Академический Документы
Профессиональный Документы
Культура Документы
90% P&S
Option 1: with Anchor Shaft
31.9%
27.6%
9.5%
9.2%
9.1%
7.0%
1.4%
1.0%
0.9%
0.8%
0.6%
0.4%
0.1%
0.1%
0.1%
0.1%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0%
25%
50%
75%
100%
Forecast: E36
Summary:
Display Range is from 6,736,607 to 9,401,632
Entire Range is from 6,251,220 to 9,933,632
After 20,000 Trials, the Std. Error of the Mean is 3,637
Statistics:
Trials
Mean
Median
Mode
Standard Deviation
Variance
Skewness
Kurtosis
Coeff. of Variability
Range Minimum
Range Maximum
Range Width
Mean Std. Error
Forecast: E36
20,000 Trials
Frequency Chart
126 Outliers
.021
417
.016
312.7
.010
208.5
.005
104.2
.000
0
6,736,607
7,402,863
8,069,119
8,735,376
9,401,632
Confidence Level: 80% would mean, For a project cost of $8,519,636 using
21% contingency would have a 80% confidence level that project cost would
not exceed this amount.
Risk No.
Risk/Opportunity Event
Concerns
PDT Discussions
Likelihood*
Impact*
Risk Level*
Project Schedule
Rough Order
Impact ($)
Likelihood*
Impact*
Risk Level*
Rough Order
Variance
Impact (mo) Distribution
Correlation
to Other(s)
Responsibility/POC
Affected Project
Component
Contract Risks (Internal Risk Items are those that are generated, caused, or controlled within the PDT's sphere of influence.)
PROJECT & PROGRAM
MGMT
Very Likely
Marginal
Moderate
Captured by
Schedule
Very Likely
Significant
High
6.0 Months
Uniform
PPM-2
Very Likely
Marginal
Moderate
Captured by
Schedule
Very Likely
Significant
High
3.2 Months
Uniform
PPM-3
Very Likely
Marginal
Moderate
Captured by
Schedule
Very Likely
Significant
High
7.2 Months
PPM-4
Very Likely
Marginal
Moderate
Captured by
Schedule
Very Likely
Significant
High
Captured by Risk
PPM-2
PPM-5
Likely
Marginal
Moderate
$1.1 M
Unlikely
Significant
Moderate
PPM-6
Very Likely
Marginal
Moderate
Captured by
Schedule
Very Likely
Significant
Likely
Significant
High
$2 M
Likely
Significant
PPM-1
Confusing and contradictory advice regarding continuously This issue presents a project management challenge in the
changing program and project requirements (i.e. Model
ability to plan, schedule, and produce, design and develop
Certification, Science Panel, Risk Assessment, ITR/ATR, documents due in some instances to indecision or lack of
EPR).
action at higher levels.
Project Manager
Project Schedule
Resource Providers
Project Schedule
Uniform
Project Manager
Project Schedule
N/A
Resource Providers
Project Schedule
1.8 Months
Triangular
Project Manager
High
2.4 Months
Uniform
High
4.8 Months
Uniform
PPM-7
PPM-8
Very Likely
Marginal
Moderate
Captured by
Schedule
Likely
Significant
High
Captured by Risk
PPM-2
N/A
PPM-9
Very Likely
Marginal
Moderate
$1.6 M
Likely
Significant
High
1.8 Months
Uniform
The PDT feels that the structural portion will likely go out
as full and open RFP, whereas the rock portion could to go
to an 8(a) or small business.
Likely
Significant
High
$2.7 M
Likely
Marginal
Moderate
3.8 Months
Unlikely
Significant
Moderate
$40 K
Unlikely
Marginal
Low
Not Studied
PPM-9
EST-1
Resource Providers
Project Schedule
District Management
District Management
Project Schedule
District Management
Triangular
TASB/Contracting
Uniform
Geotech Lead
Contract Cost
Project Schedule
PPM-1
CONTRACT ACQUISITION
CA-1
TECHNICAL
T-1
This is the first time that a hydraulic dredge has been used If the technique does not perform as planned, there will be
to place material to fill voids in the rock ramp to prevent
some rework or modification necessary to complete the
seepage though the bottom of the fishway.
work.
T-2
Likely
Negligible
Low
Not Studied
Likely
Marginal
Moderate
1.8 Months
Uniform
Technical Lead
T-3
Likely
Significant
High
$2.3 M
Unlikely
Marginal
Low
Not Studied
Triangular
Geotech Lead
Contract Cost
T-4
Project currently assumes access to small laydown/staging area footprint. Simultaneous contracts could
impact availability and congestion.
