Академический Документы
Профессиональный Документы
Культура Документы
Index
1.
2.
3.
4.
5.
6.
Introduction
Purpose Of This Document
Fixed Asset Movement Form (FAMF)
Fixed Asset Transfer Form (FATF)
Areas & National Office Departments
National Office Finance
1. Introduction
Cafcass has a significant investment in fixed assets. As such it has a statutory
responsibility to ensure that these investments are properly managed,
controlled and recorded. Currently, this information is held centrally on the
Open Accounts Fixed Assets Register (FAR).
The FAR uniquely identifies Cafcass fixed assets and records the financial
information and history of those assets. A record such as this is required to:
In all cases the original completed FAMF and the relevant back-up
documents must be returned NO Finance no later than the 26 th of each
month.
asset code and(if applicable) the asset serial number for that asset from the
FAR. These details will need to be entered onto the FAMF, along with any
proceeds from the sale.
The completed FAMF should then be passed to the relevant authoriser for
authorisation.
Asset Movements: Write-Offs
Write offs relate to existing fixed assets, which have been lost or stolen, or
those fixed assets that are to be discarded for nil proceeds. As outlined in
both the Financial Memorandum, and the Special Payments and Write Off
Guide, all write offs require prior approval from the Accounting Officer via NO
Finance.
Where a fixed asset has been lost or stolen, an Accident and Incident Report
must be completed prior to the write off request. A copy of this report can be
found on the Intranet under Health & Safety Procedures. This form should
then be attached to the write off business case request and returned to NO
Finance for consideration.
Once the write off has been approved, a FAMF should be completed. When
completing the FAMF, staff will need to obtain the unique asset code and (if
applicable) the asset serial number for that asset from the FAR. These details
will need to be entered onto the FAMF. The completed FAMF should then be
passed to the relevant authoriser for authorisation.
Asset Movements: Transfers
Transfers refer to Fixed Assets, which are moved from one cost centre to
another. Generally, these transfers will involve the relocation of assets within
the same Area.
Prior approval from the appropriate authoriser must first be sought before any
fixed asset can be transferred. Once approved, a FATF will need to be
completed. The completed FATF should then be passed to the relevant
authoriser for authorisation.
NO Finance will also ensure that all relevant back-up documents have been
attached, as per Appendix 3. NO Finance will then complete the section 20
authorisations.
Once the FAMF has been authorised, NO Finance will then update the OA
FAR with the completed FAMF. When updating the OA FAR, the asset serial
number contained in section 19 of the FAMF must be entered into the volume
and serial number fields of the system. These fields should on no account be
left blank at the entry stage as to do so will make them inaccessible for future
use.
If a FAMF contains multiple units of an asset in section 03, one sub-line of the
volume / serial number field must be used for each unit.
Costs relating to fixed asset additions are posted to the 721 series of General
Ledger accounts. On verifying the contents of the FAMF as described above,
NO Finance will prepare and post a manual General Ledger journal
transferring the cost from this series of accounts into 981420 Capital
Expense Account.
Once completed, NO Finance will retain copy of the FAMF for recordkeeping purposes.
NO Finance will complete the section T14 authorisations and then update the
OA FAR with the completed FAMF.
Once completed, NO Finance will retain copy of the FAMF for recordkeeping purposes.
Monthly Requirements
OA FAR will be closed on the 3rd working day of each month. NO Finance
must ensure:
That all completed FAMFs received in the previous month have been
processed into OA FAR.
That the OA FAR depreciation calculation has been run and the
system-based journal accurately posted.
That all other system-based journals have been accurately posted. A
listing of OA FAR system-based journals can be found in Appendix 6.
OA FAR vs. OA GL Reconciliation
On closing of OA FAR NO Finance will prepare a standard OA FAR vs. OA
GL reconciliation. This reconciliation will as normal be included in the monthly
reconciliations pack.
This states that freehold land and buildings are subject to physical revaluation at least every three years and by
indexation using current cost indices during intervening years. Other tangible assets should be stated at current
cost using appropriate indices published by the Office for National Statistics.
The minimum level for capitalisation of a tangible fixed asset is 2,500. In the case of IT equipment If they fall
below the 2,500 threshold they are to be grouped together and classified as grouped assets and should be
capitalised.
Assets costing less than 2,500 (except for IT assets) will be expensed in
the year.
Project Related Work: Due to the complexities involving such work, please
contact NO Finance for advice as each project will be judged on its merits.
Hardware
Software
Peripherals
Resources
IT Definitions
Auditing:
Would check the assets grouped in the IT Infrastructure in year of
additions.
Would take a sample from the code in the ledger entries and check
through these.
Would look for invoices confirming the purchase of a sample taken.
Would not ask for the whole line to be reconciled.
Other Controls:
NO Finance maintaining its own verification of assets
NO Finance would be carrying out quarterly IT and Estates verifications to
make sure IT and Estates records reconciles with Cafcass Fixed Asset
Register. The auditors would be relying on the controls that have been put
in place if they find these to be reliable.
Freehold buildings
Leasehold land and buildings
Leasehold improvements
Office equipment
Informatuion technology
Laptops under Flex
Laptops (non-Flex)
Up to 60 years
Up to 50 years, or over the term of the lease
Over the term of the lease
Seven years
Five years
Estimated replacement date
Five years
Fixed assets are not subject to revaluations in the financial year in which
they are purchased.
Freehold land and buildings are subject to physical revaluation by the VOA
at least every three years and by indexation using current cost indices
during intervening years.
Other tangible fixed assets except for leasehold property are subject to
annual revaluations using appropriate indices published by the Office for
National Statistics (ONS).
The contra entry for the upward revaluation of fixed assets is the
revaluation reserve account in the balance sheet.
The contra entries for the downward revaluation of fixed assets are the
diminutions accounts in I&E.
Note: Office for National Statistics indices can also be downloaded via the
website www.statistics.gov.uk.
Purchase
Disposal
Write Off
12. Prepared By
13. Signature & Date
20. Authorised By
Position
Signature & Date
11.
Supporting
Documents Required
12 & 13.
Prepared By
20.
Authorised By
T14.
Authorised By
2. Recording Transactions
Each Operational Area should ensure that all local asset transactions within
their area are adequately documented, and that this documentation is
sufficient in order to effectively update their Local Asset Register, a template
of which can be found on the intranet.
There are four main types of local asset transactions that will impact on the
Local Asset Register and which therefore need to be documented. These
transactions are:
Additions (When an asset is purchased)
Disposals (When an asset is sold)
Transfers (Between Cafcass offices)
Write-Offs (When an asset has been stolen, broken, or lost)
Column A (Cell A10 onwards): Use the drop-down menu to select the
Service area to which the local asset relates.
Column B (Cell B10 onwards): Use the drop-down menu to select the
Cafcass office to which the local asset relates.
Column C (Cell C10 onwards): Use the drop-down menu to select the
category to which the local asset relates.
Column D (Cell D10 onwards): Enter a brief description of the local asset.
Column E (Cell E10 onwards): Enter (if available) the model or serial
number of the local asset.
Column F (Cell F10 onwards): Use the drop-down menu to select the
number of units of local asset being recorded.
Column G (Cell G10 onwards): Enter (if available) the purchase date of the
local asset in DD-MM-YY format (E.g. 21-12-12).
The Local Asset Register needs to be kept updated and made available for
review by External Auditors, Internal Auditors, National Office, etc.
Office based Local Asset Registers are then prepared and an electronic
copy provided to the Area Finance Manager/National Office Manager.
GENERAL
Assets are defined as something valuable that an entity owns, benefits from,
or has use of, in generating income or performing duties. It includes tangible
items such as real estate, furniture, office and IT equipment as well as
intangible items such as property rights and website costs.
1.2
The purpose of these procedures are to provide the means for the disposal of
redundant or surplus assets, to ensure that any disposals are dealt with in an
auditable manner and are in compliance with the requirements set out in the
Financial Memorandum (section 3), Fixed and Local Asset policy and
procedures.
1.3
Asset disposal decisions and the reasons for taking them should be properly
documented. Not only does this assist in audit and other examinations, but it
highlights successes and problems for future reference.
1.4
1.5
In the interests of promoting probity, fair dealing and openness, sections must
not sell or otherwise transfer surplus assets to staff (for personal use) (or their
relatives or friends) unless arising from a public competitive process, i.e. an
advertised sale that is open to the public. Where a member of the public and
a staff member offer an equal price, the item must be sold to a member of the
public. The sale price must be the best market price and under no
circumstances may equipment be donated to staff.
2
2.1
2.2
3
3.1
3.2
Outside of the approved Cafcass Estates Strategy, Cafcass may normally retain
receipts derived from the sale of assets provided that all of the following are met:
The DfE and the Treasury are content for Cafcass to retain these
receipts;
3.3
If, notwithstanding the above, Cafcass disposes of assets which have been
purchased, improved or developed with Exchequer funds and the receipts
amount to more than 1 million, or where the disposal has unusual features of
which Parliament should be aware, Parliamentary approval shall be secured
for the receipts to be reinvested. The receipts shall therefore be surrendered
to the DFE, which will then submit an Estimate seeking approval for the
receipts to be appropriated in aid by the DFE and for a corresponding
increase in Cafcass Grant-in-Aid. If the proposed new investment exceeds
Cafcass relevant delegated authority, the approval from the DFE will be
needed. If the proposed new investment is novel or contentious, the
Treasurys approval will be also needed.
3.4
4
4.1
4.2
4.2.1
Confirm with NO Finance that the asset is appearing on the fixed asset
register and request the original purchase price, residual value and asset
code of the asset.
4.2.2
4.2.3
4.2.4
All other assets shall be sold for best price, taking into account any costs of
sale. VAT at 20% should be charged on all sales of assets. NO Finance
should maintain a log of all sales of assets as the total sales in a financial
year should not exceed 3% of the Grant-In-Aid. The following procedure
should be followed in the case of any proceeds on the disposal of the asset:
A business case needs to be submitted to the DFE, which has been
approved by the Head of Service and the Operational Director,
which should set out the conditions of sale
All the requirements of section 3.2 should be met
A fixed asset movement form should be completed and NO Finance
should be notified
4.2.5
5.1
Local assets are all physical assets owned by Cafcass that were purchased
at a cost price of less than 2,500, except for IT equipment which have been
grouped together. These will appear on the local asset registers and will
include (but is not limited to) furniture, photocopiers, franking machines, fax
machines and cameras. Local asset registers are maintained as a method for
recording and safeguarding Cafcass assets that may otherwise be neglected
and at risk.
5.2.
5.2.1
All assets shall be sold for best price, taking into account any costs of sale.
Should there be any proceeds on the sale of the asset all requirements of
section 4.2.4 should be met.
5.2.2
6.1
DISCLAIMER
Cafcass will not be held liable for any Health and Safety issues surrounding
the use of the asset. Ensure that a Furniture and Equipment Disclaimer is
signed by the recipient upon transfer.
INTRODUCTION ......................................................................................................................... 24
THE CONTROL CULTURE ....................................................................................................... 24
SUPPLIERS ................................................................................................................................. 25
SELF-EMPLOYED PRACTITIONERS ........................................................................................ 25
STAFF .......................................................................................................................................... 26
IMPLICATIONS FOR AUTHORISED SIGNATORIES ................................................................ 26
OTHER GUIDANCE AND PROCEDURES ................................................................................. 26
TRAINING NEEDS ...................................................................................................................... 27
Document Owner:
Last Updated:
Updated by:
Director of Finance
July 2012
Julie Brown
INTRODUCTION
1.1
1.2
1.3
In this context Control Culture means: taking the necessary steps to ensure that
public money is spent properly, payments are duly authorised and recorded against
the services and goods commissioned and received, and that value for money is
delivered.
1.4
This is an area of focus for Internal Audit and all areas of the organisation will be
subject to an audit of their compliance with controls.
1.5
The guidance below refers to a regional setting but applies equally to the National
Office and Legal Services.
SUPPLIERS
3.1
Suppliers include all those organisations and individuals who provide goods and
services to Cafcass. New suppliers will need to provide their bank details on letterheaded paper to help ensure that payments are only made to legitimate suppliers.
3.2
When dealing with significant suppliers, the Manager or a member of staff should be
aware of the terms and conditions. These may be contained in a contract, leaflets or
exchange of correspondence. They should be reviewed prior to agreement to ensure
that they are reasonable and could not have an adversely effect Cafcass. Further
guidance is available in the procurement manual and further advice can be obtained
from the National Procurement team.
3.3
The delivery of physical goods should be checked prior to the processing of the
Goods Received Note.
3.4
Charges for people services such as consultants, contract staff and self-employed
practitioners are usually based on time. Records of time worked by such individuals
should be kept and reviewed and approved by the relevant Manager on a regular
basis. Weekly time sheets provide the most manageable record of time. These
should be submitted promptly.
3.5
3.6
SELF-EMPLOYED PRACTITIONERS
4.1
Self-employed practitioners are subject to the same level of financial internal controls
in terms of the processes applied and value for money as other suppliers. In addition
to these managers must be aware of the contract under which they provide their
services and the procedures and guidance of the contracts issued regarding
implement.
4.2
4.3
STAFF
5.1
Staff expense claims should be scrutinised, and where applicable checked against
backing receipts and diaries and confirmed that they are in line with HR policies. It is
also the Managers responsibility to judge whether Value for Money (VFM) was
received to inform future action.
5.2
Signing-off documents should not be treated as a routine task, each instance should
be carefully considered. This also applies to signing-off transactions using e-bis
such as Purchase Orders and matching invoices, such electronic signing should
be considered as the equivalent of a written signature.
6.2
Before you sign-off any payment, authorise a Purchase Order or raise a Goods
Received Note ensure that:
You are authorised to do so and the amount falls within your delegated authority,
You are satisfied that the services have been performed or the goods have been
delivered in the manner agreed with the supplier,
You or a member of your staff, have followed up any concerns,
The price and overall costs are correct,
Correct procurement procedures have been followed,
Appropriate documentary evidence is obtained to support the payment and that
this is retained for (internal and external) audit inspection.
6.3
If in doubt do not sign. Seek the information you require from those closer to the point
of supply or the supplier. If you are still not satisfied refer the matter to your Line
Manager or Area Finance Manager who may refer the matter to Cafcass Finance for
advice.
6.4
6.5
6.6
This guidance is linked to other internal control policies and procedures that are
available on the Intranet including:
Internal Financial Control Bulletin
TRAINING NEEDS
8.1 If there are areas in which you require training to undertake the
responsibilities above, inform your Line Manager and or Area Finance
Manager of these, preferably in writing. Cafcass Finance will collate them
and arrange training.
8.2
Conversely, if you have good financial practice in your Team please share it with the
rest of Cafcass via the Area Finance Manager. This guidance will be revised in the
future to reflect such good practice.
