Вы находитесь на странице: 1из 42

John Day, Nav Lock Monolith Repair

90% P&S
Option 1: with Anchor Shaft

Crystal Ball Report


Simulation started on 11/3/03 at 12:35:13
Simulation stopped on 11/3/03 at 12:35:60

Sensitiv ity Chart


Target Forecast: E36
Plans and Specs resulting Claims

31.9%

?Anchor Shafts (Construct and abandon )

27.6%

Overall Job (Bidding Climate)

9.5%

Install Post-tensioned Anchors elevatio n

9.2%

Drill Flow Breccia Consolidation Grout H

9.1%

Weather and other jobsite conditions

7.0%

Braced Excavation (incl. Contractor des i

1.4%

Modify Existing Tainter Valve #3Remove /r

1.0%

Mobilization and Demobilization

0.9%

Install T ainter Valve Shaft #3 Pre-Cast

0.8%

Concrete Demolition T V #3 Shaft (Incl. S

0.6%

Grout Monoliths 6, 8, and 27 Lock Cham be

0.4%

Load Cells and Strain Gages (incl. Wire

0.1%

Drain Line Installation (incl. Drilling

0.1%

Repair Monolith 6 Concrete Spall Area (I

0.1%

T V Weld Repair [3/8 fill]

0.1%

Repair Concrete and Cracks in elevation

0.0%

Epoxy Grout T V Shaft #3, Monoliths 8 an d

0.0%

T emp Demob & Remob

0.0%

T V Weld Repair [9/16 cjp]

0.0%

Standby for T emp Demob

0.0%

Concrete Demolition Monolith 8 and Mon ol

0.0%

T ainter Valve Wrapper

0.0%

Flow Breccia Consolidation Grouting an d

0.0%

Install Monolith 6/8 and Monolith 8/10 J

0.0%

Replace Monolith 6 uplift Pressure Instr

0.0%

Plug Rock Drain Pipe and French Drain

0.0%

Pave Embankment Dam Access Road (incl. S

0.0%

Install Post-tensioned Anchors elevatio n

0.0%

Services of Skilled Craftsmn

0.0%

Repair Monolith 27 Bulkhead Slot Concret

0.0%
0%

25%

50%

75%

Measured by Contribution to Variance

100%

Forecast: E36
Summary:
Display Range is from 6,736,607 to 9,401,632
Entire Range is from 6,251,220 to 9,933,632
After 20,000 Trials, the Std. Error of the Mean is 3,637
Statistics:
Trials
Mean
Median
Mode
Standard Deviation
Variance
Skewness
Kurtosis
Coeff. of Variability
Range Minimum
Range Maximum
Range Width
Mean Std. Error

Forecast: E36
20,000 Trials

Frequency Chart

126 Outliers

.021

417

.016

312.7

.010

208.5

.005

104.2

.000

0
6,736,607

7,402,863

8,069,119

8,735,376

9,401,632

Forecast: E36 (cont'd)


Contingency Analysis
$
7,032,396
Confidence
Level
Value
Contingency
0%
6,251,220
5%
7,231,566
3%
10%
7,402,887
5%
15%
7,527,590
7%
20%
7,630,292
9%
25%
7,716,363
10%
30%
7,798,895
11%
35%
7,869,458
12%
40%
7,939,069
13%
45%
8,005,411
14%
50%
8,074,771
15%
55%
8,140,537
16%
60%
8,207,003
17%
65%
8,276,751
18%
70%
8,350,223
19%
75%
8,432,349
20%
80%
8,519,636
21%
85%
8,619,660
23%
90%
8,744,227
24%
95%
8,931,577
27%
100%
9,933,632
41%
Confidence Level: 80% would mean, For a project cost of $8,519,636 using
21% contingency would have a 80% confidence level that project cost would
not exceed this amount.

Confidence Level: 80% would mean, For a project cost of $8,519,636 using
21% contingency would have a 80% confidence level that project cost would
not exceed this amount.

Sample (Feasibility Phase/Recommended Plan) - PDT Risk Register


Project Scope
This project consists of constructing a debris boom upstream of the dam spillway and installing a temporary coffer dam around the
construction area to dewater the bridge and spillway notch construction zones for the fish passage. A prefabricated concrete bridge is planned
to extend across the notch in the spillway; and, will include a stop log water control structure and improved roadway access to the lock and
dam storage yard. The fish passage ramp and riffle structure is constructed of rock materials and will also incorporate hydraulic dredging
operations to use dredge spoil to fill voids in the large rock materials of the fishway.
This is a 100% Federal project and no lands and damage costs are included. No relocation costs were expected for this project.
Cost Impacts
For the Sample Project, any cost impact of $500K or higher should be considered at least "Significant."
Anything over $250 K should be considered at least "Marginal."
Schedule Impacts
For the Sample Project, any schedule impact of 3 months or greater should be considered at least "Significant."
Anything over 1 month should be considered at least "Marginal."
Project Cost

Risk No.

Risk/Opportunity Event

Concerns

PDT Discussions

Likelihood*

Impact*

Risk Level*

Project Schedule
Rough Order
Impact ($)
Likelihood*

Impact*

Risk Level*

Rough Order
Variance
Impact (mo) Distribution

Correlation
to Other(s)

Responsibility/POC

Affected Project
Component

Contract Risks (Internal Risk Items are those that are generated, caused, or controlled within the PDT's sphere of influence.)
PROJECT & PROGRAM
MGMT

Project Schedule in Question

This issue has had an effect on the overall performance of


Schedule developed with the assumption that sufficient
the planning and engineering, as far as schedule is
funding would be received on a timely basis. Thus far, this concerned. PDT feels that the overall project schedule is a
has not occurred.
bit optimistic.

Very Likely

Marginal

Moderate

Captured by
Schedule

Very Likely

Significant

High

6.0 Months

Uniform

PPM-2

No Control over Staff Priorities

Emergency response and other Corps-wide priorities have


occurred that take away ability to predict and manage inhouse staff and workload.

Presents a challenge in meeting schedules and producing


design products.

Very Likely

Marginal

Moderate

Captured by
Schedule

Very Likely

Significant

High

3.2 Months

Uniform

PPM-3

Project competing with other


projects for funding

Other priorities threaten the funding and timely receipt of


funding to complete the milestones for this project.

Has a significant impact on schedule, and marginal impact


on costs.

Very Likely

Marginal

Moderate

Captured by
Schedule

Very Likely

Significant

High

7.2 Months

PPM-4

Functional and Technical Staff


overloaded

There is an increased workload that is outpacing the


current staff level's ability to keep pace.

Has a significant impact on schedule, and marginal impact


on costs.

Very Likely

Marginal

Moderate

Captured by
Schedule

Very Likely

Significant

High

Captured by Risk
PPM-2

PPM-5

Product Development by Several


Sources/Communication
Challenges

The regional PDT includes members from other U5


Districts, as well as external agencies at the Federal and
State level.

The coordination of staff and communication presents


challenges that could impact the cost and schedule.

Likely

Marginal

Moderate

$1.1 M

Unlikely

Significant

Moderate

PPM-6

Losing Staff at Critical Milestones

PDT has already experienced loss of staff, and due to


workload and competing priorities, this is likely to occur in
the future.

Has a significant impact on schedule, and marginal impact


on costs.

Very Likely

Marginal

Moderate

Captured by
Schedule

Very Likely

Significant

Likely

Significant

High

$2 M

Likely

Significant

PPM-1

Confusing and contradictory advice regarding continuously This issue presents a project management challenge in the
changing program and project requirements (i.e. Model
ability to plan, schedule, and produce, design and develop
Certification, Science Panel, Risk Assessment, ITR/ATR, documents due in some instances to indecision or lack of
EPR).
action at higher levels.

Project Manager

Project Schedule

Resource Providers

Project Schedule

Uniform

Project Manager

Project Schedule

N/A

Resource Providers

Project Schedule

1.8 Months

Triangular

Project Manager

Project Cost & Schedule

High

2.4 Months

Uniform

High

4.8 Months

Uniform

PPM-7

Timely Response to Critical


Decision

PPM-8

Internal Red Tape Causes Delays

Due to the level of scrutiny of this project, there are many


internal and stakeholder reviews of this project before it
reaches HQ.

Has a significant impact on schedule, and marginal impact


on costs.

