Академический Документы
Профессиональный Документы
Культура Документы
2m
128.50
125.50
F.T.L ----------------------
M.W.L------------------
126.50
For the above circular opening assume a barrel size of 65cmx 75cm high . The minimum size of
the barrel is 60x75cm high.
Item no 2. Rectangular barrel
The figure shows a vertical section through the top of earth bund. It cuts the rectangular barrel at,
but it cuts the earth bund along the barrel
Internal six of the barrel has been assumed as 65cmx75cmhigh. Assume cross section of side wall
as shown , which will be checked for stability. Assume density of earth as 2200 kg/ m 3 , of
mansory as 2100 kg/ m3
a) Design of R.CC roof slab
Clear span = 0.65m bearing width= 0.2m
Effective span =l=0.85m
Assume 15cm thick slab
Self weight = 0.15x2500= 375kg/m
Weight of earth= 5.6x2200= 12320kg/m
Total mdl= 12695kg/m
M= wl2/8 = 1146.5kgm.
For M20 and CTD bars k=9.1 j=0.9
= 1146.5x102/9.1x100 = 11.22cm
Ast= = 4.62cm2
Spacing of min 12mm diameter = 1.13x100/ 4.62 = 20cm c/c
Dist steel 0.12/100 ( 100x15)
Spacing of min 8mm diameter
/ 1+ sin
earth Z
Magnitude
of V (kg)
H (kg)
force in kg
arm Moment
from A (m)
567
0.7
W2
(0.5x0.9)2100 945
0.25
W3
(1/2x
0.9
W1
(1/2x
Lever
about A
0.6x0.9)2100
597
0.6x0.9)2200
W4
(0.9x5.6)2200 11088
0.65
Wl/2
0.1
3993
Y= 0.439m
= 6665
12695x1.05/2
Pa
3993kg
/ 1+sin
= 1/3
At ri = 0.625m Fr=0
At re=1.325m Fr= Pa= 6019 kg/m2
a+ b/(0.625)2 = 0
a+ b/(1.325)2 = 6019
b= -3024, a= 7741.5
The hoop stress is given by fh= a- b/r2
At inner radius ri = 0.625m
by fh= 7741.5+ 3024/(0.625)2 = 15483 kg/m2< 60t/ m2 (hence safe).
A rectangular cistem is provided at the downstream of the barrel to decipate the K.E of water. The
size of the cistem is as shown in the drawing. The top of the cistem wall as well as the
downstream wall will be kept at the canal TBL.
The water faces of all walls will be kept vertical.
Note. The top of the floor of the barrel is at 122.00, which is the sill level. This c.c floor will be
extended to form the foundation for all walls such as the side walls of the barrel, cistem walls and
upstream wing walls ( but not for head walls) Thus the bottom of all these walls will be at 122.00.
Note . The figure shows the rough layout plan of the tank sluice as indicated below.