Академический Документы
Профессиональный Документы
Культура Документы
@
.
.
,E
Society
lADC/SPE
39399
of Petroleum
EnglneerS
*IADC Members
Copyright
1998, lADC/SPE
Drilling Conference
at the Igge
lADC/SpE
Drilflg
cofere~a
held i
Abstract
This report summarizes the testing and field application of a
rotary liner drilling system. Liner drilling was first attempted
by Amoco Norway Oil Company (ANC)C) in 1993 and there
have since been eight additional wells drilled using rotary,
motor, and a combination rotary/motor liner drilling system.
This paper will focus on six of those wells drilled with a rotary
liner drilling system.
Key learnings
from these well
applications in the Norwegian sector of the North Sea are
reviewed.
Background
The Valhall field is located in the South Central Graben in the
North Sea. The reservoir contains black oil with a relatively
high solution gas-oil ratio. The Valhall field is operated by
Amoco Norway (28. 1%) on behalf of Enterprise Oil Norge
Ltd. (28. 1%), Amerada Hess Norge A/S (28. I %), and Elf
Petroleum Norge A/S (15.7%).
Introduction
A successful rotary liner drilling system can help overcome
challenges related to wellbore stability through sections which
are depleted, contain unconsolidated
or sheared debris, or
experience flow problems.
Interest in this technique has
increased as drilling operations begin to look for additional
reserves below depleted sands which cause differential
sticking problems, below salt domes containing sheared zones
which experience flow and wellbore stability problems, and in
reservoirs with weak matrix strength were there is significant
depletion around old producers.
drilling
operations,
Development drilling began in Valhall in late 1981. A threeplatform complex was installed which included process and
compression,
drilling, and living quarters. The drilling
platform was originally designed with 24 well slots. Six
additional slots were later added bringing the total number of
slots up to 30. The processing facility consists of two stages of
must be
879
lADC/SPE
39399
Well 2/8A- I had been the most stable and prolific producer on
Valhall since it was first put on production
in 1982.
Production
history showed the well averaged
12,00016,000 BOPD from 1989-1993. The well was located in the
central crestal area of the field and had failed as a result of
casing collapse inside the overburden. The drilling objective
of Well 218A-1A was to sidetrack out of the 9-5/8 in. casing at
approximately
6,000 ft (1,830 m) and drill a vertical twin
approximately 250 ft (75 m) to the Northwest. The location
was selected to minimize risks related to fault proximity and
possible water flood effects.
ANTICIPATED STRATIGRAPHIC
WELL
COLUMN
218AIA
il 3
1431
wP\
: POINT
1825
2180
ss8
,-68.6..,
: UMESTONE STRINGERS
.1
2418
2430
2.446
2467
3 HOD
::::::::
2503
;:%
: VOLCANtC TUFF/CLAYSTONE
CtAYSTONE/LIMESTONE
CHALK51MESTONE
2563
2s81
2612
i ARGILLACEOUS LIMESTONE
I
Fig. 2: Stratigraphic
While
880
drilling
the
overburden,
the
Tor
formation
was
. . . . ..-..
IADCISPE 39399
FOR DEPLETED
RESERVOIRS
..
..
.
.
.
.
.
.
7/
.
..
.
.
-.
.
.
.
..
.
_.
.. ..
.
.
//
Shale
:
M.W. 14.5 ppg:
Chalk/Limestone
P.P. = 6.4 to 7.8 ppge
_
-
.
_
#k
1
I
I
I
I
I
.
.
-
.
_
&k
.
Shale
.
:M.W,
14.7
Ppg
-
-.
-------
_.
.
YE
Stabilizer
E-Pxer____-L
_
c
Stabilizer__
F
ANOC tested a portion of this concept in 1993 on Well 2/8AIA while drilling a 5 in. liner down with a conventional PDC
bit on bottom. The bit and liner combination reached total
depth after drilling 390 ft (119 m) of cement and fill. In 1994,
Hod well 2/1 1-A7 used an 11-3/4 in. liner coupled with a
downhole motor and underrcamer to drill 85 ft (25.9 m) of
shale until the casing could not be slid any further.
lPacker I
I
I
I
I
T;n;:yJ
I
I
I
t
Chalk/Limestone
__E
~ Bit
Fig. 4: Liner drilling into depleted zone followed by
zonal isolation with packers and cement.
