Вы находитесь на странице: 1из 49

PTT PUBLIC COMPANY LIMITED

RATCHABURI WORLD
COGENERATION COMPANY LIMITED

GAS PIPELINE AND GAS METERING AND REGULATING STATION PROJECT

02/04/13

Issued for Construction

WS

JR

NP

13/02/13

Issued for Approval

WS

JR

NP

Rev.

Date

Description

Prepared
By

Checked
By

Approved
By

CONTRACTOR:

CONSULTANT:

SIAM RAJATHANEE JOINT VENTURE

UNITY ENGINEERING AND CONSULTANCY


SERVICES CO.,LTD.

DOCUMENT TITLE:

MECHANICAL COMPLETION PROCEDURE

DOCUMENT NO.:

PR-P-1102.21-4012-004

REVISION:

DOCUMENT CHANGE RECORD

Rev

Date

Prepared/
Revised
By

Reviewed
By

Approved
By

Description

13/02/13

WS

JR

NP

Issued for Approval

02/04/13

WS

JR

NP

Issued for Construction

REVIEW STAMP
E. Work may proceed.
F. Work may proceed. Submit for Construction
Documents.
G. Revise and Resubmit. Work may proceed
Subject to incorporation of changes
indicated.
H. Revise and Resubmit. Work may not proceed.
I. Review not required. Work may proceed.
Acceptance in any of these categories shall be in no way
relieve the Contractor/Supplier of its responsibility for the
due and proper performance of the Work in accordance
with the Contract/Purchase Order.
Name:
Sign:
Date:

COMMENTS

TABLE OF CONTENT
ARTICLE

PAGE

1.

SCOPE.......................................................................................................................................... 4

2.

DEFINITIONS................................................................................................................................ 4

3.

ACTIVITIES................................................................................................................................... 4

4.

CHECKLISTS, FORMS, AND LOGBOOKS..................................................................................5

5.

SCHEDULE................................................................................................................................... 6

6.

VENDOR REPRESENTATIVES.................................................................................................... 6

7.

COMPLETION OF WORK............................................................................................................ 7
MECHANICAL COMPLETION

NOTICE OF COMPLETION

MECHANICAL COMPLETION CHECKLIST OUTLINE

10

MECHANICAL COMPLETION CHECK LIST

12

FORM TR-1:

PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 1/2)...............36

FORM TR-1:

PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 2/2).............37

FORM TR-2:

HYDROSTATIC TEST RECORD.......................................................................38

FORM TR-5:

MEGGER READINGS - GROUND RESISTANCE RECORD............................39

FORM TR-6:

ELECTRICAL TEST RECORD...........................................................................40

FORM TR-7:

SAFETY AND RELIEF VALVE RECORD...........................................................41

FORM TR-8:

INSTRUMENT TEST RECORD (Page 1/2).......................................................42

FORM TR-8:

INSTRUMENT TEST RECORD (Page 2/2).......................................................43

FORM ME-2:

VESSELS........................................................................................................... 44

FORM EE-5:

CIRCUIT BREAKERS........................................................................................45

FORM EE-8:
LIGHTING PANELS, INSULATION RESISTANCE, REMOTE TERMINAL
DISPLAY (RTD) ........................................................................................................................... 46
FORM EE-9:

ALARM CIRCUIT OPERATION TEST...............................................................47

FORM IE-1:

CONTROLLERS................................................................................................48

FORM IE-2:

DIRECT CONNECTED RECORDERS AND RECORDER CONTROLLERS.....49

FORM IE-3:

ELECTRONIC CONTROLLERS, RECORDERS AND INDICATORS................50

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

1.

SCOPE
This Specification describes and clarifies the requirements for mechanical completion and provides a
format for the Contractor to carry out these activities. It is intended to expand and supplement, but not
to supersede the general terms and conditions of the Contract concerning Completion, and
Acceptance.

2.

DEFINITIONS
For the purposes of this specification, the following definitions shall apply:
Owner

means

Ratchaburi World Cogeneration Company Limited.

Advisor

means

PTT Public Company Limited.

Project

means

Gas Pipeline and Gas Metering and Regulating Station


Project.

Consultant

means

Unity Engineering and Consultancy Services Co., Ltd.

Contractor

means

Siam Rajathanee Joint Venture

Vendor

means

The party which supplies materials, equipment, technical


Documents/drawings and services to perform the duties
specified by Contractor.

3.

ASME

means

The American Society of Mechanical Engineers.

ANSI

means

American National Standards Institute

ACTIVITIES
3.1

Mechanical Completion
Means fabrication, construction, physical installation, testing, inspection, and system
verification is complete, such that the Facilities are ready for introduction of product. Activities
associated with the term pre-commissioning are included in mechanical completion activities
and will not be described separately. Mechanical Completion shall also mean that all
requirements have been met to begin Commissioning activities, including submittal of
commissioning plans and documentation. In general, Mechanical Completion shall include
the activities listed below. More detailed activities are included in the attached checklists.

All civil work shall be complete, including fencing, final grading, and surface
preparation

Piping systems shall be checked against designs, cleaned, tested for pressure
ratings and tightness, dried, inerted, and restored to tight condition in readiness for
operation

All equipment shall be installed, assembled, inspected, calibrated, adjusted, coldaligned, tested, lubricated, and cleaned as necessary to be ready for operation

Elements such as strainers, temporary strainers, and filters shall be installed, cleaned
or replaced so that a clean element is in place for commissioning

All electrical systems shall be installed, energized, and tested for continuity, insulation
resistance, ground fault, and mechanical operation

All instrumentation shall be installed, loop checked, set to proper set-points, and
calibrated

Instrumentation loop checks to the SCADA master shall be completed

All modifications and upgrades to the SCADA system shall be completed

Probes, coupons, samplers, and other consumables shall be installed

Utility and safety systems shall be commissioned and demonstrated to be operational

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

3.2

All painting, coating, and insulation work shall be completed

All changes and modifications shall be incorporated

All functional tests of individual systems shall be performed.

All work shall be verified to be in accordance with the proper Specifications, Drawings
(Owner and Vendor), codes, and standards

Deficiencies identified during Mechanical Completion activities shall be remedied


prior to the commencement of Commissioning

Mechanical Completion documentation shall be completed and signed

Partial Activities and Exceptions


With the approval of Owner, Contractor may subdivide the overall facilities into units and
perform mechanical completion activities on these units separately. The units so selected
shall be logical, well defined, and beneficial to project scheduling. No special consideration
shall ensue as a result of the division of the Facilities into units and Contractual conditions
and guarantees for Mechanical Completion of the overall Facilities shall remain in force
regardless of the state of activities on the individual units.
Contractor may give notice of mechanical completion of a unit with a detailed list of
exceptions for items, which are incomplete, defective, or otherwise not in accordance with the
Contract. This list shall include all outstanding mechanical completion items and shall show a
schedule for completing each exception.

4.

CHECKLISTS, FORMS, AND LOGBOOKS


4.1

General
Mechanical Completion checklists and forms will be used for all significant items to be
erected, installed, and/or modified under the Contract. Contractor shall prepare these
checklists and forms following the general format of the attached samples (mechanical
completion only - Contractor to generate forms and checklists for commissioning), modified
as necessary for individual equipment and systems. Contractor shall submit these forms for
Owner approval at least thirty days prior to initiating the inspection, test, and verification
activities covered by the checklists and forms.
Contractor shall prepare and use logbooks for all activities carried out during Commissioning.
At a minimum, Contractor shall maintain a general logbook noting for each shift the personnel
onsite, events, activities, process conditions and changes, and results of any tests or
inspections. Contractor shall also maintain records of system status (such as valve position
and equipment hand-off-auto position) and temporary conditions (such as jumpers
installed/removed and valves out of service). To allow accurate reconstruction of events in the
case of an upset condition, Contractor shall have available onsite a camera and shall record
instrument readings, control panel readings, and other relevant information.