Very Likely

Marginal

Moderate

Captured by
Schedule

Likely

Significant

High

Captured by Risk
PPM-2

N/A

PPM-9

Pressure to deliver project on an


accelerated schedule

PDT has already been under pressure to accelerate.


However, there has been insufficient funding to produce
design level products.

Has a significant impact on schedule, and marginal impact


on costs.

Very Likely

Marginal

Moderate

$1.6 M

Likely

Significant

High

1.8 Months

Uniform

The PDT feels that the structural portion will likely go out
as full and open RFP, whereas the rock portion could to go
to an 8(a) or small business.

If an 8(a) or small business was selected for the rock


portion of the work, it could significantly impact costs.

Likely

Significant

High

$2.7 M

Likely

Marginal

Moderate

3.8 Months

Unlikely

Significant

Moderate

$40 K

Unlikely

Marginal

Low

Not Studied

PPM-9

EST-1

Resource Providers

Project Schedule

District Management

Project Cost & Schedule

District Management

Project Schedule

District Management

Project Cost & Schedule

Triangular

TASB/Contracting

Contract Cost & Project


Schedule

Uniform

Geotech Lead

Contract Cost

Project Schedule

PPM-1

CONTRACT ACQUISITION

CA-1

Contract Acquisition Strategy Not


Determined

TECHNICAL

T-1

Uncertainty with Filling of Voids

This is the first time that a hydraulic dredge has been used If the technique does not perform as planned, there will be
to place material to fill voids in the rock ramp to prevent
some rework or modification necessary to complete the
seepage though the bottom of the fishway.
work.

T-2

Uncertainty with Riffle Design

There is some uncertainty with the optimal riffle design


within the fishway (straight or "U" shaped). There is a
consideration for this within the adaptive management
component of the project.

Likely

Negligible

Low

Not Studied

Likely

Marginal

Moderate

1.8 Months

Uniform

Technical Lead

T-3

Confidence in the Estimated


Quantity of Rock Required

Rock fill quantities were calculated based upon pre-flood


bathymetric surveys. The project area may have scoured
or filled during the flood.

This could affect the quantity of rock required for fill


material and lead to a change in the construction cost.

Likely

Significant

High

$2.3 M

Unlikely

Marginal

Low

Not Studied

Triangular

Geotech Lead

Contract Cost

T-4

Conflicts with potential hydro-plant


and lock expansion project.

There is a potential that there will be other contracts


occurring simultaneously (hydro-plant and/or lock
expansion) that could affect the coordination and access.

Project currently assumes access to small laydown/staging area footprint. Simultaneous contracts could
impact availability and congestion.

Likely

Marginal

Moderate

Captured by Risk
PR-5

Likely

Marginal

Moderate

Captured by Risk
PR-5

N/A

Project Manager

Project Cost & Schedule

The uncertainty regarding this design could cause


fluctuations either positive or negative.

ENVIRONMENTAL/
REGULATORY

EN-1

Historical/Cultural Site

L&D facility listed on historical sites listing. Dredge


material placement issue also could be involved as a
contingency.

Plan is currently to construct from a barge. If DMMP


required, then there could be some cultural clearance
issues. There are potential adverse effects to the L&D
facility.

Very Unlikely

Negligible

Low

Not Studied

Very Unlikely

Critical

Low

Not Studied

N/A

Environmental Lead

Project Cost & Schedule

EN-2

Status of Permits

Floodplain work requires permitting from the States of


Illinois and Missouri.

There is a current understanding with State Authorities.


However, if they became more restrictive or changed their
minds, it could present challenges in the permit application
process.

Unlikely

Significant

Moderate

$66 K

Unlikely

Critical

Moderate

1.8 Months

Uniform

Environmental Lead

Project Cost & Schedule

EN-3

Water Quality Permit

401 water quality certification will be required on this


project. State provides criteria that must be met (both
States of Illinois & Missouri).

State of Illinois is slow in issuing water quality permits.


Could significantly delay the process of obtaining the
permit. Can still begin construction while the permit is
pending.

Very Likely

Negligible

Low

Not Studied

Very Likely

Marginal

Moderate

3.2 Months

Uniform

Environmental Lead

Project Schedule

EN-4

Potential Endangered Species


Issue

There is a possibility that some mitigation for mussels may


be necessary on this project.

There are currently no contemplated impacts to this


project. However, relocation of mussels would be
necessary if endangered species are discovered.

Unlikely

Marginal

Low

Not Studied

Unlikely

Marginal

Low

Not Studied

N/A

Environmental Lead

Project Cost & Schedule

There are no contemplated complications due to HTRW


issues under the existing footprint. However, if the
footprint changed, there could be some remediation
required.

PDT feels that if remediation is required, it would cost a


minimum of $1 M.

Unlikely

Marginal

Low

Not Studied

Yes-No

Technical/Environmental
Leads

Project Cost & Schedule

Unlikely

Marginal

Low

Not Studied

Uniform

Environmental Lead

Contract Cost

EN-5

HTRW Issues

EN-6

Fishway not effective

The fishway design is based upon the best available


This type of fishway has never been constructed in the
information in the scientific literature, pre-construction
Upper Mississippi River and there is a potential that it won't monitoring studies, and the advice of experts from around
work.
the country.

Unlikely

Significant

Moderate

Does Not Occur


at 80%
Confidence

Unlikely

Significant

Moderate

$949 K

CONSTRUCTION

C-1

C-2

Challenges include keeping navigation open during


construction and minimizing impacts to the facility and the
river during construction. Nature of work includes barges,
derricks, cranes, etc. that will cause congestion and
coordination issues.

In-water Work/Cofferdam
Construction

Much of the project is contemplated to be performed from


barges. Project also requires construction of a cofferdam
and significant handling of rock.

Inefficient Contractor

There is inherent risk of getting a contractor that is not as


efficient as planned in the baseline estimate.

Could affect cost and schedule.

Unlikely

Significant

Moderate

$1.4 M

Unlikely

Significant

Moderate

Unlikely

Significant

Moderate

$519 K

Unlikely

Significant

Moderate

Unlikely

Significant

Moderate

$922 K

Unlikely

Significant

Moderate

The plan currently assumes multiple contracts for this


acquisition.

There is the possibility for conflicts between the


contractors on this program, as well as other non-related
projects.

All materials and access is contemplated to be via river or


on the Illinois side. There is limited access to the site.

Site access issues are currently captured in the baseline


estimate.

Unlikely

Marginal

Low

Not Studied

Unlikely

Marginal

Low

Labor Forces from Outside Area

Marine based and bridge labor force would likely come


from outside the local area.

May increase costs due to housing and subsistence for the


labor force.

Likely

Significant

High

$1.2 M

Likely

Negligible

C-6

Material availability and delivery

There is concern regarding delivery of rock, bridge


components, etc.

Could affect costs.

Likely

Marginal

Moderate

$704 K

Likely

C-7

Differing Site Conditions

The project site has not been surveyed since the last flood
event.

There is the possibility for differing conditions due to the


effects of the last flood event.

Likely

Marginal

Moderate

$1.3 M

Likely

C-8

Contract Sequencing

PDT is not confident in the current contract phasing as


currently scheduled and contemplated.

This could have significant impact on the overall project


schedule.

Likely

Marginal

Moderate

Captured by
Schedule

Local fishermen and others use the area for recreation.


Could present challenges with safety and managing the
public during throughout the project life.

Project plan currently has a fence and signage to mitigate


public loitering and interference. There is little concern of
public safety issue during construction so long as the
contractor manages and secures the project area. There
is risk that the project site will become a lingering attractive
nuisance.

Likely

Negligible

Low

Unknowns with Reviews and


Iterative Process

The PDT feels confident in the baseline estimate


preparation. However, the various review requirements
and scrutiny has an affect on the overall confidence in the
constant revisions to the baseline estimate and schedule.

Has had an impact on the overall cost and schedule


development.

Very Likely

Marginal

Estimate and Schedule Reflecting


"Most Likely" Occurrence

PDT is concerned regarding the schedule, and therefore


the validity of the baseline estimate. The effects on project
schedule are being captured by Risk Item No. PPM-1.
The uncertainty with the schedule has a significant impact Therefore, the schedule risk level was rated low in this risk
on the development of the estimate.
item.