Likely
Marginal
Moderate
Captured by Risk
PR-5
Likely
Marginal
Moderate
Captured by Risk
PR-5
N/A
Project Manager
ENVIRONMENTAL/
REGULATORY
EN-1
Historical/Cultural Site
Very Unlikely
Negligible
Low
Not Studied
Very Unlikely
Critical
Low
Not Studied
N/A
Environmental Lead
EN-2
Status of Permits
Unlikely
Significant
Moderate
$66 K
Unlikely
Critical
Moderate
1.8 Months
Uniform
Environmental Lead
EN-3
Very Likely
Negligible
Low
Not Studied
Very Likely
Marginal
Moderate
3.2 Months
Uniform
Environmental Lead
Project Schedule
EN-4
Unlikely
Marginal
Low
Not Studied
Unlikely
Marginal
Low
Not Studied
N/A
Environmental Lead
Unlikely
Marginal
Low
Not Studied
Yes-No
Technical/Environmental
Leads
Unlikely
Marginal
Low
Not Studied
Uniform
Environmental Lead
Contract Cost
EN-5
HTRW Issues
EN-6
Unlikely
Significant
Moderate
Unlikely
Significant
Moderate
$949 K
CONSTRUCTION
C-1
C-2
In-water Work/Cofferdam
Construction
Inefficient Contractor
Unlikely
Significant
Moderate
$1.4 M
Unlikely
Significant
Moderate
Unlikely
Significant
Moderate
$519 K
Unlikely
Significant
Moderate
Unlikely
Significant
Moderate
$922 K
Unlikely
Significant
Moderate
Unlikely
Marginal
Low
Not Studied
Unlikely
Marginal
Low
Likely
Significant
High
$1.2 M
Likely
Negligible
C-6
Likely
Marginal
Moderate
$704 K
Likely
C-7
The project site has not been surveyed since the last flood
event.
Likely
Marginal
Moderate
$1.3 M
Likely
C-8
Contract Sequencing
Likely
Marginal
Moderate
Captured by
Schedule
Likely
Negligible
Low
Very Likely
Marginal
Likely
Significant
C-3
C-4
C-5
Site access/restrictions
Triangular
Cost
Engineering/Construction
2.5 Months
Triangular
Cost
Engineering/Construction
1.8 Months
Triangular
Construction
1.8 Months
PR-5
Not Studied
N/A
Cost
Engineering/Construction
Low
Not Studied
Triangular
Cost Engineering
Contract Cost
Significant
High
Captured by Cost
Risk Study
Triangular
Cost Engineering
Contract Cost
Negligible
Low
Not Studied
Uniform
Construction
Contract Cost
Likely
Significant
High
2.7 Months
Triangular
Contracting
Project Schedule
Not Studied
Likely
Negligible
Low
Not Studied
N/A
Real Estate
Moderate
Captured by Risk
PPM-7
Very Likely
Marginal
Moderate
3.2 Months
Uniform
Project Manager
Project Schedule
High
$961 K
Likely
Negligible
Low
Not Studied
Triangular
Cost Engineering
Contract Cost
REAL ESTATE
RE-1
COST ESTIMATING/
ENGINEERING
EST-1
EST-2
PPM-7
Programmatic Risks (External Risk Items are those that are generated, caused, or controlled exclusively outside the PDT's sphere of influence.)
This area is prone to regular flooding. There is a risk of a
major flood in this area during the project timeframe. This
could affect the rock placement, as well as capturing
quantities adequately before construction.
PR-1
Flooding
Likely
Significant
High
$3.7 M
Likely
Significant
High
3.2 Months
Uniform
PR-2
Unlikely
Significant
Moderate
$947 K
Unlikely
Marginal
Low
Not Studied
Triangular
Cost Engineering
Contract Cost
PR-3
Very Likely
Significant
High
Captured by
Schedule
Very Likely
Significant
High
3.3 Months
Triangular
Project Manager
Project Schedule
PR-4
Likely
Significant
High
Occurrence
would prevent
the project
Likely
Significant
High
Occurrence
would prevent
the project
N/A
Project Manager
PR-5
Hydropower
Fewer fish will use the fishway for migration if they can't
find the entrance. Entrainment mortality from hydropower
generation would negatively affect fish populations.
Likely
Significant
High
Occurrence
would prevent
the project
Likely
Significant
High
Occurrence
would prevent
the project
N/A
Project Manager
PR-6
Likely
Significant
High
Occurrence
would prevent
the project
Likely
Significant
High
Occurrence
would prevent
the project
N/A
Project Manager
C-3
*Likelihood, Impact, and Risk Level to be verified through market research and analysis (conducted by cost engineer).
1. Risk/Opportunity identified with reference to the Risk Identification Checklist and through deliberation and study of the PDT.
2. Discussions and Concerns elaborates on Risk/Opportunity Events and includes any assumptions or findings (should contain information pertinent to eventual study and analysis of event's impact to project).
3. Likelihood is a measure of the probability of the event occurring -- Very Unlikely, Unlikely, Moderately Likely, Likely, Very Likely. The likelihood of the event will be the same for both Cost and Schedule, regardless of impact.
4. Impact is a measure of the event's effect on project objectives with relation to scope, cost, and/or schedule -- Negligible, Marginal, Significant, Critical, or Crisis. Impacts on Project Cost may vary in severity from impacts on Project Schedule.
5. Risk Level is the resultant of Likelihood and Impact Low, Moderate, or High. Refer to the matrix located at top of page.