Laboratory Testing
Wells on the Valhall platform which cease to produce are
typically sidetracked inside of the 9-5/8 in. casing to minimize
the cost of slot reclamation and redrilling of the well. An 8-1/2
in. hole is drilled through the window which allows a 7 in.
liner to be run into the top of the production zone.
88
L.A. SINOR,
P. TYBERO,
O. ElDE,
AND W. WENANDE
lADC/SPE
39399
Fig. 7: Fou~blad~~~4
in. liner shoe with % in (19
m_rn)P_DCcutters used on ANOC well 28 F6.
Figures 5-7
show the progression of liner shoe bit designs
based on key Iearnings from the laboratory and field drilling
results. The results of laboratory testing in shale with five
different liner bit designs showed blade standoff and proper
pressure drop through the nozzles were important to minimize
balling. Figure 8 is an example of severe balling experienced
in Catoosa shale with nozzles that were too large for the flow
rate of 250 gpm (946 lpm) used during the test. The bit
initially balled at a rate of penetration of 26 ft/hr (8 m/hr)
during the initial testing. With nozzle improvements, the rate
of penetration increased up to 93 ftir (28 m/hr) at 7,000 Ibs
WOE with minimal balling.
Fig. 5: Two bladed 8-1/2 in. liner shoe with% in. (19mm)
carbide cutters used on ANOC we[l 218-A-2A.
After laboratory testing the bits for balling tendencies, the bit
shown in Figure 5 was drilled out with a junk mill. The 6 in.
mill had four blades and four 1 in. diameter nozzles for flow.
The primary cutting elements were 0.4 in. (10 mm) carbide
cutters with a built-in chip breaker feature.
The main
limitation observed on the mill was the lack of clearance in the
junk slots for drilled debris to pass and the lack of ,cutter
882
lADC/SPE
39399
stand-off
does not
operation
with solid
FOR DEPLETED
RESERVOIRS
mud. It was essential not to risk penetrating the top of the Tor
with the directional assembly but at tle same time min~lze
the length to be drilled with the 7 in. liner.
The liner drilling assembly would use the liner shoe design
The liner shoe in Fig. 5 was cemented inside of an existing 81/2 in. Carthage limestone rock sample prior to milling to
simulate the operating condition in the field. The milling test
was performed by first tagging the cement inside of the liner
with 60 rpm to seat the bit face. After drilling about one-third
of a foot (0.3m) the bit speed was increased up to 180 rpm.
Operation of the junk mill was much smoother at the higher
rotary speed. Sensor output from the rig showed the mill
rotating slightly off-center as it drilled. High frequency lateral
vibrations were aIso noted as th? mill tagged the steel blades
inside the liner shoe. The time from tagging the cement to
breaking through the blades was about 10 minutes. For the
field application, the mill would be modified to have larger
junk slots since it would have to drill a landing collar, cement,
float collar, and then the liner shoe. Figure 9 shows metal
shavings caught during the testing by bar magnets located on
the shale shakers.
4
ma
-.
..
Fig. 9: Bar magnet with metal shavings from liner bit.
After curing the losses, the liner drilling assembly was picked
up which included 84 joints of 7in. 29 ppf L-80. The total
liner length was 3,346 ft ( 1020m). The connections used
Hydril 521 threads to provide high torque capacity which
would be required while drilling.
The minimum makeup
torque of the threads is 8,300 ft-lbs with a minimum field
recommended makeup of 9,550 ft-lbs. Maximum yield torque
with L-80 material is 46,000 ft-lbs. The liner was made up
with the following equipment and order:
883
L.A, SINOR,
P. TVBERO,
O. ElDE,
Surge calculations
with a closed end displacement
gave
maximum
casing running speeds of around 36 ftimin
(1 I m/min) near the 9-5/8 in. window with an EMW of 15.2
ppg and speeds of 20 ftimin (6m/min) for an EMW of 15.0
ppg. Actual running speeds of 20 ft/min (6m/min) were used to
minimize losses. The pipe ran to bottom smoothly except for
the 9-5/8 in. window at *7,220 ft (2,200m) MD which was
tagged with 20,000 ibs. Slow rotation of the pipe was
eventually required to pass by the window.
IADCISPE
39399
ft-lbs
15
AND W. WENANDE
Slight losses were recorded at the 140 gpm (530 lpm) reading.
