Академический Документы
Профессиональный Документы
Культура Документы
Minerals Engineering
journal homepage: www.elsevier.com/locate/mineng
JKMRC, SMI, University of Queensland, 40 Isles Road, Indooroopilly, QLD 4068, Australia
Metso Mining and Construction Technology, 2715 Pleasant Valley Road, York, PA 17402, USA
Metso Minerals Ltd, 16 Lidco Street, Arndell Park, NSW 2148, Australia
d
Cannington Mine, BHP Billiton, PO Box 5874, Townsville, QLD 4810, Australia
b
c
a r t i c l e
i n f o
Article history:
Received 11 September 2014
Revised 13 November 2014
Accepted 14 November 2014
Available online 27 January 2015
Keywords:
VertiMill
Stirred mill
Grinding
a b s t r a c t
A substantial proportion of large industrial mines process low grade nely disseminated ore bodies that
require ne grinding to liberate valuable minerals. In response to increasing energy costs, the industry is
seeking energy efciency milling technologies that can process large tonnages. Stirred mills are an attractive option as they have the ability to grind to ne sizes (below 100 lm) at lower energy consumption
than ball mills. The VTM is one type of stirred mill that has been used in mineral processing for secondary,
tertiary and regrind duties and can be used in large throughput circuits at lower specic energy. The
JKMRC has conducted an intensive survey program on VTM circuits in various grinding duties under
the Collaborative Research in Stirred Milling Technology project funded by Metso Minerals. The survey
outcomes demonstrate that the VTM uses a low specic energy to reduce the particle size into the oatable regime by eliminating the coarser particles without producing excessive nes. This paper presents
data on the performance of VTMs in secondary and tertiary grind duties that prepare feed for rougher
otation.
2015 Elsevier Ltd. All rights reserved.
1. Introduction
It is widely reported that comminution consumes the greatest
proportion of energy in most mineral processing plants. For mines
processing low grade, hard and/or nely disseminated ore bodies,
or where there are declining metal prices, it becomes a challenge
to design and operate comminution circuits at lower specic
energy and cost without jeopardizing metal recovery. Typical comminution circuits consist of AG/SAG in primary grinding stage and
followed by ball mill in secondary/tertiary grinding, preparing the
feed for rougher stages.
With many ore types, the ore mineralogy dictates that ne
grinding is essential for effective liberation. In the past, ball mills
have been used for ne grinding but stirred mills have been shown
to grind ner at lower specic energy. It has been reported that
stirred mills consume 30% less energy in coarser ne grinding
and approximately 50% in ultra-ne grinding regime (Davey,
2006; Rahal et al., 2011). These factors have led to a steady increase
in the number of stirred mill installations in various grinding
Corresponding author.
E-mail address: s.palaniandy@uq.edu.au (S. Palaniandy).
http://dx.doi.org/10.1016/j.mineng.2014.11.014
0892-6875/ 2015 Elsevier Ltd. All rights reserved.
45
Table 1
Survey conditions.
Circuit
Survey
Tph
Cyclone
Water addition
Flowrate (m3/h)
Pressure (kPa)
Mill (m3/h)
Secondary
1
2
458 (6.9)
386 (9.2)
1418 (5.1)
2028 (0.3)
127 (2.8)
129 (1.8)
35 (56)
43.8 (12.7)
50 (1.4)
47.9 (4.7)
40 (1.0)
Tertiary
1
2
756 (2.2)
829 (0.6)
3708 (0.6)
2283 (2.1)
139 (0.6)
156 (0.9)
178 (8.2)
210 (51)
2082 (0.2)
2054 (0.3)
Regrind
226 (0.3)
175 (0.1)
42.8 (5.2)
No ow meter
573 (0.5)
36.8
1996 (0.7)
1715 (0.6)
46
47
Table 2
Measured and balanced data for Survey 1 secondary grind circuit.
Throughput (t/h)
Circuit feed
Cyclone feed
Cyclone U/F
Cyclone O/F
Mill feed A
Mill discharge A
Mill feed B
Mill discharge B
P80 (lm)
% solids
Measured
Balanced
Measured
Balanced
Measured
Balanced
458
458
1704
1246
458
406
406
839
839
67.8
70.3
83.4
83.9
74.4
83.9
77.7
67.8
70.7
83.8
49.5
84.0
74.1
83.8
73.0
155
237
226
93.9
226
212
266
200
157
189
216
93.4
215
204
220
193
458
Table 3
Measured and balanced data for survey 2 secondary grind circuit.