4.2

Procedure
The checklists and forms prepared by the Contractor and as approved by Owner shall be
used as sign-off sheets for the permanent record of inspections, tests, and mechanical
completion activities. These shall be signed by Contractor, Owners representative, and any
Subcontractors or Vendors as applicable. No system or unit shall be considered mechanically
complete if any items included in the checklists or forms are not fully signed.
Checklists, forms, reports, or other special documentation required by Vendors or Owner
shall be completed and considered a part of mechanical completion in the same manner as
above. Copies of these documents shall be reproduced by the Contractor in as many copies
as required and shall become part of the permanent project records.

4.3

Introduction of Natural Gas


Contractor shall recognize that the introduction of natural gas to any portion of the Work is a
hazardous activity requiring the full knowledge and approval of all parties involved, including

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

Contractors staff, Owner and Owners representatives, and the owners of the existing
facilities. In addition, the following criteria shall be met for introduction of natural gas:

The unit shall be mechanically complete, with any exceptions approved by Owner as
described above

All utility and safety systems, such as firewater, vent and flare, closed drains,
instrument air, and electrical, shall be completed and operational

The work area around the unit is safe, secure, and clean of all debris, unnecessary
equipment, and excess materials

A work permit system for hot work, cold work, vessel entry, etc shall be in force

Detailed emergency and evacuation procedures shall be approved by Owner for such
events as fire, loss of power, loss of instrument air, overpressure, and excessive
condensate buildup

Procedures for shutdown and standby shall be approved by Owner

In the case of a threat to the safety of personnel or equipment during commissioning, Owner
may require Contractor to halt activities, place the Facilities in a safe condition, and remedy
the cause of the threat if within the power of the Contractor. If product has been introduced,
such work may include depressurization and/or purging to render the Facilities safe.
5.

SCHEDULE
As required by the Contract, Contractor shall prepare complete schedules for mechanical completion
activities. Schedules for such units shall allow the contractually defined dates to be met.

6.

VENDOR REPRESENTATIVES
6.1

Mechanical Completion
Contractor shall schedule vendor representatives to be onsite to aid in mechanical
completion activities as necessary. At least 60 days prior to Mechanical Completion,
Contractor shall submit for Owners review a list of vendor representatives to be brought to
the site and a schedule showing their planned arrival and departure dates. Owner may
request additions to this list. Notwithstanding the planned departures shown on this schedule,
each vendor representative shall remain onsite until his equipment is fully commissioned.

6.2

Training
As required to meet the Contractors requirements for training, the scheduling for vendor
representatives shall also include ample time to provide specialized training to Owner on the
vendors equipment. The vendors representative shall bring sufficient training materials, aids,
and documentation as needed to complete the training requirements.

7.

COMPLETION OF WORK
Completion of the Work and the sequence of Notice and Acceptance shall be as defined in the
Contract. Contractor shall remain fully responsible for the Facilities and all expenses incurred
between the Start of Regular Operations and Owners issuance of the Certificate of Acceptance. The
following conditions for completion shall be met, at a minimum:

Facilities shall be mechanically and structurally complete, inspected, tested, and operable at
full design pressure

Facilities shall be in a tight and clean condition, and otherwise prepared as described in the
Contract

All checklists and documentation shall be complete and signed

Contractor shall have issued the Notice of Start of Regular Operations to Owner.

All required manuals, accounting records; quality control reports and documents, as-built
data, and other documents shall have been prepared and delivered in accordance with the
Contract

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

All deficiencies identified by Owner shall have been remedied

Any disturbed land and facilities shall have been appropriately restored and all required
landscaping shall be completed

All Contractually required training shall have been completed

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

MECHANICAL COMPLETION
TO:

DATE :
UNITS : ____________
SUBJECT: Mechanical Completion and
Acceptance

ATTN:

REF NO:

Gentlemen:
In accordance with the Contract, the following item(s) is (are) ready for commissioning:
ITEMS

EXCEPTIONS

Please sign and return two copies in acknowledgement of your acceptance.


Very truly yours,

CONTRACTOR

CERTIFICATE OF ACCEPTANCE
(Mechanical Completion)
Owner
BY
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

NOTICE OF COMPLETION
TO:

DATE :

UNITS : ___
SUBJECT: Completion of Construction and Acceptance
ATTN:

REF NO:

Gentlemen:
Work has been completed on the item(s), unit(s), facility(ies), or plant(s) listed below. This Work is in
accordance with all plans, specifications, and official instructions from Owner and articles of the Contract.
ITEMS

EXCEPTIONS

Please sign and return two copies in acknowledgement of your acceptance.


Very truly yours,

CONTRACTOR

CERTIFICATE OF ACCEPTANCE

Owner
BY
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

MECHANICAL COMPLETION CHECKLIST OUTLINE


I.

PIPING
Check list against Piping and Instrumentation Diagrams (P&IDs)
Check list against Piping Arrangement and Isometric Drawings

II.

III.

ELECTRICAL
A.

Area Classification

B.

Service Conditions

C.

Circuit Breakers, Switchgear and Motor Control Center

D.

Main Power Supply

E.

Auxiliary Power Supplies

F.

Wire and Cable

G.

Conduit Systems

H.

Electronic Instrument Loops

I.

Ground System

J.

Transformer or Generator Neutral Resistance Ground

K.

Lighting

L.

Control Stations

M.

Cathodic Protection

INSTRUMENTATION
A.

General Check List

B.

Inspection and Calibration of Instruments


1.

Manufacturer's Check Lists

2.

Differential Pressure Type Flow Meters

3.

Orifice Plates

4.

Differential Level Transmitters

5.

Level Switches

6.

Flow Switches

7.

Pressure Switches

8.

Temperature Switches

9.

Miscellaneous Switches

10.

Gage Glasses

11.

Pressure Gages

12.

Pressure Instruments

13.

Temperature Instruments

14.

Control Valves

15.

Safety and Relief Valves

16.

Regulators

17.

Instrument Piping and Tubing

18.

Analytical Instruments and Specialties

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

IV.

19.

Receiver Instruments and Control Panel

20.

Annunciators

21.

Annubars

22.

Detection and Safety Devices

23.

Interface to SCADA

EQUIPMENT
Vessels, Tanks and Drums

V.

FLUSHING AND CLEANING

VI.

OTHER FACILITIES
A.

Safety and Fire Protection

B.

Concrete Placement and Testing

C.

Roads, Fences and Gates

D.

Soil Compaction

E.

Waste Disposal

F.

Documentation

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

MECHANICAL COMPLETION CHECK LIST


This Mechanical Completion Check List is intended to assist Contractor to develop the documentation
required to prepare the work for Commissioning. Items not explicitly listed but reflected in specifications or on
drawings shall from part of the scope of this activity. Contractor shall be responsible to ensure that all
components and systems shown on the various contract documents are properly verified after incorporation
into the work to the ultimate satisfaction of the Owner.

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM
111111112.2

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

PIPING

Prior to hydrostatic test of station piping, it is


necessary to check the station for complete
conformance with the final piping and instrumentation
diagrams. The final inspection must include the
Owner operations representatives. It may be a
combined operations, contractor and engineering
effort. This check will help to reveal any errors and
prevent retest of the piping in case omissions and
errors are found and corrections have to be made. A
thorough check must be made of all piping supports,
spring hanger settings and spring support settings,
anchors and welded attachments. If any welded
attachments are found to be incorrect and must be
changed, or if some have been omitted and have to
be added, this should be done prior to hydrostatic
testing if possible. If this is not possible, the welding
performed after pressure test must be thoroughly
supervised and carefully inspected after completion.
3. All piping systems must be checked for proper
venting and draining. Check for proper slope
where required.

_______

________

________

4. Is there any configuration not previously


observed or corrected likely to result in hydraulic
shock (water hammer), slug flow or vapor
binding?

