
15010
---_
.
_ / - -
Fig. 9. Example of
measurement on
retaining wall taken
during excavation
at 1A
291
Downloaded by [] on [17/11/16]. Copyright ICE Publishing, all rights reserved.
FURUYA AND
TATSUMI
4
Fig. 10. View of
anchorage work at I A
in December 1993
concrete pipes, a s shown in Fig. 11. Five to six
pipes are arranged at approximate intervals
of
5 m in one concreting block, which has a
maximum plane area of 1200 m; the gate
valves from which the concrete is poured are
attached along the lengthof the pipe at 5 m
intervals. On each pipe, the numberof gates
open at any onemoment is always one; the
opening of one gate and the closing
of the other
are programmed to occur automatically at
about 1 min intervals. The casting speed
through one pipe is about40 m/h; and the pro.
duction volumeof one centralized on-site conCrete plant is approximately 240 m3/h. The
total volume of this concrete castfor the two
anchorages was380 000 m, and it was completed by April 1994.
26. It is also noteworthy that for the outer
form of the bodywork, which is not removed,
precast concrete panels were used.The main
purposes of this are: precast panels whose
concrete hasbeen carefully compacted in a factory
have a superior surface than on-site cast mass
concrete, a fact which contributes towards
raising the appearanceof the anchorages to be
located in a future park; the panels made
from
ordinary cement can protect low-heat concrete,
in which the cement content of the clinkeris
less than 30%, from a marine atmosphere.
Rebars used in the panels are epoxy-coatedin
order to resist penetrationof chloric ion.
of research, investigation and on-site experimental work was conducted to establish the
method, while the constructionof many underwater foundations were carried out successfully
on the Kojima-Sakaide route, which was
another of the Honshu-Shikoku Bridges and
was completed in 1988.
28. The method used on the KojimaSakaide hasbeen called the laying-down
caisson method, although a foundation constructed by this method is not, in fact, a caisson
(a deep rigid foundationwhich has aneffective
embedment), but a spread foundation. Themain
characteristics of this method are asfollows.
Excavation and the buildingof a form for
underwater concrete are split into separate
procedures: i.e. excavation up to bearing
layer is carried out initiallyat open sea
with a grab dredger, concurrent with the
building of a steel form (conveniently
called a caisson but not a structural
member) in a shipyard.
As a resultof this separation, themethod
of excavation and the machineryfor it are
not restricted by the sizeof the dredging
wells of the caisson, thereby enabling the
work period to be shortened while a larger
volume of the excavation is completed.
After the completion of the excavation, the
steel caisson is towed to the site, sunk with
high accuracy to theposition specified in
the design, whereupon underwaterconcrete
was cast into the bulk
of the foundation a s
rapidly a s possible and ordinary reinforced
concrete was applied to the top part to
complete the foundation. Fig. 12 shows the
sinking operation of a steel caisson in 1989
at the Akashi Straits.
AKASHI-KAIKYO
RRIDGE
Table 1 compares and contrasts the layingdown caisson method used for the KojimaSakaide and the Akashi-KaikyoBridges.
29. In the case of the excavation for the
main piersof the Akashi-Kaikyo Bridge, the
grab dredgers used achievea maximum dredging capacity perblow of 32.5 m, but a grab
weighing 2 MN with 17.5 m was used for the
excavation of the Kobe layer. Although such
gigantic dredgers (one vessel for onepier) were
used, the excavation had to be halted
when the
tidal speed exceeded about 4 kt (approximately
2 m/?,). The vessels had a mooring capacity up
to 8.5 kt when the sideof the ship was clear,
but 5.5 kt when a fully-loaded barge to carry
out the dredged material was
moored at its
side. This grab dredging must be carried out
accurately (specified value = k50 cm) to allow
the caisson to be sunk within the permitted
inclination or height error. This requirement
was fulfilledby the following means: the useof
a special operation in which a flat-edged grab
was closed while it was being lifted up; the limiting of the work toweak tide; the repeated
measuring with a multi-fan ultrasonicbeam
sensor; and so on.
30. With regard to concreting, a concrete
plant mounted on a large barge was constructed for each pier by the contractors. This
plant barge could store the material equivalent
to 9000-10000 m of the concrete, and could be
moored at the site with many anchor
lines.
Material was supplied duringweak tide, and
Fig. 11. View ojconcreting with highly workable concrete
then underwater concreting was carried out
on
Items
Type
Plain dimension
Bottom of foundation
Original sea depth
Maximum tidal speed
Geological condition
Excavation method
Finishing the bottom
Weight of mooring anchor
Diameter of mooring anchor rope
Steel weight of a caisson
Method of underwater concreting
Volume of underwater concrete
Work period for foundation
-14
-22 m
1.0 m/s
2P of Akashi-Kaikyo Bridge
dia. 80 m (=5020 m)
+ 45 m
3.5 m/sec
Akashi-layer (sand andgravel)
Dredger
Flat teeth bucket
1000 ton (10 MN)
6 mm
120 mm
repacked concrete
!33000m3
ibout
years
FURUYA AND
TATSIIMI
three successive days and nights during strong reinforced concrete, into which tower anchortide to complete the
volume. As the steel
frames to fasten the baseof the tower legs were
caisson was a double-walled structure-a botembedded.
