Site: Kalpakkam
Unit No: 1x500 MWe PFBR Project
FORMAT NO:
QMS/SR/12F24/01
Date:28.07.16
Report No:100
PROGRESS:
TURBINE:
Control Fluid System:
Governing system commissioning and Turbine control valves & stop valves
operation checking expected to be completed 26.08.16.
TDBFP-B:
Remote barring gear was completed.
Governing system- ESV stroking was completed and Control valve is to be
checked.
TDBFP-A:
Remote barring gear was completed.
Governing system- ESV stroking was completed and Control valve is to be
checked.
MDBFP:
MDBFP Pump trial run with recirculation was completed on 14.08.15.
Feed water control valve hunting problems are to be checked.
VACCUM PUMP:
Vacuum pump motors 2 nos. trail run completed on 20.11.14.
Suction lines modifications are to be completed.
Interlocks and protection logics are to be demonstrated to BHAVINI.
Condenser Vacuum Pump:
Both the vacuum pump trial runs were completed. Tank safety relief valve is to
be replaced.
POWER CYCLE PIPING & PIPING:
SGB-2 side NRV passing problem was rectified on 19.07.2016.
In SGB-2 side BABCOK valve passing problems are rectified of SG
module-5,6,8.
TYCO Vlave in SGB-2 side passing problems are rectified.
SGB-2 side depressurization system Electrical Motorised valves passing
CEP
Auxiliary Boiler:
Master Pressure control and PG test to be completed.(Awaiting
Customer clearance)
DOSING SYSTEM:
All dosing pumps trial run were completed.
COLTCS and DEBRIS FILTER Drives :
Both the debris filters are jammed condition and are to be rectified.
TRANSFORMER:
1. 4 Nos. GT to be commissioned
2. 2 Nos. UAT to be commissioned
PROGRAMME
1. CEP-A trial run is planned To-day. BHEL (T) service engineer is in
site to rectify the CEP-A discharge valve problem.
2. SGB-2 side depressurization system Electrical Motorised valves
passing problems are rectified. SGB-2 module SG-7 hydro test is
planned to-day by BHAVINI. During hydro test the valve passing
problem of Babcock valve and MOV are to be checked.
3. Haridwar-TG scope C& I instruments loop checking are under
progress.