Q1:What are the difference between free float, total float and what is different between

Float and Slack?


Float and slack are the two different words for the same meaning.
Top 10 Primavera Interview questions and Model Answers
Free Float : amount of time , an activity can be delayed without delaying the successor activity
Total Float : amount of time , an activity can be delayed without delaying the project finish date.
Q2:What is a constraint in primavera?
Constrains in primavera is to fix the start or finish date as per following options:
1) Project Must Finish by
2) Mandatory Start / Mandatory Finish
3) Start / Finish On or After
4) Start / Finish On or Before
5) Start / Finish On
6) Expected Finish

Q3:How can you define the Critical Path in primavera?


Its the longest path through the project with the least amount of float,Filter the activities with total
float equal to or less than 0
Q4:What is WBS?
WBS means Work Breakdown Structure. it represents a hierarchical breakdown of a Project into
elements and deliverables.
Q5:What is an open end activity in primavera?
The open end activity is the activity that does not have any successor. Normally open end activity is
not accepted in schedule because the total float will be calculate from the end of the project and
these entire activities late dates gather at the end of the project and can not be prepare a logical late
start plan.
Q6:What is the difference between Retained Logic & Override Logic in progress update?
If a project is generally running according to plan and activities are not progressed out of sequence
then there will be virtually no difference between the two methods. BIG differences come when
activities are progressed out of sequence.
I believe in retained logic. Invariably that will produce the longest critical path but if activities have
been progressed out of sequence, there could be some resulting illogical dependencies remaining, in
particular resulting from dependencies with durations.
Progress override invariably produces a shorter critical path and again there could be some illogical
lack of dependencies resulting from activities having been progressed out of sequence.

Q7:How do u measure & compare the progress using primavera?


progress can be measured using EVM earned value management as per the following terms:
Budget at Completion (BAC)
Planned Value (PV) = budget at Completion (BAC) x Planned % Complete
Earned Value (EV) = budget at Completion (BAC) x Actual% Complete
Actual Cost (AC) = No formula What youve actually spent on the project
Schedule Performance Index (SPl) =Earned Value (EV) / Planned Value (PV)
Schedule Variance (SV) =Earned Value (EV) Planned Value (PV)
Cost Performance Index (CPI) =Earned Value (EV) / Actual Cost (AC)
To Complete Performance Index (TCPI) =(Budget at Completion (BAC) Earned Value (EV) ) / (Budget
at Completion (BAC) -Actual Cost (AC) )
Cost Variance (CV) = Earned Value (EV) -Actual Cost (AC)
For more information see this article:EVM earned value management
Q8:What is resource allocation and resource leveling?
Resource allocation is assigning resources to activities,determine the amount of labor, equipment
and money required for any activity.
Resource leveling is Resource requirements of all scheduled activities are compared to the maximum
quantity available at the time of leveling.An activity is delayed if too few resources are available at
any time during the activitys duration.The maximum quantity for a resource is determined through
the Max units/time for a particular resource in the Resources Tab.
Q9:What is an S Curve and how to create S Curve in primavera?
An S-curve is the cumulative cost function plotted on a histogram, which can vaguely resemble the
letter S. BCWS, BCWP, and ACWP are frequently plotted and compared on a histogram as separate
and shadowing S-curves.
Use the Activity Usage Profile to view cost or unit values for activities in the open project over time
according to a timescale you specify. The Activity Usage Profile displays resource allocations for all
activities or for the activities you select in the Activity Table, Activity Usage Spreadsheet, Gantt Chart,
or the Activity Network.
Q10:What are the difference between flag and milestone activity in primavera?
Mile stone & flags both are events rather then activities. Some client likes to use flags rather than
mile stone due the following differences.
1- With the use of flags the logic of main event can be easily tracked as these can not be created
without predecessor as stand alone allocating the constraint.Where as mile stone can.
2- Flags can not update manually as Primavera automatically update the status where as milestone
can be update manually.
3- Flags can not be constraint only driven by predecessor where as milestone can.