The equivalent mud weight based on annular pressure losses
at 140 gpm (530 lpm) was 15.4 ppge. No additional losses
were recorded while tripping into the hole and breaking
circulation until 10,269 ft (3, 130m). Attempts to circulate and
work the pipe resulted in only 10% returns back to surface.
The liner running continued until total depth of the hole where
it picked up weight at 10,354 ft (3, 156m). The top of the ~or
formation was estimated at 10,398.6 ft (3, 169.5m). Hole drag
prior to drilling showed the up drag to be 275,00 lbs while the
down drag was 270,000 lbs. Drilling began with 225 gpm
(1, 100 psi/7684 kPa) with returns of only 10%,60 rpm, and O4,000 lbs measured weight. The rotating torque varied
between 10,000-15,000
ft-lbs.
21
24
<d
18
&
.,----
A--
.--Torque
-RPM
3.162
884
IADCISPE 39399
FOR DEPLETED
RESERVOIRS
The well was then shut-in with 1,000 psi (6895 kPa) until the
cement samples on the surface became hard. Caution was
taken since the casing could not be tested at higher pressures
without losing pressure. There was reason to believe that the
wiper had not seated properly in the landing collar preventing
a positive seal. This was later confirmed by testing the casing
to 1,500 psi (10343 kPa) after allowing the cement to cure.
The well was displaced to sea water and a 6 in. mill assembly
was picked up with 26 joints of 3- 1/2 in. HWDP and 91 joints
of 3-I/2 in. drill pipe. The assembly was run to bottom
without trouble and the sea water was displaced to 8.7 ppg
water based mud. Firm cement was drilled from 10,315 ft
(3, 144m) to the landing collar at 10,400 ft (3, 170m) with 75
rpm and 7,000 Ibs weight. The landing collar, float collar, and
bit shoe were drilled quickly in I hr 5 minutes with 120 rpm
and 2,000-12,000
lbs weight. The mill torqued up as it broke
through the bit shoe at 10,405.5 ft (3,17 1.6m) and was
averaging 33 ftihr (10 m/hr) just below the casing shoe.
The liner drilling approach cut the time from spud of the
S-l/in. section to completing the clean out of the 5 in. liner,
excluding logs, from 33.8 days (A-1A) to 15.6 days. The
unscheduled
events for the liner section was 55.6V0.
Savings
was estimated
at $1.82MM
US using a
conservative spread rate of $100,000 US/day (1995).
The drilling plan for this well was almost identical to the one
used to drill well 2/8-A-2A with the addition of key learnings
generated during the post analysis. The drilling plan called for
squeeze cementing the window after sidetracking. The liner
drilling assembly would use a redesigned bit shoe (Fig. 6)
with one inflatable external casing packer for formation and
pressure
isolation. Major changes
included Anti-Whirl
features for bit stability, bicenter design for improved annular
clearance and hole cleaning, PDC vs. carbide cutters for
impact and wear resistance through the carbonate stringers,
and larger nozzles for LCM material.
The 7 in. liner was run at 2 minutes per stand to the bottom of
the 9-5/8 in. window without any mud losses. The rotating
torque of the liner was measured to be 4,200 ft-lbs (120 amps)
885
lADC/SPE
39399
just above the 9-5/8 in. casing window. The liner was then run
to bottom and the 14.7 ppg oil base mud was cut back to 14.5
ppg prior to drilling. Hydraulics estimated a pressure drop of
675 psi (4654 kPa) at 200 gpm (757 Iprn) vs. a measured 730
psi (5033 kPa). Additional simulations at 300 and 350 gpm
(II 36 and 1325 Ipm) gave pressure drops of 1,075 and 1,325
psi (7412 and 9 i 36 kPa), respectively.
New formation was drilled from 8,307 ft - 8,314 ft (25322534 m) at rates averaging 10-16 m/hr, The torque then
jumped to over 15,000 ft-lbs and the pressure increased
requiring the pumps to be slowed to prevent premature s&ttingof the liner hanger. At 270 gpm (1022 lpm) the pump pressure
was reading 1,400 psi (9653 kPa). The pipe was picked up off
bottom and worked slowly to bottom with erratic torque
readings. Fluid losses started requiring the flow rate to be
slowed to 175 gpm (662 lpm) to regain full returns.
The liner drilling approach cut the time from spud of the
8-1/2 in. section to completing the clean out of the 5 in.
liner, excluding logs, from 33.8 days (A-1A) to 12.1 days.
The unscheduled events for the liner section was 43.6%.