________

________

________

5. Check accessibility of all operating valves.

________

________

________

6. Check all valves for correct body material, trim


and packing.

________

________

________

7. Check pipe valves and fittings for specification


material, correct size, type, pipe schedule, flange
rating, and metallurgy.

________

________

________

8. Check all bolted joints for proper studding, bolt


length and gasket material.

________

________

________

9. Check for expansion and vibration. Check for


adequate, proper and safe supports, undue
stresses and alignment.

________

________

________

10. Operate all hand valves. Check for chain wheels


where required, platforms and ladders. Grease
all stems and hand wheels.

________

________

________

11. Check all check valves for proper flow direction.

________

________

________

12. If internal lining or sleeves are specified, are they


in place? Any wear plates left out?

________

________

________

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

13. Has stress relief been performed where required?


If cold springing specified, has this been
checked?

________

________

________

14. Check connections and branch piping for proper


reinforcement.

________

________

________

15. Check to see that unusual or excessive piping


loads and temperature strains have not been
imposed on pump flanges.

________

________

________

16. Check all lubricated valves for proper lubrication


as recommended by the manufacturer for the
service in which the valve is to function. Verify
standardization with depot personnel.

________

________

________

17. Check installation and stroke of valve operators


and their lubrication and limit settings.

________

________

________

18. Check motor valve settings for proper support


accessibility.

________

________

________

19. Blank off all relief valves prior to testing piping


systems.

________

________

________

20. Hydraulically or hydrostatically test all pipe in


accordance
with
applicable
codes and
specifications and complete Owner Form TR-1.
Provide hydrostatic test record, such as form
TR-2 to supplement Owner form, properly
witnessed by Owner.
Do not test through
instruments or rotating equipment.

________

________

________

21. Perform any special tests required by the


Contract specifications or drawings. Complete
any required records.

________

________

________

________

________

________

________

________

________

________

________

________

22. Has blowing and/or flushing been performed?


Most debris and dirt should have been routinely
removed during construction. Avoid flushing dirt
and debris from one section to another where it
may become lodged. Do not flush into instrument
take-offs.
(See Flushing and Cleaning,
Section V).
23. After flushing is complete and piping
reassembled, check for installation of start-up
strainers on pumps as specified by the drawings
and specifications. Strainers must be in place
before equipment has final alignment check.
Check and remove any blinds used during
construction and test.
24. Check to see that proper orifice plates, pressure
gauges, sample valves, thermowells and other
such accessories are installed as per drawings
and specifications. Orifice plates should be
installed after prestart flush.

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

25. Check to see that all insulation, whether for


process, noise, or personnel protection required
at start-up, is installed.

________

________

________

26. Is all sentinel drilling (tell-tale holes) complete?

________

________

________

27. Special procedures are required when air or


moisture must be removed or excluded. Has this
work been performed?

________

________

________

28. Checks if Stamp and data reports that are


required for API 5L Piping Standards are in place.
Check if ASTM data reports that are required are
in place.

________

________

________

29. Make the necessary tie-ins at the unit limits as


required by the drawings and specifications.

________

________

________

30. Prepare operating (live) systems for safe tie-ins.

________

________

________

________

________

________

31. Install car seals or locks on valves designated as


car sealed or locked valves. Check and record
position of all car sealed or locked valves.

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

PTT

WITNESSED:
OTHER

3.32
ELECTRICAL
Contractor
shall
prepare
a
comprehensive
Mechanical Completion form for each set of electrical
connections and electrical loops to supplement:
instrument data sheets, including electrical wiring and
electrical connections to equipment furnished for the
Work.
Contractor shall follow the requirements in the
Electrical Installation Specification; Vendor supplied
instructions, instruction provided in this section and
directions received from Owner.
33.

Area Classification
Check that all equipment is suitable for the
relevant area classification.

________

________

________

Service Conditions
Check that all material meets the conditions
specified in the plan drawings.

________

________

________

1. Equipment shall be visually inspected for damage


and missing parts, and thoroughly cleaned of any
dirt, debris or foreign material accumulated during
construction.

________

________

________

2. All field wiring shall be checked for connection to


proper terminals.

________

________

________

3. All components shall be megger tested (600-volt


megger) minimum reading to be one (1)
megohm, before being energized.

________

________

________

4. Make continuity checks of all circuits simulating


actual operating conditions as far as possible
without energizing equipment.

________

________

________

5. Verify that instruments, instrument transformers,


relays, fuses and other devices are of proper
type, size and rating, in accordance with relay
and fuse coordination information provided.

________

________

________

6. With breaker in test position, test operation with


local, remote and manual operation.

________

________

________

________

________

________

________

________

________

________

________

________

34.

C.2 Circuit Breakers, Switchgear and Motor Control


Centers

7. Secure approval
equipment.

of

Owner

to

energize

8. Induction type relays and other protective devices


shall be set and tested per manufacturer's
recommendation.
9. All seals in conduit shall be checked to determine
if installed correctly and properly filled with
approved sealing compound.
10. Fences and other enclosures for high voltage

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.
apparatus must be complete and locks installed
on gates.

PTT

WITNESSED:
OTHER

________

________

________

4. Before closing main breaker, check phase rotation


and voltage.

________

________

________

5.

________

________

________

7. Check battery and charger for damage and check


electrolyte for level and specified gravity. Follow
manufacturer's pre-commissioning instructions.

________

________

________

8. Check emergency generator and automatic


transfer equipment for automatic starting,
generation and transfer with simulated loss of
normal power.

________

________

________

9. Check UPS static "no-break" power system for


AC and DC input voltage and check that output is
"no-break" by simulating loss of AC supply and
loss of battery.

________

________

________

________

________

________

________

________

________

13. All high voltage cables (above 600 volts) shall be


given a high potential test according to
manufacturer's instructions. This test shall be at
a voltage not less than IPCEA or AEIC standard
voltage test. Cable shall be tested on reel as
soon as possible after delivery and again after
installation (DC Volt to be applied 10 min.).

________

________

________

14. Cable runs shall be tested with a megger prior to


high-potential test.

________

________

________

D.3 Main Power Supply

Energize feeders.

E. 6Auxiliary Power Supplies

F.10

Wire and Cable

11. 600-volt wiring and cable shall be inspected for


mechanical defects at time of installation. Wire
with damaged or non-concentric insulation shall
not be used. All 600-volt wire shall be tested with
a megger and shall show minimum reading as
indicated in (2) to ground or between each wire
and all others in a common conduit or raceway.
12. The insulation resistance will vary with conditions;
the following should serve as a guide:
Wire Size
Insulation Resistance
#12 & smaller (4mm2)
1 megohm
#10 to #8 (6/10mm2)
500,000 ohms
#6 to #2(16/35 mm2)
400,000 ohms
#1 to #4/10 (50/95 mm2)
300,000 ohms
250 thru 750 MCM (120/300 mm2) 200,000 ohms

15. All potheads or cable terminations installed on the


site shall be given the same high potential test as

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM
the cable to which it is attached.
16. Complete Form EE-8 (typical) where applicable.

PERFORMED:
WITNESSED:
CONTR.
PTT
OTHER
________
________
________
________

________

________

18. Underground Check for compliance with


construction drawings.

________

________

________

19. Above Ground - Check for compliance with


detailed design drawings and the construction
specification.

________

________

________

21. Check all terminations for proper and tight


connections, check loops for continuity and
accidental ground.

________

________

________

22. Inspect all terminal boxes for drains, cable


seals and moisture.

________

________

________

23. Check for proper type RTD wire. Use Form


EE-8 (typical) if necessary.

________

________

________

24. Check power supply and fuses at control board,


control loops and field instruments. Use Form
TR-6 (typical).

________

________

________

26. The ground system should be inspected for


defective or incomplete connections.

