ANNEXURE-1

List of Activities/Mile stone of Auxiliary Boiler (1x35 tph)


1. Auxiliary Boiler Lighted up for 1st time

on :16.08.2013

2. Auxiliary Boiler Alkali boil-out completion on:26.11.2013


3. Auxiliary Boiler Steam blowing completion on: 24.12.2013.

4. Auxiliary Boiler Safety valve floating and all the commissioning


activities/mile stone of Auxiliary Boiler are completed on: 31.12.2013

The protocols of the above activities are enclosed for your kind reference.