Likely

Significant

C-3

C-4

C-5

Conflicts with Other Contracts

Site access/restrictions

Triangular

Cost
Engineering/Construction

Contract Cost & Project


Schedule

2.5 Months

Triangular

Cost
Engineering/Construction

Contract Cost & Project


Schedule

1.8 Months

Triangular

Construction

Contract Cost & Project


Schedule

Contract Cost & Project


Schedule

1.8 Months

PR-5

Not Studied

N/A

Cost
Engineering/Construction

Low

Not Studied

Triangular

Cost Engineering

Contract Cost

Significant

High

Captured by Cost
Risk Study

Triangular

Cost Engineering

Contract Cost

Negligible

Low

Not Studied

Uniform

Construction

Contract Cost

Likely

Significant

High

2.7 Months

Triangular

Contracting

Project Schedule

Not Studied

Likely

Negligible

Low

Not Studied

N/A

Real Estate

Project Cost & Schedule

Moderate

Captured by Risk
PPM-7

Very Likely

Marginal

Moderate

3.2 Months

Uniform

Project Manager

Project Schedule

High

$961 K

Likely

Negligible

Low

Not Studied

Triangular

Cost Engineering

Contract Cost

REAL ESTATE

RE-1

Vagrancy and Loitering Issues

COST ESTIMATING/
ENGINEERING

EST-1

EST-2

PPM-7

Programmatic Risks (External Risk Items are those that are generated, caused, or controlled exclusively outside the PDT's sphere of influence.)
This area is prone to regular flooding. There is a risk of a
major flood in this area during the project timeframe. This
could affect the rock placement, as well as capturing
quantities adequately before construction.

There is a risk of flooding during construction. Contractor


will have to prepare for 10-year flood event. This could
cause dewatering delays and minor rework. However, a
significant flood event (greater than 10-year), it could
impact the project costs and schedule.

PR-1

Flooding

Likely

Significant

High

$3.7 M

Likely

Significant

High

3.2 Months

Uniform

PR-2

Market Conditions (saturated


construction market)

There are currently several competing projects that may


draw contractors away from this project and onto others,
limiting the field of prospective bidders.

There are other contemplated major projects happening


potentially simultaneously. This could significantly affect
costs.

Unlikely

Significant

Moderate

$947 K

Unlikely

Marginal

Low

Not Studied

Triangular

Cost Engineering

Project Cost & Schedule

Contract Cost

PR-3

Adequacy of project funding


(incremental)

In the past, this has been a concern in obtaining funds on


a timely basis or in the expected increments. Receiving
less increment or delayed increment is a concern.

Could significantly impact cost and schedule.

Very Likely

Significant

High

Captured by
Schedule

Very Likely

Significant

High

3.3 Months

Triangular

Project Manager

Project Schedule

PR-4

Political Factors Change at


Federal, State, or Local Level

There is a concern that the rise in costs could price the


project out of the ecosystem restoration business line's
ability to execute.

If this concern became reality, the project would not occur.


This item likely will not be studied in the analysis, as if it
occurs, the project will not occur.

Likely

Significant

High

Occurrence
would prevent
the project

Likely

Significant

High

Occurrence
would prevent
the project

N/A

Project Manager

Project Cost & Schedule

PR-5

Hydropower

Hydropower development is being considered in the


spillway which may change the flow patterns that attract
fish to the fishway entrance.

Fewer fish will use the fishway for migration if they can't
find the entrance. Entrainment mortality from hydropower
generation would negatively affect fish populations.

Likely

Significant

High

Occurrence
would prevent
the project

Likely

Significant

High

Occurrence
would prevent
the project

N/A

Project Manager

Project Cost & Schedule

PR-6

Stakeholders choose cost or time


over quality

Stakeholders could choose to strip the adaptive


If this concern became reality, the project would not occur.
management component, or change certain features such
This item likely will not be studied in the analysis, as if it
that project assumptions are no longer valid.
occurs, the project will not occur.

Likely

Significant

High

Occurrence
would prevent
the project

Likely

Significant

High

Occurrence
would prevent
the project

N/A

Project Manager

Project Cost & Schedule

C-3

*Likelihood, Impact, and Risk Level to be verified through market research and analysis (conducted by cost engineer).
1. Risk/Opportunity identified with reference to the Risk Identification Checklist and through deliberation and study of the PDT.
2. Discussions and Concerns elaborates on Risk/Opportunity Events and includes any assumptions or findings (should contain information pertinent to eventual study and analysis of event's impact to project).
3. Likelihood is a measure of the probability of the event occurring -- Very Unlikely, Unlikely, Moderately Likely, Likely, Very Likely. The likelihood of the event will be the same for both Cost and Schedule, regardless of impact.
4. Impact is a measure of the event's effect on project objectives with relation to scope, cost, and/or schedule -- Negligible, Marginal, Significant, Critical, or Crisis. Impacts on Project Cost may vary in severity from impacts on Project Schedule.

5. Risk Level is the resultant of Likelihood and Impact Low, Moderate, or High. Refer to the matrix located at top of page.
6. Variance Distribution refers to the behavior of the individual risk item with respect to its potential effects on Project Cost and Schedule. For example, an item with clearly defined parameters and a solid most likely scenario would probably follow a triangular or normal distribution. A risk item for which the PDT has little data or probability
of modeling with respect to effects on cost or schedule (i.e. "anyone's guess") would probably follow a uniform or discrete uniform distribution.
7. The responsibility or POC is the entity responsible as the Subject Matter Expert (SME) for action, monitoring, or information on the PDT for the identified risk or opportunity.
8. Correlation recognizes those risk events that may be related to one another. Care should be given to ensure the risks are handled correctly without a "double counting."
9. Affected Project Component identifies the specific item of the project to which the risk directly or strongly correlates.
10. Project Implications identifies whether or not the risk item affects project cost, project schedule, or both. The PDT is responsible for conducting studies for both Project Cost and for Project Schedule.
11. Results of the risk identification process are studied and further developed by the Cost Engineer, then analyzed through the Monte Carlo Analysis Method for Cost (Contingency) and Schedule (Escalation) Growth.

Project Scope
Contingency on Base Estimate
Baseline Estimate Cost (Most Likely) ->
Baseline Estimate Cost Contingency Amount ->
Baseline Estimate Construction Cost (80% Confidence) ->

This project consists of constructing a debris boom upstream of the dam


spillway and installing a temporary coffer dam around the construction area
to dewater the bridge and spillway notch construction zones for the fish
passage. A prefabricated concrete bridge is planned to extend across the
notch in the spillway; and, will include a stop log water control structure and
improved roadway access to the lock and dam storage yard. The fish
passage ramp and riffle structure is constructed of rock materials and will
also incorporate hydraulic dredging operations to use dredge spoil to fill
voids in the large rock materials of the fishway.

80% Confidence Project Cost


$40,014,944
$13,741,700
$53,756,644

Contingency on Schedule
80% Confidence Project Schedule
Project Schedule Duration (Most Likely) ->
46.0 Months
Schedule Contingency Duration ->
29.3 Months
Project Schedule Duration (80% Confidence) ->
75.3 Months
Project Schedule Contingency Amount (80% Confidence) ->
$2,111,954

This is a 100% Federal project and no lands and damage costs are included.
No relocation costs were expected for this project.