Director of Finance
April 2013
Zubeda Seedat
Introduction
This document describes the budget delegation process within Cafcass. It is
Cafcass policy to give operational managers the maximum flexibility in the use
of resources commensurate with proper overall control of the organisations
finances by devolving financial responsibility to managers.
Authorisation
Within the financial and control limits of the delegation letter a Budget Holder
has the authority to:
Accountability
Budget Holders are accountable for safeguarding expenditure; higher budget holders must
set and assess their staff's dealing with financial management to ensure that financial
standards are maintained. This should be done via performance management records.
Assistant Directors/Head of Service are assessed on resource management via the iTrent
performance framework and must ensure that standards are met.
Segregation of Duties
Budget Holders have the authority to incur expenditure within the limits of their
delegation letter, however where the expenditure relates directly to them
specifically e.g. expenditure on travel and subsistence, training, overtime etc
the expenditure must be approved by the line manager of the Budget Holder.
Appendice A:
To:
Budget:
Budget allocation ()
Subject to the following restrictions, you are free to manage your budget as you think
best, to deliver your plans for 20XX/XX.
Delegations
Expenditure must not be incurred beyond the total delegated limits shown
above. You have the power to incur and authorise expenditure directly, and
through sub delegation, subject to compliance with the procedures and limits
as prescribed in the Finance Manual and the Financial Memorandum.
You have the power to delegate financial and accounting responsibility for elements
of this budget, by issuing a formal secondary budget delegation letter. You must use
this power unless you know of particular reasons why it should not be exercised.
Budget Reporting
You must report to the Director of Finance either using the Confirmation of
Review of Monthly Management Reports and Budget Monitoring (MMR)
document or via the submission of the monthly Operational Management
Team (OMT) finance report and minutes. This report will be required on a
monthly basis; in addition all budget holders will be required to submit, as a
minimum, quarterly budget forecasts in line with the agreed and published
timetable.
Partnership budgets
Each year both the baseline partnership funding (previously included in
Operational budgets) and the DfE partnership funding will be held by the
National Commissioning and Partnership team with agreement by the Head of
Service and the National Commissioning and Partnership team for all new
commitments.
Segregation of Duties
As budget holder you have the authority to incur expenditure, however where the
expenditure relates directly to you as budget holder i.e. expenditure on travel and
subsistence, training, overtime etc prior approval must be obtained from your line
manager.
Purchase Orders
As budget holder you should ensure that all expenditure is incurred in line with
existing financial and procurement policies and procedures. This includes ensuring
compliance with purchase order procedures i.e. no expenditure to be entered into or
incurred before a purchase order has been raised. As well as good financial practice it
also indicates that the budget holder has given approval for the expenditure.
Timeliness in paying invoices
Ensure at all times that, supplier invoices are properly approved and paid within 30
days of the invoice date, with the exception of disputed invoices which should be
resolved as soon as possible. Similarly, monies owed to Cafcass are collected with 30
days of the invoice date.
Authorised Signatories
You must ensure that the list of authorised signatories for your budget area
remains current with deletions and amendments processed on a timely basis,
with a full review undertaken quarterly. You should only delegate budgets to
authorised signatories; similarly staffs who are not budget holders should
have no requirement to be authorised signatories.
Internal Financial Controls
You are accountable for safeguarding expenditure and ensuring your staffs
compliance with this guidance. Therefore, you must set and assess your
staff's dealing with financial management to confirm that an adequate financial
framework exists to safeguard the budget that I have delegated to you in this
document. This should be done via performance management records.
Assistant Directors/Head of Service should be assessed on resource management via
the iTrent performance framework and you must ensure that the standards are met.
Internal and External Auditors
I will be looking to our internal audit and assurance activities to provide me
with independent assurance of your operations and financial controls. Your
budget area may therefore be subject to independent scrutiny in this financial
year. You will receive a copy of the internal audit programme for the year, you
need to ensure that you are familiar with this and you should share this with
relevant staff within your area.
The National Audit Office (NAO) may also seek to provide me with
independent assurance for their external audit of Cafcass Annual Accounts.
This may involve visits to your budget area to review your systems and
controls.
Payroll
Each month you are provided with a copy of the Payroll Report detailing all payroll
payments (including T&S) made to staff in the month in your budget area. You are
required to review the report and confirm the salaries, allowances and travel and
subsistence claims paid are complete and accurate. This confirmation/sign off is part
of the budget monitoring report referred to above. This function can be delegated (i.e.
to the Head of Service/ ABM/Area Finance Manager/HR Transactional Coordinator/Service Manager etc) with the appropriate knowledge and skills to do this.
This delegation should be appropriately documented.
Starters and Leavers
You must take steps to ensure that HR staff and any staff with line management are
aware of their responsibility to submit Starter / Leaver and payroll data / changes
forms on a timely basis to the HR Transaction Team to ensure payroll deadlines are
met and reduce the risk of salary overpayments or delayed payments. Where
overpayments do occur you must ensure that adequate steps are taken by your HR
Transactional Co-ordinator to secure a signed recovery plan and recover the
overpayment as soon as possible.
Fixed Assets
Other than the National Office Estates and IT cost centres, your delegated
budget has no provision for capital/fixed asset purchases (i.e. items over
2,500) unless otherwise stated. Only Estates and IT departments have
regular authority to commit and incur such expenditures. In the event that a
capital purchase needs to be made, prior authority must first be obtained from
the Head of Finance.
Special Payments
The Chief Executive as Accounting Officer is ultimately responsible for authorising
any special payments made by Cafcass. Special payments may include compensation
payments, ex-gratia payments and write-offs.
However, the Chief Executive has delegated approval values of below 500 to
Directors and up to 100 to Head of Service. Please refer to the Special payments
and write-off guidance for further detail, this can be found under Financial Control
section of the Finance Manual on the Intranet.
Debtor Management
All sales / income must be supported by the issuing of a properly
constituted invoice with VAT charged where applicable. Where invoices need
to be raised for income due to Cafcass, this is coordinated via Cafcass
Finance through use of an AR1 invoice request form. As with POs an invoice
should be raised as a first step in the process. Review and follow-up any
outstanding invoices that have not been paid by third party.
Signed:
_____________________________
Name:
Date:
_____________________________
I confirm that I have read, understood and accept the responsibilities as laid
down in this document and I am familiar with the policies and procedures
referred to in this letter including but not limited to the Finance Manual, the
Procurement Manual and the Financial Memorandum.
Signed: _____________________________
Name:
Date:
_____________________________
To:
Budget:
Category of Expenditure
Workforce Costs
Other Running Costs
TOTAL BUDGET
Budget allocation ()
Subject to the following restrictions, you are free to manage your budget as you think
best, to deliver your plans for 20XX/XX.
Delegations
Expenditure must not be incurred beyond the total delegated limits shown
above. Each budget by category of expenditure is ring fenced and any
transfer of budgets between categories of expenditure within your total budget
can only be undertaken with prior written agreement from the Primary Budget
Holder. You have the power to incur and authorise expenditure directly,
subject to compliance with the procedures and limits as prescribed in the
Finance Manual and the Financial Memorandum.
You have the power to delegate financial and accounting responsibility for elements
of this budget by issuing Authorisation to spend letters to your managers. This will
allow managers to approve costs i.e. iTrent expenditure. You will however be
deemed accountable for the overall budget and you must ensure that the said manager
is aware that it is their responsibility to scrutinise claims/POs before approval. You
must also ensure that they are adequately trained.
Budget Reporting
You must report to Finance or the Primary Budget Holder using the
Confirmation of Review of Monthly Management Reports and Budget
Monitoring (MMR) document. This report will be required on a monthly basis;
in addition all budget holders will be required to submit, as a minimum,
quarterly budget forecasts in line with the agreed and published timetable.
Partnership budgets
Each year both the baseline partnership funding (previously included in
Operational budgets) and the DfE partnership funding will be held by the
National Commissioning and Partnership team with agreement by the Head of
Service and the National Commissioning and Partnership team for all new
commitments.
Segregation of Duties
As budget holder you have the authority to incur expenditure, however where the
expenditure relates directly to you as budget holder i.e. expenditure on travel and
subsistence, training, overtime etc prior approval must be obtained from your line
manager.
Purchase Orders
As budget holder you should ensure that all expenditure is incurred in line with
existing financial and procurement policies and procedures. This includes
ensuring compliance with purchase order procedures i.e. no expenditure to be
entered into or incurred before a purchase order has been raised. As well as
good financial practice it also indicates that the budget holder has given approval
for the expenditure.
Timeliness in paying invoices
Ensure at all times that, supplier invoices are properly approved and paid within 30
days of the invoice date, with the exception of disputed invoices which should be
resolved as soon as possible. Similarly, monies owed to Cafcass are collected with 30
days of the invoice date.
Authorised Signatories
You must ensure that the list of authorised signatories for your budget area
remains current with deletions and amendments processed on a timely basis,
with a full review undertaken quarterly. You should only delegate budgets to
authorised signatories; similarly staffs who are not budget holders should
have no requirement to be authorised signatories.
Internal Financial Controls
You are accountable for safeguarding expenditure and ensuring your staffs
compliance with this guidance. Therefore, you must set and assess your
staff's dealing with financial management to confirm that an adequate financial
framework exists to safeguard the budget that I have delegated to you in this
document. This should be done via performance management records.
Debtor Management
All sales / income must be supported by the issuing of a properly
constituted invoice with VAT charged where applicable. Where invoices need
to be raised for income due to Cafcass, this is coordinated via Cafcass
Finance through use of an AR1 invoice request form. As with POs an invoice
should be raised as a first step in the process. Review and follow-up any
outstanding invoices that have not been paid by third party.
Signed:
_____________________________
Name:
Date:
_____________________________
I confirm that I have read, understood and accept the responsibilities as laid
down in this document and I am familiar with the policies and procedures
referred to in this letter including but not limited to the Finance Manual, the
Procurement Manual and the Financial Memorandum.
Signed: _____________________________
Name:
Date:
_____________________________
To:
Budget:
As the Budget Holder for the above budget, I hereby give permission to
you to process and approve financial items against the above cost
centre(s) for the following categories of cost:
PURCHASE ORDERS FOR:
EXPENSE NAME
EXPENSE CODE
LIMIT
PERMISSION
Yes/No
Yes/No
Yes/No
Yes/No
LIMIT
PAYCOSTS FOR:
TYPE
Travel & Subsistence
Overtime
Sessional Hours
Bank costs
Signed:
_____________________________
Name:
(BUDGET HOLDERS)
Date:
I confirm that I have read, understood and accept the responsibilities as laid
down in this document and I am familiar with the Cafcass policies and
procedures.
Signed:
_____________________________
Date:
1.
INTRODUCTION
1.1
This guidance details the process and procedures relating to
Special Payments and Losses, including who has the authority
to approve such transactions and procedure.
2.
SPECIAL PAYMENT
2.1
Special payments are those made, at Cafcass discretion, to
meet an obligation which Cafcass feels honour bound to pay but
for
which it is not legally liable. By their very nature they are
payments which Cafcass could not have contemplated making
when the grant funding was made. Because of this, the
delegated authority for special payments rests with Cafcass via
DfE.
2.2
HM Treasury Guidance on Managing Public Money categories
special payments as the following:
2.3
2.4
2.5
3.
3.3
3. 4
4.
AUTHORITY
4.1
As per the Cafcass Financial Memorandum the current authority
for any special payment or losses transactions sits with the
Accounting Officer (Chief Executive) only.
5.
6.
6.2 After consideration of the above, a Business Case detailing all the relevant information must be completed
and submitted to the Chief Executive via National Office Finance Department for further consideration. The
business case template can be found on the intranet under Finance Department/Finance Manual/Financial
Control/Special Payments and Write-offs.
7.
WRITE-OFFS AUTHORITY
7.1
The Accounting Officer has the personal authority to authorise
write-off transactions up to a value of 5,000 for an individual
claim, within a total limit of 50,000 in any one financial year.
Write-off requests with a value of 5,000 or more are subject to
DfE approval (see Appendix B of the Financial Memorandum).
8.
9.
8.2
Debtors
Failure to recover the debt using the guidelines set out in the
Debtors Policy. A request for a debt to be written-off must be
submitted via a Business Case (can be found on the intranet
under
Finance
Department/Finance
Manual/Financial
Control/Special Payments and Write-offs/Business Case) and
the recovering supporting documents addressed to the Chief
Executive and sent via National Office Finance Department.
8.3
8.4
8.5
9.1
10.
The Request
10.1 The member of CMT must submit all Business Cases and it
should include all relevant information required for the Chief
Executive to make a decision. Decisions will be notified within 5
working days of receipt.
For further assistance on Special Payments and Losses please contact
Finance on 0844 353 3357.
Cafcass Finance
Created:
Last Updated:
December 2005
September 2009
Contents:
Section 1 General information
Section 2 Details
2.1 Local Losses and Write Offs
2.2 Fruitless Payments
2.3 Constructive Losses
2.4 Corporate contingency Bid request
Ongoing Cost: Are you making any commitments that would have to
continue at the end of this work? E.g. Staffing cost i.e. ongoing training
&recruitment, maintenance, fees etc.
Section 2 Details
Please mark an X in the correct reason for the Business case and complete
the relevant section (by double clicking the document contained within the
form). You will need to save the embedded document by clicking the Save
button, (this will enable the embedded document to be automatically saved
within your Business Case template) do not use Save As. Please note, you
can copy and paste text from other documents into the relevant section of the
form, you can also attach other documents within this form as long as it is
linked/pasted into the correct section and provides the relevant information
sought.
2.1 Local Losses and Write Offs
Losses or a Write-off is where a transaction has already been incurred and is
usually for failure to recover debt, salary overpayment or theft and loss write offs. For example:
Local losses Cash losses i.e. Petty Cash (PC) loss or stolen items.
All salary related write-off requests must state how the overpayment occurred
and why there is a need for a write-off. Please refer to the Salary
Overpayment and Recovery policy for further guidance on overpayments.
To write-off stolen or loss items i.e. PC losses, fixed assets etc the Accident &
Incident Report must be completed prior to the write-off request. This can be
found on the intranet under Forms/ Health & Safety Forms or via the below
link:
Accident and Incident Report
A copy of this form should be attached to this Business Case request when
submitted for authorisation. Please refer to the Special Payments and Write
Off section on the intranet for more details before completing the Business
Case:
http://cafcassintranet/Intranet/departments/finance/finance_manual_new
/financial_control_new.aspx
What to do:
a) In this section please select the appropriate box that applies for your
request. To determine which category your request falls into please see
the guidance above.
b) Reason for the loss/write off Please detail the circumstances that led to
the loss of cash/asset or reason that there is a need for a write off. Please
also state:
Include any information that you think would be helpful for the
authoriser to know about to enable them to make a decision on the
proposal.
c) Action taken to resolve issue Please detail what has been done so far to
resolve the issue in hand?
d) Learning points and action taken to prevent reoccurrence Please detail
the learning points recognised and what action has been taken to ensure
that the current issue will not arise again and all risks have been mitigated.
e) Has an Incident & Accident Form been completed and attached? This is
only applicable for stolen or loss items (see above).
