Академический Документы
Профессиональный Документы
Культура Документы
Project Analysis
1.
Scenario analysis - Project NPV is recalculated by changing several inputs to new but
consistent values.
Real option - Opportunity to modify a project at a future date.
Sensitivity analysis - Analysis of how project NPV changes if different assumptions are
made about sales, costs, and other key variables.
Operating leverage - The degree to which fixed costs magnify the effect on profits of a
shortfall in sales.
Decision tree - A graphical technique for displaying possible future events and decisions
taken in response to those events.
Break-even analysis - Determines the level of future sales at which project profitability or
NPV equals zero.
Est time: 0105
Project analysis and evaluation
2.
False - Approval of the capital budget allows manager to go ahead with any project
included in the budget.
True - Project authorizations are mostly developed bottomup. Strategic planning is a
topdown process.
True - Project sponsors are likely to be overly optimistic.
False - The problem of overoptimism in cashflow forecasts can always be solved by
setting a higher discount rate.
Est time: 0105
Project analysis and evaluation
3.
True - Sensitivity analysis can be used to identify the variables most crucial to a projects
success.
10-1
False - Sensitivity analysis is used to obtain expected, optimistic, and pessimistic values
for total project cash flows.
False - Rather than basing ones estimate of NPV just on expected cash flows, it makes
more sense to average the NPVs calculated from the pessimistic and optimistic estimates
of cash flow.
False - Risk is reduced when a high proportion of costs are fixed.
True - The breakeven level of sales for a project is higher when breakeven is defined in
terms of NPV rather than accounting income.
Est time: 0105
Project analysis and evaluation
4.
The extra 2 million burgers increase total costs by $1.0 million.
Therefore, variable cost = $1.0 mil/2 mil burgers or $0.50 per burger.
$3.5 mil = (2 mil burgers $0.50) + fixed costs
Fixed costs = $2.5 mil
a. Fixed costs = $2.5 million
b. Variable costs = $0.50 per burger
c. Total cost = (1 mil burgers $0.50) + $2.5 mil = $3.0 mil
5.
10-1
6.
NPV = $478,141
NPV = $627,900
NPV = $770,660
NPV = $1,180,758
10-1
NPV = $627,900
NPV = $3,340,888
NPV = $185,996
NPV = $627,900
NPV = $1,034,849
NPV = $1,180,758
NPV = $627,900
NPV = $1,984,394
7.
1
1
9,000,000 $40,357
10
0.12 0.12 (1.12)
NPV $1,600,000
a.
1
1
9,000,000 $2,330,446
10
0.12 0.12 (1.12)
NPV $2,000,000
b.
1
1
9,000,000 $6,820,624
10
0.12 0.12 (1.12)
NPV $2,800,000
c.
10-1
1
1
9,000,000 $3,349,777
10
0.12 0.12 (1.12)
NPV $1,000,000
d.
1
1
9,000,000 $2,330,446
10
0.12 0.12 (1.12)
NPV $2,000,000
e.
1
1
9,000,000 $5,125,558
10
0.12 0.12 (1.12)
NPV $2,500,000
f.
1
1
9,000,000 $127,513
7
0.12 0.12 (1.12)
NPV $2,000,000
g.
1
1
9,000,000 $2,330,4465
10
0.12 0.12 (1.12)
NPV $2,000,000
h.
1
1
9,000,000 $3,847,097
13
0.12 0.12 (1.12)
NPV $2,000,000
i.
Est time: 0610
Sensitivity analysis
8.
1
1
$5.61
5
0.10 0.10 (1.10)
million
10-1
1
1
$2.88
5
0.10 0.10 (1.10)
million
1
1
$6.75
5
0.10 0.10 (1.10)
million
1
1
5
0.10 0.10 (1.10)
= 5 + [(3.6P 4.4)
Est time: 1115
Sensitivity analysis
9.