6. Variance Distribution refers to the behavior of the individual risk item with respect to its potential effects on Project Cost and Schedule. For example, an item with clearly defined parameters and a solid most likely scenario would probably follow a triangular or normal distribution. A risk item for which the PDT has little data or probability
of modeling with respect to effects on cost or schedule (i.e. "anyone's guess") would probably follow a uniform or discrete uniform distribution.
7. The responsibility or POC is the entity responsible as the Subject Matter Expert (SME) for action, monitoring, or information on the PDT for the identified risk or opportunity.
8. Correlation recognizes those risk events that may be related to one another. Care should be given to ensure the risks are handled correctly without a "double counting."
9. Affected Project Component identifies the specific item of the project to which the risk directly or strongly correlates.
10. Project Implications identifies whether or not the risk item affects project cost, project schedule, or both. The PDT is responsible for conducting studies for both Project Cost and for Project Schedule.
11. Results of the risk identification process are studied and further developed by the Cost Engineer, then analyzed through the Monte Carlo Analysis Method for Cost (Contingency) and Schedule (Escalation) Growth.
Project Scope
Contingency on Base Estimate
Baseline Estimate Cost (Most Likely) ->
Baseline Estimate Cost Contingency Amount ->
Baseline Estimate Construction Cost (80% Confidence) ->
Contingency on Schedule
80% Confidence Project Schedule
Project Schedule Duration (Most Likely) ->
46.0 Months
Schedule Contingency Duration ->
29.3 Months
Project Schedule Duration (80% Confidence) ->
75.3 Months
Project Schedule Contingency Amount (80% Confidence) ->
$2,111,954
This is a 100% Federal project and no lands and damage costs are included.
No relocation costs were expected for this project.
Project Contingency
Project Contingency Amount (80% Confidence) ->
Project Contingency Percentage (80% Confidence) ->
$55,868,598
Contingency Analysis
Contingency
$35,833,239
-10.45%
###
5%
$44,839,308
12.06%
###
$46,442,558
16.06%
###
15%
$47,497,895
18.70%
###80,000,000
20%
$48,400,180
20.96%
25%
$49,132,023
22.78%
###
###70,000,000
30%
$49,744,595
24.32%
35%
$50,360,782
25.85%
40%
$50,988,057
27.42%
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
$51,575,622
$52,151,692
$52,737,247
$53,286,037
$53,856,537
$54,462,516
$55,094,405
$55,868,598
$56,665,502
$57,672,460
$59,268,192
$67,240,463
28.89%
30.33%
31.79%
33.17%
34.59%
36.11%
37.68%
39.62%
41.61%
44.13%
48.12%
68.04%
Cost
###50,000,000
###
###40,000,000
###
###30,000,000
###
###20,000,000
###
###10,000,000
###
###
0
###
###
###
60,000,000
###
95%
90%
Confidence Levels
100%
85%
80%
75%
70%
65%
60%
55%
50%
45%
40%
35%
30%
25%
20%
5%
"M os t Likely"
Baseline Cos t
15%
Value
0%
10%
0%
Confidence Level
$40,014,944
10%
Most Likely
Cost Estimate
Contingency Analysis
###
###
###
###
###80,000,000
###
###
###60,000,000
###
###
###
###40,000,000
###
###
###
###20,000,000
Corresponding Contingency
Am ount
95%
90%
85%
80%
75%
70%
65%
60%
55%
100%
50%
45%
40%
35%
30%
25%
20%
0
15%
###
###
###
###
###
5%
Contingency
-9.01%
10.72%
14.19%
16.46%
18.41%
19.96%
21.25%
22.57%
23.92%
25.18%
26.41%
27.66%
28.81%
30.01%
31.31%
32.67%
34.34%
36.02%
38.20%
41.62%
58.85%
0%
Value
$36,408,945
$44,302,729
$45,692,598
$46,603,024
$47,383,181
$48,001,018
$48,517,176
$49,044,633
$49,586,489
$50,090,006
$50,584,341
$51,083,142
$51,542,773
$52,025,214
$52,543,790
$53,088,118
$53,756,644
$54,430,091
$55,298,936
$56,667,978
$63,563,297
10%
Confidence Level
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
$40,014,944
Cost
Most Likely
Cost Estimate
Contingency Analysis
46.0 Months
Contingency
52.1 Months
13.25%
64
55.3 Months
20.08%
64
15%
57.4 Months
24.72%
64
20%
59.2 Months
28.62%
25%
60.9 Months
32.27%
64120
64
30%
62.3 Months
35.36%
35%
63.6 Months
38.20%
64100
64
40%
64.9 Months
40.94%
64
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