________

________

________

27. Measure actual resistance to ground at the


ground loop or grid with a ground resistance
megger.

________

________

________

28. Check resistance to ground of all equipment


and tanks that connect to individual ground
rods. Each ground should test 5 ohms or less.

_______

________

________

29. Verify integrity of separate "instrument ground"


needs.

________

________

________

30. Complete Form TR-5 (typical).

________

________

________

32. For resistance grounding: Check grounding


transformer, resistor, current transformer, and
relay for size and rating.

________

________

________

33. Set relay in accordance with relay coordination


settings.

________

________

________

G.17

Conduit Systems

H. 20Electronic Instrument Loops

I.25 Ground System

J.31 Transformer or Generator Neutral Ground

K.34 Lighting

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

PTT

WITNESSED:
OTHER

35. All light fixtures and convenience outlets shall


be checked for proper voltage and operation.

________

________

________

36. Floodlights shall be checked at night and


directed to obtain correct lighting design
illumination levels.

________

________

________

37. Verify all illumination levels.

________

________

________

________

________

________

41. Check continuity of system.

________

________

________

42. Turn on and adjust current as appropriate


before piping is placed in service.

________

________

________

43. Balance CP circuits after piping is put in service


with pipeline CP.

________

________

________

L.38 Control Stations


39. Check out manual control stations.
M.40 Cathodic Protection

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

4.3544 INSTRUMENTATION
Contractor
shall
prepare
a
comprehensive
Mechanical Completion form to supplement each
instrument data sheet furnished for the Work
Contractor shall follow the requirements in the
applicable
Specifications,
Vendor
supplied
instructions, instructions provided in this section and
directions received from Owner.
36. General Check List
45. Check to see that specification materials
have been used in the installation of
instrument distribution piping, connecting
tubing, and fittings.

________

________

________

46. Check all instrument loops for proper


installation in accordance with the latest
approved drawings.

________

________

________

47. Check to see that all parts are accessible.

________

________

________

48. Check to see that control lines are not in


contact with hot lines or equipment.

________

________

________

49. Check to see that instrument air dryers and


filters are working properly.

________

________

________

50. Check to see that all parts, including


instrument piping and tubing, are properly
supported and protected from possible
damage due to operating or maintenance
activities in the area.

________

________

________

51. Check to see that the power to valves and


gas to instruments supplied with air by lateral
lines or tubing is ready to be filled with air.

________

________

________

52. Warning hydrotest.

________

________

________

53. All piping and tubing is to be cleaned by


disconnecting at both ends and blowing out.
All instrument air distribution piping shall
require a pneumatic test with air. Tubing
shall be tested for leaks with an air bubbler in
accordance with ISA standards.

________

________

________

54. After lines are cleaned and tested, they


should be immediately capped or connected
to the instrument to prevent any
contamination or water from entering. The
loop drawings should be used to record this
test and cleaning.
Complete Form TR-8
(typical).

________

Isolate

instruments

during

________

55. Check to see that lighting is adequate for

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

________

ITEM
operations and maintenance. Check at night.
37.56

PERFORMED:
WITNESSED:
CONTR.
PTT
OTHER
________ ________
________

Inspection and Calibration of Instruments

57. Manufacturer's Check List


2. Calibrate instrument and control system
in accordance with manufacturer's
information and instrument data sheets.

________

________

________

3. All instrument elements should be


checked against design data for
correctness of location, connection,
labeling, and range of measurement.

________

________

________

4. Check to see that all measuring


elements, control valves, or other
instruments removed for the flushing and
cleaning operation are replaced and
connected.

________

________

________

5. Operate all hand valves


instrument air supply valves.

________

________

________

6. Check to see that all electrical circuits


are tested. Grounding for safety and
shielding is to be checked.

________

________

________

7. Control valves should be tested for


proper response to their control devices
and for proper action on signal failure.

________

________

________

8. Alarm devices and automatic safety


switches are tested. Shutdown systems
are to be checked. Set all switches in
accordance with instrument data sheets.

________

________

________

9. Maintain a log of instrument calibrations.

________

________

________

10. The
calibration
of
transmitters,
controllers, etc., shall be checked to
comply and
meet
manufacturer's
guaranteed accuracys.

________

________

________

11. Each control valve shall be checked by


local pressure reduction to comply with
and meet manufacturer's guaranteed
accuracys.

________

________

________

12. Set all controllers with preliminary modes


per Vendor's documentation.

________

________

________

13.Complete Form IE-1 (typical) as required.

________

________

________

including

14. All thermocouples and RTDs are to be


checked in a single operation from the
thermocouple to the indicator at the
panel board. After disconnecting the
wires from the element, the calibration of
PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.
the indicator is to be checked at three
points or more by the use of a
potentiometer.

WITNESSED:
PTT
OTHER

________

________

________

________

________

________

a. Bench calibrate against a standard


water column manometer at three
points (zero, line 5 and line 9).

________

________

________

b. Complete manufacturer's check list.

________

________

________

a. Check nameplate data.

________

________

________

b. Check for an upstream sharp edge.

________

________

________

Measure and record bore with inside


micrometer to ensure compliance
with specifications.

________

________

________

Check material.

________

________

________

17. Bench calibrate against a standard


water column manometer at three
points

________

________

________

18. Use a precision output meter or gage


to monitor output

________

________

________

19. Fill seal legs.

________

________

________

20. Complete manufacturer's check list.

________

________

________

________

________

________

22. Check and set differential pressure types


using
standard
water
column
manometer.

________

________

________

23. Mechanically check only - through-flow


types.

________

________

________

15. Install seal fluids where


Properly seal instruments.

required.

2. Differential Pressure Type Flowmeter

3. Orifice Plates

c.

d.

4.16
Differential
Transmitter

Pressure

Type

Level

5.21
Level Switches
Check mechanical movement against output
on float or displace types. No calibration
required.]
6. Flow Switches

7.24

Pressure Switches

25. Check using a hydraulic or dead-weight

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

test and set to the required alarm and/or


trip point.

________

________

________

26. Set receiver types to the required trip


point using a precision pressure gage.

________

________

________

________

________

________

________

________

________

________

________

________

31. Install as received.

________

________

________

32. Clean and check illuminators and check


protectors and other accessories.

________

________

________

33. Do not replace any broken glasses


without proper instruction and torque
wrenches. Clean broken glass from
piping.

________

________

________

11.34 Pressure Gages


35. Gages are subject to construction
damage and should not be installed until
immediately prior to commissioning.

________

________

________

36. Do not calibrate direct connected,


bourbon-tube type gages, but where
required zero instrument prior to
installation.

________

________

________

37. Receiver-type pressure gages shall be


three-point calibrated using a precision
pressure gage and precision air
regulator.

________

________

________

38. Draft gages, diaphragm type shall be


three-point calibrated using a water
column manometer.

________

________

________

39. Glass tube manometers and draft gages


shall be filled with the proper fluid and
properly zeroed.

________

________

________

8.27

Temperature Switches

28. Bench check using


temperature bath.

controlled

29. Set to required alarm and/or trip point.


9.30

Miscellaneous Switches - Solenoid


valves,
electrical
relays,
timers,
pushbuttons, etc. shall be checked for
proper operation.

10. Gage Glasses

12.40

Pressure Instruments

41. Pressure and pressure differential


transmitters and transducers shall be
three-point bench calibrated using a

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.
hydraulic or dead weight tester prior to
installation. A precision output meter or
gage shall be used to monitor the output.

WITNESSED:
PTT
OTHER

________

________

________

________

________

________

44. Gages are subject to construction


damage and should not be installed until
immediately prior to commissioning.

________

________

________

45. Prior to installation, filled system


instruments shall be three-point bench
calibrated using a controlled temperature
bath.

________

________

________

46. Thermocouple transducers shall be


calibrated using a portable precision
potentiometer in place in the racks.