Project Contingency
Project Contingency Amount (80% Confidence) ->
Project Contingency Percentage (80% Confidence) ->

80% Confidence Project Cost


$15,853,654
40%

Project Cost (80% Confidence) ->

$55,868,598

- PROJECT CONTINGENCY DEVELOPMENT -

Contingency Analysis

Contingency

$35,833,239

-10.45%

###

5%

$44,839,308

12.06%

###

$46,442,558

16.06%

###

15%

$47,497,895

18.70%

###80,000,000

20%

$48,400,180

20.96%

25%

$49,132,023

22.78%

###
###70,000,000

30%

$49,744,595

24.32%

35%

$50,360,782

25.85%

40%

$50,988,057

27.42%

45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%

$51,575,622
$52,151,692
$52,737,247
$53,286,037
$53,856,537
$54,462,516
$55,094,405
$55,868,598
$56,665,502
$57,672,460
$59,268,192
$67,240,463

28.89%
30.33%
31.79%
33.17%
34.59%
36.11%
37.68%
39.62%
41.61%
44.13%
48.12%
68.04%

Cost

###50,000,000
###
###40,000,000
###
###30,000,000
###
###20,000,000
###
###10,000,000
###
###
0
###
###

Baseline Cost at 80%


Confidence Le vel

Corres ponding Contingency


Am ount

###
60,000,000
###

95%

90%

Confidence Levels

100%

85%

80%

75%

70%

65%

60%

55%

50%

45%

40%

35%

30%

25%

20%

5%

"M os t Likely"
Baseline Cos t

15%

Value

0%
10%

0%

Confidence Level

BASELINE COST WITH CONTINGENCY DEVELOPMENT

$40,014,944

10%

Most Likely
Cost Estimate

- BASELINE ESTIMATE CONTINGENCY DEVELOPMENT -

Contingency Analysis

###
###
###
###
###80,000,000
###
###
###60,000,000
###
###
###
###40,000,000
###
###
###
###20,000,000

Bas eline Estim ate Cos t


at 80% Confide nce Level

Corresponding Contingency
Am ount

"M ost Lik ely"


Bas eline Cost

95%

90%

85%

80%

75%

70%

65%

60%

55%

100%

Confide nce Levels

50%

45%

40%

35%

30%

25%

20%

0
15%

###
###
###
###
###

5%

Contingency
-9.01%
10.72%
14.19%
16.46%
18.41%
19.96%
21.25%
22.57%
23.92%
25.18%
26.41%
27.66%
28.81%
30.01%
31.31%
32.67%
34.34%
36.02%
38.20%
41.62%
58.85%

0%

Value
$36,408,945
$44,302,729
$45,692,598
$46,603,024
$47,383,181
$48,001,018
$48,517,176
$49,044,633
$49,586,489
$50,090,006
$50,584,341
$51,083,142
$51,542,773
$52,025,214
$52,543,790
$53,088,118
$53,756,644
$54,430,091
$55,298,936
$56,667,978
$63,563,297

10%

Confidence Level
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%

BASELINE ESTIMATE CONTINGENCY DEVELOPMENT (Does not Include Escalation)

$40,014,944

Cost

Most Likely
Cost Estimate

- SCHEDULE CONTINGENCY (DURATION) DEVELOPMENT -

Contingency Analysis
46.0 Months

Schedule Contingency (Duration) Analysis

Contingency

52.1 Months

13.25%

64

55.3 Months

20.08%

64

15%

57.4 Months

24.72%

64

20%

59.2 Months

28.62%

25%

60.9 Months

32.27%

64120
64

30%

62.3 Months

35.36%

35%

63.6 Months

38.20%

64100
64

40%

64.9 Months

40.94%

64

45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%

66.1 Months
67.3 Months
68.6 Months
69.9 Months
71.2 Months
72.5 Months
73.8 Months
75.3 Months
77.1 Months
79.2 Months
82.5 Months
98.4 Months

43.63%
46.24%
49.02%
51.87%
54.69%
57.49%
60.29%
63.68%
67.63%
72.05%
79.31%
113.78%

64
64
64
64
64
64
64
64
64
64
64
64

Project Duration at 80%


Confidence Level

Corre sponding V ariance


Duration

80
60
40

Current Proje ct
Duration

20

95%

100%
100%

90%

95%

85%

80%

75%

70%

65%

60%

55%

50%

45%

40%

0
35%

Duration

5%
10%

30%

64

25%

-22.36%

20%

35.7 Months

15%

0%

5%

Value

10%

Confidence Level

0%

Most Likely
Cost Estimate

Confidence Levels

- SCHEDULE CONTINGENCY (AMOUNT) DEVELOPMENT -

Contingency Analysis
Schedule Contingency (Amount) Analysis

$40,014,944

Contingency

0%

$(575,707)

-1.44%

###

5%

$536,579

1.34%

###

10%

$749,960

1.87%

###

15%

$894,871

2.24%

20%

$1,016,999

2.54%

###
###$50,000,000

25%

$1,131,005

2.83%

30%

$1,227,419

3.07%

35%

$1,316,148

3.29%

40%

$1,401,568

3.50%

45%

$1,485,617

3.71%

50%

$1,567,351

3.92%

55%

$1,654,105

4.13%

60%

$1,743,263

4.36%

65%

$1,831,324

4.58%

70%

$1,918,726

4.80%

75%

###
$48,000,000
###
###$46,000,000

Baseline Cost Plus Sche dule


Contingency at 80% Confide nce
Level

Corres ponding Schedule


Contingency
Am ount

Cost

###
$44,000,000
###
###$42,000,000
###$40,000,000
###
###$38,000,000
###$36,000,000
###
$34,000,000
###

Confidence Levels

90%

85%

80%

75%

70%

###

65%

9.19%

60%

6.50%

$3,677,165

55%

$2,600,213

100%

"M ost Lik ely"


Bas eline Cost

50%

95%

###$32,000,000
###
$30,000,000
###

45%

5.93%

40%

$2,373,524

35%

90%

30%

5.59%

25%

5.28%

20%

5.01%

$2,111,954
$2,235,411

15%

$2,006,287

80%
85%

10%

Value

5%

Confidence Level

0%

Most Likely
Cost Estimate

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis Model


Crystal Ball Simulation
Expected Values ($$$)

Project Cost

Risk No.

Risk/Opportunity Event

Discussion and Concerns

Likelihood*

Impact*

Risk Level*

Variance
Distribution

Correlation
to Other(s)

Low

Most Likely

Crystal Ball Simulation


Expected Values (%s)

High

Low

Most Likely

High

-2.5%

0.0%

5.8%

0.0%

0.0%

6.2%

Internal Risks (Internal Risk Items are those that are generated, caused, or controlled within the PDT's sphere of influence.)
PROJECT & PROGRAM MGMT
This issue has had an effect on the
Schedule developed with the overall performance of the planning
assumption that sufficient
and engineering, as far as schedule
funding would be received on a
is concerned. PDT feels that the
timely basis. Thus far, this has
overall project schedule is a bit
not occurred.
optimistic.

Very Likely

Marginal

Moderate

Removed from Cost Risk Study This item is captured by the


Schedule Analysis

Emergency response and


other Corps-wide priorities
have occurred that take away
ability to predict and manage
in-house staff and workload.

Presents a challenge in meeting


schedules and producing design
products.

Very Likely

Marginal

Moderate

Removed from Cost Risk Study This item is captured by the


Schedule Analysis

Other priorities threaten the


funding and timely receipt of
funding to complete the
milestones for this project.

Has a significant impact on


schedule, and marginal impact on
costs.

Very Likely

Marginal

Moderate

Removed from Cost Risk Study This item is captured by the


Schedule Analysis

There is an increased
workload that is outpacing the
current staff level's ability to
keep pace.

Has a significant impact on


schedule, and marginal impact on
costs.

Very Likely

Marginal

Moderate

Removed from Cost Risk Study This item is captured by the


Schedule Analysis

Product Development by Several


Sources/Communication
Challenges

The regional PDT includes


members from other U5
Districts, as well as external
agencies at the Federal and
State level.

The coordination of staff and


communication presents challenges
that could impact the cost and
schedule.

Likely

Marginal

Moderate

Losing Staff at Critical Milestones

PDT has already experienced


loss of staff, and due to
workload and competing
priorities, this is likely to occur
in the future.

Has a significant impact on


schedule, and marginal impact on
costs.

Very Likely

Marginal

PPM-7

Timely Response to Critical


Decision

Confusing and contradictory


advice regarding continuously
changing program and project
requirements (i.e. Model
Certification, Science Panel,
Risk Assessment, ITR/ATR,
EPR).

This issue presents a project


management challenge in the ability
to plan, schedule, and produce,
design and develop documents due
in some instances to indecision or
lack of action at higher levels .

Likely

Significant

High

PPM-8

Internal Red Tape Causes Delays

Due to the level of scrutiny of


this project, there are many
internal and stakeholder
reviews of this project before it
reaches HQ.

Has a significant impact on


schedule, and marginal impact on
costs.

Very Likely

Marginal

Moderate

PPM-9

Pressure to deliver project on an


accelerated schedule

PDT has already been under


pressure to accelerate.
However, there has been
insufficient funding to produce
design level products.

Has a significant impact on


schedule, and marginal impact on
costs.