Price
Variable cost
Fixed cost
Sales
Most Likely
$50
$30
$300,000
30,000 units
Best Case
$55
$27
$270,000
33,000 units
Worst Case
$45
$33
$330,000
27,000 units
10-1
1
1
5.65022
0.12
10
0.12 (1.12)
10.
11.
a. Each dollar of sales generates $0.60 of pretax profit. Depreciation expense
is $100,000 per year, and fixed costs are $200,000. Therefore:
1
1
5.65022
0.12
10
0.12 (1.12)
10-1
12.
a. The accounting break-even point would be unaffected since taxes paid are zero when
pretax profit is zero, regardless of the tax rate.
b. The NPV break-even point would increase since the after-tax cash flow corresponding to any
level of sales falls when the tax rate increases.
Est time: 0105
Break-even analysis
13.
If depreciation is positive, then cash flow will be positive even when net income = 0.
Therefore, the level of sales necessary for cash flow break-even is less than the level of sales
necessary for zero-profit break-even.
b. If cash flow = 0 for the entire life of the project, then the present value of
cash flows = 0, and project NPV will be negative in the amount of the
required investment.
14.
a., b.
Investment
Sales
Var. Cost
Fixed Costs
Depreciati on
Pretax Profit
Taxes (0%)
Net Profit
Net Cash Flow
Year 0 Years 1 - 5
$3000
80 M
- 60 M
- 3000
- 1000
- 600
(20 M) - 1600
0
(20 M) - 1600
(20 M) - 1000
(20 M) - 1600
a.
=0
10-1
M = 80
80 is the accounting break even number of unit sales
1
1
3.79079
0.10
5
0.10
(1.10)
Year 0 Years 1 - 5
$3000
80 M
- 60 M
- 3000
(20 M)
- (7 M
13 M
13 M -
- 1000
- 600
- 1600
- 560)
- 1040
440
(13 M ) 1040
c.
=0
M = 80
80 is the accounting break even number of unit sales.
1
1
3.79079
0.10
5
0.10 (1.10)
Break-even analysis
15.
c. MACRS makes the project more attractive. The PV of the tax shield is higher,
so the NPV of the project at any given level of sales is higher.
16.
Sales
Variable costs
Fixed costs
Depreciation
$16,000,000
12,800,000
2,000,000
500,000
= Pretax profit
Taxes (at 40%)
= Profit after tax
+ Depreciation
= Cash flow from operations
a.
(80% of sales)
(includes depreciation on
new checkout equipment)
$700,000
280,000
$420,000
500,000
$920,000
Cash flow increases by $140,000 [from $780,000 (see Table 9-1) to $920,000].
The cost of the investment is $600,000. Therefore:
NPV = $600,000 + [$140,000 annuity factor (8%, 12 years)]
1
1
12
0.08 0.08 (1.08)
= $600,000 + $140,000
10-1
The equipment reduces variable costs from 81.25% of sales to 80% of sales. Pretax
savings are therefore equal to (0.0125 sales). On the other hand, annual depreciation
expense increases by $600,000/12 = $50,000. Therefore, accounting profits are unaffected
if sales equal $50,000/0.0125 = $4,000,000.
c.
The project reduces variable costs from 81.25% of sales to 80% of sales. Pretax savings
are therefore equal to (0.0125 sales). Annual depreciation expense increases by $50,000.
Therefore, after-tax cash flow increases by:
[(1 T) (revenue expenses)] + (T depreciation)
= [(1 0.4) (0.0125 sales)] + (0.4 50,000) = (0.0075 sales) + 20,000
For NPV to equal zero, the increment to cash flow times the 12-year annuity factor must
equal the initial investment:
Cash flow 7.53608 = 600,000 cash flow = $79,617
Therefore: (0.0075 sales) + 20,000 = 79,617 sales = $7,948,933
17.
NPV will be negative. Weve shown in the previous problem that the accounting breakeven level of sales is less than the economic break-even level of sales.