________

________

________

47. The multi-point temperature indicator


calibration shall be checked using a
portable precision potentiometer.

________

________

________

48. Temperature recorder calibration shall be


checked using a portable precision
potentiometer.

________

________

________

49. Complete Form IE-2 (typical) and


manufacturer's check list as needed.

________

________

________

50. Bi-metallic dial thermometers shall not be


calibrated but the dial or the pointer reset
shall be set to the known ambient
temperature before installing.

________

________

________

51. Thermocouples shall be checked for


type, polarity, double reversals, shielding,
and proper point identification.

________

________

________

53. All diaphragm and piston-operated


control valves shall be pneumatically
stroked using a pressure regulator and
pressure gage against the spring range
shown on the nameplate. Mechanical
seating and travel shall be checked
against the nameplate. It is desirable
that this check be made in the shop prior
to installation.

________

________

________

54. Valve positioners shall be calibrated on


the control valve in accordance with the
instrument specifications. Split range
positioners shall not have bypasses and
shall be carefully checked.

________

________

________

42. Complete manufacturer's check list.


13.43

14.52

Temperature Instruments

Control Valves

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

55. Prior to installation, electropneumatic


valve transducers shall be bench
calibrated with a portable or bench power
supply and meter and output gage. If
transducers are received mounted on
valves, calibration should be done in
place.

________

________

________

56. Control valve accessories, such as


handwheels, booster relays, etc., shall
be operationally checked.

________

________

________

57. All control valves shall be carefully


checked by nameplate data and
specifications and lubricated as required.

________

________

________

58. Butterfly valves shall be carefully


checked to see that the vane moves
freely into the upstream and downstream
piping. Throttling butterfly valves shall be
set for maximum travel in accordance
with the vendor's data.

________

________

________

60. Check all safety valves for proper


nameplate setting as per the valve and
instrument specifications.

________

________

________

61. Test all relief and safety valves for proper


relieving pressure and possible leakage
before installation. This test shall be
performed by a qualified person.
Qualified person is one who as attended
a school of instruction or received
training pertinent to the equipment
involved.

________

________

________

62. Where seals are found broken on relief


valves, the relief valve is to be retested
and resealed in accordance with plant
safety practice.

________

________

________

63. Where block valves are permitted under


the relief valve, they shall be full line size
and locked in the open position.

________

________

________

64. Where rupture discs are used to isolate


the safety valve from process fluid, their
pressure rating is to be checked.

________

________

________

65. Conduct all operating tests required by


code, law and insurance.

________

________

________

15.59

Safety and Relief Valves

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
WITNESSED:
CONTR.
PTT
OTHER
________
________
________

66. Complete Form TR-7.


16.67

Regulators

68. Install self-contained pressure and


temperature regulators as received.

________

________

________

69. Check inlet and


nameplate data.

________

________

________

71. Check against specifications.

________

________

________

72. Verify correct installation.

________

________

________

74. Calibrate analyzers and sampling


systems, using product samples where
furnished.

________

________

________

75. Check recording, peak-picking, alarm


interrupt circuitry.
(Manufacturer to
calibrate after installation.)

________

________

________

76. Package instrument systems shall be


carefully checked and calibrated to
vendor's specifications.

________

________

________

78. Check all instrument nameplates, both


front and rear, and all panelboard
nameplates for tag number, service,
location, and proper spelling.

________

________

________

79. Install and check all charts and scales for


range in accordance with specification.

________

________

________

80. Calibrate all principal front-of-panel, rearof-panel, and rack mounted instruments
in accordance with manufacturer's
instructions.

________

________

________

81. Panel
instrument
calibration
test
instruments shall be precision devices
and shall be the standard for loop
matching.

________

________

________

82. Check loop matching, such as zeroing


transmitter to receiver.

________

________

________

83. Pressure test all signal air lines to ensure


leak tightness.

________

________

________

84. Check all wiring for continuity.

________

________

________

17.70

18.73

19.77

outlet

ports

and

Instrument Piping and Tubing

Analytical Instruments and Specialties

Receiver Instruments and Control Panels

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.
85. Perform megger tests for proper
grounding and no shorts. Use Form
TR-5 (typical).

WITNESSED:
PTT
OTHER

________

________

________

87. Check nameplates for engraving,


spelling, and proper location.

________

________

________

88. Check operation and point continuity by


mechanically actuating all trouble
contacts for low-high-deviation alarm
operation, auxiliary contact operation and
sequence. Use Form EE-9.

________

________

________

________

________

________

________

________

________

20.86

Annunciators

21.89
Check operation and calibration of
all annubars
22. Check all detection and safety devices. Are
they property calibrated? Do they initiate the
proper alarms and shutdowns upon
activation?
23. Interface to SCADA
a.

b.

Check transfer of digital inputs from field


to SCADA display screen.

__________

_________

________

Check 0, 25, 50, 75, and 100% rising


and falling levels for each analog input
to SCADA display screen.

___________

_________

________

__________

_________

________

__________

_________

________

__________

__________

_______

c. Check frequency inputs at 10 Hz and


maximum frequency to SCADA display
screen.
d. Check control outputs from SCADA
command to end device in field.
e.

Check analog setpoints from SCADA


output to end device. Verify that
feedback of setpoint is correctly shown
on SCADA display with controller in local
and remote.

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

5.3858 EQUIPMENT
Contractor
shall
prepare
a
comprehensive
Mechanical Completion form for each unit shown in
the Equipment List as furnished for the Work.
Contractor shall pre-plan and notify Owner in
advance when manufacturer's representatives or
service engineers are to be present at the job site to
implement the Mechanical Completion program.
Contractor shall follow the requirements in the
applicable Specifications, Vendor supplied instruction,
instructions provided in this section, and directions
received from Owner.
Vessels, Tanks and Drums
Contractor shall verify under this section:
Completeness of gas dehydrators, dryers, filters,
flame
arrestors and silencers.
1.

__________

________

________

__________

_________

________

___________

_________

________

__________

_________

________

__________

__________

________

__________

__________

_______

Internal Inspection
Before the final bolting of cover plates on
manways, the interiors of the vessels must be
inspected for cleanliness, completeness, and
proper installation of internal components.
Metallurgy of internals and interior cladding must
be checked. Measurements and locations of
internals must be verified as to drawings and
specifications.
This check shall be a joint
inspection with Owner. A more detailed check list
is given below.
a.

Are all nozzles. Pipes. And internals installed


at proper location with correct orientation
and
clearances as shown on the drawings
and
called
for
in
the
vessel
specification ?
b. Are all internals fabricated of
proper
materials
as per the vessel specifications?
Are cladding.
lining. And wear plates installed
as specified
and of proper metallurgy ?
c. Check tightness of all bolting, fitting, and
positioning of vessel internals.
d.

Are all thermowells in correct position and of


correct alloy and length? Are level
control or
indicator floats of proper size and
free to move,
with stilling wells were specified?

2.

External Inspection
a.
b.

Are all specified nozzles and other


connections installed at proper location?
Are all valve connections for sampling or

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

__________

__________

_______

__________

__________

_______

Are all ladders and platforms installed? Are


there any safety hazards such as piping,
valves, conduits too close to ladder
rails?

__________

________

________

If vessel requires pressure test separately


connected piping, has this been done?
Complete From TR-2 (typical).

__________

__________

________

__________

__________

________

___________

__________

_______

5.3858 EQUIPMENT
Contractor
shall
prepare
a
comprehensive
Mechanical Completion form for each unit shown in
the Equipment List as furnished for the Work.
Contractor shall pre-plan and notify Owner in
advance when manufacturer's representatives or
service engineers are to be present at the job site to
implement the Mechanical Completion program.
pressure installed and at correct
locations?
c. Are all thermowells installed?
d.
rungs and
e.
form
f.