Please now complete Section 3 and obtain authorisation as per Section 4.
2.2 Fruitless Payments
There are two types of Fruitless Payments which require a Business Case to be
completed; these are Court Orders and Compensation.
Court orders - It is essential for the Service Manager to contact Legal via the duty
line immediately, whenever the issue of a costs order against Cafcass is raised.
Please refer to the Cost Order guidance before completing the Business
Case:
Cost Order Guidance
i.
ii.
What to do:
a) In this section please select the appropriate box that applies for your
request.
b) Reason for the Court Order/Compensation Please detail the
circumstances that led to the Court order or why you feel a compensation
payment is required? Please also state:
Include any information that you think would be helpful for the
authoriser to know about to enable them to make a decision on the
proposal.
c) Has Cafcass Legal been notified of Court cost order? This only applies to
Court orders but it is essential that this has been done even if the hearing
is months away.
d) Has the Customer Service Team (CST) recommended this payment? This
only applies to compensation payments.
e) Action taken to resolve issue Please detail what has been done so far to
try and put things right?
f) Learning points and action taken to prevent reoccurrence Please detail
the learning points recognised and what action has been taken to ensure
that the current issue will not arise again and all risks have been mitigated.
Please now complete Section 3 and obtain authorisation as per Section 4.
2.3 Constructive Losses
Constructive Losses are those losses which have occurred due to the
decision taken to abandon a project as it is no longer a viable proposition and
will not add value if completed. This is to be used corporately only.
What to do:
In this section please state:
a) Key facts about your proposal
i.
ii.
iii.
Include any information that you think would be helpful for the authoriser to
know about to enable them to make a decision on the proposal.
b) Action taken to resolve issue Please detail what has been done so far to
try and put things right?
c) Learning points and action taken to prevent reoccurrence Please detail
the learning points recognised and what action has been taken to ensure
that the current issue will not arise again and all risks have been mitigated.
Please now complete Section 3 and obtain authorisation as per Section 4.
2.4 Corporate contingency Bid request
A Business Case is required when making a bid for funds via the corporate
contingency so that the proposal can be assessed and an informed decision
made by the relevant parties.
What to do:
a) In this section please select the Operating priority this bid will support.
b) Please provide the timescale expected for the proposal.
c) Key facts about your proposal
i.
ii.
iii.
iv.
Include any information that you think would be helpful for the authoriser to
know about to enable them to make a decision on the proposal.
Please now complete Section 3 and obtain authorisation as per Section 4.
Section 4 Authorisation
The Business Case must be completed electronically and sent to the
appropriate person to authorise electronically.
There are different Authorisation requirements dependent on the nature of the
Business Case, please follow the below guidance.
Write Offs, Losses and Fruitless payments
There are different authority levels dependent on value of the item when
approving Write Offs, Losses and Fruitless Payments. Head of Service (HoS)
and Core Management Team (CMT) members are also able to authorise
these if they fall within their threshold. The Chief Executive (CE) has an
overall limit set of 5k, after which the approval will be subject to Department
for Education (DfE) approval.
Please refer to the Special payments/Write Off section on the intranet under
Finance Department/Finance Manual/Financial Control/Special Payments and
Write-offs to ensure all supporting documentation is attached to the Business
Case before submission for approval.
The Four levels of authority are as follows:
3 : 500 - 5k
4: 5k and above
Please note: The final approved Business Case must be sent to National
Office Finance for action.
Please complete this form electronically with reference to the 'Business Case
Guidance' to ensure all relevant information is provided in order to assess
and approve the proposal.
Section 1 General information
(d) Details : Proposer (Name & Job title)
(e) Service Area:
Centre:
Cost
(f) Cost () :
Date:
Section 2 Details
Please mark X in the relevant box and complete the relevant document:
2.1 Local Losses and Write offs
2.2 Fruitless Payments (Court Orders and Compensation)
2.3 Constructive Losses
2.4 Corporate Contingency Bids
Section 3 Value for Money
Please complete this section to help us consider the Value for Money
element.
(a) What is the alternative Option to what is being proposed and why is this
not being considered?
HIGH
MEDIUM
Approver 4 Only for Write Offs, Losses and Fruitless payments over
5k
Name
Position
(c) What benefit will be received if this Business Case is approved?
Section 4 Authorisation
Please sign and authorise electronically according to the 'Business Case
Guidance'.
Originato
r
Name
Approve
r1
Name
Position
Position
Date
Date
Approver
2
Name
Approve
r3
Name
Position
Position
Date
Date
Date
4.1 A decision to offer financial compensation may be made even if the complainant
does not request it, if compensation is assessed by the CST as appearing to be
necessary to put things right.
4.2 If, following a recommendation by the CST the Head of Service (HoS) believes
that compensation should be offered, the HoS forwards a business case to the
Chief Executive (CEO). If the CEO approves the payment, the CST makes the
offer of compensation to the complainant.
3.
3.1 Financial loss occurs when a complainant is for any reason out of pocket as a
result of Cafcass maladministration. The CST should always seek advice from
Cafcass Legal before recommending to a Head of Service that financial loss
compensation should be paid.
3.2 Cafcass aim is, wherever possible, to place a complainant in the position that
s/he would have been in if the maladministration had not occurred. So
compensation for actual, financial loss should be offered if the complainant is
financially worse off as a result of maladministration, and the payment is
necessary to reimburse the complainant for that loss.
4.
CONSOLATORY COMPENSATION
4.3 Where a complainant has not suffered financial loss but has suffered injustice as
a result of Cafcass maladministration, a consolatory payment may sometimes
(though not always) be appropriate. The CST may wish to seek advice from
Cafcass Legal in such situations, but is not required to do so. The guidance
below should be used.
4.4 A decision on whether to make a consolatory payment should have regard to
the impact that the maladministration had on the complainant;
the length of time Cafcass took to resolve the complaint; and
the time and trouble the complainant had to take, to get it resolved.
4.5 Consolatory payments will usually range between 25 and 300, although higher
payments may be appropriate, depending on the circumstances of the case.
4.6 The figures in the examples below are taken from recommendations by the
Ombudsman with other examples by way of contrast, and can be used as a
rough guideline when making a decision on how much should be offered.
Accruals accounting is a system whereby the goods and services are accounted for in the
period they are used, rather than the period the invoice is paid.
The term Accruals accounting, relates both to accruals and prepayments. Prepayments
are, in effect, negative accruals. Any reference to accruals in this paper includes
prepayments.
The accruals are the accounting entries (debits) to reflect goods and services which have
been used in the period to date, but for which no cash expenditure has been incurred.
Accruals add in missing expenditure.
Prepayments are the accounting entries (credits) to reflect goods and services that have
been paid for in the period, but the benefit will not be received until future periods.
Prepayments remove expenditure.
Ideally we should make adjustments for all areas of expenditure, however, the key is to
focus on areas of significant expenditure, i.e., those that if ignored would result in a
misleading view of actual expenditure.
The 80/20 rule (supported by yearend accruals data) tells us that a small number of
budget areas (20% say) will represent the majority (80% say) of the missing expenditure.
Our attention and effort should therefore be concentrated on the key areas where accruals
will have the largest impact on expenditure.
Flexible staffing i.e., SEC, bank staff, overtime and temporary staff
Accommodation costs i.e., rent, rates and service charge
T&S
Partnerships
The above covers the minimum Service Areas should be considering. Service Areas are
of course free (and encouraged) to expand the scope of the accruals exercise to include
further categories of expenditure, where they feel they can achieve this.
Unlike year-end, there is no de-minimis limit i.e. no lower limit on: the value of monthly
accruals although as above the focus should be on significant items.
If these items are accrued, the monthly reports will provide a more accurate view of the
service areas and organisational resource usage. This will lead to a position where both
the monthly reports and the year-end Accounts, provide a true and fair view of Cafcass
activity.
The accruals made in any month are cumulative accruals and should cover any goods
and services used in period one (April) to the current month, for which no payment has
been made.
Ideally we should be able to generate automated accruals from EBIS using information on
outstanding PO and GRNs and this process is used by a limited number of budget holders
where appropriate..
Given the issues above, a manual review needs to be undertaken informed by the system
information available and local knowledge.
The accruals will be loaded on to the system on a reversing journal. Full final (2 cut)
h
monthly reports will be issued around the 6 working day of the month. These are the
reports that will be used to report Cafcass position both internally and externally.
Monthly accruals and year end accruals follow the same principles. Year end accruals
form part of Cafcass's annual accounts and are the subject of external audit scrutiny. As
such all year end accruals must be fully supported by comprehensive supporting
documentation. Internal and external audit will be interested in monthly accruals, but they
do not require the same level of certainty and supporting documentation. Monthly accruals
require a clear rationale and supporting documentation however this is more likely to be
based on estimates, assumptions and workings, than actual invoices/claims.
nd
NO Finance
st
Written: 1 June 2006
Updated by: Julie Brown
Updated on: July 2012
You can work your way through the guidance or click on each section below
to be taken to it.
Contents:
1. Overview
2. Delegation of Cafcass Budget
3. The Budget Process/Financial Cycle
4. Budgetary Information
5. Budget Monitoring
6. Interpreting Budgetary Information
7. Financial Accountability
8. Conclusion
9. Further Information
Overview
Overall financial context in which Cafcass operates
As a Budget Holder you will be primarily concerned with your own budget.
However, it is useful to know the "big picture" when managing and monitoring
your budget.
http://cafcassintranet/Intranet/departments/finance/finance_manual
_new/financial_control_new.aspx
Budgetary responsibility of the Line/Office Manager (OM)
Generally HoS has overall budget responsibility for staffing costs, whilst OM
has budget responsibility for running costs. However, Service Managers
(SMs) and other line managers have responsibility for costs such as Bank,
Overtime, Sessional hours etc which they approve via I-Trent.
It is important that practitioners and Service Managers work closely with the
Office Manager to provide them with the relevant information so that they can
raise purchase orders and approve costs for which they are responsible for.
If budget holders (HoS and OM) are not aware of decisions SMs make which
have a financial impact then they cannot manage their budgets effectively.
The below terms explains more about OM responsibilities.
Purchase Orders (PO)
It is the Office Managers responsibility to ensure that purchase orders are
raised before the receipt of an invoice/before the cost is incurred, for all
running costs they hold budget responsibility for. If the PO is raised before
the order is placed then the PO number can be provided to the supplier which
will mean that the PO number will appear on the invoice once received.
Purchase orders are used to confirm approval; indicate types, quantities, and
agreed prices for products/services.
The Office Managers must arrange for purchase orders to be raised before
an expense is committed or soon after (but before the receipt of an invoice)
for all costs that they manage as this shows that they have control of their
budgets (by approving the costs before it is incurred) and this is also a finance
Financial Cycle
The financial cycle is a series of stages which link together. See each bullet
point below for the various stages in the financial cycle:
Budget Estimates -
The budget is based on estimating the future needs and level of service
required as well as incorporating issues identified and agreed from the
business plans, thus ensuring change is budgeted for. This does not
necessarily mean an injection of new money but could mean the
reassignment of existing resource or even a possibility of a reduction in
budget.
Estimate Assumptions
The estimate for the coming year, which is approved by CMT, will be based
on various assumptions. Some will be of a general financial nature requiring
input from the Finance Department eg: Inflation, salary increment
assumptions etc. Others will be of a more service specific nature requiring
input from Service Managers eg: Staff Numbers/workload/Demand. Thus, the
budget setting process should be considered a corporate exercise.
Budget Monitoring
Once the Budgets are set, these will be monitored against the expenditure on
a monthly basis.
The Accounting Officer obtains assurance that arrangements agreed when
setting the budget are working properly through the Expenditure Control
Group, the Budget Approval Panel, and Star Chamber sessions directly with
Budget Holders, as well as routine monitoring by managers and finance staff
working together.
Monitoring of Budgets is dealt with in more detail in the next section.
Final Accounts
The annual cycle ends with the reporting of the actual performance
(management accounts outturn) for the year, and the reporting, publication
and audit of the final accounts of Cafcass. The final Annual Report and
Accounts of Cafcass will be presented to Houses of Parliament via the DfE.
Staffing
o Have there been or are there likely to be any staffing changes? This
could include redundancies, retirements, maternity leave, sickness and
changes in hours, ongoing recruitment, vacancies etc.
o What is the productivity of existing staff?
o Are there going to be/or have been any redeployment costs? (due to
change in area structure) i.e. increase in Travel costs
Assets
What assets are you responsible for and is there any health and safety or
other unavoidable commitments which cannot be met from National budgets?
Changes
o Are there any legislative, demographic or social changes that could
impact on the caseload/budget?
o Are there any changes planned for the Service Area in terms of
restructuring/relocation and its impact?
o Are there any planned changes in the way we work as an
organisation? Will this have an impact? I.e. changes in approach to
work due to change in culture or technology.
1. Details of the approved established posts and the actual situation including
review of all posts including vacancies.
2. The salary grade and salary point for each post and details of increments due in
the year for example, Golden Hello or enhancements.
3. If the department/area is due to be restructured, approved restructuring plans
must be incorporated in the budget. Information required will include the date the
restructuring comes into effect, details of new and reviewed posts.
4. Details of pay awards.
5. Any additional known allowances i.e. Home working. It is not usual to include
overtime in the budget except in exceptional circumstances where there is
planned overtime for specific duties.
6. Details of long term sickness or maternity leave and details of temporary staff
providing cover if required.
7. Details of any flexible workforce budget, such as Bank, Sessional, Agency and
SEC.
Budget Monitoring
Purpose
Budgetary control in the broader sense is more than the scrutiny of historic
expenditure and income. It is a continuous management process reviewing:
The regular review of the budget against actual committed spend, is obviously
an integral part of this process.
Approach
The budgetary control process is a partnership between the
Area/Departments (who are responsible for controlling and monitoring service
budgets and the performance assumptions underpinning them) and Finance,
who provide technical assistance in compiling budgets, interpreting
information, providing financial performance data and assisting managers in
solving finance related business problems as they occur throughout the year.
The ultimate responsibility for managing and monitoring financial
performance is the Budget Holders.
Key Principles
Managers need to establish a budgetary framework which takes account of
the following principles:
I.
II.
systems and procedures that are in place to assist with the monitoring
process. It is the Directors/Heads of Service responsibility to ensure the
staff(s) tasked with budgetary control are adequately trained.
V.
Corporate Awareness
The action or inaction of one budget manager can impact on the performance
and service delivery of another area or Cafcass as a whole e.g. Budget
Managers should be aware of the Bank worker costs for their service area as
overspends in one service area may have to be met by reduced spending in
other services.