Est time: 0105
Break-even analysis
Operating leverage
1
19.
DOL =
a.
Profit = revenues variable costs fixed costs depreciation
10-1
b.
$1,600
11.67
$150
$1,600
2.14
$1,400
c.
DOL is higher when profits are lower because a $1 change in sales leads to a greater
percentage change in profits.
Est time: 0610
Operating leverage
20.
DOL =
If profits are positive, DOL cannot be less than 1.0. At sales = $7,000, profits for Modern
Artifacts (if fixed costs and depreciation were zero) would be $7,000 0.25 = $1,750.
At sales of $12,000, profits would be $12,000 0.25 = $3,000.
Profit is one-quarter of sales regardless of the level of sales. If sales increase by 1%, so will
profits. Thus DOL = 1.
Est time: 0610
Operating leverage
21.
DOL =
10-1
22.
a
b. While the initial NPV is negative, the existence of the production capability
gives the company the Option to Expand when the market demand rises.
c. By delaying installation of a fully integrated production line, the company
retains its Option to Abandon and can upgrade to newer technology if it
emerges.
d. The ability to switch the use of the plane gives the company a Production
Flexibility Option.
Est time: 0610
Real options
23.
We compare expected NPV with and without testing. If the field is large, then:
NPV = $8 million $3 million = $5 million
If the field is small, then:
NPV = $2 million $3 million = $1 million
If the test is performed and the field is found to be small, then the project is abandoned and
NPV = zero (minus the cost of the test, which is $0.1 million).
Therefore, without testing:
NPV = (0.5 $5 million) + [0.5 ($1 million)] = $2 million
With testing, expected NPV is higher:
NPV = $0.1 million + (0.5 $5 million) + (0.5 0) = $2.4 million
Therefore, it pays to perform the test.
The decision tree is as follows:
10-1
NPV = $5 million
Big oil field
Test (cost =
$100,000)
Small oil field
NPV = 0 (abandon)
Do not test
NPV = $5 million
24.
a.
b.
If you can shut down the mine 50% of the time, CF in the low-price years will be zero. In
the remaining years:
Average cash flow = $240,000 (0.5 $360,000) = $60,000
(We assume fixed costs are incurred only if the mine is operating. The fixed costs do not
rise with the amount of silver extracted, but they are not incurred unless the mine is in
production.)
Est time: 0610
Real options
10-1
25.
a.
b.
Now the worst-case value of the installed project is $95 million rather than $50 million.
Expected NPV increases to a positive value:
[0.5 ($140 $100)] + [0.5 ($95 $100)] = $17.5 million
Therefore, you should build the plant.
c.
PV = $140 million
Success
Invest
$100 million
Failure
Sell plant for
$95 million
Est time: 0610
Real Options
26.
Options provide the ability to cut losses or to extend gains. You benefit from good
outcomes but can limit damage from bad outcomes. The ability to change your actions
(e.g., to abandon or to expand or to change timing) is most important when the ultimate
best course of action is most difficult to forecast.
Est time: 0105
Real Options
10-1
Business
grows
27.
Priority plane
purchase
Yes
Business does
not grow
Do not buy
planes
Decision to
buy option
No
No priority
on future
planes
Real Options
28.
a.
Given a $100 per barrel price, the annual level of sales necessary for an NPV break-even
is 45.00 million barrels. The value was found using Excels Goal Seek, shown below:
10-1
10-1
c.
The accounting break-even level of sales changes each year with the changes in
depreciation expense. Given that depreciation is a noncash expense, the true break-even
level of sales should not vary if prices are unchanged.
d. The NPV of $1,200.33 million is found as an equally weighted average for all NPV
values given in part (a).
e. The facility may be worth building if the firm has the option to shut down the facilities
under price scenarios where the NPV is zero, or where the NPV can be significantly
reduced during these periods.
Est time: 1620
Break Even
10-1