Академический Документы
Профессиональный Документы
Культура Документы
This job aid is organized under a number of Sections and two Appendices:
1.
2.
3.
4.
5.
6.
A.
B.
1 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
$8,000
$7,000
$6,000
$5,000
$4,000
$3,000
$2,000
Plan EV (bcws)
Actual EV (bcwp)
$1,000
$0
Plan EV (bcws)
Actual EV (bcwp)
Actual Costs (acwp)
Sched. Index (bcwp/bcws)
Cost Index (bcwp/acwp)
Sched. Variance (bcwp-bcws)
Cost Variance (bcwp-acwp)
Per 01
$1,000
$1,500
$1,000
1.50
1.50
500
500
Per 02
$3,000
$3,500
$3,300
1.17
1.06
500
200
Per 03
$6,000
$6,800
$6,500
1.13
1.05
800
300
Per 04
$8,000
Per 06
Per 05
Per 04
Per 03
Per 02
Per 01
Per 05
$9,500
Per 06
$10,000
(physical) quantities as the basis for measuring earned value or progress. SAP uses the
following concepts, all of which are based on project costs.
BCWS Budget Cost Work Scheduled: Plan Version 0 Cost Plan through time
measured as Planned Percent of Completion (POC).
BCWP Budgeted Cost Work Performed: Earned value measured against Plan 0
Cost Plan as Actual Percent of Completion (POC).
ACWP Actual Cost Work Performed: Actual Costs expended to accomplish BCWP.
Performance (or Cost Index) equals ACWP/BCWP (NOTE: This differs from
Productivity, which is quantity based).
TOP
2 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Not all the above methods are available for all Network Activities and WBS Elements.
The following table shows the methods available and the qualifications that apply:
Methods and Qualifications
Method:
Start-Finish
Milestone
Degree of Processing (Work)
Estimate
Time Proportionality
Secondary Proportionality
Plan % complete
Actual % complete (BCWP)
(BCWS)
Network
WBS
Network
WBS
x
1
2
4
x
x
x
x
x
x
5
x
5
x
1
3
4
x
x
x
x
x - No restrictions
Blank = Not available
1 - Requires Basic Dates entered for WBS elements.
2 - In the confirmation process, the "finish % complete" is applied when
the activity status is set to "final confirmation". See the related procedure
Maintain Confirmations.
3 - Calculates % complete based upon actual start date entered at first
confirmation, and planned end date. See the related procedure Maintain
Confirmations.
4 - WBS Element must be released and have actual dates entered to get
actual % complete. See the related procedure Enter Actual Dates.
5 - You can only enter Estimate % complete (Planned and Actual) for
WBS elements through Structure Planning or the Project Planning Board.
NOTE: See Appendix B for a discussion on Quantity-based Earned value. This method
is not recommended at this time.
The following are the recommended methods for the various objects.
Cost Object
WBS element
Activity / element, internal
Activity / element, external
Activity / element, general cost
Planned % of Completion
(BCWS)
Actual % of Completion
(BCWP)
Estimate
Degree of Processing
0 - 100
Estimate
Estimate
Estimate *
0 - 100
Estimate
* Actual Earned Value is normally tracked by progress item on an external system and
transferred to SAP as an aggregate percent complete for the Activity (Work Package).
NOTE: Milestones can also be used for any of the above Cost Objects.
TOP
4 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Enter the Progress Version. This determines whether or not you can plan and/or
perform actual progress on this item. We will discuss the
set up Project Versions and Measurement Types
immediately following the overall mechanics of entering
the POC.
Note that for Estimation, the period percentages are limited to the duration of the
object.
5 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Object Weighting. You can weight the objects of the project in relative weighting.
The entire project Weighting should total 100 (percent) or 1000, else you may get
unintended results. To weight the object, whether network or WBS, enter a value in
the field POC weight that represents the objects relative contribution to progress.
NOTE: The Progress Version must be set to Weight active project for this method
to function. See section on Progress Versions, below.
NOTE: Default Method You can set up POC Measurement Method Defaults in
configuration for Networks and WBS elements so that all you need to enter in set up
is the exceptions. See configuration, Appendix A.
TOP
6 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
4 - Milestones
The Milestones Method is the most powerful earned value method. You can:
define standard milestones, with an array of attributes,
tie these standard milestones to a milestone group creating a chain
copy and modify standard milestones to an object or
create unique milestones for the particular object
See job aid Maintain Standard Milestones for details on the specific functions of a
milestone.
Maintain Milestones - The process for both WBS elements and Network Activities are
similar. The major difference is that the Networks are scheduled. The network also has
more milestone functionality than the WBS element.
Select a WBS element or Network Activity. Go to menu path WBS element (or Activity)
and select Milestone overview.
Network
WBS
Enter Usage, this is a fixed
category, but can be ignored and
used as a sort by milestone.
Enter description.
You can use The Include Standard Milestone or
Include Standard Milestone Group to copy existing standard milestones and
attributes.
The Grp column allows you to enter an authorization group to restrict update. This
is normally left blank.