Very Likely

Marginal

Moderate

Uniform

$0

$0

$2,000,747

0.0%

0.0%

5.0%

The PDT feels that the


structural portion will likely go
out as full and open RFP,
whereas the rock portion could
to go to an 8(a) or small
business.

If an 8(a) or small business was


selected for the rock portion of the
work, it could significantly impact
costs.

Likely

Significant

High

Triangular

($2,403,729)

$0

$5,835,042

-6.0%

0.0%

14.6%

This is the first time that a


hydraulic dredge has been
used to place material to fill
voids in the rock ramp to
prevent seepage though the
bottom of the fishway.

If the technique does not perform as


planned, there will be some rework
or modification necessary to
complete the work.

Unlikely

Significant

Moderate

Uniform

($47,228)

$0

$61,602

-0.1%

0.0%

0.2%

Triangular

($2,451,874)

$0

$4,903,748

0.0%

0.0%

0.2%

PPM-1

PPM-2

PPM-3

PPM-4

PPM-5

PPM-6

Project Schedule in Question

No Control over Staff Priorities

Project competing with other


projects for funding

Functional and Technical Staff


overloaded

Triangular

($1,003,749)

$0

$2,333,653

Removed from Cost Risk Study This item is captured by the


Schedule Analysis

Moderate

Uniform

EST-1

$0

$0

$2,476,886

Removed from Cost Risk Study This item is captured by Risk PPM7

CONTRACT ACQUISITION

CA-1

Contract Acquisition Strategy Not


Determined

TECHNICAL

T-1

Uncertainty with Filling of Voids

T-3

Confidence in the Estimated


Quantity of Rock Required

T-4

Conflicts with potential hydro-plant


and lock expansion project.

Rock fill quantities were


calculated based upon preflood bathymetric surveys. The This could affect the quantity of rock
project area may have scoured required for fill material and lead to a
or filled during the flood.
change in the construction cost.

Likely

Significant

High

There is a potential that there


will be other contracts
occurring simultaneously
(hydro-plant and/or lock
expansion) that could affect
the coordination and access.

Project currently assumes access to


small lay-down/staging area
footprint. Simultaneous contracts
could impact availability and
congestion.

Likely

Marginal

Moderate

Floodplain work requires


permitting from the States of
Illinois and Missouri.

There is a current understanding


with State Authorities. However, if
they became more restrictive or
changed their minds, it could present
challenges in the permit application
process.

Unlikely

Significant

Moderate

Removed from Risk Study - This


item is captured by PR-5

ENVIRONMENTAL/REGULATORY

EN-2

Status of Permits

Uniform

HTRW Issues

There are no contemplated


complications due to HTRW
issues under the existing
footprint. However, if the
PDT feels that if remediation is
footprint changed, there could required, it would cost a minimum of
be some remediation required.
$1 M.

Unlikely

Significant

Moderate

Fishway not effective

The fishway design is based upon


This type of fishway has never the best available information in the
been constructed in the Upper scientific literature, pre-construction
Mississippi River and there is a monitoring studies, and the advice of
potential that it won't work.
experts from around the country

Unlikely

Significant

Moderate

Uniform

C-1

In-water Work/Cofferdam
Construction

Challenges include keeping


Much of the project is
navigation open during construction
contemplated to be performed and minimizing impacts to the facility
from barges. Project also
and the river during construction.
requires construction of a
Nature of work includes barges,
cofferdam and significant
derricks, cranes, etc. that will cause
handling of rock.
congestion and coordination issues.

Unlikely

Significant

Moderate

C-2

Inefficient Contractor

There is inherent risk of getting


a contractor that is not as
efficient as planned in the
baseline estimate.

Could affect cost and schedule.

Unlikely

Significant

Moderate

C-3

Conflicts with Other Contracts

The plan currently assumes


multiple contracts for this
acquisition.

There is the possibility for conflicts


between the contractors on this
program, as well as other nonrelated projects.

Unlikely

Significant

Moderate

Triangular

C-5

Labor Forces from Outside Area

Marine based and bridge labor


force would likely come from
outside the local area.

May increase costs due to housing


and subsistence for the labor force.

Likely

Significant

High

Material availability and delivery

There is concern regarding


delivery of rock, bridge
components, etc.

Could affect costs.

Likely

Marginal

The project site has not been


surveyed since the last flood
event.

There is the possibility for differing


conditions due to the effects of the
last flood event.

Likely

PDT is not confident in the


current contract phasing as
currently scheduled and
contemplated.

This could have significant impact


on the overall project schedule.

The PDT feels confident in the


baseline estimate preparation.
However, the various review
requirements and scrutiny has
an affect on the overall
confidence in the constant
revisions to the baseline
estimate and schedule.

Has had an impact on the overall


cost and schedule development.

EN-5

EN-6

$0

$0

$82,286

Removed from Final Cost Risk


Study - At a probability of 15%, this
event does not occur at the 80%
confidence level.

$0

$0

$1,200,448

0.0%

0.0%

3.0%

Triangular

($855,703)

$0

$1,996,641

-2.1%

0.0%

5.0%

Triangular

($1,633,615)

$0

$3,171,136

-4.1%

0.0%

7.9%

$0

$0

$945,777

0.0%

0.0%

2.4%

Triangular

$0

$0

$2,131,366

0.0%

0.0%

5.3%

Moderate

Triangular

($486,721)

$0

$1,460,163

-1.2%

0.0%

3.6%

Marginal

Moderate

Uniform

$0

$0

$1,630,778

0.0%

0.0%

4.1%

Likely

Marginal

Moderate

Very Likely

Marginal

Moderate

CONSTRUCTION

C-6

C-7

C-8

Differing Site Conditions

Contract Sequencing

PR-5

Removed from Cost Risk Study This item is captured by the


Schedule Analysis

COST ESTIMATING/ENGINEERING

EST-1

Unknowns with Reviews and


Iterative Process

PPM-7

Removed from Risk Study - This


item is captured by PPM-7

Percentages are calculated as the


variance from the assumption value to
facilitate iteration of the model should
the cost values change throughout the
project phases. Uniform distribution
percentages reflect variation from the
total project cost.

EST-2

Estimate and Schedule Reflecting


"Most Likely" Occurrence

The uncertainty with the


schedule has a significant
impact on the development of
the estimate.

PDT is concerned regarding the


schedule, and therefore the validity
of the baseline estimate. The effects
on project schedule are being
captured by Risk Item No. PPM-1.
Therefore, the schedule risk level
was rated low in this risk item.

Likely

Significant

High

Triangular

($759,957)

$0

$2,000,747

-1.9%

0.0%

5.0%

0.0%

0.0%

11.5%

-12.2%

0.0%

8.2%

Programmatic Risks (External Risk Items are those that are generated, caused, or controlled exclusively outside the PDT's sphere of influence.)

PR-1

Flooding

This area is prone to regular


flooding. There is a risk of a
major flood in this area during
the project timeframe. This
could affect the rock
placement, as well as
capturing quantities adequately
before construction.

PR-2

Market Conditions (saturated


construction market)

There are currently several


competing projects that may
draw contractors away from
this project and onto others,
limiting the field of prospective
bidders.

There are other contemplated major


projects happening potentially
simultaneously. This could
significantly affect costs.

Unlikely

Significant

Moderate

Adequacy of project funding


(incremental)

In the past, this has been a


concern in obtaining funds on
a timely basis or in the
expected increments.
Receiving less increment or
delayed increment is a
concern.

Could significantly impact cost and


schedule.

Very Likely

Significant

High

Removed from Cost Risk Study This item is captured by the


Schedule Analysis

Political Factors Change at


Federal, State, or Local Level

There is a concern that the rise


in costs could price the project
out of the ecosystem
restoration business line's
ability to execute.

If this concern became reality, the


project would not occur. This item
likely will not be studied in the
analysis, as if it occurs, the project
will not occur.

Likely

Significant

High

This Risk Item is not being


quantitatively studied. Occurrence
would prevent the project.

Hydropower

Hydropower development is
being considered in the
spillway which may change the
flow patterns that attract fish to
the fishway entrance.

Fewer fish will use the fishway for


migration if they can't find the
entrance. Entrainment mortality
from hydropower generation would
negatively affect fish populations.