Are all required pressure relief valves


installed?
Do nameplate pressure
settings
agree with specifications? If the
assignment
includes testing, has this been
done?
g. Is all lifting gear, such as davits, etc., in
place?
(As per drawings)
i.

Are adequate vents and drains provided?


Plugs or valves installed? Make check
for
plastic shipping plugs that must be
removed
and replaced with specification
steel plugs for
vessel rating and service.

_________

__________

________

Are plugs removed from tell-tale holes in


reinforcing pads? Pipe vent outside
using open end pipe.

_________

___________

________

Is electrical grounding system complete?

_________

___________

________

_________

_________

________

m. Special procedures are required when air or


moisture must be removed or excluded.
this work been done?

_________

_________

________

n. Check adequacy of lighting. This should be


done at night with cooperation of Owner.

_________

_________

________

_________

_________

________

j.
insulation
k.

o. Is painting
complete?

Has

3.

required

before

start-up

is

Complete typical Form ME-2.

ITEM

PERFORMED:
CONTR.

6.3959 FLUSHING AND CLEANING


40. All piping and vessels should be thoroughly
cleaned of loose scale and internal debris that

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

WITNESSED:
PTT
OTHER

ITEM
5.3858 EQUIPMENT
Contractor
shall
prepare
a
comprehensive
Mechanical Completion form for each unit shown in
the Equipment List as furnished for the Work.
Contractor shall pre-plan and notify Owner in
advance when manufacturer's representatives or
service engineers are to be present at the job site to
implement the Mechanical Completion program.
accumulates during construction. Flush or blow
lines to remove the bulk of this loose material. A
large part of this flushing can be accomplished by
removing water from lines and equipment after
hydrotesting or during the run-in of pumps.
During test and flushing operations all lines and
systems must be checked for proper drainage
and venting. Most of the process and auxiliary
lines may be flushed through established circuits
from vessels, which are filled with water for that
purpose. A single filling of a vessel may not
provide adequate water for flushing all lines for
which it is a reservoir, in which case a continuous
or intermittent flow of water into the vessel should
be maintained. Water may be admitted to most
vessels via temporary connection to a nozzle on
the bottom outlet line. If washing of the vessel
itself is a primary object, introduce water into the
top of the vessel by hose connection or by other
means. Overhead lines may be flushed by
overflowing the related vessel. When washing
lines from a vessel always be certain that the
vessel is adequately vented to prevent a vacuum
condition. Verified?

PERFORMED:
CONTR.

________

WITNESSED:
PTT
OTHER

________

41. In any system to the greatest extent possible,


flush downward or horizontally, and out at low
points. The low point discharge openings will
usually be temporary openings made by
disconnecting flanges or fittings; normal drains
may be used for flush outlets provided they are
equal to line size or nearly so. For best results,
there should be no restriction at the outlet or any
other point in a line undergoing cleaning; where it
is necessary to throttle the flushing flow, do so at
the supply end.
The higher the velocity of flushing, the more
thoroughly a line will be cleaned. With a limited
supply of flushing medium, do not flush through
too many circuits or openings simultaneously.
Flush through all vents, drains and other side
connections. Flush by-passes alternately with
their main channels. Try to avoid flushing line
debris into equipment where it may become
lodged or trapped. This is particularly important
when washing towers containing perforated trays.
So far as it can be done conveniently and
economically, divert the initial flow ahead of, or
around such equipment until lines upstream are
clean, and then flush into or through the item

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

________

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

5.3858 EQUIPMENT
Contractor
shall
prepare
a
comprehensive
Mechanical Completion form for each unit shown in
the Equipment List as furnished for the Work.
Contractor shall pre-plan and notify Owner in
advance when manufacturer's representatives or
service engineers are to be present at the job site to
implement the Mechanical Completion program.
concerned. Verified?

________

________

________

42. When flushing of the lines is finished, drain water


from the system as completely as possible.
Provide ample top venting of all lines and vessels
during the draining operation and drains must be
provided in all low spots of the system to ensure
removal of all flushing water or media. Blow lines
with air to effect further water removal. Done?

________

________

________

43. At the conclusion of flushing any system, check


carefully to see that normal alignments are
restored,
temporary
connections
broken,
temporary breaks reconnected, check valve
flappers and/or cover plates replaced, orifices
installed, etc.
Start-up strainers are to be
installed for pump and alignment of equipment
checked after piping has been bolted in place.
Completed and checked?

________

________

________

44. Special instructions shall be issued outlining


cleaning procedures for units or sections where
moisture cannot be tolerated due to process
considerations. Done?

________

________

________

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

7.45
OTHER FACILITIES
Contractor
shall
prepare
a
comprehensive
Mechanical Completion form for each facility installed
as shown on drawings.
Contractor shall follow the requirements in the
applicable
Specifications,
Vendor
supplied
instructions, instructions provided in this section and
directions received from Owner.
46. Safety and Fire Protection
60. Are all systems operable? All components
tested "end-to-end," verified and working?

________

________

________

61. Ladders and platforms are installed for safe


operation and access.

________

________

________

62. Any safety hazards? Identify and describe.

________

________

________

________

________

________

65. Verify that minimum strength has been


achieved for all pours.

________

________

________

66. Has all concrete work been inspected for


cracks? Make necessary repairs.

________

________

________

68. Verify all new road surfaces suffered no


damage and all damages have been
repaired. The repairs have been accepted?

________

________

________

69. Verify all new and/or relocated gates operate


properly.

________

________

________

70. Verify all fencing materials suffered no


damage and all damages have been repaired
to Owner satisfaction.

________

________

________

71. Verify all new road culverts and headwalls


suffered no damage and all damages have
been repaired to PTT satisfaction.

________

________

________

72. Have security fences, gates, and guard


houses been completed?

________

________

________

73. Has construction equipment such as cranes,


welding machines, etc., no long being used,
been removed from operation areas?

________

________

________

47.63

Concrete Placement and Testing

64. Were all concrete tests completed?


laboratory and field reports on file?

C.67

D.74

Are

Roads, Fences and Gates

Soil Compaction

75. Has

test

been

conducted,

results

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

ITEM

PERFORMED:
CONTR.

WITNESSED:
PTT
OTHER

documented and degree of compaction


accepted?

________

________

________

76. If treatments to accelerate process were


used, describe and verify acceptance.

________

________

________

78. Have required governmental approvals been


obtained?

________

________

________

79. Do all underground drains flow freely? Have


seals been established where required?

________

________

________

80. Are outfall lines, ditches, etc., ready for use?

________

________

________

82. Complete all work shown on drawings and


verify all check lists are complete.

________

________

________

2. Have required identifying


signs been installed?

________

________

________

E.77

F.81

Waste Disposal

Documentation

markers

and

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

MECHANICAL COMPLETION FORMS


The sample forms on the following pages may be used for recording field inspection results and tests. The
list is not necessarily complete and the specific requirements for each facility or system must be a matter of
agreement between Contractor and Owner.
FORM NO.
Test and Record Forms:
TR-1, p. 1

Piping Strength Test Pressure Report (Page 1/2)

TR-1, p. 2

Piping Strength Test Pressure Report (Page 2/2)

TR-2

Hydrostatic Test Record

TR-5

Megger Readings - Ground Resistance Record

TR-6

Electrical Test Record

TR-7

Safety and Relief Valve Record

TR-8, p. 1

Instrument Test Record (Page 1/2)

TR-8, p. 2

Instrument Test Record (Page 2/2)


Mechanical Equipment Check List

ME-2

Vessels
Electrical Equipment Check List

EE-5

Circuit Breakers

EE-8

Lighting Panels, Insulation Resistance, and Remote Terminal Display (RTD)

EE-9

Alarm Circuit Operation Test


Instrument Check List

IE-1

Controllers

IE-2

Direct Connected Recorders and Recorder Controllers

IE-3

Electronic Controllers, Recorders & Indicators

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

FORM TR-1:

PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 1/2)

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM TR-1
DEPARTMENT CONDUCTING TEST

LEAK AND STRENGTH PROOF TEST


REPORT (Page 1 of 2)
REPORT DATE

REASON FOR TEST: NEW CONSTRUCTION EXISTING FACILITY


1.

