PROJECT
TITLE
DATE
SURVEYER
:
:
:
:
4. Potential clash identification (Lighting pole, Solar panel, fence, Communication panel, cab
1. Possible location for relocation of the clash element
2. Exit route
3. Removal and maintenance requirement of heavy instruments
5. Self verification before Starting
1. Check the validity of the Site and Gate pass
2. Validity of the safety training pass
3. Writing pad
4. Paper binding clips
5. Pens and Highlighters
6. Laser measuring tapes
7. Masking tapes and Market pen
8. Measuring pole
9. All Docs and Drawings related to Survey
Before Survey
Prepared By
After Survey
Checked By
Check Box
Checked By
Site Survey
1. Safety Momment
Agenda For Presentation
1.
2.
3.
4.
5.
6.
7.
4. Site Surveying
1. Have a walk through of the entaire piping system for Leakage, piping disengagement of su
Vibration, External corrosion, flymsy support or support member, and any further abnorma
2. Use appropriate tag to identifiy the line, valve or equipment
3. Use appropriate tools to measure and make note
4. Make note of all related info (Flange hole orientation, Demolision, construction, clearence a
5. Use checklist in survey so you know status and pending action
6. Make note of all the details which covered and which needs further action plan
7. Identifiy and markup the potential clash clearly
5. Safety rules
1. Do a risk Assesment
2. You must Intervene
3. Manage any change
3. Wear the correct PPE
4. Take time to talk
5. Communication between team members for the task and duties
6. Carry plenty of water with you
7. Have a short brake in between
5. Summary of survey
1. Address the summary to respective coordiantors for clarity of the understanding
2. Day to day communication to the coordinaters and to prepration of work pass
7. Attachments
Survey Tools
1.
2.
3.
4.
5.
Survey tools
Site survey checklist
Markups
PPE
Typical survey report
8. Question ?
9. Thankyou for Participation
1.
2.
3.
4.
5.
6.
7.
8.
9.
PPE
1. Coverall
2. Saefty hard shoes
3. Gloves
4. Ear plug
nd Night stays)
e understanding
n of work pass
n posiblities
ty and to resudule the pending
ction glasses
1
2
3
Type of support (Rest, Guide (N-S-E-W), Axial Stop (N-S-E-W), Hold Down, springs, Struts, Rigid hangerets.
Equipmet saddle detail (Fixed (Without slots) and sliding (Without slots))
Springs Hangers
1. Name plate detail
2. Manufacturer
3. Type No
4. Model No
5. Preset load
6. Operating load
7. Spring stiffness
Struts and Rigid hanger
1. Name plate detail
2. Manufacturer
3. Type No
4. Model No
5. Rod size detail
6. Operating load
If Trunion or Dummy type support - Record - Height and Trunion Pipe size and with repad or without repad
If Study routing and tie-in location does not suit the site condition try to redesign the possible routing option and tie-in location
If the tie-in is of flange connection identifiy the bolt orientation for mating flange
5
6
7
8
id hangerets.