Likely

Significant

High

Stakeholders choose cost or time


over quality

Stakeholders could choose to


strip the adaptive management
component, or change certain
features such that project
assumptions are no longer
valid.

If this concern became reality, the


project would not occur. This item
likely will not be studied in the
analysis, as if it occurs, the project
will not occur.

Likely

Significant

High

PR-3

PR-4

PR-5

PR-6

There is a risk of flooding during


construction. Contractor will have to
prepare for 10-year flood event.
This could cause dewatering delays
and minor rework. However, a
significant flood event (greater than
10-year), it could impact the project
costs

Likely

Significant

High

Uniform

$0

$0

$4,619,050

Triangular

($4,892,335)

$0

$3,261,557

This Risk Item is not being


quantitatively studied. Occurrence
would prevent the project.

C-3

This Risk Item is not being


quantitatively studied. Occurrence
would prevent the project.

Placeholder for summation of risks being studied.

$40,014,944

$40,014,944

TOTAL PROJECT
COST (BASELINE)

Percentile

Forecast values

0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%

$36,408,945
$44,302,729
$45,692,598
$46,603,024
$47,383,181
$48,001,018
$48,517,176
$49,044,633
$49,586,489
$50,090,006
$50,584,341
$51,083,142
$51,542,773
$52,025,214
$52,543,790
$53,088,118
$53,756,644
$54,430,091
$55,298,936
$56,667,978
$63,563,297

39920822.796
47879342.361
49755944.601
51175947.967
52391087.8
53436537.928
54404040.843
55369007.171
56296401.168
57191455.73
58057715.8
58993474.558
59931683.628
60897196.228
61940032.855
62894655.254
63994740.82
65225732.27
66720886.435
68882273.726
77260091.279

Contingency
Amount
($3,605,999)
$4,287,785
$5,677,654
$6,588,081
$7,368,237
$7,986,074
$8,502,232
$9,029,689
$9,571,545
$10,075,062
$10,569,397
$11,068,199
$11,527,829
$12,010,270
$12,528,846
$13,073,174
$13,741,700
$14,415,148
$15,283,992
$16,653,034
$23,548,354

This risk models the probability of


a 10-year flood event. At a 10%
chance per year for the 3 year
construction period, this occurs
once at the 80% confidence level.

Contingency
%
-9.01%
10.72%
14.19%
16.46%
18.41%
19.96%
21.25%
22.57%
23.92%
25.18%
26.41%
27.66%
28.81%
30.01%
31.31%
32.67%
34.34%
36.02%
38.20%
41.62%
58.85%

Not Part of Study Placeholder for Project


Summation Purposes Only

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-1

Risk Event
Project Schedule in Question

Low

Most Likely

High

Removed from Cost Risk Study - This item is captured by


the Schedule Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-2

Risk Event
No Control over Staff Priorities

Low

Most Likely

High

Removed from Cost Risk Study - This item is captured by


the Schedule Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-3

Risk Event
Project competing with other projects for funding

Low

Most Likely

High

Removed from Cost Risk Study - This item is captured by


the Schedule Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-4

Risk Event
Functional and Technical Staff overloaded

Low

Most Likely

High

Removed from Cost Risk Study - This item is captured by


the Schedule Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-5

Risk Event
Product Development by Several
Sources/Communication Challenges

Low

Most Likely

High

($1,003,749)

$0

$2,333,653
$0

-$1,003,749

Notes:
Likely
Low
High

This item captures the risk of cost growth due to coordination/communication challenges,
as the products are developed by several sources.
Likely assumes no change from the baseline estimate.
Low assumes improvement of PED costs by up to 10%, and improvement of construction
costs by up to 2%.
High assumes increase in PED costs by up to 20% as well as increase to construction
costs by up to 5%.
Phase
Phase 1 Construction
Phase 1 PED
Phase 1 Total
Phase 2 Construction
Phase 2 PED
Phase 2 Total
Total
Difference

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

$2,333,653

Low
$15,149,822
$3,072,938
$18,222,760
$16,813,435
$90,000
$16,903,435
$35,126,195
($1,003,749)

Likely
$15,459,002
$3,414,375
$18,873,377
$17,156,567
$100,000
$17,256,567
$36,129,944
$0

Product Development by Several Sources/Communication Challenges


Assumption values
($990,043)
($430,892)
($174,778)
$2,662
$181,892
$381,304
$589,304
$822,936
$1,107,446
$1,469,839
$2,305,318

High
$16,231,952
$4,097,250
$20,329,202
$18,014,395
$120,000
$18,134,395
$38,463,597
$2,333,653

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-6

Risk Event
Losing Staff at Critical Milestones

Low

Most Likely

High

Removed from Cost Risk Study - This item is captured by


the Schedule Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-7

Notes:
Likely
Low
High

Risk Event
Timely Response to Critical Decision

Low
$0
$0

Most Likely
$0
$0

High
$2,476,886
$2,476,886

This item captures the risk that responses to critical decisions may not come in a timely
manner, and could impact project costs.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.

6 Month
Cumulative
Interruption
Phase 1
Phase 2
Subtotals

High assumes that additional review is required, adding the cost of another review, as well
as prolonging the project such that the PDT incurs more cost in their time spent on the
project.
Monthly
PM Costs
Design Costs (14% Phase 1/1% Contracting
Construction Cost
Duration
S&A (9%)
Review Costs Total
Burn
(0.5%)
Phase 2)
(0.5%)
$15,459,002
12
$1,288,250
$38,648
$1,082,130
$38,648
$695,655
$75,000 $1,930,080.26
$17,156,567
24
$714,857
$21,446
$42,891
$21,446
$386,023
$75,000 $546,805.58
$32,615,569
36
$2,003,107
$60,093
$1,125,022
$60,093
$1,081,678
$150,000
$2,476,886

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Timely Response to Critical Decision


Assumption values
$66
$249,534
$504,993
$752,065
$991,482
$1,234,463
$1,484,703
$1,721,234
$1,984,943
$2,232,532
$2,476,735

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-8

Risk Event
Internal Red Tape Causes Delays

Low

Most Likely

High

Removed from Cost Risk Study - This item is captured by


the Schedule Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PPM-9

Notes:
Likely
Low
High

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Risk Event
Pressure to deliver project on an accelerated schedule

Low
$0
$0

Most Likely
$0
$40,014,944

High
$2,000,747
$2,000,747

This item captures the risk that pressure to deliver the project on an accelerated schedule
has impact on costs.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that pressure to deliver on an accelerated schedule may produce
unintended consequences of construction modifications due to lesser quality products due
to the expediency in producing the planning and design deliverables. Up to 5% changes
assumed as worst case.

Pressure to deliver project on an accelerated schedule


Assumption values
$25
$185,741
$395,343
$580,883
$782,841
$987,265
$1,192,191
$1,399,331
$1,605,350
$1,801,827
$2,000,675

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


CA-1

Notes:

Likely
Low

High

Risk Event
Contract Acquisition Strategy Not Determined

Most Likely
$0
$0

High
$5,835,042
$5,835,042

This item captures the risk that the eventual acquisition method could add costs to the
project. Currently, Phase I is contemplated to be a full and open negotiated procurement.
Phase II could potentially go out to an 8(a) or a small business.
Likely assumes no change from the baseline estimate.
Low assumes cost savings due to favorable procurement effects on costs. For Phase I,
assuming it could use a "trade-off" acquisition process, it was assumed that the contract
cost could be up to 10% less. For Phase II, it was assumed that setting aside to a small
business or 8(a) could decrease the contract cost by up to 5%.
High assumes increase to contract costs due to the acquisition methods used. For Phase
I, assuming it could use a "trade-off" acquisition process, it was assumed that the contract
cost could be up to 10% higher. For Phase II, it was assumed that setting aside to a small
business or 8(a) could increase the contract cost by up to 25%.
Phase
Phase 1 Construction
Phase 2 Construction
Total
Difference

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Low
($2,403,729)
-$2,403,729

Low
$13,913,102
$16,298,738
$30,211,840
($2,403,729)

Contract Acquisition Strategy Not Determined


Assumption values
($2,366,377)
($1,035,332)
($428,371)
$28,551
$459,825
$908,662
$1,421,524
$1,996,006
$2,690,897
$3,606,742
$5,765,588

Likely
$15,459,002
$17,156,567
$32,615,569
$0

High
$17,004,902
$21,445,708
$38,450,611
$5,835,042

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


T-1

Notes:
Likely
Low

Risk Event
Uncertainty with Filling of Voids

Low
($47,228)
$576,562

Most Likely
$0
$623,790

High
$61,602
$685,392

This item captures the risk of incurring additional costs due to rework if the hydraulic
dredge placement does not perform as planned.
Likely assumes no change from the baseline estimate.
Low assumes that the current quantity of material to dredge (215,992 CY) is more than
actual conditions. Per the standard VEQ clause (FAR 52.211-18), up to 15% less quantity
is assumed (183,593 CY).