Throughput (t/h)
Circuit feed
Cyclone feed
Cyclone U/F
Cyclone O/F
Mill feed A
Mill discharge A
Mill feed B
Mill discharge B
P80 (lm)
% solids
Measured
Balanced
Measured
Balanced
Measured
Balanced
386
386
1590
1204
386
220
220
984
984
65.6
69.9
80.5
80.5
76.3
80.9
69.2
65.8
69.4
80.7
48.4
80.5
76.3
80.7
69.5
186
240
258
101
271
229
276
227
189
225
262
102
269
231
260
235
386
Table 4
Measured and balance data for survey 1 tertiary grind circuit.
Stream
Circuit feed
Cyclone feed
Cyclone U/F
Cyclone O/F
Mill discharge
Throughput (t/h)
P80 (lm)
% solids
Measured
Balanced
Measured
Balanced
Measured
Balanced
756
756
2392
1636
756
1636
42.1
55.0
67.2
37.5
67.0
42.0
54.2
67.3
38.2
67.2
144
188
213
92.0
179
150
180
206
93.0
189
756
48
Table 5
Measured and balanced data for survey 2 tertiary grind circuit.
Equipment
Throughput (t/h)
Circuit feed
Hydrocyclone feed
Hydrocyclone U/F
Hydrocyclone O/F
Mill discharge
P80 (lm)
% solids
Measured
Balanced
Measured
Balanced
Measured
Balanced
829
829
2564
1734
829
1734
38.7
51.9
70.5
32.6
69.4
38.2
51.8
70.0
33.5
70.0
128
182
212
76.0
193
129
182
209
78.0
197
829
Table 6
Measured and balanced data for regrind circuit survey.
Equipment
Throughput (t/h)
Circuit feed
Hydrocyclone feed
Hydrocyclone U/F
Hydrocyclone O/F
Mill discharge
Balanced
Measured
Balanced
Measured
Balanced
36.8
36.8
120
82.7
36.8
82.7
34.6
38.0
56.3
19.3
54.5
34.6
35.6
56.3
19.5
54.5
32.0
30.4
36.2
18.9
32.3
31.2
31.5
36.5
20.0
31.5
36.8
100
100
(a)
90
(b)
90
80
70
Circuit feed
60
Cyclone feed
50
Cyclone OF
40
Cyclone UF
Mill feed A
30
cumm. % passing
80
cumm. % passing
P80 (lm)
% solids
Measured
70
60
Circuit feed
50
Cyclone feed
Cyclone OF
40
Cyclone UF
30
Mill feed A
20
Mill feed B
Mill feed B
20
Mill Discharge A
10
Mill Discharge A
10
Mill Discharge B
Mill Discharge B
0
1
10
100
1000
10
100
1000
size (m)
size (m)
Fig. 4. Measured and balanced particle size distribution for secondary circuit (a) 4.36 kW h/t and (b) 4.45 kW h/t.
100
100
90
(a)
90
80
80
70
70
60
Circuit Feed
50
Cyclone feed
% passing
% passing
(b)
60
Circuit feed
50
40
Cyclone feed
30
Cyclone OF
30
Cyclone OF
20
Cyclone UF
20
Cyclone UF
40
10
Mill Discharge
10
Mill Discharge
0
10
100
1000
10000
size (mm)
10
100
1000
10000
size (mm)
Fig. 5. Measured and balanced particle size distribution for tertiary circuit (a) 2.75 kW h/t and (b) 2.48 kW h/t.
49
SI
D75
D25
OWi
SE
p10 p10
P80
SSE75
SE
For secondary and tertiary grind
P75 F 75 =100
SSE25
SE
For regrind circuit
P25 F 25 =100
The subscript for SSE refers to the size at which this is calculated, as an appropriate size needed depending on the nal product
size distribution.
Reduction ratio
Mill power draw kW
SE
Circuit throughput ht
F 80
Fi
Pi
100
90
cumm. % passing
80
70
Circuit feed
60
Cyclone feed
50
Cyclone OF
40
Cyclone UF
30
Mill discharge
20
10
0
1
10
100
1000
size (m)
Fig. 6. Measured and balanced particle size distribution for regrind circuit.
100
(a)
90
100
(b)
80
60
50
% feed to UF
70
70
60
50
40
Survey 1 (Actual)
30
Survey 1 (Corrected)
30
20
Survey 2 (Actual)
20
10
Survey 2 (Corrected)
Survey 1 (Actual)
40
Survey 1
(Corrected)
Survey 2 (Actual)
Survey 2
(Corrected)
10
0
10
100
1000
size (m)
10
100
size (m)
100
(c)
90
80
% feed to UF
% feed reports to UF
90
80
70
60
50
40
30
20
Actual
Corrected
10
0
1
10
100
size (m)
Fig. 7. Hydrocyclone efciency curve (a) secondary circuit, (b) tertiary circuit and (c) regrind circuit.