66.1 Months
67.3 Months
68.6 Months
69.9 Months
71.2 Months
72.5 Months
73.8 Months
75.3 Months
77.1 Months
79.2 Months
82.5 Months
98.4 Months
43.63%
46.24%
49.02%
51.87%
54.69%
57.49%
60.29%
63.68%
67.63%
72.05%
79.31%
113.78%
64
64
64
64
64
64
64
64
64
64
64
64
80
60
40
Current Proje ct
Duration
20
95%
100%
100%
90%
95%
85%
80%
75%
70%
65%
60%
55%
50%
45%
40%
0
35%
Duration
5%
10%
30%
64
25%
-22.36%
20%
35.7 Months
15%
0%
5%
Value
10%
Confidence Level
0%
Most Likely
Cost Estimate
Confidence Levels
Contingency Analysis
Schedule Contingency (Amount) Analysis
$40,014,944
Contingency
0%
$(575,707)
-1.44%
###
5%
$536,579
1.34%
###
10%
$749,960
1.87%
###
15%
$894,871
2.24%
20%
$1,016,999
2.54%
###
###$50,000,000
25%
$1,131,005
2.83%
30%
$1,227,419
3.07%
35%
$1,316,148
3.29%
40%
$1,401,568
3.50%
45%
$1,485,617
3.71%
50%
$1,567,351
3.92%
55%
$1,654,105
4.13%
60%
$1,743,263
4.36%
65%
$1,831,324
4.58%
70%
$1,918,726
4.80%
75%
###
$48,000,000
###
###$46,000,000
Cost
###
$44,000,000
###
###$42,000,000
###$40,000,000
###
###$38,000,000
###$36,000,000
###
$34,000,000
###
Confidence Levels
90%
85%
80%
75%
70%
###
65%
9.19%
60%
6.50%
$3,677,165
55%
$2,600,213
100%
50%
95%
###$32,000,000
###
$30,000,000
###
45%
5.93%
40%
$2,373,524
35%
90%
30%
5.59%
25%
5.28%
20%
5.01%
$2,111,954
$2,235,411
15%
$2,006,287
80%
85%
10%
Value
5%
Confidence Level
0%
Most Likely
Cost Estimate
Project Cost
Risk No.
Risk/Opportunity Event
Likelihood*
Impact*
Risk Level*
Variance
Distribution
Correlation
to Other(s)
Low
Most Likely
High
Low
Most Likely
High
-2.5%
0.0%
5.8%
0.0%
0.0%
6.2%
Internal Risks (Internal Risk Items are those that are generated, caused, or controlled within the PDT's sphere of influence.)
PROJECT & PROGRAM MGMT
This issue has had an effect on the
Schedule developed with the overall performance of the planning
assumption that sufficient
and engineering, as far as schedule
funding would be received on a
is concerned. PDT feels that the
timely basis. Thus far, this has
overall project schedule is a bit
not occurred.
optimistic.
Very Likely
Marginal
Moderate
Very Likely
Marginal
Moderate
Very Likely
Marginal
Moderate
There is an increased
workload that is outpacing the
current staff level's ability to
keep pace.
Very Likely
Marginal
Moderate
Likely
Marginal
Moderate
Very Likely
Marginal
PPM-7
Likely
Significant
High
PPM-8
Very Likely
Marginal
Moderate
PPM-9
Very Likely
Marginal
Moderate
Uniform
$0
$0
$2,000,747
0.0%
0.0%
5.0%
Likely
Significant
High
Triangular
($2,403,729)
$0
$5,835,042
-6.0%
0.0%
14.6%
Unlikely
Significant
Moderate
Uniform
($47,228)
$0
$61,602
-0.1%
0.0%
0.2%
Triangular
($2,451,874)
$0
$4,903,748
0.0%
0.0%
0.2%
PPM-1
PPM-2
PPM-3
PPM-4
PPM-5
PPM-6
Triangular
($1,003,749)
$0
$2,333,653
Moderate
Uniform
EST-1
$0
$0
$2,476,886
Removed from Cost Risk Study This item is captured by Risk PPM7
CONTRACT ACQUISITION
CA-1
TECHNICAL
T-1
T-3
T-4
Likely
Significant
High
Likely
Marginal
Moderate
Unlikely
Significant
Moderate
ENVIRONMENTAL/REGULATORY
EN-2
Status of Permits
Uniform
HTRW Issues
Unlikely
Significant
Moderate
Unlikely
Significant
Moderate
Uniform
C-1
In-water Work/Cofferdam
Construction
Unlikely
Significant
Moderate
C-2
Inefficient Contractor
Unlikely
Significant
Moderate
C-3
Unlikely
Significant
Moderate
Triangular
C-5
Likely
Significant
High
Likely
Marginal
Likely
EN-5
EN-6
$0
$0
$82,286
$0
$0
$1,200,448
0.0%
0.0%
3.0%
Triangular
($855,703)
$0
$1,996,641
-2.1%
0.0%
5.0%
Triangular
($1,633,615)
$0
$3,171,136
-4.1%
0.0%
7.9%
$0
$0
$945,777
0.0%
0.0%
2.4%
Triangular
$0
$0
$2,131,366
0.0%
0.0%
5.3%
Moderate
Triangular
($486,721)
$0
$1,460,163
-1.2%
0.0%
3.6%
Marginal
Moderate
Uniform
$0
$0
$1,630,778
0.0%
0.0%
4.1%
Likely
Marginal
Moderate
Very Likely
Marginal
Moderate
CONSTRUCTION
C-6
C-7
C-8
Contract Sequencing
PR-5
COST ESTIMATING/ENGINEERING
EST-1
PPM-7
EST-2
Likely
Significant
High
Triangular
($759,957)
$0
$2,000,747
-1.9%
0.0%
5.0%
0.0%
0.0%
11.5%
-12.2%
0.0%
8.2%
Programmatic Risks (External Risk Items are those that are generated, caused, or controlled exclusively outside the PDT's sphere of influence.)