High

High assumes that current quantity of material to dredge is less than actual conditions.
Up to 20% is assumed (259,190 CY).

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Uncertainty with Filling of Voids


Assumption values
($47,218)
($36,434)
($25,375)
($14,118)
($2,820)
$7,900
$18,574
$29,585
$40,196
$50,837
$61,550

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


T-3

Notes:
Likely
Low
High

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Risk Event

Low

Most Likely

High

Confidence in the Estimated Quantity of Rock Required

($2,451,874)

$0

$4,903,748

$14,080,903

$16,532,777

$21,436,525

This item captures the risk that the Midwest flooding of 2008 could have scoured rock
from the area or deposited more, altering the actual quantity of rock required from the
baseline estimate.
Likely assumes no change from the baseline estimate.
Low assumes that less rock is required to be placed than anticipated. Per the standard
VEQ clause (FAR 52.211-18), up to 15% less quantity is assumed.
High assumes that more rock is required than currently estimated. Up to 30% more was
assumed as worst case.

Confidence in the Estimated Quantity of Rock Required


Assumption values
($2,418,183)
($1,112,202)
($567,968)
($132,456)
$254,280
$656,869
$1,122,864
$1,654,205
$2,264,209
$3,024,604
$4,848,533

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


T-4

Risk Event
Conflicts with potential hydro-plant and lock expansion
project.

Low

Most Likely

High
Removed from Risk Study - This item is captured by PR-5

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


EN-2

Notes:
Likely
Low
High

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Risk Event
Status of Permits

Low
$0
$0

Most Likely
$0
$0

High
$82,286
$82,286

This item captures the risk that the permit application process becomes more complicated
than anticipated.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that complications in the permitting process cause up to 4 months of labor
for 4 people for 30% of their workload ~ $82,286.

Status of Permits
Assumption values
$6
$8,077
$16,394
$24,986
$33,330
$41,652
$49,729
$57,817
$66,159
$74,098
$82,285

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


EN-5

Notes:

Likely
Low
High

Risk Event
HTRW Issues

Low
$0
$0

Most Likely
$0
$41,972,976

High
$1,000,000
$1,000,000

This item captures the risk that HTRW remediation may be necessary, if the project
footprint changes. Assuming that there is a 15% chance of finding HTRW contamination,
this does not occur at the 80% confidence level.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes the project incurs remediation costs up to $1 Million.
0
0

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


EN-6

Notes:
Likely
Low
High

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Risk Event
Fishway not effective

Low
$0
$0

Most Likely
$0
$40,014,944

High
$1,200,448
$1,200,448

This item captures the risk that the fishway, as designed, will not be effective since this
type of structure has never been built or tested elsewhere.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that the costs increase by up to 3% for inclusion of adaptive management
features.

Fishway not effective


Assumption values
$110
$119,318
$238,535
$359,313
$480,291
$599,291
$718,543
$835,102
$949,314
$1,073,677
$1,200,404

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


C-1

Risk Event
In-water Work/Cofferdam Construction

Low
($855,703)
$39,159,241

Most Likely
$0
$40,014,944

High
$1,996,641
$42,011,585

Notes:
Likely
Low
High

This item captures the risk of cost growth due to the challenges of in-water work.
Likely assumes no change from the baseline estimate.
Low assumes that productivity is up to 5% improved from the baseline estimate.

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

In-water Work/Cofferdam Construction


Assumption values
($836,266)
($365,538)
($171,303)
($11,156)
$138,616
$298,023
$481,695
$681,515
$921,561
$1,239,300
$1,977,083

High assumes that productivity is reduced by up to 10% due to complications and


challenges in maintaining operation of the river in conjunction with the project.

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


C-2

Risk Event
Inefficient Contractor

Low
($1,633,615)
$38,381,329

Most Likely
$0
$40,014,944

High
$3,171,136
$43,186,079

Notes:
Likely
Low

This item captures the risk of acquiring inefficient contractors.


Likely assumes no change from the baseline estimate.

High

High assumes that the eventual contractors are less efficient than currently contemplated
(up to 15% less productive).

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Inefficient Contractor
Assumption values
($1,598,881)
($742,894)
($382,913)
($101,928)
$152,184
$427,477
$720,520
$1,027,626
$1,418,739
$1,937,381
$3,137,999

Low assumes that the eventual contractors are more efficient than currently contemplated
(up to 10% more productive).

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


C-3

Notes:

Risk Event
Conflicts with Other Contracts

Low
$0
$40,014,944

Most Likely
$0
$40,014,944

High
$945,777
$40,960,721

Likely
Low
High

This item captures the risk of cost growth due to challenges in working concurrently with
other contractors on related and unrelated projects.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that conflicts with other contractors reduced productivity by up to 5%.

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Conflicts with Other Contracts


Assumption values
$109
$51,138
$100,467
$157,726
$215,031
$276,373
$347,189
$424,116
$518,652
$638,453
$942,258

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


C-5

Notes:
Likely
Low
High

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Risk Event
Labor Forces from Outside Area

Low
$0
$40,014,944

Most Likely
$0
$40,014,944

High
$2,131,366
$42,146,309

This item captures the risk that labor will have to be paid a premium for working out of the
area.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that all skilled craft labor must be paid a premium for travel from outside
the area amounting to $52.50 per day for lodging ($6.56/hour) and $29.25 per day for
subsistence ($3.66/hour). Rates are 75% of the current National General GSA rates.

Labor Forces from Outside Area


Assumption values
$3
$108,419
$226,038
$353,797
$491,695
$637,460
$794,065
$981,921
$1,195,155
$1,460,303
$2,114,965

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


C-6

Notes:
Likely
Low

Risk Event
Material availability and delivery

Low
($486,721)
$9,247,702

Most Likely
$0
$9,734,423

High
$1,460,163
$11,194,586

This item captures the risk of cost growth due to extraordinary escalation on some key
items.
Likely assumes no change from the baseline estimate.
Low assumes that the overall material costs are up to 5% lower than currently estimated.

High
High assumes that overall material costs are up to 15% higher than currently estimated.

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Material availability and delivery


Assumption values
($479,100)
($180,025)
($49,390)
$43,106
$151,166
$263,195
$390,496
$527,826
$704,374
$928,365
$1,430,677

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


C-7

Notes:
Likely
Low
High

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Risk Event
Differing Site Conditions

Low
$0
$0

Most Likely
$0
$32,615,569

High
$1,630,778
$1,630,778

This item captures the risk that flood events could have created differing underground
conditions than assumed in the baseline estimate.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that differing geotechnical conditions could generate changes up to 5% of
the overall construction cost, as currently estimated.

Differing Site Conditions


Assumption values
$487
$161,106
$332,061
$497,770
$657,896
$827,405
$987,265
$1,142,108
$1,308,067
$1,470,202
$1,630,686

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


C-8

Risk Event
Contract Sequencing

Low

Most Likely

High

Removed from Cost Risk Study - This item is captured by


the Schedule Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


EST-1

Risk Event
Unknowns with Reviews and Iterative Process

Low

Most Likely

High
Removed from Risk Study - This item is captured by PPM-7

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


EST-2

Notes:
Likely
Low

Risk Event
Estimate and Schedule Reflecting "Most Likely"
Occurrence

Low

Most Likely

High

($759,957)

$0

$2,000,747

$39,254,987

$40,014,944

$42,015,691

This item captures the risk that uncertainty with the schedule and with the baseline
scoping documents introduced potential for variance of the baseline cost estimate.
Likely assumes no change from the baseline estimate.
Low assumes that scoping and scheduling issues reduce the overall costs by requiring no
overtime.

High
High assumes that scoping and scheduling issues increase the overall costs by up to 5%.