VIII.
Service Improvement
The forecast also helps finance teams and Directors to understand the
pressures within all service areas so that budgets can be prioritised
accordingly by them to ensure all areas remain at a safe level of funding
across the operational area.
The monthly results are also analysed by National Office so that they can
report to DfE.
have been made in their construction about the number of people employed,
their pay levels, the cost of their travel, the cost of other services
(interpretation etc) and the level of demand expected for our service. If these
assumptions are realised, then the actual expenditure position will reflect the
budget/estimate set at the start.
Key Questions for a Budget Manager
A Budget Manager must consider the following:
Estimated Figures:
1. Do I understand the assumptions behind the figures?
2. Have I identified my high risk areas? E.g. an office with high demand and which
cannot cut its costs easily.
3. Do I know what costs I can directly control and what are agreed annual charges?
E.g. Operating Lease charges.
Actual Figures
1. Do I understand what information I am looking at? When was the information last
updated?
2. Do I understand the pattern of expenditure throughout the year? Are contract
payments made at the start, the end, or each month? Are any payments missing
which appear to produce an under spend, or have any payments been made
early which appear to give an over spend?
3. Have any commitments been entered into which have used up the budget but
which are not reflected in the actual figures?
Technical Terms
When dealing with budgetary information you may come across technical
terms you are unfamiliar with, some of these are explained below:
Virements These are transfers of budget from one place to another within
financial limits. This can be an amount from or to a cost centre or natural
account code.
Journals This is a method used by finance staff to make adjustments to the
accounts once a cost has been realised. It is used to transfer the expenditure
from one place to another. This can be an amount from or to a cost centre or
natural account code.
Commitments These are future costs which have not yet been paid but for
which there is a commitment to pay at a later date or in other words they are
forecasted costs which are committed. This is more relevant for National
Office Departments.
Cost Centres (CC) These are numbers assigned to a team/local office e.g.
CC006 is the code for HQ Finance.
Natural Account Codes (NAC) - These are numbers assigned to an item of
expenditure e.g. 350100 is the code for Travel and Subsistence expenditure.
A comprehensive list of CC and NACs can be found on the intranet by
clicking here.
Reading monthly financial reports
Part 2 of this module (on MySkills) will help you gain an understanding of what
monthly reports look like and what they are telling us. The Screen cast will
take you through a report and show you how to manipulate the report and
what to look out for.
In the meantime if you would like to learn more about what the reports look
like and what to look out for then you can access the Monthly Returns Guide
for Budget Holders and Administrators here.
Information and Communication
Financial Accountability
Why follow procedures?
Here is a brief insight of why we need to ensure that financial procedures are
followed.
Integrity and Efficiency This is reinforced by internal and external audit
and inspection regimes. Included in these are Financial Regulations which are
part of the governance regime to ensure income and expenditure are properly
accounted for and controlled.
Financial Regulation - Financial regulation in the United Kingdom is divided
into three departments:
1. The Bank of England,
2. The Financial Services Authority, and
3. The Treasury.
These three departments regulate various facets of British financial life. The
Treasury regulates Local Government. As Cafcass is accountable to the
Secretary of State in the Department for Education (the Department) Cafcass
must also abide by these regulations.
area business plan. The Head of Service owns the risk register and has the
responsibility to identify, evaluate and manage operational risks. They are
ideally placed to pick up on those early warning indicators that could identify
where problems are developing and this is an important responsibility.
Staffing Conditions Ensuring that the correct staffing conditions in respect
of salary (banding/ scale), pensions, redundancy and compensations are
followed.
Capital Expenditure How to deal with Capital expenditure, in terms of
recording and dealing with disposal/acquisition of assets. This is for National
Office Finance use only.
Others Dealing with transfer of funds, write-offs, gifts and many more
issues. You can access the full Financial Memorandum on the Finance
intranet page.
Conclusion
Getting the best for our service users.....
Remember we can get the best for our service users by:
Efficient budget management - In other words using money efficiently. This
means focusing it on outcomes for service users.
Good financial information Producing good financial information means
good decisions will be made.
Finally.....
We work in a highly regulated and closely scrutinised environment. The
challenge is to have in place processes that automatically minimise risk and
allow us to focus on delivering the services our users require in a way that
derives the most value from the available resources.
All Budget Holders are accountable for the budgets they manage and Cafcass is
accountable to the DfE.
Further Information:
Contact Information:
If you have any questions or concerns, please do not hesitate to get in touch
with your finance team. They are at hand to help you with your finance
queries.
For general queries you can email the Area Finance inbox.
If you need to speak to a finance colleague then you can contact them on the
below contact numbers.
NO Finance contact details: Christiana Iwalesin 0844 353 3357
Area Finance Manager: Heather Jefferies 0844 353 1764
Estates, Accommodation and NIS Business Support Finance Officer:
Natalie Padfield
07854113118
Area Business Support Finance Officer's:
A1-A5:
Aisha Mahdi
Marie Barry
Back to top
To set up a new Natural Account Code / Cost Centre which is currently not
in use
To amend the details of an existing Natural Account Code / Cost Centre
How do I know if a Cost Centre already exists?
Action
Type N in the action box if you are creating a new code and A if you are
amending an existing one.
You need to give the new code a name. The name should not exceed 40
characters including spaces. Type the name in the spaces provided.
Short Name
You need to enter a relevant logical short name for example; a possible short
name for University of Glamorgan could be Uniglam. The short name must
not exceed 16 characters. If this section is left blank, Finance will enter a
short name using the first 16 letters of the filename.
Requested by
The person requesting the new account code/cost centre needs to sign and
date here.
All other sections will be completed by Finance. Please contact Finance HQ
on 0844 353 3350 should you have any queries.
MONTHLY RETURNS
A Guide for Budget Holders and Administrators
1.
2.
AIM .......................................................................................................... 81
SOME USEFUL ACCOUNTING CONCEPTS ......................................... 81
a. Cost Allocation ................................................................................... 81
b. Journals............................................................................................... 82
c. Accruals Basis .................................................................................... 82
3. MONTH-END TIMETABLE ...................................................................... 83
4. WHAT WE GIVE YOU 1st Cut ........................................................... 84
a. 1st Cut MPS (Example - Appendix 4) ................................................. 84
b. 1st Cut Transaction Report (Example Appendix 5) ....................... 85
c. Outstanding Purchase Order Report (Example Appendix 6) .......... 85
d. SEC Reports........................................................................................ 85
e. PO Compliance and Prompt Payment Reports ................................ 85
f. Payroll Reports ................................................................................... 86
5. WHAT TO LOOK FOR............................................................................. 86
a. Things that just look wrong ............................................................... 86
b. Significant overspends ...................................................................... 86
c. Significant underspends .................................................................... 86
d. General review of transaction listing ................................................ 87
6. JOURNALS ............................................................................................. 87
a. How to complete a journal ................................................................. 87
b. What to do when the journal has been completed .......................... 88
c. What happens after I have emailed the journal ................................ 88
7. ACCRUALS ............................................................................................. 88
a. How do I know when to raise an accrual? ........................................ 88
b. How do I complete the accruals sheet on the return?..................... 89
8. REACCRUALS ........................................................................................ 90
a. How do I know what needs to be reaccrued? .................................. 90
b. How do I complete the reaccruals return? ....................................... 90
9. PREPAYMENTS ...................................................................................... 91
a. How do I know when to raise a prepayment? .................................. 91
b. How do I complete the prepayment return? ..................................... 91
10.
SUBMITTING YOUR RETURN ............................................................ 92
11.
AFTER SUBMISSION .......................................................................... 92
12.
THE 2ND CUT........................................................................................ 92
a. What is the 2nd Cut? ........................................................................... 92
b. What should I do with the 2nd Cut? ................................................... 92
13.
THE MONTHLY MONITORING REVIEW ............................................ 93
a. Why do I need to prepare a monthly monitoring review? ............... 93
b. How do I prepare the monthly monitoring review? ......................... 93
c. What do I do with the review once it is completed? ........................ 94
14.
FURTHER GUIDANCE ........................................................................ 95
Appendices
1.
2.
3.
4.
st
Document Owner:
Last Updated:
Updated by:
Director of Finance
February 2011
Julie Brown
1. AIM
The aim of the monthly report cycle is:
o To have results that reflect the activity for that month.
o To report performance to senior managers, the Board and the DFE.
o To be able to accurately assess performance against budget.
o To be able to use the results to make informed decisions about future spending.
o To make sure costs are in the right place (through use of journals) and the right period
(through use of accruals and prepayments).
Cost Allocation
Finance uses a number of different ways of organising costs. These enable us to analyse
costs by department (i.e. cost centre) or analyse costs by type of expenditure across the
organization. The main ways costs are allocated are as follows
Cost Centres (CC) Each local office and national office department is a cost centre.
These are denoted by a 3-digit number followed by a hyphen (-). For example Durham is
062- and KLD is 015-. Local offices are currently grouped into 19 Service Areas. A full list
of cost centres has been included in Appendix 1 and can be found on the intranet under
Finance. A list is also included within the monthly return excel file under tab CC.
An example of how the costs of a train fare and sandwiches might be allocated is given
below:
Expense
Cost Centre
Budget Head/ Expenditure Type
NAC/ Expense Type
Train Fare
027- Partnerships
Travel and Subsistence
350100- T&S UK
Sandwiches
008- Customer Services
Supplies and Services
425000- Catering
To help ensure correct coding Finance has developed a list of common coding errors and this
is included as Appendix 3. The list is not exhaustive, however, it does cover the major
problem areas. A copy can also be found on the Intranet under Finance/Financial
Management/Month-End
So we place an order i.e. raise a PO it will be allocated to a cost centre and a NAC. When the
invoice is paid it will be charged to this CC/NAC On the basis of this information it will appear
within a cost centres monthly results included within the expenditure type related to that NAC.
b.
Journals
It is possible that expenses may get coded to the incorrect cost centre or expense code and it
is part of the month-end returns process to check whether this has happened.
Journals may also be required where you do not have eBis access to another cost centre but
need to split out an invoice between various cost centres. E.g. HR may pay a hotel bill that
includes charges for 5 staff members (each from a different Regional cost centre). HR can
raise the PO and pay the invoice in full, then afterwards complete a journal to split out the
invoice between the various staff members cost centres and allocate costs to local budgets
c.
Accruals Basis
The CAFCASS monthly accounts are prepared on an accruals basis. This means that they
should reflect all the costs that relate to the current month not simply the costs for which
invoices have been received or been paid. The idea is that the accounts and expenditure
should match the activity in the period.
Accruals relate to when we have had the benefit of a good or service but we have not yet
been charged for the good or service.
It may be useful to consider the expense life cycle as shown below. We start accruing when
the good or service is received and stop accruing when the invoice is entered on the
accounting system, which is when it will appear on the monthly transaction listing.
1
2
3
4
5
6
PO Raised
Good received/Service delivered
Invoice received
PO GRNd on eBis
Invoice sent to Cafcass Finance
Cafcass Finance enter invoice on Open
Accounts (OA) and pay it. It will then appear on
the monthly transaction listing (see 4b below).
Accrue
Accrue
Accrue
Accrue
Example In April 10 we raise a PO for an external company to provide training in May 107
at cost of 10k. They send the invoice in and it is entered onto the system and paid in June
10.
We should accrue for the cost of the service in May, as this is the month the organisation
gains the benefit and the invoice has not yet reached the accounts. Once the invoice is
entered on the system and paid in June and it appears on the transaction report there is no
need to accrue further.
Therefore we raise accruals to in effect put missing costs into the accounts in the month.
At CAFCASS the term Reaccruals is used to refer to accruals that were outstanding at the
last year-end. Conceptually these are no different to other accruals, but they are identified
separately to give them increased visibility so they can be easily monitored to check they are
being released and test the accuracy of the year-end accruals.
Prepayments relate to when the invoice has been entered on the system and paid but we
have not yet had the whole benefit of the good or service.
Therefore prepayments would be raised at the following points in the expense life cycle. We
start prepaying when the invoice is entered and appears on the monthly transaction listing
and stop when the good/service is received.
1
2
3
4
5
PO Raised
Invoice received
PO GRNd on eBis
Invoice sent to Cafcass Finance
Cafcass Finance enter invoice on Open
Accounts (OA) and pay it. This will then appear
on the monthly transaction listing
Good received/Service delivered
Prepay
Therefore we raise prepayments to take costs out of the accounts in the month for goods
and services which have been paid for but we have not had the benefit of.
Accruals and prepayments are always reversed at the start of each new month so we should
always consider the cumulative accruals and prepayment adjustment required.
3. MONTH-END TIMETABLE
Task
Responsibility
(Finance or Cost
Centres
Finance
1WD
Finance
Finance
Finance
Cost Centres
Finance
2WD
2WD
5WD
5WD
5WD
Finance
Finance
Finance
Finance
6WD
7WD (PM)
8WD (PM)
8WD (PM)
Cost Centres
18WD
st
The 1 Cut is in effect the 1 draft of the results for the month. For the month under review
they will include any expenses that have been invoiced and put on the accounting system in
st
the month. All in year accruals will have been reversed, so in effect the 1 Cut shows cash
spend less year-end accruals.
st
These reports will be saved in your finance folder during the 1 working day of the month.
a.
An MPS report is a budget statement that shows actual spend in the month and year to date
against a list of expense codes and then compares these to the spend budgeted. Other
terms that are sometimes used to describe this kind of statement are Income and
Expenditure Statement or Profit and Loss Account.
st
The expenditure types are listed in the first column. If the +sign is clicked the expenditure
types are ungrouped and you will be able to see the NACs expenditure against each expense
code.
b.
The transaction report is produced directly from the accounting system and shows all the
individual transactions for each cost centre these may be invoices, credit notes, journals,
accruals or prepayments,
The Transaction report has three sheets:
Cost Centre_Current_Trans list of expenditure posted to the accounts in the
current month.
Cost Centre_YTD_ Trans list of expenditure posted to the accounts in the
financial year so far.
Pivot a summary of expenditure in the financial year so far, analysed by month, by
budget category (i.e. expenditure type) and by name (i.e. NAC/expense code).
If you double click on any number within the pivot table it will explode out a new sheet giving
you details of the individual transactions that make up that expenditure. Please note that all
values include VAT.
In the transaction lists the key columns to look at are
E - Name (i.e. expense code)
I - Description
J - Value
c.
This report is emailed out on the first working day after month-end (WD1). There are two
spreadsheets
POs No GRNs lists details of purchase orders for which a goods received note
has not yet been processed on eBis. See Appendix 6a.
GRN No invoice lists details of purchase orders for which a goods received note
(GRN) has been processed but for which an invoice has not yet been received. See
Appendix 6b
The examples in the appendix go through what each column in the reports refers to. Where
these reports cover more than one department or cost centre you can easily filter for those
that relate to your department cost centre by clicking on the downward arrow in column B and
selecting your cost centre number.