PR-1
Flooding
PR-2
Unlikely
Significant
Moderate
Very Likely
Significant
High
Likely
Significant
High
Hydropower
Hydropower development is
being considered in the
spillway which may change the
flow patterns that attract fish to
the fishway entrance.
Likely
Significant
High
Likely
Significant
High
PR-3
PR-4
PR-5
PR-6
Likely
Significant
High
Uniform
$0
$0
$4,619,050
Triangular
($4,892,335)
$0
$3,261,557
C-3
$40,014,944
$40,014,944
TOTAL PROJECT
COST (BASELINE)
Percentile
Forecast values
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
$36,408,945
$44,302,729
$45,692,598
$46,603,024
$47,383,181
$48,001,018
$48,517,176
$49,044,633
$49,586,489
$50,090,006
$50,584,341
$51,083,142
$51,542,773
$52,025,214
$52,543,790
$53,088,118
$53,756,644
$54,430,091
$55,298,936
$56,667,978
$63,563,297
39920822.796
47879342.361
49755944.601
51175947.967
52391087.8
53436537.928
54404040.843
55369007.171
56296401.168
57191455.73
58057715.8
58993474.558
59931683.628
60897196.228
61940032.855
62894655.254
63994740.82
65225732.27
66720886.435
68882273.726
77260091.279
Contingency
Amount
($3,605,999)
$4,287,785
$5,677,654
$6,588,081
$7,368,237
$7,986,074
$8,502,232
$9,029,689
$9,571,545
$10,075,062
$10,569,397
$11,068,199
$11,527,829
$12,010,270
$12,528,846
$13,073,174
$13,741,700
$14,415,148
$15,283,992
$16,653,034
$23,548,354
Contingency
%
-9.01%
10.72%
14.19%
16.46%
18.41%
19.96%
21.25%
22.57%
23.92%
25.18%
26.41%
27.66%
28.81%
30.01%
31.31%
32.67%
34.34%
36.02%
38.20%
41.62%
58.85%
Risk Event
Project Schedule in Question
Low
Most Likely
High
Risk Event
No Control over Staff Priorities
Low
Most Likely
High
Risk Event
Project competing with other projects for funding
Low
Most Likely
High
Risk Event
Functional and Technical Staff overloaded
Low
Most Likely
High
Risk Event
Product Development by Several
Sources/Communication Challenges
Low
Most Likely
High
($1,003,749)
$0
$2,333,653
$0
-$1,003,749
Notes:
Likely
Low
High
This item captures the risk of cost growth due to coordination/communication challenges,
as the products are developed by several sources.
Likely assumes no change from the baseline estimate.
Low assumes improvement of PED costs by up to 10%, and improvement of construction
costs by up to 2%.
High assumes increase in PED costs by up to 20% as well as increase to construction
costs by up to 5%.
Phase
Phase 1 Construction
Phase 1 PED
Phase 1 Total
Phase 2 Construction
Phase 2 PED
Phase 2 Total
Total
Difference
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
$2,333,653
Low
$15,149,822
$3,072,938
$18,222,760
$16,813,435
$90,000
$16,903,435
$35,126,195
($1,003,749)
Likely
$15,459,002
$3,414,375
$18,873,377
$17,156,567
$100,000
$17,256,567
$36,129,944
$0
High
$16,231,952
$4,097,250
$20,329,202
$18,014,395
$120,000
$18,134,395
$38,463,597
$2,333,653
Risk Event
Losing Staff at Critical Milestones
Low
Most Likely
High
Notes:
Likely
Low
High
Risk Event
Timely Response to Critical Decision
Low
$0
$0
Most Likely
$0
$0
High
$2,476,886
$2,476,886
This item captures the risk that responses to critical decisions may not come in a timely
manner, and could impact project costs.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
6 Month
Cumulative
Interruption
Phase 1
Phase 2
Subtotals
High assumes that additional review is required, adding the cost of another review, as well
as prolonging the project such that the PDT incurs more cost in their time spent on the
project.
Monthly
PM Costs
Design Costs (14% Phase 1/1% Contracting
Construction Cost
Duration
S&A (9%)
Review Costs Total
Burn
(0.5%)
Phase 2)
(0.5%)
$15,459,002
12
$1,288,250
$38,648
$1,082,130
$38,648
$695,655
$75,000 $1,930,080.26
$17,156,567
24
$714,857
$21,446
$42,891
$21,446
$386,023
$75,000 $546,805.58
$32,615,569
36
$2,003,107
$60,093
$1,125,022
$60,093
$1,081,678
$150,000
$2,476,886
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Internal Red Tape Causes Delays
Low
Most Likely
High
Notes:
Likely
Low
High
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Pressure to deliver project on an accelerated schedule
Low
$0
$0
Most Likely
$0
$40,014,944
High
$2,000,747
$2,000,747
This item captures the risk that pressure to deliver the project on an accelerated schedule
has impact on costs.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that pressure to deliver on an accelerated schedule may produce
unintended consequences of construction modifications due to lesser quality products due
to the expediency in producing the planning and design deliverables. Up to 5% changes
assumed as worst case.