STOCK PIPE

LOCATION:

Compressor Station
(Name.________________)

Metering Station
(Name.________________)

Pipeline
Milepost
Station

Gas Piping

A
B
to
to

Oil/Water/Other Piping
DRAWING REFERENCES:
2. PIPE DATA AND TEST PRESSURE REQUIREMENTS
a. Size

b. Wall

c. Spec

d. Material

e. Min. Test
Pressure

f. Min. Test
Time

g. Footage
Tested

Columns a. through f. need to be completed and approved prior to test.


3. TEST MEDIUM INFORMATION
Water
Natural Gas Nitrogen
Other:_________________________
If water is to be used, the following must be completed:
Source____________________________
Sample Analysis____________________________
Agency
How to be
Consulted_________________________
Disposed__________________________________
ENGINEERING
APPROVAL BY:

DATE:

4. TEST INSTRUMENTS AND EQUIPMENT:


Type

Make

Range

Pressure
Recorder
Temperature
Recorder
Dead Weight
Tester
Others:

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

Serial No.

Date Last
Calibrated

FORM TR-1:

PIPING LEAK AND STRENGTH PROOF TEST REPORT (Page 2/2)

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM TR-1

LEAK AND STRENGTH PROOF TEST REPORT


Page 2 of 2

5. PROFILE DATA:
ELEVATION

PRESSURING
POINT

LOCATION OF
DEAD WEIGHT TESTER

Survey Station
Elevation
6. FIELD TEST PRESSURE DATA:
Date of Test
1.
Clock
Time

2.
Press.
Point
(psig)

Time Test Began


3.
Min.
Press.
@
Max.
Elev.
(psig)

4.
Max.
Press.
@
Min.
Elev.
(psig)

5.
Amb.
Temp.
(C)

6.
Test
Mediu
m
Temp.
(C)

Date & Time Test Ended

Weather:

1.
Clock
Time

4.
Max.
Press.
@
Min.
Elev.
(psig)

2.
Press.
Point
(psig)

3.
Min.
Press.
@
Max.
Elev.
(psig)

5.
Amb.
Temp.
(C)

6.
Test
Medium
Temp.
(C)

Enter in column 2, the pressure reading from the dead weight tester. Columns 3 and 4 data may be calculated if
accurate elevation information is available.
For compressor station piping, furnish a field sketch if test layout differs from reference drawings.
Temperature and pressure recorder charts and gage calibration charts are to be attached to the original of this
report together with the water analysis if such a test was necessary.
For mainline piping, furnish field profile sketch recording the pipeline length tested and the elevations and pressure
as at high and low elevations. Existing bench marks & survey monuments shall be referenced in the test section.
TEST PERFORMED BY:
Signature of Representatives
OWNER/CONSULTANT
Contractor (Firm) ______________________
Subcontractor (Firm)____________________

By: _______________________________________
By: _______________________________________
By: _______________________________________

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

FORM TR-2:

HYDROSTATIC TEST RECORD

GAS PIPELINE AND GAS METERING


HYDROSTATIC TEST RECORD
AND REGULATING STATION PROJECT
FORM TR-2
TEST SECTION NO. ______________________________ (1)
PIPING SERVICE SYSTEM____________________________ DATE OF TEST ________________________
METHOD OF TEST _____________TEST MEDIUM SOURCE ________________ COMPOSITION_________
AMBIENT TEMPERATURE __________________________ TEST MEDIUM TEMPERATURE
___________________
DESIGN PRESSURE ______________________________ TEST PRESSURE _________________________
(2) Line Numbers

Origin

Destination

TEST INSTRUMENTATION AND TEST RECORDS


CALIBRATION
READINGS THROUGH TEST PERIOD
DATE

TEST
INSTRUMENT
DESCRIPTION
AND RANGE

TIME
1

DESCRIBE:

PRESS.
2
3

FILL PUMP
PRESSURE PUMP
MAXIMUM PRESSURE
DEADWEIGHT TESTER
TEST HEADERS AND BLINDS

EQUIPMENT INCLUDED IN TEST


TAG NO.
DESCRIPTION
REMARKS

NOTES:

Drawing No.

(1)
(2)

TEMP.
2
3

ISO No.

REMARKS

LEAKS
2
3

GPM MAX
GPM
GPM AT MAX

EQUIPMENT EXCLUDED - SHOP TESTED


TAG NO.
DESCRIPTION
REMARKS

Prepare documentation for each Test Section - include schematics, layout and periodic
notes during test period.
Use data from Project issued sheets

SUMMITTED:
SUBCONTRACTOR

DATE

ACCEPTED:
CONTRACTOR

DATE

OWNER /CONSULTANT
LOCATION
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

FORM TR-5:

MEGGER READINGS - GROUND RESISTANCE RECORD

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM TR-5
GROUND
SYSTEM
TEST
LOCATION

SYSTEM
NUMBER

RESIST.
(OHMS)

AMB.
TEMP.
C

SUMMITTED

MEGGER READINGS GROUND RESISTANCE RECORD


WEATHER

DATE

OWNER/CONSULTANT
SUBCONTRACTOR
LOCATION

DATE

DATE
ACCEPTED
DATE

CONTRACTOR

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

TESTER'S
INITIALS

EQUIPMENT

FORM TR-6:

ELECTRICAL TEST RECORD

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM TR-6
SYSTEM
METHOD OF TEST
DESIGN VOLTAGE
CIRCUIT NUMBERS

ITEM NO.

ELECTRICAL TEST RECORD

DATE OF TEST
TEST VOLTAGE
VOLTAGE

ORIGIN

DESTINATION

EQUIPMENT INCLUDED IN TEST


DESCRIPTION
ITEM NO.

SUMMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION
DATE

ACCEPTED
CONTRACTOR
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

RUN IN

DRAWING NO.

DESCRIPTION

FORM TR-7:

SAFETY AND RELIEF VALVE RECORD

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM TR-7

SAFETY & RELIEF VALVE RECORD

SAFETY VALVES
ITEM
NUMBER

EQUIPMENT

SIZE

PRESSURE

SETTING
TESTED

RELIEF VALVES

SYSTEM TEST

REMARKS:

SUMMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION
DATE

ACCEPTED
CONTRACTOR
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

DATE
TESTED

INSTALLED
OK

FORM TR-8:

INSTRUMENT TEST RECORD (Page 1/2)

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM TR-8

INSTRUMENT BANK TEST AND


CALIBRATION RECORD
Sheet 1 of 2

TYPICAL FORM:
TITLE FROM INSTRUMENT INPUT/OUTPUT LIST
TAG
NO.

NAME

(T)
(1)

(C)
(2)

INSTALLED
LOCATION
OK?
(3)

VERIFY (4)

REMARKS
AND
OTHER
R

NOTES: (1) Show date of bank test completed and accepted. Describe below test method used.
(2) Verify calibration of instrument and describe procedure followed. Include separately approved
calibration certificate.
(3) Indicate compliance with drawings.
(4) M = mounting with all brackets and identifiers finished
I = installation complete ready for use
E = piping ends connected after piping test and cleaning
W = electrical wiring tested, passed and connections finished
R = recorders with printing media verified (inks, pens, paper, etc.); verify with data collected
during precommissioning
S = remote receipt of data

SUMMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION
DATE

ACCEPTED
CONTRACTOR
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

FORM TR-8:

INSTRUMENT TEST RECORD (Page 2/2)

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM TR-8

INSTRUMENT BANK TEST AND


CALIBRATION RECORD
Sheet 2 of 2

TYPICAL FORM:
TITLE FROM INSTRUMENT INPUT/OUTPUT LIST
TAG
NO.

