Академический Документы
Профессиональный Документы
Культура Документы
E-ISSN22498974
Research Paper
Civil, M.E appeared (CT &M) Department, S.S.G.B.C.O.E.T Bhusawal MH, India
2
Associate Prof Civil, M.E Structure, S.S.G.B.C.O.E.T Bhusawal MH, India
3
Director, Ethika Engineering Solutions (I) Pvt.Ltd, Pune, MH, India
ABSTRACT
There are so many approaches have been used for repetitive construction projects towards optimizing time and cost. In this
project we have implemented a proposed theoretical model for effective utilization of Activity Based Costing to get optimum
duration and cost. Generally critical path method is used for repetitive type of construction but in this project we use activity
based costing grant chart to find the duration of project. The goal of any construction project is to complete the project
within the estimated time and with minimum cost. The delay in a construction projects affects both owner and contractor.
The main goal of this study is to find out the optimum duration for the completion of project. In this project the data is
collected from the housing construction project. The expected time for the completion of project is finding out by using the
grant chart and by software. The collected data is analyzed and find out the optimum duration and cost. The outcomes of the
project will be shown that there still have rooms for construction process improvements with the application of Activity
Based Costing.
KEYWORDS Activity based costing, Grant chart, cost, duration.
1.1 INTRODUCTION
Activity Based Costing is a costing approach that
assigns resource costs to cost objects such as
products, services, or customers based on activities
performed for the cost objects. The premise of this
costing approach is that a firms products or services
are the results of activities and activities use
resources which incur costs. Costs of resources are
assigned to activities based on the activities that use
or consume resources (resource consumption
drivers), and costs of activities are assigned to cost
objects based on activities performed for the cost
objects (activity consumption drivers). ABC
recognizes the causal or direct relationships between
resource costs, cost drivers, activities, and cost
objects in assigning costs to activities and then to cost
objects. ABC assigns factory overhead costs to cost
objects such as products or services by identifying
the resources and activities as well as their costs and
amounts needed to produce output. Using resource
consumption cost drivers, a firm determines the
resource costs consumed by activities or activity
centres (activity cost pools) and calculates the cost of
a unit of activity. The firm then assigns the cost of an
activity to products or services by multiplying the
cost of each activity by the amount of the activity
consumed by each of the cost objects.
1.2 Objective of Study
The goal of any construction industry is to achieve
higher productivity with optimum duration and
optimum cost. The present study aims to evaluate the
effective management of activities to achieve the
optimum duration for project.
The objectives of the project are
To study the concept of activity based
costing in construction projects.
To involve the study regarding unnecessary
activity & losses occurring during the
project.
Identifying the sources of activities using
software base & compare with actual project
on site.
Analysis the above collected data.
To give the discussion and suggestion for
effective activity based costing management
for construction project
Int. J. Adv. Engg. Res. Studies/IV/I/Oct.-Dec,2014/09-14
1.3 Methodology
At initial stage the project will be studied from
Details drawings obtained from construction site.
Planning of all the activities will be done and
scheduling will be done depending upon the number
of activities in Software.
The data is collected from the housing construction
project. The data is based on the residential buildings
consisting of various types of blocks. The following
data is collected from the construction site for various
types of blocks i.e. expected Completion time of
project, Quantity of work for each activity,
optimistic, pessimistic and most likely time for each
activity, expected skilled and unskilled labor required
for completion project etc.
Analyze the above collected information and prepare
a result. In the analysis to minimize the overall
project duration in the construction projects by
activity based and spread sheet are used to prepare
optimum scheduling for the effective utilization of
the project on the basis of data collected from
housing project.
To outcome of this will be feasibility of the project
before execution, during execution and after
execution can be analyzed.
2 PREVIOUS RESEARCHES
2.1 Cost object
Traditional costing methods normally utilize a single
cost object a product or service. However, an
effective and accurate costing system has to
incorporate multiple cost objects. The activities are
classified as
1. Unit level activities, which are performed each
time a unit of a product or service is produced.