Notes:
Likely
Low
High
Risk Event
Contract Acquisition Strategy Not Determined
Most Likely
$0
$0
High
$5,835,042
$5,835,042
This item captures the risk that the eventual acquisition method could add costs to the
project. Currently, Phase I is contemplated to be a full and open negotiated procurement.
Phase II could potentially go out to an 8(a) or a small business.
Likely assumes no change from the baseline estimate.
Low assumes cost savings due to favorable procurement effects on costs. For Phase I,
assuming it could use a "trade-off" acquisition process, it was assumed that the contract
cost could be up to 10% less. For Phase II, it was assumed that setting aside to a small
business or 8(a) could decrease the contract cost by up to 5%.
High assumes increase to contract costs due to the acquisition methods used. For Phase
I, assuming it could use a "trade-off" acquisition process, it was assumed that the contract
cost could be up to 10% higher. For Phase II, it was assumed that setting aside to a small
business or 8(a) could increase the contract cost by up to 25%.
Phase
Phase 1 Construction
Phase 2 Construction
Total
Difference
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Low
($2,403,729)
-$2,403,729
Low
$13,913,102
$16,298,738
$30,211,840
($2,403,729)
Likely
$15,459,002
$17,156,567
$32,615,569
$0
High
$17,004,902
$21,445,708
$38,450,611
$5,835,042
Notes:
Likely
Low
Risk Event
Uncertainty with Filling of Voids
Low
($47,228)
$576,562
Most Likely
$0
$623,790
High
$61,602
$685,392
This item captures the risk of incurring additional costs due to rework if the hydraulic
dredge placement does not perform as planned.
Likely assumes no change from the baseline estimate.
Low assumes that the current quantity of material to dredge (215,992 CY) is more than
actual conditions. Per the standard VEQ clause (FAR 52.211-18), up to 15% less quantity
is assumed (183,593 CY).
High
High assumes that current quantity of material to dredge is less than actual conditions.
Up to 20% is assumed (259,190 CY).
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Notes:
Likely
Low
High
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Low
Most Likely
High
($2,451,874)
$0
$4,903,748
$14,080,903
$16,532,777
$21,436,525
This item captures the risk that the Midwest flooding of 2008 could have scoured rock
from the area or deposited more, altering the actual quantity of rock required from the
baseline estimate.
Likely assumes no change from the baseline estimate.
Low assumes that less rock is required to be placed than anticipated. Per the standard
VEQ clause (FAR 52.211-18), up to 15% less quantity is assumed.
High assumes that more rock is required than currently estimated. Up to 30% more was
assumed as worst case.
Risk Event
Conflicts with potential hydro-plant and lock expansion
project.
Low
Most Likely
High
Removed from Risk Study - This item is captured by PR-5
Notes:
Likely
Low
High
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Status of Permits
Low
$0
$0
Most Likely
$0
$0
High
$82,286
$82,286
This item captures the risk that the permit application process becomes more complicated
than anticipated.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that complications in the permitting process cause up to 4 months of labor
for 4 people for 30% of their workload ~ $82,286.
Status of Permits
Assumption values
$6
$8,077
$16,394
$24,986
$33,330
$41,652
$49,729
$57,817
$66,159
$74,098
$82,285
Notes:
Likely
Low
High
Risk Event
HTRW Issues
Low
$0
$0
Most Likely
$0
$41,972,976
High
$1,000,000
$1,000,000
This item captures the risk that HTRW remediation may be necessary, if the project
footprint changes. Assuming that there is a 15% chance of finding HTRW contamination,
this does not occur at the 80% confidence level.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes the project incurs remediation costs up to $1 Million.
0
0
Notes:
Likely
Low
High
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Fishway not effective
Low
$0
$0
Most Likely
$0
$40,014,944
High
$1,200,448
$1,200,448
This item captures the risk that the fishway, as designed, will not be effective since this
type of structure has never been built or tested elsewhere.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that the costs increase by up to 3% for inclusion of adaptive management
features.
Risk Event
In-water Work/Cofferdam Construction
Low
($855,703)
$39,159,241
Most Likely
$0
$40,014,944
High
$1,996,641
$42,011,585
Notes:
Likely
Low
High
This item captures the risk of cost growth due to the challenges of in-water work.
Likely assumes no change from the baseline estimate.
Low assumes that productivity is up to 5% improved from the baseline estimate.
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Inefficient Contractor
Low
($1,633,615)
$38,381,329
Most Likely
$0
$40,014,944
High
$3,171,136
$43,186,079
Notes:
Likely
Low
High
High assumes that the eventual contractors are less efficient than currently contemplated
(up to 15% less productive).