These reports are useful to help in deciding what needs to be accrued and this will be
discussed in more detail in the accruals section.
Detailed guidance on understanding and using this report can be found on the Finance
manual on the Intranet Understanding and Using the Outstanding Purchase Order Report.
d.
SEC Reports
This report is issued via email on the 2nd working day of the month by NO Finance. The
purpose of this report is to give regions detail of their spend on Self-employed Contractors
(SECs). Detailed guidance on understanding and using this report can be found in the
Finance manual on the Intranet Understanding the SEC Expenditure Report.
e.
This report is issued via email on the 5 working day of the month by NO Finance. The
purpose of the report is to give service areas and National Office departments information on
their compliance with Cafcass compliance targets for raising POs in advance of invoices and
paying invoices within 30 days of receipt.
f.
Payroll Reports
This report is saved in the Finance Folders of regions and National Office departments on the
th
5 working day of the month by NO Finance. The report provides details on all payments to
employee through the payroll system in the month. This includes both the main and
supplementary payroll includes these payments a breakdown of the cost to Cafcass by
splitting the salary paid into its constituent parts.
a.
b.
Significant overspends
c.
Mispostings?
o Check transaction report for detail of expenditure type
o Are expenses in right category?
o If something has been misposted a journal will need to be raised.
Need to prepay?
o Check transaction report
o Do expenses relate to future periods?
o If so include in prepayments
Overspend correct, why?
o Compare whats happened in month to what was expected in budget
o E.g. Timing difference cost is budgeted in a future month
o E.g. Unforeseen circumstances explain
o E.g. Use of temps rather than full time staff
o Include reason in commentary
Significant underspends
Mispostings?
o Check transaction report for detail of expenditure type.
o Have costs been included in another expenditure category.
d.
a.
An example of a journal can be found in Appendix 7a. This has been annotated with notes to
aid completion.
Only enter information in the cells that have been highlighted red in the example in
the Appendix
Enter cost centre codes in the format xxxEnter expense codes in the format xxxxxxEnter line descriptions that give a meaningful description of the journal. These will
appear on the transaction report so it is useful to put in as much information as you
will need to understand why the journal was raised.
Only the first 40 characters will appear on the transaction list.
Amounts in the debit column will increase expenditure in the cost centre and expense
code.
Amounts in the credit column will decrease expenditure in the cost centre and
expense code.
The journal must balance the sum of all the items in the debit column must equal
the some of all the amounts in the credit column.
Dont leave any blank lines between entries
b.
1. Double check that the journal is formatted correctly. The journal voucher is an
electronic form which is imported into Open Accounts. If the journal is not formatted
correctly, the form will not load into Open Accounts.
2. Common formatting errors include missing dashes (-) after CC and NAC codes, blank
lines between entries, debit and credit columns not balancing, missing Journal
Description, more than one worksheet per journal.
3. If the journal is moving costs to another cost centre authorization in the form of email
confirmation of acceptance by the relevant budget holders must be included with the
journal.
4. All journals should be accompanied by back-up where possible. For example when
correcting mispostings you should attach a spreadsheet showing the relevant lines in
the transaction report. This is necessary for the audit trail and will also help NO finance
provide a double check of the transactions.
5. Journals should be emailed to CAFCASS NO Finance by the budget administrator or
budget holder; except for GPC journals, which should be sent to the GPC Administrator
(Cafcass Finance). Only Journals from Area Finance Manager/Finance BSOs will be
accepted, any journals prepared by any other individual should be sent via the budget
administrator or holder.
c.
You will receive an email confirmation from Finance that the journal has been posted. If
there are any queries, the journal will be sent back along with the queries that require
rectification before the journal can be posted.
Finance will review the journal for any major errors; however, it is ultimately the Service
Areas responsibility to ensure all entries are correct.
When you receive the second draft of the monthly results, you will be able to see that the
journal has been posted, as it will appear on the Transaction Report.
7. ACCRUALS
a.
As discussed in accrual theory in section 2c accruals need to be raised when you have
had the benefit of the expenditure but an invoice has not yet been processed for the cost.
There are a number of ways that you may become aware that you need to accrue for
something. You do not need to accrue for every single cost to the penny that you havent
yet been expensed for the idea is just to get a reasonable reflection of your expenditure
in the month.
The steps to go through when thinking about what accruals need to be raised are.
1. Focus on large cost items. For Service Areas these are likely to be
Flexible staffing i.e., SEC, bank staff, overtime and temporary staff
Accommodation costs i.e., rent, rates and service charge
Travel and Subsistence
Partnerships
For National Office the large cost items will be more varied but the following are likely to
impact on a number of the departments and should be considered:
Temporary Staff Costs
Travel and Subsistence
External consultancy
5. Look at the accruals that were raised last month and consider whether they are still
required in the current month. They will no longer be required if
a. The invoice for the cost is in the transaction report.
b. The order for the good or service has been cancelled (in this case the accrual
should really not have been raised in the first place).
c. For whatever reason it is not expected that the cost will be invoiced.
It may also be possible that you now have a better idea of the expected cost and therefore
might need to adjust the amount accrued in the previous month up or down.
b.
An example of an accruals return is included in Appendix 8a. This has been annotated to
explain what should be included in each column and how to present the accruals.
You need to include the cumulative amount to be accrued not just the costs that
havent been invoiced for the current month but also for previous months where
invoices have not yet been processed.
It is useful to leave the accruals history (the entries in the previous months in the year)
in the spreadsheet. This will give a record of how the accrual has moved over time and
show clearly when accruals were raised and released.
It is useful to use a different line for each month of an expense that needs to be
accrued as this will make it easier to see which accruals are no longer required. For
example each month of a temps costs that have not yet been invoiced to show on a
separate line.
It is useful to add the related PO number to this sheet. You can then check these
numbers against the transaction report each month to check whether the invoice has
been received.
8. REACCRUALS
a.
Reaccruals are accruals that were outstanding at year-end and have not yet been released.
Each month they are reaccrued unless they are marked as paid. You should not add any
new reaccruals to the list but you may need to release (i.e. remove) some that are there
already. Reasons to remove a reaccrual would be:
a. The invoice that relates to the cost has appeared in the transaction listing for the
month.
b. An invoice is no longer anticipated to be received for the cost.
If there are still reaccruals after Q1 (June), a full check should be undertaken to ensure that
the invoice has not been received and missed. A full check should then be done every
quarter end. This can be done by looking at the full cumulative transaction listing for invoices
that have gone against your cost centre. If there are other invoices that you would have
expected to have received by this point talk to someone in finance to help you check on the
accounting system as perhaps the invoice has been charged against another cost centre.
b.
An example of a reaccruals return is included in Appendix 8b. The return lists all the
accruals that were in place at the year-end.
Select the month of the return from the drop-down box in the top left hand corner.
If a reaccrual is no longer required type paid in column G and then that accrual will no
longer be reaccrued each month.
9. PREPAYMENTS
a.
the costs for one month seem a lot higher than budgeted as it may be that the cost
relates to more than one month, for example rent, quarterly utility charges,
maintenance charges
you are aware that you have purchased something in advance of its use for
example external training costs, external room bookings, marketing campaigns or
conference space
you notice on the transaction listing that the narrative relates to a future time period.
These costs need to be prepaid so that the costs are deferred until the benefit of the cost
is taken in the business.
b.
An example of a prepayment return is included in Appendix 8c. This has been annotated to
explain what should be included in each column and how to present the prepayments.
You need to include the cumulative amount to be prepaid not just the costs that
have been invoiced in advance in the current month but also for previous months
where the company has not yet received the benefit.
It is useful to leave the prepayment history (the entries in the previous months in the
year) in the spreadsheet. This will give a record of how the prepayment has moved
over time and show clearly when prepayments were raised and released. It should
help each month in deciding how much of a prepayment may need to be released.
It is useful to use a different line for each month of an expense that needs to be
prepaid as this will make it easier to see which prepayments are no longer required.
10.
The return should be saved in your finance folder by the end of working day 5 after the
month-end.
Please do not change the name of the file or change the formatting of any of the sheets within
the returns as they are all linked up to centrally kept spreadsheets.
11.
AFTER SUBMISSION
Finance creates journals to post the returns into the accounting system. When the journals
nd
have been processed a second version of the monthly results is run the 2 cut.
nd
Finance will undertake a brief review of the 2 Cut and the NO returns and they may contact
you at this time to clarify any queries. As review time is limited between receipt of the returns
nd
(WD5), their processing (WD6) and the issue of 2 Cut (WD8), finance only have time to
undertake a brief review. They may undertake a more detailed review of some cost centres
after WD8 and if any changes arise these will need to be processed in the following month.
12.
a.
nd
b.
You should review the MPS report and check that the numbers look reasonable and meet
your expectations of what they should be following the posting of the return and journals.
One quick way to check that the postings have been put through correctly is to take your
st
spend figure from 1 cut, add on all your accruals and reaccruals, deduct your
prepayments, add/deduct any costs that have been journalled in/out of your cost centre
nd
and this should give you the total spend in 2 cut.
st
25,000
5,000
12,500
(3,000)
1,000
(1,500)
39,000
If you think anything has been posted incorrectly or have any queries on your
numbers please contact NO finance to discuss.
nd
It helps ensure that both budget holders and administrators are aware of their
expenditure and if necessary can take action regarding over/underspends
It gives NO finance early visibility of any significant variances to forecast.
It can assist budget holders and administrators with budgets and forecasts by
ensuring familiarity with variances to budget and the reasons for these
b.
Section 3 Overview
This section asks you to complete some details regarding your expected full year position.
Latest Forecast you can take this figure from your latest quarterly forecast (Q1, Q2 or
Q3). Please note this is NOT the same figure as the Forecast Expenditure column in the
MPS report.
Budget This can be taken from the MPS report the total of column M.
Var & % - You need to calculate the difference between the budget and the forecast
put a forecast overspend in brackets.
Outturn As explained on the form, the outturn is a calculation of what the full year spend
would be if spend in the month was the same as the current month for all future months.
To calculate this you would take the total from column G of your MPS and then add to this
the total of column B multiplied by the number of remaining months in the financial year.
For example if in August the monthly spend was 24k and the year to date spend was
140k, then the outturn would be calculated as follows:
140,000+(24,000*7 remaining months) = 308,000
i) You are then asked to give reasons if there is a significant (+/-50k, 10%) variance
between the outturn and the latest forecast. Reasons for such a variance might be:
Profiling e.g.s.
- Your departments spend is not even throughout the year therefore this
months spend is not representative of the monthly spend for the remainder of the
year.
- There is a one-off cost this month or in a future months which means this
months spend is not representative. Please identify the relevant cost.
Over/understated forecast
c.
14.
FURTHER GUIDANCE
If you require further guidance or have any specific queries please contact National Office
Finance on 020 7510 7000 or at NOFinance@cafcass.gov.uk.
There are also lots of useful documents on the Finance Section of the Intranet.
Also if you have any suggestions for improving this guidance please let us know!
Summary
1.1
1.2
1.3
Other electronic forms are also available for opening and closing a
petty cash account, increases and decreases in a petty cash account,
and closing a petty cash account.
2. Principles
2.1
Petty Cash is a small fund retained in the local office for day-today expenditure on small miscellaneous purchases or incidental
office expenses, where payment by any other means is not
economical or practical. Examples of items usually purchased
with petty cash are minor office supplies and cleaning products.
2.2
2.3
2.4
2.5
Petty cash records should only be amended by: drawing a single line
through the original entry, initialling the deletion and entering the
amendment either above or below it. Erasers or correction fluid should
never be used.
2.6
The cash box should be checked against the balance shown in the
cash book at the end of each month and spot checks should be
carried by the Area Finance Manager. The box on the PC2 form
indicating that the cash box has indeed been counted should be ticked
before sending the form to the Area Finance Manager for review. Any
discrepancies found should be investigated and reported immediately
to the Accounts Department. Under no circumstances should you
attempt to top up any differences/discrepancies to make the physical
cash balance agree to the authorised float from your personal funds.
2.7
2.8
3.
3.1
3.2
Completing these Petty Cash forms are detailed in the Petty Cash
Explanatory notes.
3.3
Late Returns
Any late petty cash returns will be chased in the first instance by the
Finance Bureau to the Area Finance Team, whom in turn will chase the
Office manager.
Any return that is outstanding for more than 2 months will be escalated
by the Finance Manager / Financial accountant to Head of Service or
CMT Director.
Owner:
Issued date:
Revise date:
Finance Department
July 2012
November 2012
July 2013
Julie Brown
Procedure Deadline/Frequency:
Last Updated:
Updated by:
When Required
September 2013
Heather Jeffries
Introduction
On occasion you will need to raise an Invoice to an individual, or an
organisation, as they owe Cafcass an amount of money. To raise an invoice
you need to complete an AR1 form.
Process
The AR1 form can be found on the Intranet under the following links:
Forms > Finance Forms > AR1 Form.
Once from the intranet, save the file in Excel
Close the Intranet and open the Excel AR1 form.
In Section A enter the details to whom the invoice is to be made out
to and their address.
In Section B enter any special instructions you may have. This could
include a purchase order number or where to send the invoice to if a
different address. Invoices may be rejected by organisations if a
purchase order number is not quoted.
In Section C select whether the invoice is to be a one off or if it is to
be a recurrent invoice. If it is to be recurrent, you will need to enter the
date of the 1st and last invoices.
In Section D enter the Cost Centre and Natural Account Code of
where the invoice is to be coded to and the value of the invoice. If you
are unsure of the VAT treatment please refer to the relevant section in
the finance manual or contact a member of the NO finance team or
CAFCASS FINANCE for advice
In Section E enter the value that is to be shown on the invoice and
the description that is to appear on the invoice. This needs to describe
the reason for the invoice and where necessary give quantities and
dates etc.
In Section F, the authoriser must date the form and add the address
details and contact details as required. The authoriser must be a
signatory for the cost centre on the AR1
Once completed, email the AR1 form and all backing documents to
CAFCASS Finance with the following statement I authorise the
attached AR1 form and conform that Cafcass is entitled to this income.
Please raise an invoice.
Julie Brown
When Required
September 2013
Heather Jeffries
Introduction
On occasion you may receive a cheque from a supplier or member of staff. In
the case of suppliers, these will normally be to reimburse CAFCASS for an
invoice paid in error. Where we received a cheque from a supplier, we should
expect to have the invoice/statement that it relates to attached to the
cheque.In the case of staff, these will normally be received to reimburse
expense on GPC cards or for agency staff to reimburse personal phone calls
made on Cafcass mobiles etc. In the case of service users these will
normally be received for Subject Access Requests.
NB Insurance excess cheques must be passed to the Finance car lease
contact in the first instance.
Process
1. Aims of Policy
The Debtors Policy refers to all debts owed to Cafcass. Cafcass will
actively recover debts by making early contact with individuals,
suppliers and organisations.