2. Batch level activities, which are performed each
time a batch of goods is produced(1)
Reciprocal allocation method allocates costs by
recognizing that the support departments provide
services to each other as well as to the production
departments jobs, or project. (2) The stage of the
ABC system attributes activity costs to the cost
objects, through cost drivers which correlate the
activities with those products and services. Cost
drivers are used to identify the way activities are
consumed by products/services.(3) Seven behavioral
and organizational variables are important to cost
E-ISSN22498974
Task Name
Resi. Appartment
Part "A" :- CIVIL
WORK
PLINTH LEVEL
STRUCTURE
RCC WORK
MASONARY
WORKS
WATERPROOFING
WORKS
PLASTER WORKS
COLOURING
WORKS
FLOORING &
DADO WORKS
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
366 days
17,120,368.11
327 days
1,583,597.40
40 days
6,051,327.97
161 days
750,903.19
128 days
1,144,323.13
24 days
1,625,100.47
79 days
743,787.98
55 days
2,135,670.19
82 days
1,270,480.64
50 days
1.8
DOORS &
WINDOW WORKS
1,717,958.00
90 days
1.8.1
497,600.00
30 days
1.9
S.S. Railing
MS Grill work @ 25
kg/sqm.
M.S. PERGOLA
Kitchen / Pantry
Platform
TRIMIX AT STILT
1.14Electrification
Plumbing
202,219.68
20 days
368,138.76
25 days
57,683.34
10 days
378,840.00
30 days
360,818.00
300,000.00
260,000.00
10 days
176 days
160 days
1.12
Duration
1.11
Summarized
Cost
17,680,368.11
1.7.1
1.10
E-ISSN22498974
1.13
1.14
1.15
Task Name
Resi. Appartment
Part"A":-CIVIL
WORK
RCC WORK
MASONARY
WORKS
0.15m thick CLC
Block Wall
WATERPROOFING
WORKS
PLASTER WORKS
COLOURING
WORKS
FLOORING &
DADO WORKS
DOORS & WINDOW
WORKS
S.S. Railing
MS Grill work @ 25
kg/sqm.
M.S. PERGOLA
Kitchen / Pantry
Platform
TRIMIX AT STILT
Electrification
Plumbing
1
1.2
1.3
1.3.1
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
1.12
1.13
1.14
1.15
Summarized
Cost
18,996,293.24
Duration
401 days
18,441,293.24
401 days
6,641,327.97
185 days
770,903.19
145 days
584,002.48
145 days
1,157,323.14
38 days
1,785,100.45
120 days
743,787.98
61 days
2,138,670.19
111 days
1,889,883.00
119 days
282,219.68
20 days
509,138.90
48 days
77,683.34
10 days
468,840.00
30 days
360,818.00
300,000.00
255,000.00
10 days
170 days
170 days
E-ISSN22498974
E-ISSN22498974
material
management
and
space
management.
10. As we know that if the cost and time for the
construction
industry
is
reduce
simultaneously the productivity of project is
get increase. There are so many methods to
find out the time duration to complete the
project like Microsoft Project and CPM. But
practically the project is not completed
within the estimated time. There are so
many factors which affect the time and cost
of the project gets adversely affected.
11. From the study conducted on housing
construction project for 2BHK flats and
shops it is observed that we get the optimum
duration for project with minimum cost the
actual duration for project was maximum.
12. So by applying the grant chart analysis we
get the optimum duration for both blocks.
So we manage activities effectively by grant
chart analysis we get the optimum solution.
13. The Table 4.2 shows the cost for various
scenarios, and from that we observe that for
the minimum duration, cost is also minimum
as compare to original duration and cost.
And important thing is that we get the
optimum duration without crashing any
activity.
REFERENCES
1.
E-ISSN22498974