Enter the fixed Basic (and / or Forecast dates). You can lag the milestone using the
Detail screen. See Details.
7 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Enter planned Percent of Completion (POC) and PA indicator to indicate that the
milestone is sued for Progress Analysis.
You can double-click on the description, if you want a long text. A long text is
indicated by the LT indicator at the far right.
To view the milestone details, click the Detail Button at the bottom of the
screen. See Details.
For Networks,
Update the Fixed date (and time) or the offset from the start / finish of the activity,
either in absolute time or percentage of duration. The column Fin Offset should be
checked only if the offset is from the finish date. The Lat column, if checked,
indicates that the latest dates should be used.
Check the Fct (function) box to set up milestone functions. Select the
milestone and click the Detail icon at the bottom of the screen. See Details.
For all,
Each milestone carries a system number. You can double-click on the Usage to
create, change or display the detailed attributes of the milestone. For details on these
functions, see job aid Maintain Standard Milestones. Arrow back to return to the
milestone overview.
Update the Actual date when milestone is complete.
Update the other, selected objects by using the navigation buttons.
Details - The milestone details differ from the WBS and the Network. The Network has
many more functions.
WBS
Network
For WBS,
Usage You can extend the usage of the Milestone to trigger a Sales Order billing
date when the milestone is complete. You can also set the Milestone as part of Trend
Analysis, which is not discussed here.
Percent Complete Invoice Plan. You can set a percent complete for an Invoice
Plan.
8 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Dates you can view or update the Basic, Forecast and Actual completion dates.
You can set the milestone offset from the start / finish dates relative to the WBS
dates.
9 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
For Networks,
The Network Milestone has a number of added functions compared to the WBS element
Milestone. These are organized within the Basic and Functions tabs.
Usage Like the WBS milestone, you can set the usage of the Network milestone
to include Sales Document date and Trend analysis. In addition, there are a Release
Stop indicator and other Functions. A Release Stop Indicator prevents the automatic
release of the Activity based upon the Release up to stop indicator function in the
Functions tab of a predecessor activity. The Function indicator indicates the
functions are activitated within the Function Tab.
Billing Invoice Plan - You can set a proposed percent of (lump sum) Client
billing. This can be over-ridden at the time of the Sales Order Billing Plan.
Each of the functions allows the user to set the conditions when the function will be
executed.
The function can be executed based upon System and / or a user status attained by
the Activity.
The function can be performed more than once or only once depending on how
the Change and Once columns are set.
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
View Network Milestones - You can view the milestones by going to the Gantt Bar
Chart report. Use menu path Goto > Graphics > Gantt chart. You can also use the
Project Planning Board, CJ2B.
TOP
11 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Plan version 0 should exclude forecast deviation, that is, deviations that are not
included in approved scope changes. This is necessary because earned value
calculations are based on Plan version 0.
Plan version FB should include all deviations, including those deviations not
approved by the client.
The Forecast work field can be aligned with Plan version FB, thus creating a
secondary version of Work. The forecast Work field can be updated through
manual confirmations, transaction CN25, to include these unapproved deviations
that include Work. See job aid Maintain Confirmations.
CAUTION: If you are using automated confirmations through CATS, when labor is
confirmed SAP automatically assigns an actual start date and an actual finish date to
the network activity. If the activity is not complete, you MUST assign a forecast
finish date to the activity. This will overrule the actual date.
TOP
12 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Reporting Earned Value - There are three standard SAP reports that can be executed,
CNE5 and two Cost Hierarchy Reports.
CNE5 generates a Structure Overview report and process
the same as any other Structure Overview report. Be sure
to change the PS Information Profile to SAPPS_EV0001.
Next, Click the Progress version button and
select the Progress version you wish to
report against
NOTE: There are other Profiles that SAP has set up for earned value.
NOTE: You can compare with a Simulation Version by changing the parameters of the
DB Profile to include Versions.
13 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
The report processes like any Cost Hierarchy Report and compares Planned (from
Progress Version) with Actuals from the Operational Plan. You can call the EV detail
report from the hierarchy report by selecting a line item, clicking the Call report button
and select the Detail report.
14 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
15 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Measurement Statistical Key Figures (SKF) - You must first set up the measures by
creating Statistical Key Figures within PS Progress Analysis node. In this case, SKF
has been set to 10, 20 and 30 for PS non-aggregated POC, PS aggregated POC and PS
results analysis POC.
17 of 19
Rev 0
01-Aug-2002
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
Enter the Value Category and sequence number if entering more than one Statistical
Key Figure that is out of a range.
Enter the Statistical Key Figure (or range, if appropriate).
JA-GL-BU-PMA-PCS-MX201
Earned Value Methods 4.6
The WBS element screen is the same layout. The only difference is that the range is by
WBS elements and not networks.
Measuring Actual Quantities - Once the project is set up,
you can begin to take progress based on quantities.
Transaction KB31N creates the progress entry; KB34N
cancel the entry. KB33 displays the progress document.
19 of 19
Rev 0
01-Aug-2002