1000
50
Table 7
Hydrocyclone performance index.
Table 9
Performance criteria of VTM circuit.
Circuit
Survey
Performance index
Circuit
Survey
% water to OF
Sharpness index
d50c
Secondary
1
2
67
59
0.11
0.21
56
64
Secondary
Tertiary
1
2
60
68
0.38
0.44
77
78
1
2
Tertiary
Regrind
70
0.33
10
1
2
Regrind
Performance indicator
SE (kW h/t)
OWi
(kW h/t)
4.36
4.45
17.9
16.8
36.7
27.4
2.75
2.48
12.3
9.85
30.3
17.0
31.0
15.6
Table 8
Mineral composition of Cannington ore (Holloway et al., 2008).
Mineral
Galena
Sphalerite
Pyrrhotite
Pyrite
Other sulphides
Flourite
Talc
Quartz
Magnetite
Other NSG
Composition (%)
11.7
5.9
2.2
0.8
0.3
5.9
1.5
29.5
7.3
34.9
51
2.2
Survey 1
(b)
Survey 2
3.0
1.8
reduction ratio
reduction ratio
2.0
3.5
(a)
1.6
1.4
1.2
2.5
Survey 1
Survey 2
2.0
1.5
% passing
1.0
100
98
96
94
92
90
88
86
84
82
80
78
76
74
72
70
68
66
64
62
60
58
56
54
52
100
96
92
88
84
80
76
72
68
64
60
56
52
48
44
40
36
32
28
24
20
16
12
8
4
1.0
% passing
3.0
2.8
(c)
reduction ratio
2.6
2.4
2.2
2.0
1.8
1.6
1.4
1.2
100
96
92
88
84
80
76
72
68
64
60
56
52
48
44
40
36
32
28
24
20
1.0
% passing
Fig. 8. Reduction ratio plot (a) secondary circuit, (b) tertiary circuit and (c) regrind circuit.
5. Conclusion
VTM circuit installations in secondary, tertiary and regrind
duties can successfully prepare otation feed within the oatable
particle size range by removing the coarse tail (non-oatable particles) at lower specic energy. The good agreement between measured and balanced data indicates that the sampling practice and
procedures are that have been applied to these circuits are suitable.
Based on the survey data, the mills are operating as expected in
their grinding duties, but do show upside potential in terms of classication control.
Acknowledgements
JKMRC would like to thank BHP-Billitons Cannington Mine for
permitting the survey results to be published and the assistance
given for undertaking the successful surveys in 2013. The JKMRC
also would like to thank Metso Minerals for providing the research
funds to undertake the Development in the Stirred Milling Technology project. The authors would like to thank The JKMRC staff
and students who were involve during the surveys and sample processing. The authors also would like to thank Peter Radziszewski
for reviewing this paper.
References
Davey, G., 2006. Fine Grinding Applicants Using the Metso VertiMill Grinding Mill
and the Metso Stirred Media Detritor (SMD) in Gold Processing. In: 38th Annual
Meeting of the Canadian Mineral Processors Ottawa, Canada.
Holloway, B., Clarke, G., Lumsden, B., 2008. Improving Fine Lead and Silver Flotation
Recovery ar BHP-Billitons Cannington Mine. In: 40th Annual Meeting of the
Canadian Mineral Processor, Ottawa, Ontario, Canada.
Jankovic, A., Valery, V., Clarke, G., 2006. Design and implementation of an AVC
grinding circuit at BHP Billiton Cannington. In: Third International Conference
on Autogeneous and Semiautogeneous grinding technology, Vancouver, British
Columbia, Canada.
Ntengwe, F., Witika, L.K., 2011. Optimization of the operating density and particle
size distribution of the cyclone overow to enhance the recovery of the otation
52
of copper sulphide and oxide minerals. J. Southern Afr. Inst. Min. Metall. 111,
295300.
Palaniandy, S., Powell, M., Hilden, M., Kermanshahi, K., Allen, J., Mwansa, S., 2013.
VertiMill Development of Circuit Survey and Performance Evaluation
Protocols, Metplant 2013, Perth, Australia.
Powell, M., Mainza, A., 2006. Extended grinding curves are essential to the
comparison of milling performance. Min. Eng. 19 (15), 14871494.
Rahal, D., Roberts, K. and Rivett, T., 2011. Knelson-Deswik: Evaluation of Operating
Variables, SME Annual Meeting, Denver, CO.