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Estimate and Schedule Reflecting "Most Likely" Occurrence


Assumption values
($747,257)
($298,410)
($109,023)
$40,324
$182,590
$343,320
$519,506
$725,984
$961,428
$1,268,961
$1,981,166

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PR-1

Notes:

Likely
Low
High

Risk Event
Flooding

Low
$0
$0

Most Likely
$0
$0

High
$4,619,050
$4,619,050

This item captures the risk that flooding, if it occurs, could cause significant
rework/damage. This risk models the probability of a 10-year flood event. At a 10%
chance per year for the 3 year construction period, this occurs once at the 80%
confidence level.
Likely assumes no change from the baseline estimate.
Low assumes no change from the baseline estimate.
High assumes that a major flood event occurs during construction, causing rework of the
cofferdam and additional dewatering, amounting to 50% of the currently estimated
cofferdam and dewatering work.
Cofferdam
$8,666,625
$4,333,313
Dewatering
$571,475
$285,738
Total
$9,238,100
$4,619,050

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Flooding

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Flooding

Assumption values
$63
$461,482
$929,506
$1,400,774
$1,872,577
$2,331,115
$2,783,411
$3,229,459
$3,690,801
$4,138,977
$4,618,459

Assumption values
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
1.0
1.0
3.0

0
0

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PR-2

Notes:
Likely
Low

Risk Event
Market Conditions (saturated construction market)

Low
($4,892,335)
$27,723,233

Most Likely
$0
$32,615,569

High
$3,261,557
$35,877,126

This item captures the risk of cost variance due to market conditions.
Likely assumes no change from the baseline estimate.
Low assumes that the ultimate contract costs are up to 15% lower than currently
estimated.

High
High assumes that ultimate contract costs are up to 10% higher than currently estimated.

Assumption:
Percentile
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%

Market Conditions (saturated construction market)


Assumption values
($4,808,841)
($2,859,535)
($2,073,903)
($1,427,318)
($901,339)
($438,902)
($14,493)
$405,356
$947,312
$1,603,884
$3,214,161

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PR-3

Risk Event
Adequacy of project funding (incremental)

Low

Most Likely

High

Removed from Cost Risk Study - This item is captured by


the Schedule Analysis

Sample (Feasibility Phase/Recommended Plan) - Cost Risk Analysis

Risk Refer No.


PR-5

Risk Event
Hydropower

Low

Most Likely

High

This Risk Item is not being quantitatively studied.


Occurrence would prevent the project.

Risk Analysis

John Day, LOCK MONOLITH REPAIRS


5,210,615
Model

Project Description
1 Mobilization and Demobilization
Modify Existing Tainter Valve #3Remove/replace bushing with greaseless bushing/reinstall
2 Valve
3 Install Monolith 6/8 and Monolith 8/10 Joint Grout Plug (similar to water stops)
4 ?Anchor Shafts (Construct and abandon)

5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

Concrete Demolition TV #3 Shaft (Incl. Setting bulkheads on either side of TV, dewater
shaft and culvert (Project pumps are inadequate, extra pumping capacity will be required))
Concrete Demolition Monolith 8 and Monolith 27
Plug Rock Drain Pipe and French Drain
Repair Concrete and Cracks in elevation 263 Gallery
Replace Monolith 6 uplift Pressure Instruments
Drill Flow Breccia Consolidation Grout Holes and Rock Drain Abandonment Holes
Flow Breccia Consolidation Grouting and Rock Column Drain Grouting
Epoxy Grout TV Shaft #3, Monoliths 8 and 27 Bulkhead Slots (incl. Epoxy surface
patching, installing 6' grout tubes, and epoxy grouting)
Grout Monoliths 6, 8, and 27 Lock Chamber Cracks and Lift Lines
Install Post-tensioned Anchors elevation 170' and below
Install Post-tensioned Anchors elevation above 170'
Install Tainter Valve Shaft #3 Pre-Cast Concrete Panels (incl. Panel fabrication, drilling and
grouting dowels, and grouting behind panels)
Repair Monolith 6 Concrete Spall Area (Incl. Demo, drilling and grouting dowels,
reinforcement, new cnc.)
Repair Monolith 27 Bulkhead Slot Concrete Spalls
Braced Excavation (incl. Contractor design, excavation, dewatering, anchor block
fabrication, backfill, piezometer cable rerouting)
Load Cells and Strain Gages (incl. Wire routing in to be constructed slots in lock face, and
terminus)
Drain Line Installation (incl. Drilling from within brace excavation, open excavation behind
most of lock, MH's and weirs, drilling at D/S to terminus)
Pave Embankment Dam Access Road (incl. Subgrade prep, line stripes, Guard Rail
Replacement).
Services of Skilled Craftsmn
Temp Demob & Remob
Standby for Temp Demob
Tainter Valve Wrapper
TV Weld Repair [9/16 cjp]
TV Weld Repair [3/8 fill]

Estimate
326,430

$
136,195
$
24,104
$ 1,057,633

$ 231,531
$
25,443
$ 1,410,178

$
$
$

272,389
26,782
1,762,722

$
$
$
$
$
$
$

$
$
$
$
$
$
$

317,344
76,706
1,293
31,011
12,404
462,225
1

$
$
$
$
$
$
$

352,604
80,743
1,361
32,643
13,057
616,300
1

$
59,493
$
221,802
$ 1,642,562
$
1

$
62,798
$ 234,125
$ 1,564,345
$
1

$
$
$
$

66,103
246,447
1,564,345
1

330,918

350,384

$
$

124,482
32,412

$
$

131,804
32,412

316,563

110,343

$
$
$
$
$
$
$
$

Construction Project Summary

11,042,515

High
375,395

EX High
424,359

$
286,008
$
30,799
$ 1,850,858

$
$
$

340,486
36,156
2,027,130

$
$
$
$
$
$
$

405,495
92,854
1,701
48,965
19,586
770,375
2

$
$
$
$
$
$
$

458,385
100,929
2,042
65,286
26,114
924,450
2

$
76,018
$
283,414
$ 1,955,431
$
2

$
$
$
$

389,315

467,178

$
$

146,449
32,412

$
$

353,806

372,427

116,473

120,329

145,446

7,601
14,598
51,054
108,113
77,180
85,000
42,500

$
$
$
$
$
$
$

8,024
15,409
54,057
114,120
81,720
95,000
47,500

299,713
72,669
1,225
29,379
11,751
369,780
1

Plans and Specs resulting Claims

9,269,259

Weather and other jobsite conditions


Overall Job (Bidding Climate)

7,032,396

Low
323,166

EX Low
163,215

6,198,722

(300,000) $

(100,000)

EX Low

Low%

High%

30%

-15%

5%

25%

-5%
-20%

15%
5%

35%
15%

-15%

-10%

15%

30%

-10%
-10%
-10%
-10%
-40%
-10%

-5%
-5%
-5%
-5%
-25%
-5%

15%
25%
50%
50%
25%
50%

25%
50%
100%
100%
50%
100%

89,239
332,703
2,190,083
2

-10%

-5%

15%

35%

-10%
-5%
-10%

-5%
0%
-5%

15%
25%
50%

35%
40%
100%

506,110

-15%

-10%

20%

30%

175,739
48,618

$
$

190,384
64,824

-15%

-10%

20%

30%

0%

0%

50%

100%

465,534

521,398

-15%

-5%

25%

40%

122,603

153,254

171,644

-10%

-5%

25%

40%

161,607

184,032

198,188

-15%

-10%

30%

40%

$
$
$
$
$
$
$

8,446
16,220
60,063
120,126
90,800
100,000
50,000

$
$
$
$
$
$
$

10,980
17,842
72,076
138,145
108,960
120,000
60,000

$
$
$
$
$
$
$

12,669
18,653
78,082
150,158
118,040
130,000
65,000

-10%

-5%

30%

50%

-10%
-15%
-10%
-15%
-15%
-15%

-5%
-10%
-5%
-10%
-5%
-5%

10%
20%
15%
20%
20%
20%

15%
30%
25%
30%
30%
30%

500,000

200,000

100,000

300,000

750,000

1,000,000

7,032,396

-1%

-50%
-10%
-40%

EX High

15%

-50%

200,000

500,000

(300,000) $ (100,000) $

100,000

300,000

750,000

1,000,000

Вам также может понравиться