NAME

(T)
(1)

(C)
(2)

INSTALLED
LOCATION
OK?
(3)

VERIFY (4)

REMARKS
AND
OTHER
R

NOTES: (1) Show date of bank test completed and accepted. Describe below test method used.
(2) Verify calibration of instrument and describe procedure followed. Include separately approved
calibration certificate.
(3) Indicate compliance with drawings.
(4) M = mounting with all brackets and identifiers finished
I = installation complete ready for use
E = piping ends connected after piping test and cleaning
W = electrical wiring tested, passed and connections finished
R = recorders with printing media verified (inks, pens, paper, etc.); verify with data collected
during pre-commissioning
S = remote receipt of data

SUMMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION
DATE

ACCEPTED
CONTRACTOR
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

FORM ME-2:

VESSELS

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM ME-2

FIELD INSTALLATION CHECK LIST

VESSELS
EQUIPMENT NO.
FABRICATOR
TYPE
MATERIAL
THICKNESS

SERVICE
P.O. NUMBER
CODE
DATE RECEIVED

ITEM TO CHECK
CONDITION WHEN RECEIVED?

REMARKS/OK

ERECTION
ALIGNMENT, ELEVATION & PLUMB
GROUNDING STRAP INSTALLED?
INTERNALS
INSULATION & FIREPROOFING
GROUTED
CLEANED
TESTED
LADDERS, PLATFORMS, DAVITS
CLOSED
REMARKS:

SUMMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION
DATE

ACCEPTED
CONTRACTOR
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

DATE TESTED

FORM EE-5:

CIRCUIT BREAKERS

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM EE-5

FIELD INSTALLATION CHECK LIST

CIRCUIT BREAKERS
EQUIPMENT NO.
MANUFACTURER

SERVICE
INSTALLED BY

ITEM TO CHECK
CONTACT PARTS CLEAN?

REMARKS/OK

VISUALLY CLEAN? (NOT CORRODED)


NO MOISTURE PRESENT?
ENCLOSURE HAS BREATHER & DRAIN?
COVERS ON TIGHT?
SEALS FILLED?
INSTANTANEOUS TRIP SETTING:

PHASE A
PHASE B
PHASE C

REMARKS:

SUBMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION
DATE

ACCEPTED
CONTRACTOR
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

DATE TESTED

FORM EE-8:

LIGHTING PANELS, INSULATION RESISTANCE, REMOTE TERMINAL DISPLAY (RTD)

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM EE-8
TYPICAL FORM FOR:

CIRCUIT
NUMBER

WIRE
NUMBE
R

ELECTRICAL TEST RECORD

LIGHTING PANELS
INSULATION RESISTANCE
REMOTE TERMINAL DISPLAY (RTD)
WIRE
SIZE

FROM

TO

MEGGER READING
(MEG OHM) @
1

DATE

AMB.
TEMP.
C

WEATHER

NOTE: @ MEGGER READINGS TO BE WITH WIRES COMPLETELY INSTALLED, CONDUIT FITTINGS


CLOSED, SEALS FILLED, AND WITH THE CIRCUIT BREAKER OPEN
INSTALLED BY _________________________________________ DATE____________
SUBMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION
DATE

ACCEPTED
CONTRACTOR
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

FORM EE-9:

ALARM CIRCUIT OPERATION TEST

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM EE-9

FIELD INSTALLATION
CHECK LIST

ALARM CIRCUIT OPERATION TEST


ALARM UNIT
NUMBER

EQUIPMENT
LOCATION

TESTER'S
INITIALS

DATE

REMARKS

NOTE: EACH DEVICE SHOULD BE ACTUATED BY ACTUAL PRESSURE, TEMPERATURE, LEVEL, SPEED,
FLOW, ETC. ALL ITEMS MUST BE SIGNED AS BEING IN SATISFACTORY CONDITION BEFORE
OPERATION IS PERMITTED.

SUBMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION
DATE

ACCEPTED
CONTRACTOR
DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

FORM IE-1:

CONTROLLERS

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM IE-1

INSTRUMENT CHECK LIST

CONTROLLERS
INSTRUMENT NO.

SERVICE

MANUFACTURER

SERIAL NO.

ITEM TO CHECK
1. Blow air supply line at filter. Adjust air supply to specified pressure.
2. Align or synchronize controller so that when both process and set point are
together near mid-range, the output air pressure does not drift. Observe for at
least 2 minutes. The proportional bank adjustment should be able to be moved
through its full range (2 to 300%) without change in output pressure.
3. Check the tubing from output to valve or pneumatic set unit of another instrument.
There should be no restriction or leaks. Check stack for leaks - tighten bolts if
necessary. (Bubble test should be used on all pneumatic controller systems.)
4. Controller is connected to proper valve and to proper connections.
5. Check manual control position. Put instrument on manual, adjust output to about
9 psig, move set point above and below process pen. No change in output air
pressure should result.
6. Check that controller output air action is correct for valve or instrument to which it
is connected. Control action is set "as process measurement increases" output
air. (INCREASES for direct action and DECREASES for reverse action.)
7. Affix calibration sticker.
REMARKS:

SUBMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION

ACCEPTED

DATE
CONTRACTOR

DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

DATE CHECKED

FORM IE-2:

DIRECT CONNECTED RECORDERS AND RECORDER CONTROLLERS

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM IE-2

INSTRUMENT CHECK LIST

DIRECT CONNECTED RECORDERS AND RECORDER CONTROLLERS


INSTRUMENT NO.

SERVICE

MANUFACTURER

SERIAL NO.

ITEM TO CHECK
1. Remove all paper tags, strings, shipping stops, and install chart.
2. Check pen linkages for proper connection and freedom of movement.
3. Check calibration of recording pens at three points: 0, 50%, 100% of span; if not
within 0.5% of span, recalibrate and report results on attached sheet.
4. If instrument is a controller, synchronize and align controller. Blow air supply line
and adjust regulator to 20 psig before connecting controller to air supply.
5. Check output air tubing for leaks and connection to proper valve. Check that
control action is correct.
6. Fill pens with ink and see the ink flows freely.
7. Check that chart drive operates.
8. Check nameplates for correct identification.
9. Affix calibration sticker. Shut off chart drive. Leave instrument clean and neat,
ready for operation.
REMARKS:

SUBMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION

ACCEPTED

DATE
CONTRACTOR

DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

DATE CHECKED

FORM IE-3:

ELECTRONIC CONTROLLERS, RECORDERS AND INDICATORS

GAS PIPELINE AND GAS METERING


AND REGULATING STATION PROJECT
FORM IE-3

INSTRUMENT CHECK LIST

ELECTRONIC CONTROLLERS, RECORDERS AND INDICATORS


INSTRUMENT NO.

SERVICE

MANUFACTURER

SERIAL NO.

ITEM TO CHECK
1. Check continuity of wiring, location and value of dropping resistors, and verify
service manual feature (if provided) is disengaged.
2. Turn on power supply and check voltage level and polarity.
3. Check and adjust input span and zero.
4. Set output signal limits. (High = 100%; Low = 0%)
5. Place controller in Automatic Mode and check alignment.
6. Transfer controller to the Manual Mode and check both up and down scale ramp
rates.
7. Verify output signal action is correct for receiver.
"Output is to _______________ with input signal increase."
8. Check correct chart and scale ranges.
9. Install recorder ink capsules
10. Affix calibration sticker.
REMARKS:

SUBMITTED

OWNER /CONSULTANT
SUBCONTRACTOR

DATE

LOCATION

ACCEPTED

DATE
CONTRACTOR

DATE

PR-P-1102.21-4012-004 Rev.0 (MECHANICAL COMPLETION PROCEDURE)

DATE CHECKED

Вам также может понравиться