Planning of VEDANTA -MERAMANDALI 400KV LINE

Loc.8/2
Sl.No
1
2
3
4
5
6
7

Activities
Start Date
End Date
Foundation
Completed
Backfilling
Completed
Material Shifting to site
Completed
Shifting Conductor
Completed
Erection of Tower
18.06.2016
20.06.2016
Stringing
21.06.2016
23.06.2016
Antitheft Charging from 8/0 to upto location
No.35 of Vedanta End
25.06.2016
26.06.2016

Sl.No
1
2
3
4
5
6
7

Loc.34
Activities
Excavation of 3 Leg
PCC and Stub Setting 3 Leg
3 numbers Raft and 2 numbers Chimney
4th pit stubsetting and raft and Chimney
Tower material to be reach
Erection Of tower
Stringing

Start Date
End Date
Completed
18.06.2016
18.06.2016
19.06.2016
19.06.2016
20.06.2016
20.06.2016
23.06.2016
24.06.2016
26.06.2016
27.06.2016
30.06.2016

Note:Due to hard rock excavation of 4th leg is taking time,expected completion by


19/06/2016.