2. Definition of a Debtor
A debtor is someone or an organisation that owes Cafcass money.
How to request an invoice to be raised?
Once a debt has been identified, an invoice must be raised as soon as
possible via an AR1 form. The AR1 must be fully completed,
authorised by the budget manager and sent to the Accounts
Processing Team for processing.
Payment terms
The invoice date and due date are the same, as all invoices are
payable immediately upon receipt. Payment should be received within
30 days from the date of the invoice.
3. Debt Recovery Procedure
Outstanding debts will result in prompt and decisive measures being
taken.
Should no payment be received within 35 days, the following actions
must be taken by the Accounts Processing Team:
35 to 40 days
First letter of demand
40 to 50 days
Second letter of demand
50 to 60 days
Final letter of demand
61 to 70 days
Accounts Processing Team to refer debt
back to Budget Manager for advice, with the view of chasing
directly or pursue via legal action.
71+ days
Matter referred to the Area Finance
Manager to make a recommendation to pursue via legal action
or write-off.
4. Legal Action
Where efforts to recover the debts have been unsuccessful, the Area
Finance Manager may decide to pursue the recovery through legal
actions. The Director of Finance will make the ultimate decision upon
recommendation from the Area Finance Manager to pursue recovery
via legal action.
Where the debts are referred for legal actions, the Accounts
Processing Team are required to forward all documentations (invoice,
purchase order, letter of demands and phone conversation notes) to
the Area Finance Manager.
Any legal and associated costs incurred for debts recovery will be
passed on to the appropriate customer. However, where the recovery
is unsuccessful, the costs will be transferred to the budget manager.
5. Write-offs
Debts should only be written-off after following decisions that it is
fruitless to pursue the debt any further. All applications to write-off the
debts should be done using the special payment and write-off business
case which can be found in the Finance Manual on the intranet then
forwarded to the Director of Finance via the Financial Accountant.
The write-off amounts will be charged to the relevant cost centre.
6. Debt Monitoring
At the beginning of each month, a list of current debt outstanding will
be placed in the shared drive for Areas and National Office by the
Accounts Processing Team.
NO Finance
Issued: November 2012
Review due:
November 2013
Owner
Finance
Issued
December 2008
Approved by
Julie Brown
Version No
3.0
July 2013
Ref
2012 CAFCASS
Contents
Page No.
1.0
Introduction
2.0
Booking Process
3.0
4.0
Conditions of Use
5.0
1.
Introduction
This document details the arrangements for booking hotels and meeting rooms. The
contract procedure in place will save CAFCASS significant time, effort and resource by
placing all of its requirements through a specialist service provider at pre-agreed
preferential rates.
The contract with Redfern is secured as part of the OGC framework and as such provides
a significant saving for Cafcass. To ensure we realise the full cost and efficiency savings
that working with Redfern can provide, all your hotel and meeting room requirements are
to be placed with Redfern.
1. ALL hotels bookings must be booked through Redfern. Any hotels booked on GPC
cards or through invoicing, evidence must be provided that Redfern were unable to
provide a hotel for you on the day that you requested.
2.
Booking Process
2.1
Bookings
can
be
made
via
https://www.trips.uk.com/js/SABS/Corporate.html
2.2
2.3
Any hotel booking above the Cafcass budget policy, as noted below, must be
approved by the line manager prior to booking. The line manager approval must be
obtained before booking if above the budget limit. The agreed budget limits are:
London
All other areas
the
Redfern
website
130
90
2.4
2.5
Cancellations must be made in accordance with the individual hotel policies. You
must contact Redfern if you are unsure of the cancellation policy.
2.6
Where possible please book hotels using the Crown Programme. These are indicated
with a small gold star to indicate participating hotels in the main display and the
specific rate in the rates display
2.7
Please be aware that hotels booked outside the Crown Programme, may not include
VAT (in London) and breakfast. Please make sure you read the Hotels policy.
2.8
3.
3.1
Redfern will provide one consolidated invoice for the whole of Cafcass. It is the
responsibility of the Accounts Payable to process and pay the invoice.
3.2
Any queries in relation to the charges should be raised by the Cost centre directly with
Redfern via accounts_mail@redfern-travel.com, copying in, the Redfern contract
manager.
4.
Conditions of Use
4.1
Hotel accommodation cannot be used for personal travel. Hotels will only be provided
when staff is travelling on Cafcass business and this requires an overnight stay as part
of the business.
4.2
4.3
Staff who continues to use GPC for hotel accommodation without first contacting
Redfern, will have their GPC access reviewed.
4.4
If Redfern are unable to provide a hotel within the agreed budget limit, line manager
authority must be obtained and provided to Redfern.
4.5
Any expenditure that is incurred during the hotel stay is to be settled at the time of
departure from the hotel and claimed as expenses where appropriate. This includes
breakfast if this wasnt included within the original rate booked
5.
5.1
Should you have any complaint or should you experience any difficulty with the hotel
in question and you are unable to resolve this during your stay - DO NOT CONTINUE
TO DEAL WITH THE HOTEL DIRECTLY, but contact Redfern immediately who are
available 24 hours a day.
5.2
It is the responsibility of the Area Finance Team and National Office Departments to
handle disputes on their cost centre charges and follow up with Redfern directly.
August 2012
Document Owner:
Last Updated:
Updated by:
Director of Finance
July 2012
Julie Brown
2. VAT Status
As Cafcass is a Non Departmental Public Body it is unable to reclaim any VAT it is charged
by suppliers (unlike Local Authorities and Government Departments). However Cafcass does
have to charge VAT when it raises invoices for taxable supplies.
eBis
Tax
Code
E
Description
Rate
Comments
Exempt
0%
Reduced
Rate
5%
Not VAT
Registered
0%
Standard
Rate
20%
Travel &
Subsistence
0%
Zero rated
0%
Some types of expenditure are exempt from VAT. This includes certain
types of education and training and some property transactions (selling,
leasing and letting land and buildings). Please also see note on SECs
below.
(Shown as Electricity & Gas on eBis)
Some categories of expenditure are subject to a reduced rate of VAT at
5%. Examples are domestic fuel or power, installation of energy saving
materials, children car seat.
Not all businesses are required to be VAT registered. Businesses with an
annual turnover exceeding the current VAT threshold (70,000) must be
VAT registered and show a VAT registration number on their invoice.
Some self employed individuals such as SECs may not be required to be
VAT registered because their turnover is below the VAT threshold. This
code should be used when there is no VAT number shown on invoice.
This is the standard rate of VAT applicable on the majority of VAT
registered businesses. The standard rate of VAT will apply in respect of a
good or service received from a VAT registered business, which does not
fall in any other category. (Examples: Agency Staff, advertisements). A
VAT registration number must be shown on the suppliers invoice.
This code should only be used when there is no VAT shown on the invoice
in respect of T&S. Some examples are when a payment is being made
through eBis for interview candidate travel expenses or clients T&S.
Some types of expenditure are zero-rated, some examples are childrens
clothing and footwear, most food and drink (but not catering or takeaway).
5. Further Information
HMRC Website -
http://www.hmrc.gov.uk/
VAT Helpline -
Owner
Chris Iwalesin
Financial Accountant
Issued
June 2012
Approved by
Julie Brown
Director of Finance
Version No
6.3
Sep 2014
Ref
Sep 13
2007 CAFCASS
Contents
Page No.
1.0
Introduction
2.0
Overview of Process
6.0
Obtaining a GPC
7.0
8.0
9.0
10
10
11
Appendix
Page No.
1.0
12
2.0
13
3.0
Key Dates
14
4.0
15
5.0
16
6.0
17
7.0
18
8.0
19
9.0
20
6.
Introduction
2
6.1
6.2
6.3
The GPC allows for greater flexibility in areas of expenditure where a Purchase
Order or indeed the use of Petty Cash for certain low value transactions is not
appropriate. However the GPC must not be used to circumvent existing
procurement rules.
6.4
For Cafcass the GPC will aide in alleviating costs and administration relating to
supplier set-ups, raising of purchase orders, GRN of purchase orders, multiple
BACS payments etc. Further benefits of GPC programmes are outlined by the
Office of Government Commerce (OGC) in the link below:
http://www.ogc.gov.uk/tools_services_government_procurement_card.asp
7.
Overview of Process
7.1
Just like an ordinary credit card, National Westminster (our card issuer) debits
each card transaction against the cardholders individual account. The
transactions are then aggregated on to a single statement. On the 28 th of each
month National Westminster will send out memo statements directly to all
cardholders. An electronic consolidated statement/invoice will also be sent to the
GPC Administrator. They will make arrangements for the National Westminster
invoice to be paid. The GPC Coordinator will oversee this process by
coordinating and managing this scheme.
7.2
The GPC Administrator will send the Area Finance Manager and National Office
Line Managers a monthly log of cardholder expenditure for all cardholders under
their remit. This will act as an aide for checking cardholders submissions and
reviewing expenditure.
7.3
7.4
7.5
The Line Manager must forward the electronic version of the GPC002 to the
Area Finance mailbox in the Operational areas and to the GPC Administrator
3
for National Office with authorisation message by 15th working day of the month
contained within an auto signature:
I am the approving manager for this cost and have thoroughly checked this form
GPC002 and can confirm I am satisfied that the entries made are correct and
reflect appropriate goods and services received. Please process for payment.
Name of approving line manager
7.6
For the Operational area the Area Finance team checks the E-GPC002
particularly about details of transaction and coding of the expenses to make sure
everything is correct. E-GPC002 and email authorisation is saved in relevant
folder in G drive.
7.7
7.8
The Area Finance Manager (AFM) conducts final checks and authorises the
GPC003 and submits to the GPC Administrator at the end of the month, in PDF
format. The AFM should submit an electronic copy using the authorisation
statement:
I am the AFM for the Operational Area and confirm that Area Finance have
thoroughly checked GPC returns and can confirm I am satisfied that the entries
made are correct and reflect appropriate goods and services received. Please
process for payment.
8.
Obtaining a GPC
8.1
The major consideration when deciding who will be given a card is effectiveness
in local purchasing. Cards will only be issued to staff with a continuing need to
purchase goods and services. They will not be issued to staff that may have
occasional use for such a facility.
8.2
8.3
The Line Manager must complete and authorise a Request for New GPC form
(GPC004) electronically, this must then be sent electronically to the CMT
member for authorisation before being forwarded to the GPC Coordinator.
8.4
8.5
The proposed cardholder will receive the pin details a few weeks ahead of
receiving the card.
8.6
On receipt of the new card, the cardholder must sign it straight away. The
cardholder should complete a form (GPC001) acknowledging they have read
and agree to abide by the cards conditions of use - they will also receive training
4
when the card is issued to them. The GPC001 form should be emailed to the
Area Finance Manager who will then forward this electronically to the GPC
Coordinator. A copy of this form should also be retained on the employee
personnel file. The cardholder should record the contact telephone number for
Nat West in the event of the card being lost or stolen.
9.
9.1
9.2
When completing the transaction log (GPC002) you must record each
transaction on the National Westminster statement of account on a separate
line. All details must be completed, including the expense coding under the
heading Natural Account Code. The transaction log must be completed
electronically. The total amount of expenditure on the transaction log must
always match the National Westminster statement.
9.3
9.4
9.5
Original receipts should be kept by the cardholder for 7 years. The receipts
should be numbered as per the return and kept in an envelope with the
cardholder name and month of the statement written on it.
10.
10.1
The cardholder must not use the GPC for personal expenditure. However if an
exceptional circumstance does arise and it is not possible to meet the cost any
other way, a cheque for that sum should be made out in favour of Children and
Family Court Advisory Support Service. The cheque and completed MR1 form
should be supported with a calculation, and an explanation as to what it relates
to, and enclosed with the claim. The overall total of your Transaction Log
(GPC002), prior to any adjustments for personal expenses, MUST equal what
the National Westminster Cardholder Statement.
10.2
10.3
Ensure that the GPC is used only if it is impractical to use other existing
methods of payment, and/or it is more cost effective to do so.
10.4
10.5
Ensure that the prices paid for goods and services are fair and reasonable.
10.6
Ensure that all goods and services are received. It is the cardholders
responsibility to verify that the goods received are indeed what were ordered.
5
10.7
10.8
Take all reasonable steps to secure and safeguard the GPC as you would your
own personal credit card. Ensure that the card is kept in a secure location at all
times.
10.9
Ensure that no one else uses the card bearing your name and that you never
disclose your pin to another person.
10.10 Hand in their cards for destruction by their Line Manager if they cease to be an
employee of Cafcass, or have been transferred to another division where the
use of a GPC is no longer required. The Line Manager will then ensure that the
GPC Coordinator is notified and the cards will then be cancelled with immediate
effect.
10.11 Ensure purchases are not split into multiple purchases when the total purchase
price would exceed the credit limit.
10.12 Cardholders must not authorise their own statements or have a subordinate
counter-sign them.
10.13 Receipts/supporting documentation must be kept by the cardholder. If receipts
are missing, the cardholder is required to provide an electronic signed memo
(Appendix 9) to their Line Manager within their monthly return, acknowledging
the expense(s) incurred. This memo must be printed and kept with the relevant
months receipts.
10.14 Cardholders must be able to produce receipts on demand for audit purposes.
10.15 Under no circumstances can the GPC be used for the following:
10.16 Authorised expenditure, subject to the limits defined in the Travel & Subsistence
rules, and the conditions set out in this policy, include the following:
Office equipment
Membership fees
Conference costs
Catering for meetings when required for external purposes
Redfern must be used for all trains, flights, hotels and accommodation bookings.
The GPC can only be used for train travel in exceptional circumstances and the
reasons for this should be properly documented on the returns.
11.
11.1
Training must be provided to the cardholder before the GPC is handed over.
Area Finance Manager and National Office Line Managers have been trained to
provide this. For further information please contact the GPC Coordinator.
11.2
Line Managers are responsible for ensuring all expenditure incurred is correctly
coded, narrative completed and expenditure is legitimate Cafcass expenditure,
and is incurred within the cardholders authority. The Line Manager should
speak directly with the cardholder if there are any queries with the return.
11.3
Verify that the cardholder has complied with all procedures as outlined in this
document.
Verify that the cardholders statement of account and transaction log is
reconciled.
Ensure the Natural Account and Cost Centre Code details on the transaction log
are correct.
All other details on the log have been correctly completed and authorised.
Ensure that transaction descriptions provide enough detail to ensure an audit
trail.
Ensure that for any personal expenditure a copy of the cheque and completed
MR1 form have been sent to the Finance Bureau.
11.4
Line Managers must also compare monthly logs against conventional travel and
subsistence claims, to ensure there is no double claiming/payment is occurring.
11.5
For National Office, Line Managers must check the GPC002 returns received
from the cardholders; authorise these electronically with the appropriate
statement as per section 2.5 and submit to the GPC Administrator by the last
working day of the month.