tomless centre core part and an outer fringe
part with a bottom to generatebuoyancy-the
Development of high-strength wire
core was cast first step by step, with an approx-31. On account of the fact that a suspension
imate lift of 4 m, and then the fringe, which had bridge can span a long distance by being hung
a small plane area, wascast from the bottom to
from the cable, the strengthof the cable
the top while bulkheads to increase the
material strongly influences designof the
caissons stability while afloatwere utilized as
bridge. In Fig. 13,the history of the breaking
a form of partitioning. The uppermost part
strength and the allowable stress
of the wires
from -10 m to + l 0 m of the pier is ordinary
used in famous suspension bridges isshown. It
190
C.Tensilestrength
-Mount Hope
-Benjamin Franklin
Verrazano-Narrows
(Kgf/mm2
1900
1910
294
1950
192019401930
1960
Year
+ 10 MPa)
,1970
19901980
2wO
AKASHI-KAIKYO
BRIDGE
is obvious that the strength had not
been
improved much between the 1930s and the
present day.
32. In the case of the Akashi-Kaikyo
Bridge, however, an improvement in the
strength was requestedin order to refine the
design of the entire bridge,as is discussedin
0 14. The enhanced strength of the wire was
achieved by adding more silicon to conventional high carbon wires. The contentof silicon is
increased from 0.12-0.32% to 0.8-1.0%. This
method does not decrease productivity, ascom.
pared with a method in which more manganese
and chrome are added to raise the strength, nor
lower the strength after galvanization with
zinc, as compared with a method in which more
carbon is added or the original wire (usually
around 12 mm) is drawn into a finer diameter
(less than 5 mm).
33. As the main cables of many of the suspension bridges in the Honshu-Shikoku Bridge
Project have been constructed by meansof the
' Prefabricated strand method', the cables of the
Akashi-Kaikyo Bridge are also going tobe
erected by this method. In Japan, the number
of
wires not permitted to have any jointshas been
127 for suspension bridges, and the numberof
strands in the main cable of the bridge was
designed at 290 (Fig. 14). It was therefore
decided that the diameterof each individual
wire was to be 5.23 mm so as to avoid any
redundancy. The weightof a strand with a
length of approximately 4 km is about
900 000 N.
34. When the prefabricated strand method
is adopted, eachof the strands mustbe given
an exact lengthin the factory (for the bridge:
4074.284-4071.402 m), although a few adjustments after erection are possible.An essential
prerequisite for this is the making
of a 'gauge
wire ' which designates not only the entire
length but also such important points as the
centre of each span, of the saddles, and so on.
Since the constructionof the Ohnaruto Bridge
in the early part of 1980s, the method used for
this has been the ' magnetic measurement
system ', which is a system akin to a tape
recorder. In this system, an objective wire
which corresponds to the tape runs through two
sets of head : one is a marking head, and the
other is a detecting head whose distance is
exactly 5 m. The first marking head gives the
wire magnetic mark which is tobe read by the
second detecting head; the latter head sends a
signal to the former head to mark
one more as
soon as it detects the mark on an incoming
wire. The accuracy of measurement of this
system is about 1/30000.
Cable section
"
Conclusions
38. Construction work for the AkashiKaikyo Bridge has been progressing smoothly
so far, asis shown in the figures, with the
implementation of the various technical innovations that are discussed. The first stageof the
cable work as well as the first link between the
two shores-spanning the pilot rope-were
finished on 10 November, 1993, and thiswill be
followed by the erection of the catwalk and the
main cables in 1994. The erection of the stiffening girder will be started in the spring of 1995,
working towards the scheduledcompletion date
of March 1998.
295
Downloaded by [] on [17/11/16]. Copyright ICE Publishing, all rights reserved.
FURUYA AND
Fig. 15. V i e w o f w i n d
tunnel test w i t h f u l l
model
References
using
foundationwall
for concrete
strength
ternary blended cement with intermixtureof blast
A u r n o ~ mAkashi.
furnace slag andfly ash. Proc. 4th Int.Conf. on
Kaikyo Bridge Engineering Note.Honshu-Shikoku
Fly Ask, Slag and Natural Pozzolans in Concrete.
Bridge Authority, Tokyo,1991.
Istanbul. May 1992, 2,1451-1469.
MIYATAT., MATsuMom H. and YASUDAM. Circum.
6. FURWA N. et al.Basic research on highly workstances of wind-resistant design.J. Wind Engng
able concrete with low-heat cement and large
&/nd.Aerodyn., 1992,41-44,1371-1382.
amount o/limestone powder. Japan Society of
FUJINO
Y. et al. Wind tunnel studyof long-span
Civil Engineers, Tokyo, 1994, Concrete Library
suspension bridge under smooth and turbulent
International 23.
flow. J. Wind Engng, 19%. No. 37, Oct.
7. KANAZAWA
K., YWA K. and so00 S. Properties
FURWAN.,YAUAOKA
R. and PAULSON
P. C. The
of low-heat generating concrete containing large
Akashi-Kaikyo Bridge Project. Construction
volumes of blast furnace slag and fly
ash. Proc.
Congr. of ASCE. San Francisco,Feb. 1993 (to be
4th Int.Con/. on Fly Ash, Slag and Natural Pozpublished in/. Construc. Engng & Mngmt Am.
zolans in Concrete, Istanbul. May 1992,1,97-115.
Soc. Ciu. Engrs, 1994).
KASHIMA
S., FURWAN. and YAMAOKAR. High-
1. HONSHU-SHIKOKU
BWE
2.
3.
4.
5.