KERALA STATE ELECTRICITY BOARD LIMITED

220kV SUB STATION SUB-DIVISION, POOVANTHURU


ESTIMATE

Name of Work:- Dynamic Contact Resistance Measurement with St


Traveling Curve of 220kV Circuit Breaker at 220kV Sub Station, Pa
Sl.
No.

Description
DCRM testing for 220KV Circuit
Breaker
(1,DCRM measurement with stroke
curve of the breaker using a linear
type or rotary type Transducer
( result
contains DCRM and stroke curve
graph together)
2,Tripping closing timing and static
contact resistance of the breaker)

Quantity Unit

No.

TOTA
Transport Charges for Test Kit

Service Charge-12.36

Tot

Unforsee

Grand Tot
(Rupees Seventy Five Only)

PART B - LABOUR
Sl. No.

Description

Quantity

Unit

Deputation charges for 2 Service Engineers / day

Day

TOT
Service Charge @ 1
GRAND TOT
(Rupees Sixty Two Thousand One Hundred only)

ABSTRACT
1
2

PART I - MATERIALS
PART II - LABOUR
ADD FOR UNFORESEEN

GRAND TOTAL
(Rupees Four Lakh Ninty Thousand only)

KERALA STATE ELECTRICITY BOARD LIMITED


220kV SUB STATION SUB-DIVISION, POOVANTHURUTHU

ESTIMATE
Name of Work:- Overhauling of 220kV SB-PL Feeder Circuit Breaker at 220kV Substation, Pallom
Estimate Amount :- Rs.4,90,000/- (Rupees Four Lakh Ninty Thousand only)

220kV Substation, Pallom is an important grid substation in


220/110kV transformers, 3 Nos. of 110/66kV transformers & 2 Nos. of 66/11kV transformers. It also has 3 N
Nos of 110kV feeders, 6 Nos of 66kV feeders & 8 Nos of 11kV feeders in addition to a 110kV Capacitor Bank
analysis of the breaker of SB-PL 220kV feeder by PET team, it was found that during the closing of the brea
in the R-phase pole which is undesirable. The SF6 breaker of SB-PL 220kV feeder is of CGL make bearing S
200-SFM-40A). This breaker was manufactured during 1998 and is already 17 years old. Since bouncing is n
to carry out the overhauling of the breaker at the earliest. Otherwise there are high chances that the bre
operation. The bounce may be due to the wear and tear of the bearings and O rings. During overhauling, the
dismantled and re-assembled after cleaning and applying anabond and changing the old O-rings of gas joint
sets with new ones etc. After the work vacuum shall be applied and the poles will be filled with positive gas
Necessary manpower, dismantling of pole units from the breaker and re-assemblying the same pole uni
overhauling shall be arranged by us.

Hence an estimate is prepared based on the CPWD Delhi Analysis of Rates 20


for substation works. The estimate include lifting of pole unit from the breaker and assembled back to the br
for the above work may be met from the budget provision for the O&M works of 220kV Substation, Pallom for
17.

ELECTRICITY BOARD LIMITED


SUB-DIVISION, POOVANTHURUTHU
ESTIMATE

t Resistance Measurement with Stroke Curve or


Breaker at 220kV Sub Station, Pallom
Rate

Amount

11000.00 55,000.00

TOTAL 55,000.00

Charges for Test Kit

7,500.00

Service Charge-12.36% 6798.00


Total 69298.00
Unforseen
Grand Total

5,702
75,000

PART B - LABOUR
Rate

Amount

18000

54,000.00

TOTAL
Service Charge @ 15%
GRAND TOTAL
ty Two Thousand One Hundred only)

54,000.00
8100.00

62100.00

ABSTRACT
UNFORESEEN

ND TOTAL

5,702
62,100
422,198

490,000

ELECTRICITY BOARD LIMITED

ON SUB-DIVISION, POOVANTHURUTHU

ESTIMATE

r Circuit Breaker at 220kV Substation, Pallom

Lakh Ninty Thousand only)

kV Substation, Pallom is an important grid substation in Kerala. It has 2 Nos. of


mers & 2 Nos. of 66/11kV transformers. It also has 3 Nos of 220kV feeders, 7
s of 11kV feeders in addition to a 110kV Capacitor Bank. During the timing test
ET team, it was found that during the closing of the breaker, there was a bounce
eaker of SB-PL 220kV feeder is of CGL make bearing Serial No.10444 C (Type
ng 1998 and is already 17 years old. Since bouncing is noted, it is very essential
arliest. Otherwise there are high chances that the breaker may fail during its
ear of the bearings and O rings. During overhauling, the pole unit flanges will be
lying anabond and changing the old O-rings of gas joints, replacing the old seal
be applied and the poles will be filled with positive gas pressure. For this work
m the breaker and re-assemblying the same pole units on the breaker after

repared based on the CPWD Delhi Analysis of Rates 2014 & Transmission data
pole unit from the breaker and assembled back to the breaker . The expenditure
sion for the O&M works of 220kV Substation, Pallom for the financial year 2016-