11.6
For Service Areas, Line Managers must check the GPC002 returns received
from the cardholders; authorise these electronically with the appropriate
statement as per section 2.5 and submit to the Area Finance by the 15th working
day of the month.
11.7
An MR1 form must be sent to Finance Bureau for any cheque received from the
cardholder for personal expenses incurred on the GPC. The cheque(s) should
be attached to the MR1. The total of the cheques received from the cardholder
must equal the Total of Cheques amount entered on the transaction log
(GPC002). The MR1 form should be submitted to Finance Bureau by the last
working day of the month. A copy of the MR1 form and the cheque must be held
with other receipts for audit purposes. Spot checks will be conducted as part of
7
the Business Assurance Health check at which point requests may be made to
see copies of cheques and MR1 forms.
11.8
12.
12.1
The Area Finance Manager (AFM) must have in their possession, all GPC
submissions from his/her Operational Area, checked and signed by 17th working
day of the month.
12.2
The (AFM) must ensure appropriate systems are in place for the monitoring and
tracking of GPC returns. They must also ensure that spots checks of returns as
per requirements of the Line Manager are performed on a regular basis and
logged. Any issues with compliance must be raised immediately with the Line
Manager.
12.3
Once all documentation has been reviewed, the (AFM) must then prepare an
electronic copy of a fully reconciled cardholder summary (GPC003).
12.4
12.5
The GPC Administrator will post the monthly GPC journal for all areas and
National Office, on to the Open Account system. The monthly journal must be
posted in the same month of spend, for example the March 28th statement must
be posted in the March accounts.
13.
13.1
13.2
13.3
14.
14.1
14.2
14.3
15.
15.1
16.
Cancellation of GPC
16.1
All requests to cancel a GPC must be emailed to the GPC Coordinator by the
cardholders Area Finance Manager (for the regions) or by the cardholders Line
Manger (for National Office) as soon as notification is received that the
cardholder is leaving or no longer requires the card due to a change of role. In
addition to this the Line Manager must:
Ensure that the cardholder is making regular use of the GPC and as per the policy and procedures have systems in
place to identify and report to the GPC Coordinator any GPCs not used over a period of four consecutive months and
therefore require revoking.
17.
Revocation of GPCs
17.1
Misuse of the card can result in revocation, or indeed disciplinary action being
taken against the cardholder. The following may result in the GPC being
revoked:
18.
18.1
The table below outlines the GPC credit limits based on the current levels of
usage. The current limits allow for flexibility whilst balancing the risks of the
organisation. Limits will only be increased above the standard credit limit where
there is evidence of a genuine need.
Job Title
Office Manager
Service Manager
Head of Service
Area Finance Manager
Service Director
Corporate Director
CEO
Credit Limit
1000
2000
3000
18.2
A request to increase a credit limit must be raised through the Area Finance
Manager (for the Operational Areas) or the CMT member (for National Office) by
an electronic completion of a GPC005 Request to Increase Credit Limit
(Appendix 8). This form should then be sent electronically to the GPC
Coordinator.
18.3
All requests will be reviewed and if the reasons are considered to be valid,
authorised by the GPC Coordinator.
19.
GPC Queries
19.1
10
19.2
Any other issues or queries in relation to the use of the GPC should initially be
raised with your Line Manager. Should any matters still remain unresolved, they
should be directed to Operational/National Office for further consideration.
Finally, the GPC Coordinator (see contact details below) can be contacted for
assistance on issues that cannot be adequately addressed at the operational
level.
GPC Coordinator contact details:
Chris Iwalesin
Cafcass National Office Finance
Sanctuary Buildings
Great Smith Street
London
SW1P 3BT
Tel: 07500 553 897
GPC Administrator Jamie Wates
11
Appendix 1
Operational Area Lines of Authorisation
GPC
Holder
Line
Manager
GPC
Administrator
Area Finance
Manager
OM
Service
Manager
Area
Finance
Manager
Head of
Service
GPC
holder
(left)
must
have
their
returns
authorised
electronically
by their line
manager
(right) with the
appropriate
statement
contained
in
the email
The
Line
Manager checks
and
electronically
authorises
all
returns,
and
then
sends
electronically to
their
Area
Finance by the
15th
working
day
of
the
month.
Head of Service
Service
Director
Service
Director
Cardholder
Summary
(GPC003) is
prepared &
signed by the
Finance
Manager
The
signed
Cardholder
Summary must
be forwarded
electronically
to the GPC
Administrator
as
per
the
timetable.
Appendix 2
12
Line Manager
Service Director
Chief Exec
Head of Service
Corporate
Directors
Chief
Executive
Chairperson
The
GPC
holder
(left),
must have their
returns
authorised
electronically
by their Line
Managers
(right) with the
appropriate
statement
contained in the
email
Corporate Director/
Chief Exec
Chief Executive
Chairperson
Chief Executive
13
GPC
Administrator
The
Line
Manager
checks
and
electronically
authorises all
returns,
with
the appropriate
statement
contained in the
email and then
sends
electronically to
the
GPC
Administrator
by the last
working day of
the month.
GPC
Administrator
will check all
documents are
received.
Prepare and post
the journal for
the month.
Appendix 3
Key Dates
Date
28th
2nd
2nd
10th Working
Day
15th Working
Day
17th Working
Day
Last Working
Day
5th Working
Day of new
month
15
App
endix 4
GPC004
Request for New Government Procurement
Card
CARDHOLDER DETAILS
Proposed Card Holder Name
Position
Office Address
Cost Centre
Reason for Application
AUTHORISATION DETAILS
16
App
endix 5
GPC001
Receipt of CAFCASS Government
Procurement Card
CAFCASS CARDHOLDER DETAILS
NAME
JOB TITLE
OFFICE ADDRESS
TELEPHONE
17
GPC CARD NO
Please mark the box with a X to confirm you agree with the below statement
I, the Cardholder, have read and agreed to abide with the CAFCASS Policy regarding
Government Procurement Card use, and the Terms and Conditions of the Government
Procurement Card. I can also confirm that I have received training for the appropriate use of
the card.
DATE
Return this form electronically to your Finance Manager to be forwarded to the GPC
Coordinator, and retain a copy on your employee personnel file.
18
App
endix 6
GPC002 MONTHLY TRANSACTION LOG (PLEASE RETAIN A COPY OF YOUR MONTHLY STATEMENT &
RECEIPTS)
Name:
Mike Anybody
1122334455667788
Jun 13
062-
Transaction
Transaction Description
2
3
4
5
6
7
8
9
10
11
12
13
Desk Fan
Catering for judges
meeting 15/06/13
Cost
Centre
(Journal
Format)
Total
(Inc.
VAT)
062-
350100
8.00
062-
430100
10.00
062-
425000
20.00
38.00
Total of Cheques
0.00
38.00
Cardholder:
Please send completed form via email to your line manager with the following statement contained within the body of the
email:
I am the preparing officer for this form GPC002 and can confirm I am satisfied that the entries made are correct and reflect
appropriate goods and services received. Please approve for processing.
19
App
endix 7
GPC003 - GPC CARDHOLDER SUMMARY FOR OPERATIONAL AREA ONLY
Statement Month:
Area:
Cardholder
Card Number
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
20
Cost Centre
(Journal
Format)
Monthly
Statement
Total (Inc.
VAT)
0.00
Less: Cheques for Personal Expenditure
1
2
3
4
5
0.00
0.00
This Summary is to be check by the Area Finance Manager and submitted to the GPC Administrator in PDF format.
The AFM should submit an electronic copy using the authorisation statement:
I am the AFM for the Operational Area and confirm that Area Finance have thoroughly checked GPC returns and
can confirm I am satisfied that the entries made are correct and reflect appropriate goods and services received.
Please process for payment.
Name of Area Finance Manager
App
endix 8
GPC005
Request to Increase Credit Limit on
CAFCASS Government Procurement
Card
CAFCASS CARDHOLDER DETAILS
CARDHOLDER
CARD NUMBR
POSITION
OFFICE ADDRESS
21
TELEPHONE
COST CENTRE
PREVIOUS CREDIT LIMIT
REASON FOR INCREASE
AUTHORISATION
PREPARED BY (CARDHOLDERS MANAGER) NAME
POSITION
DATE
N.B This form should be completed by the cardholders Line Manager and sent electronically
to the Area Finance Manager (for the Operational Areas) or the CMT Member (for National
Office). This form should then be forwarded electronically to the GPC Coordinator.
22
Appendix 9
Memorandum
To:
Line Manager
CC:
From: Cardholder
Date:
Re:
Date
Description
Acc Code
CONFIDENTIAL
23
Total (Inc
VAT)
N.B Cardholders must complete this form and email it to their line
manager with their monthly GPC002 and retain a printed copy with the
monthly receipts.
24
Section Contents
Intro. How to open eBis and Amend Personal Settings
1. Raising a Requisition (Commitment)
2. Raising a Requisition to Cover Multiple Invoices
e.g. Annual or Quarterly / Rent/Rates, Mobiles
etc.
3. A Guide to Blanket Purchase Orders
4. Sending for Authorisation and View All Orders raised
5. Viewing/Printing Authorised Purchase Orders
6. Entering a Goods Received Note (GRN)
7. Cancelling a Purchase Order
e.g. No longer required, Duplicate etc.
Authoriser Contents
8. Authorising a Requisition
General Contents
9. Procedure for Invoice matching
10.
25
You will now be presented with the following screen. If you want you may now
amend your settings Including changing of your password. To enable this, click
on My Settings
26
Using this screen you can enter a New Password and Contact Details then
+Save
27
You are now ready to use the system for transactions and requisitions.
Proceed to Step 1 on the next page.
28
29
1.3 Make sure Company is 1-CAFCASS and Cost Centre is your office. Click
OK
If you now click on Keep Company/Department for future Adds theneach
time you open this screen, these settings will be saved and you will
automatically proceed to the next screen as shown below in 1.4
30
1.5 When this page is complete click on More to add a product or Service
Goods Description and Cost Detail
1.6 Entries in Blue/Underlined Click on the Actual Text and Select Entry from
Listing
1.7 Entries in Black text should be entered/typed in manually (Quantity, Unit
Price etc.)
1.8 The text you enter in the Description box is printed on the Purchase Order
so include suppliers catalogue or product numbers here. Also refer to Note
on 1.11 below.
1.9 If the order is an annual one change the Due Date to cover the whole year.
1.10 Fill in all the boxes then click on click on Save. Add a new line for each
type of product or service.
31
2.1 To manually enter a second line, Click on +Add and a second Line will
appear below the first, now follow steps 1.5 to 1.11 for each line you enter in this
way.
Alternatively, if second and subsequent lines are similar, Click on +Copy
and previous
line details will be carried down which
you may edit by clicking on More
When you send the requisition off for authorisation, note the Item Number that
will appear as this will help to match up the order when authorised.
Also once it is sent a box appears with the name of the person the requisition has been sent to
and the ID number. This has to be OK'd before the requisition is actually sent and therefore,
gives a chance to change the name of the authoriser at this point if need be. If the authoriser is
correct then click OK to send the requisition.
33
A Blanket (or Bulk) PO is used for the committing and recording of expenditure
for a time period within a financial year.
3.2
1) Periodic/Fixed Invoices
Where the frequency and fixed of the invoice is known i.e. annually, quarterly,
and weekly.
E.g. Rent, Rates, Utilities, Mobile phones rental, Video Conference line rental,
telephone line rental, cleaning costs, photocopier hire and vehicle rental.
2) Variable Invoices
Regular invoices are received yet at varying amounts yet on a regular basis.
E.g. Temporary staff, phone call charges, Recruitment, Occupational Health and
catering.
3.3
For both types of Invoice follow the initial process detailed in Steps 1 and 2
above, then proceed to the following;
1) Periodic/Fixed Invoices
As the amount per period is known the PO can be set up using the
appropriate amount of lines (i.e. one for each month)
E.g. Rent- 1000 per month set up 12 lines at 1000 each. When an invoice
is receive simply GRN that appropriate line for the corresponding month)
It is recommended that you set up the PO using suitable units. (Tip: its useful
to use the same value unit for all POs to avoid confusion) The value of the PO
should be calculated using the NET amount.
For example- Temporary staff- If you anticipate committing 10,000 in total
on temporary staff throughout the year the following calculation can be made
to determine the NET value of the PO and the number of units required
Calculation
NET VALUE = Total commitment * 85% / (chosen unit value) =
number of units
DESCRIPTION
3.4 General information describing the PO and the period that it covers i.e. Annually or 6
months and Office details.
UNITS
Units of 5 have been used in this
example. You are free to use
whatever value of units suits you
QUANTITY
Step 1
Wherever possible, the Invoice Number should always
be available. It should be entered into the GRN Step 4
SAVE CLICK ON HERE AFTER ENTERING
Reference Box
THE UNITS RECEIVED
36
For info
DO NOT
CLICK ON
THIS AS IT
WILL GRN
THE WHOLE
PURCHASE
ORDER
3.7
Step 3
RECEIVED
CLICK RECEIVED
AFTER THE UNIT
AMOUNT HAS BEEN
ENTERED INTO THE
PURCHASE ORDER
AND SAVED
For info
For info
TOTAL NET COST
OF BLANKET
PURCHASE
ORDER
Step 2
GRN UNITS RECEIVED
NET COST ON INVOICE /
UNIT PRICE (5.00)
What happens when there are only a few units left to GRN
on a Variable Invoice?
If the value of the invoice is within 20% or 500 (whichever is less) of the
remaining value of the PO then you can click on Complete. If not then you
will need to raise a new PO. (Tip: It is better to make provision to raise a
new order if you anticipate that the current PO will not cover the next
invoice).
37
DO NOT CLICK
ON UNTIL ALL
UNITS ARE
USED UP BY
INCOMING
INVOICES
3.8
38
4.2 To find your Cost Centre entries enter your 3 digit code in the Dept:
box.
This will show orders made by you and on your behalf by Regional
office.
Or:To search for your own entries click on Advanced
39
4.3 If you have used Advanced Click in the 2nd box down (Circled)
Search All Stages Once Owned By Me. Then Find
40
4.4 The next screen will list all the orders you have created and the stage
they are at e.g. Entry, Approval or Approved. Use this screen to find
orders and their status. Click on the ID number quoted in the e-mail
warning and open it to see the order.
4.5 Click on Request Print. An e-mail will arrive in your in box with a
Word attachment. This is the Purchase Order.
41
4.6 Open the Word document. You can save it in your G drive under your
own e-bis directory. File them in Supplier folders or type of order. If
you want, print off a copy and file until the invoice or goods arrive
The above G: drive storage guideline is optional. Not all regions do this, although
Some find it helpful as it gives them easy access to copies of PO's without having
to 1) Start up eBis or 2) Dig out paper copies from files.