Savings was estimated at $2.17MM using a conservative
spread rate of $100k/day (1996). This reduction included
two days required to sidetrack around junk left by an
unsuccessful liner run which left parts of the liner bit and
packer rubber in the weIIbore.
Two days (47 hours) were required to go into the hole with a
junk mill and work the rubber element to bottom, spot a 30
bbl 15.8 ppg cement plug on bottom, and sidetrack around the
junk. The well was kicked off at 7,940 ft (2,420 m) and
stopped at 8,314 ft (2,534 m).
The bottom was tagged at 8,314 ft (2534 m). The pumps were
886
IADCISPE 39399
_____
____
hang-up
cone to
cutters
to gage.
rounded
The liner drilling system was washed down to the top of the
gunk pill at 9,06 ft (2745m) where mud losses were averaging
2 bpm. The liner required 24,000 ft-lbs to initiate rotation
(while reciprocating) before dropping down to 20,000 ft-lbs.
Washing and reaming continued to 9,029 ft (2752m) where
drilling was initiated with 250 gpm (946 Ipm), 800 psi (5516
kPa), 110 rpm, and 18,000-20,000
ft-lbs torque with no mud
returns. One meter of formation was drilled while pumping
275 bbl of 6.8 ppg base oil down the annulus. The drill string
stalled at 25,000 ft-lbs torque indicating that the hole was
caving around the liner shoe with the reduced EMW. Mud
returns up the annuhrs were lost but the annulus was staying
full without the pumps.
The drilling planned called for placing the bottom of the hole
10- 15 ft (3 - 5m) TVD from the prognosed top of TOR but
the Lista fortnation was 33 ft (10 rn) thinner than estimated.
Unknown at the time, the actual depth above the Tor was 1.5
ft (0.5m) which resulted in total mud losses with the steerable
assembly. The mud weight was 14.7 ppg with an equivalent
circulating density of 15.6 ppg at total depth.
During the losses, the
bbi of 6.9 ppg base
squeeze was pumped
while-drilling (MWD)
RESERVOIRS
887
10
IADCISPE
39399
Table 1
I Year I Hole IL]ner I Elner ILength] Drill I
I Name ]
lAngle] Size ILength IDrilled I Time I
(ft)
(ft)
(hrs)
(deg) (in.)
5.00
568
899
29.0
1993
0
A-1A
5?35
1175
89
2.5
Hod A-7B * 1QQ~ 4n
.
.1 1995 I 7 I 7.001 33~
Well
./
--,.-
,.
1 nnL
A-8A
<
177UI
..,-,-
7 Ml
J.w
---
1A,
1 du
L.J
2;
I .5
1996 I 5 I 7.00 1640
31
2.5
3960
1996I I
-41/. -00
3
1.0
1996 [ 60 I 9.63 4472
.nnl
,- 1 -l/*
.-99
64
12.0
I IYY/ I 14 I /.0.11L/(
66 I 2.5
I 1997 ] 60 I 7.631 4~~ I
I 19971
63
{u
. . ---- 60 ,. 9.63
.-., I 6890
--* Bit and underreamer. inner string motor, and casing spear
** Drilled in three attempts due to ;asing failure at wi~dow
** Baker liner drilling
systems using a motor and thruster
A-8A(T2)
A-3B
F-6
A-QAw~
00
gwg40-
%%20.
3
.c lo-
3
~
0+
A-iA
A-2A
A-8A
A-3%
F6
Well
ANOC well 2/8-A-5B was drilled as a sidetrack to well 2/8-A5B which was producing at 1800 BOPD, far below its
potential of 8000 BOPD as a horizontal well. The drilling
plan called for drilling with a very short section of 7-5/8 in.
liner (433 ft/132m) into the Tor formation at an angle of 60.
for ANOC
Acknowledgment
The authors would like to thank Amoco Norway Oil Company
and Amoco Production Company- Exploration and Production
Technology Group (EPTG) for permission to publish this
work. Special thanks to Phil Pattillo, Steve Morey, and Jim
Powers for
the tubular analysis and testing; Hydril for
supplying the pup joints used with the 7 in. and 7-5/8 in liner
drilling shoes; and Mike Murphy, publisher of THE BRIEF
for his assistance in obtaining archived information, Lastly,
we would like to thank Baker Oil Tools for supplying the 6 in.
mill used during the laboratory testing.
References
1. Warren, T.M., and Armagost,
2.
-3.
4.
5.
888