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Inefficient Contractor
Assumption values
($1,598,881)
($742,894)
($382,913)
($101,928)
$152,184
$427,477
$720,520
$1,027,626
$1,418,739
$1,937,381
$3,137,999
Low assumes that the eventual contractors are more efficient than currently contemplated
(up to 10% more productive).
Notes:
Risk Event
Conflicts with Other Contracts
Low
$0
$40,014,944
Most Likely
$0
$40,014,944
High
$945,777
$40,960,721
Likely
Low
High
This item captures the risk of cost growth due to challenges in working concurrently with
other contractors on related and unrelated projects.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that conflicts with other contractors reduced productivity by up to 5%.
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Notes:
Likely
Low
High
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Labor Forces from Outside Area
Low
$0
$40,014,944
Most Likely
$0
$40,014,944
High
$2,131,366
$42,146,309
This item captures the risk that labor will have to be paid a premium for working out of the
area.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that all skilled craft labor must be paid a premium for travel from outside
the area amounting to $52.50 per day for lodging ($6.56/hour) and $29.25 per day for
subsistence ($3.66/hour). Rates are 75% of the current National General GSA rates.
Notes:
Likely
Low
Risk Event
Material availability and delivery
Low
($486,721)
$9,247,702
Most Likely
$0
$9,734,423
High
$1,460,163
$11,194,586
This item captures the risk of cost growth due to extraordinary escalation on some key
items.
Likely assumes no change from the baseline estimate.
Low assumes that the overall material costs are up to 5% lower than currently estimated.
High
High assumes that overall material costs are up to 15% higher than currently estimated.
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Notes:
Likely
Low
High
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Differing Site Conditions
Low
$0
$0
Most Likely
$0
$32,615,569
High
$1,630,778
$1,630,778
This item captures the risk that flood events could have created differing underground
conditions than assumed in the baseline estimate.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that differing geotechnical conditions could generate changes up to 5% of
the overall construction cost, as currently estimated.
Risk Event
Contract Sequencing
Low
Most Likely
High
Risk Event
Unknowns with Reviews and Iterative Process
Low
Most Likely
High
Removed from Risk Study - This item is captured by PPM-7
Notes:
Likely
Low
Risk Event
Estimate and Schedule Reflecting "Most Likely"
Occurrence
Low
Most Likely
High
($759,957)
$0
$2,000,747
$39,254,987
$40,014,944
$42,015,691
This item captures the risk that uncertainty with the schedule and with the baseline
scoping documents introduced potential for variance of the baseline cost estimate.
Likely assumes no change from the baseline estimate.
Low assumes that scoping and scheduling issues reduce the overall costs by requiring no
overtime.
High
High assumes that scoping and scheduling issues increase the overall costs by up to 5%.
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Notes:
Likely
Low
High
Risk Event
Flooding
Low
$0
$0
Most Likely
$0
$0
High
$4,619,050
$4,619,050
This item captures the risk that flooding, if it occurs, could cause significant
rework/damage. This risk models the probability of a 10-year flood event. At a 10%
chance per year for the 3 year construction period, this occurs once at the 80%
confidence level.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that a major flood event occurs during construction, causing rework of the
cofferdam and additional dewatering, amounting to 50% of the currently estimated
cofferdam and dewatering work.
Cofferdam
$8,666,625
$4,333,313
Dewatering
$571,475
$285,738
Total
$9,238,100
$4,619,050
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Flooding
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Flooding
Assumption values
$63
$461,482
$929,506
$1,400,774
$1,872,577
$2,331,115
$2,783,411
$3,229,459
$3,690,801
$4,138,977
$4,618,459
Assumption values
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
1.0
1.0
3.0
0
0
Notes:
Likely
Low
Risk Event
Market Conditions (saturated construction market)
Low
($4,892,335)
$27,723,233
Most Likely
$0
$32,615,569
High
$3,261,557
$35,877,126
This item captures the risk of cost variance due to market conditions.
Likely assumes no change from the baseline estimate.
Low assumes that the ultimate contract costs are up to 15% lower than currently
estimated.
High
High assumes that ultimate contract costs are up to 10% higher than currently estimated.
Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Risk Event
Adequacy of project funding (incremental)
Low
Most Likely
High
Risk Event
Hydropower
Low
Most Likely
High
Risk Analysis
Project Description
1 Mobilization and Demobilization
Modify Existing Tainter Valve #3Remove/replace bushing with greaseless bushing/reinstall
2 Valve
3 Install Monolith 6/8 and Monolith 8/10 Joint Grout Plug (similar to water stops)
4 ?Anchor Shafts (Construct and abandon)
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Concrete Demolition TV #3 Shaft (Incl. Setting bulkheads on either side of TV, dewater
shaft and culvert (Project pumps are inadequate, extra pumping capacity will be required))
Concrete Demolition Monolith 8 and Monolith 27
Plug Rock Drain Pipe and French Drain
Repair Concrete and Cracks in elevation 263 Gallery
Replace Monolith 6 uplift Pressure Instruments
Drill Flow Breccia Consolidation Grout Holes and Rock Drain Abandonment Holes
Flow Breccia Consolidation Grouting and Rock Column Drain Grouting
Epoxy Grout TV Shaft #3, Monoliths 8 and 27 Bulkhead Slots (incl. Epoxy surface
patching, installing 6' grout tubes, and epoxy grouting)
Grout Monoliths 6, 8, and 27 Lock Chamber Cracks and Lift Lines
Install Post-tensioned Anchors elevation 170' and below
Install Post-tensioned Anchors elevation above 170'
Install Tainter Valve Shaft #3 Pre-Cast Concrete Panels (incl. Panel fabrication, drilling and
grouting dowels, and grouting behind panels)
Repair Monolith 6 Concrete Spall Area (Incl. Demo, drilling and grouting dowels,
reinforcement, new cnc.)
Repair Monolith 27 Bulkhead Slot Concrete Spalls
Braced Excavation (incl. Contractor design, excavation, dewatering, anchor block
fabrication, backfill, piezometer cable rerouting)
Load Cells and Strain Gages (incl. Wire routing in to be constructed slots in lock face, and
terminus)
Drain Line Installation (incl. Drilling from within brace excavation, open excavation behind
most of lock, MH's and weirs, drilling at D/S to terminus)
Pave Embankment Dam Access Road (incl. Subgrade prep, line stripes, Guard Rail
Replacement).
Services of Skilled Craftsmn
Temp Demob & Remob
Standby for Temp Demob
Tainter Valve Wrapper
TV Weld Repair [9/16 cjp]
TV Weld Repair [3/8 fill]
Estimate
326,430
$
136,195
$
24,104
$ 1,057,633
$ 231,531
$
25,443
$ 1,410,178
$
$
$
272,389
26,782
1,762,722
$
$
$
$
$
$
$
$
$
$
$
$
$
$
317,344
76,706
1,293
31,011
12,404
462,225
1
$
$
$
$
$
$
$
352,604
80,743
1,361
32,643
13,057
616,300
1
$
59,493
$
221,802
$ 1,642,562
$
1
$
62,798
$ 234,125
$ 1,564,345
$
1
$
$
$
$
66,103
246,447
1,564,345
1
330,918
350,384
$
$
124,482
32,412
$
$
131,804
32,412
316,563
110,343
$
$
$
$
$
$
$
$
11,042,515
High
375,395
EX High
424,359
$
286,008
$
30,799
$ 1,850,858
$
$
$
340,486
36,156
2,027,130
$
$
$
$
$
$
$
405,495
92,854
1,701
48,965
19,586
770,375
2
$
$
$
$
$
$
$
458,385
100,929
2,042
65,286
26,114
924,450
2
$
76,018
$
283,414
$ 1,955,431
$
2
$
$
$
$
389,315
467,178
$
$
146,449
32,412
$
$
353,806
372,427
116,473
120,329
145,446
7,601
14,598
51,054
108,113
77,180
85,000
42,500
$
$
$
$
$
$
$
8,024
15,409
54,057
114,120
81,720
95,000
47,500
299,713
72,669
1,225
29,379
11,751
369,780
1
9,269,259
7,032,396
Low
323,166
EX Low
163,215
6,198,722
(300,000) $
(100,000)
EX Low
Low%
High%
30%
-15%
5%
25%
-5%
-20%
15%
5%
35%
15%
-15%
-10%
15%
30%
-10%
-10%
-10%
-10%
-40%
-10%
-5%
-5%
-5%
-5%
-25%
-5%
15%
25%
50%
50%
25%
50%
25%
50%
100%
100%
50%
100%
89,239
332,703
2,190,083
2
-10%
-5%
15%
35%
-10%
-5%
-10%
-5%
0%
-5%
15%
25%
50%
35%
40%
100%
506,110
-15%
-10%
20%
30%
175,739
48,618
$
$
190,384
64,824
-15%
-10%
20%
30%
0%
0%
50%
100%
465,534
521,398
-15%
-5%
25%
40%
122,603
153,254
171,644
-10%
-5%
25%
40%
161,607
184,032
198,188
-15%
-10%
30%
40%
$
$
$
$
$
$
$
8,446
16,220
60,063
120,126
90,800
100,000
50,000
$
$
$
$
$
$
$
10,980
17,842
72,076
138,145
108,960
120,000
60,000
$
$
$
$
$
$
$
12,669
18,653
78,082
150,158
118,040
130,000
65,000
-10%
-5%
30%
50%
-10%
-15%
-10%
-15%
-15%
-15%
-5%
-10%
-5%
-10%
-5%
-5%
10%
20%
15%
20%
20%
20%
15%
30%
25%
30%
30%
30%
500,000
200,000
100,000
300,000
750,000
1,000,000
7,032,396
-1%
-50%
-10%
-40%
EX High
15%
-50%
200,000
500,000
(300,000) $ (100,000) $
100,000
300,000
750,000
1,000,000