4.7 A copy of the purchase order should be sent to the supplier by post or
fax.
42
43
44
45
Please note, you can Request Print (Purchase Order) at this stage,
however, to ensure the order is all correct (Proof Read), I suggest you
carry on as below.
5.5 The following screen will appear, Click on Your chosen Entry
Number.
46
5.6 Check the details of the Approved Item, if all o.k. Click on Request Print
47
48
6.3 Click on +Add. Make sure the correct Cost Centre is selected. Click OK
You can now see all outstanding Approved orders for your cost centre waiting
for delivery or the latest invoice
49
6.4 Click on the Order number link on the left hand side
Note. If Invoice does not show order number refer to part 3.3 and repeat process
In the Qty Received box enter the number of goods (e.g. 2 desks) or invoices
received against an annual or ongoing order whichever is appropriate. If the
Outstanding quantity is nil a
tick will appear in the Completed box.
Complete all the
lines of the order.
Please Re-enter the
Invoice number (or your original GRN Ref)
50
Entries
51
This will copy all Qty Ordered amounts into Qty Received column.
Only perform this function if you are certain all items or services have indeed
been received.
52
53
54
7.6 Finally click on received which will inform CAFCASS FINANCE that
this order will no longer be required.
7.7 If the GRN has already been raised for a PO but needs to be reversed,
you will have to contact Cafcass Finance by Email with: PO number,
Values, Supplier details, and they will cancel the PO for you.
55
8.2 EBIS now shows you the list of requisitions that are waiting for you to
approve.
By clicking on the box marked APPROVAL you can choose to see any
that you have raised yourself (unlikely), waiting for approval.
56
8.3 After selecting approval, and you will be restricted to those waiting for your
decision now. Click on the ID number relating to the requisition that you
wish to process.
57
8.4 As shown in the image below, you now have access to the requisition details
of supplier.
You are able now to change any of the details by using the procedure for
raising a requisition as shown in sections 1 and 2 of the guide. However,
we will concentrate on enabling you to authorise and go straight to dealing
with the details of the requisition itself. Scroll down.
58
8.5 The following details will have been included by the originator who raised the
requisition, Ensure they are clear enough to be able to make a decision as
to approve or not. If not you may need to look at further details, to do this
you should click on the MORE box.
59
8.6 This opens up the details of the order. By clicking on the boxes with Blue
Font underlined, you can change the details by using the look-up facility.
However it is best practice that if you do need to make changes to use the
Next>> button, insert message and then close this detail, and select
reject.
60
8.7 If you need to use the notes column, click on notes and the following free txt
window opens. Simply type in your message and then save. You will note
that a pencil will appear to the top right hand corner of the requisition.
61
8.8 You can choose, +Save Rejected or Approved to do later. Click on one of
the three options at the top.
62
8.9 The requisition now goes into Open accounts for the first time and
undergoes the transformation from requisition to an Order and also a
Commitment.
An email will be sent back to the originator saying that the order has been
approved and is ready to be printed out.
It is at this point that you, as the approver, have committed the service to
spend the value as stated on the order. By selecting approval, this is the
same as signing a hard copy with your name.
63
64
65
The password box is where you enter your Invoice Matching Password.
To see the details of this request, click on the Show Details of Matching link at the bottom
of the screen. This will show a summary of the invoice and the Purchase Order including
their reference numbers, supplier, invoice amount, purchase order amount and the
difference.
If you wish to see more details of the invoice and/or Purchase Order, click on the
reference numbers highlighted and underlined in blue.
Close these screens by clicking on "X" in the right hand corner.
If you are satisfied that there is a genuine reason for the discrepancy and would like
Cafcass Finance to go ahead and pay the amount on the invoice, you should enter your
Invoice Matching Password in the Password box. If you do not have an Invoice Matching
Password, you should speak to National Office Finance dept.
After that, click on Generate Override Password. A password for this matching session
will be automatically generated (your own password will not be seen by anyone else).
The override password takes the form of a random collection of letters and numbers that
appear in a box next to the password box.
Finally click Respond by Open Messenger. This will send the authorisation password to
Cafcass Finance who will then be able to pay the invoice.
You can now click on any remaining, outstanding invoice matching request on your list
and repeat the process above.
When they are all done, log out.
If the invoice matching request has been sent to you in error or does not relate to you, let
Cafcass Finance know by typing a message in the Approver Reply Box and then clicking
on the Respond by Open Messenger button. This will alert them to the situation.
If you have any queries or problems with this procedure, please contact
National Office Finance Dept. on 0207 510 7006.
66
10.2 There are 2 reports that you will use most often:
Purchase Order Report or Single Supplier Details Report
67
10.3
Purch
ase
Order Reports
Search Supplier to Identify PO numbers, or
Identify PO line content and value - Quick ref, or
Identify Origin of the original requisition and the
s
t
a
t
u
s
o
f
t
h
e
P
O
.
68
69
10.5 After clicking the blue supplier link (See above), the screen on next page
will appear.
Search for the supplier as one would when raising a requisition (See
Section 1.4)
Enter first few letters of the supplier in SUPPLIER NAME: and click on
+Find, then
select the correct Supplier by clicking once on the coloured number
adjacent to the name.
10.6 At this point, you can press +Submit, or if you wish to narrow the
search, enter some Order Dates. You must click both Order Date and to
and select dates from calendar. Or use an eBis ID (Our Ref) if other eBis
users use the supplier.
70
10.7 You will now be able to view all orders raised against your chosen
supplier, and if specified, between certain dates.
A PO number can be obtained in this way and used to print off a PO.
71
10.8 Single Supplier Details Report Used to identify if a supplier is set up,
clarify an existing
suppliers details, to identify payments to specific supplier in a certain
period or to view
scanned images of invoices that have previously been paid!
We will look at Mail Merge Purchase Orders in Section 11
72
10.9 After selecting Single Supplier Details from the Reports section of eBis the
screen below will appear. Select the supplier as described previously (10.4)
then select
Document Type Click +Submit for the next page of options.
73
10.11 Ensure the Include Matched and Include Unposted boxes are checked
and enter the year and period as appropriate.
Tip Current year is 2006, period 1 is April. Lastly, click +Submit.
10.12 Below the suppliers details is a list of all invoices received by Cafcass
Finance in the period.
You will note that some invoices have the status Paid, whilst others do
not.
74
10.16 Finally click the printer icon to obtain a hard copy of the invoice.
Use the arrows ( ) to scroll through pages.
76
11.1 The POs are split into Un-printed or Reprint - If for example you request a
reprint of an unprinted PO it will not work and vice versa.
Branch always needs to be filled in with the relevant Cost centre code. Clicking
on the
Order number gives you a selection of all the POs available on the mail merge
(Below)
11.2 If you have only recently completed order and not printed PO off then
select Un-printed
77
11.3 You may now click the first and last purchase orders you require (see
above).
This will then include for printing all the visible purchase orders in between
your selections. Then click on OK
Press +submit and an email with attachment will be sent to your outlook
account. The POs can then be edited or printed off as required.
The same process is used for Reprint purchase orders.
78
Appendix 1.
eBis Tax Codes
EBis
Tax
Code
Description
Rate
Exempt
0%
Reduced Rate
(Shown as Electricity
& Gas on eBis)
5%
0%
Standard Rate
20%
Travel and
Subsistence
0%
Zero Rates
0%
T
Z
Comments
Some types of expenditure are exempt from VAT. Including
certain types of education and training and some property
transactions (e.g. selling, leasing and letting land and
buildings). This will also include Occupational Health
(Mayfair) Invoices.
Some categories of expenditure are subject to a reduced
rate of VAT at 5%. Examples are domestic fuel or power,
installation of energy saving materials, safety equipment i.e.
childrens car seats
Not all businesses are required to be VAT registered.
Businesses with an annual turnover exceeding the current
VAT threshold of 60,000 must be VAT registered and
show a VAT registration number on their invoices. Some
self employed individuals such as self employed guardians
may not be required to be VAT registered because their
turnover is below the VAT threshold.
This code should be used when there is no VAT
number shown on the invoice.
This is the standard rate of VAT applicable on the majority
of VAT registered businesses. The standard rate of VAT will
apply in respect of supply to, or a service received from a
VAT registered business that does not fall into any other
category. (Examples: Self Employed Guardians who are
VAT registered, Agency Staff, Advertising and most other
goods and services including Telecommunications,
Stationery stores orders etc.)
This code should only be used when there is no VAT shown
on the invoice in respect of T & S. Some examples are
when payment is being made through eBis for interview
candidate travel expenses or clients T & S.
Some types of expenditure are Zero Rated. Some
examples are childrens clothing and footwear, most food
and drink (but not Catering and Takeaways)
th
I wont list all the contributors by name as this is an ongoing piece of work and the list will
eventually
end up requiring more space than the instruction pages!
Thank You All Regards from Roy Dudley
BSO Southern and South East
01256 392790 roy.dudley@cafcass.gov.uk
80
Document Owner:
Last Updated:
Updated by:
Julie Brown
October 2013
Zubeda Seedat
Contents
1. Introduction 82
2. Overview
82
84
85
92
6. Contact Information 93
81
1. Introduction
Accounts Payable is an area which is monitored via reports. The two main
reports used as finance performance indicators and which are reported on a
monthly basis are:
The above reports allows us to understand whether correct procedures are being
followed when making purchases and payment, this is vital in ensuring that
appropriate financial controls are in place,
Understanding the Accounts Payable processes and procedures should help to
improve performance, hence this Accounts Payable Guide should be used in
conjunction with the various procedure notes.
Items highlighted in blue in this guide are clickable links to documents on the
Cafcass Intranet or the definitions section of the guide. If you have any queries,
comments or suggestions regarding this guide, or the Accounts Payable process
in general, please e-mail the National Office Finance Dept.
2. Overview
Accounts Payable (AP) refers to process used to pay suppliers from whom
Cafcass receives goods or services on account, i.e. payment of invoices.
An effective Accounts Payable service has several important roles within the
organisation:Internal Controls
If set-up and followed correctly the AP process can help to mitigate the risk of
fraud and unauthorised expenditure. This is achieved through appropriate checks
and the segregation of duties. An example of this is the purchase order process
on the eBis system whereby a PO cannot be raised and approved by the same
person.
82
Prompt Payment
Cafcass has an obligation to ensure that payments to our suppliers are made in a
timely manner and in accordance with their payment terms. Failure to make
payments on time can result in Cafcass having to pay interest and/or late
payment fees. It can also damage the reputation of the organisation and in
extreme cases lead to suppliers refusing to supply Cafcass with goods or
services.
Budget Monitoring
Another important function of Accounts Payable is to ensure that Cafcass can
maintain control over its budget. By raising Purchase Orders we are able to
identify not only expenditure that we have already incurred, but also expenditure
to which we have committed ourselves in the future. This is one of the main
reasons that it is essential to raise a PO as the first step in ordering goods or
services from a supplier.
Audit
As a public funded organisation, Cafcass Annual Accounts are audited after each financial year. Only by following the AP
process correctly we can ensure that we have all supporting documentation and checks to satisfy the audit requirements.
83
NO
Is the supplier
set-up on eBis?
WHEN
SUPPLIER IS
SET-UP
The Good or Service is
received by Cafcass.
GRN is raised by
PO Originator on
eBis
Scenario 2:
Supplier sends invoice to
local office/Dept who
check if goods/service is
received and raise a
Goods Received Note on
Ebis and then send to
Finance Bureau.
YES
NO
Finance Bureau notify
relevant PO Originator by
email that an invoice has
been received and a GRN is
required
4. Processes
85
The eBis User Guide on the intranet provides comprehensive instructions on how
to raise a Purchase Order correctly. This guide should give staff an
understanding of what a Purchase Order is and its applications within Cafcass.
Purchase Orders may sometimes seem to be an unnecessary bureaucracy, but
they are in fact a vital part of the AP process. They serve several functions:
From an accounting point of view the last function is vital. In order to monitor
Cafcass expenditure against our budget, we need to be able to identify money
that we have committed to spending or we run a great risk of significantly under
spending or overspending.
Areas and National Office Departments are required to produce Accruals on a
monthly basis. If used correctly, Purchase Orders and Goods Received Notes
can greatly simplify this task. For this to be achieved it is not only essential that
POs are raised in advance, but also that they are raised correctly with attention
to completing the Due Date field correctly for each line.
To monitor compliance with this requirement, Cafcass produces monthly reports
on the proportion of POs that have been raised in advance, i.e. before the
invoice date. Departments should use these reports to identify problem areas
and improve compliance.
86
On receipt of goods/service
By raising a GRN on satisfactory receipt of goods/service we are able to use
reports such as GRN no invoice report to determine the monthly Accruals or for
the purpose of automatic accruals. If a GRN has been raised prior to the invoice
being received then the invoice can also be sent directly to the Finance Bureau
to process for payment preventing any delay in payment.
On receipt of Invoice
By raising a GRN on receipt of invoice, the invoice number can be used to keep
track of any issues that may have arrived on delivery of goods/service. The
invoice in this case will need to come to the local office first for the GRN to be
raised before it can be sent to the Finance Bureau for payment.
Both of the above procedures are acceptable. Please check with your
local/finance team which methods is being utilised.
(d) Invoices
Invoices are usually issued by a supplier either at or shortly after delivery of
goods or services. An invoice is, in effect, a demand for payment from a supplier
Cafcass can only pay invoices if they meet certain minimum standards. These
standards and a sample invoice can be found on the intranet. Some of these
standards are necessary to protect Cafcass from fraud or duplicate payments,
whilst others are HM Revenue & Customs requirements for tax purposes. These
standards include the requirement for a valid Purchase Order number to be
included on the invoice.
If the process has been followed correctly, when we receive an invoice, we
should already have raised a PO and therefore the invoice should state the PO
number which we would have provided to the supplier when placing an order. In
some instances a GRN for the relevant goods or services may also have been
raised by this point.
If an invoice is received and the PO has not yet been raised, the reason for this
should be identified and measures put in place to prevent, as far as possible,
future occurrences.
If the invoice arrives at the local office, the local office staff must check that the
goods/service has been received and the GRN has been raised on the system.
The invoice should then be sent to Finance Bureau for payment.
When Finance Bureau receives an invoice (either form the local office or directly
from the supplier) they will use the details to match it to a GRN on a PO. When
the invoice is matched they will then pay the invoice using the payment details
held on eBis.
87
Copy Invoices
If the original invoice is missing and is unpaid, we should ask the supplier to
issue a copy invoice. Any copy invoices (this includes faxes, photocopies or a reissued invoice marked as a copy or duplicate) need to be signed by an
authorised individual before being sent to Finance Bureau for payment. By
signing the copy invoice, the authoriser is confirming that the original invoice is
not available and that the invoice has not already been paid. If there is any doubt
as to whether an invoice has been paid, this should be checked with Finance
Bureau before signing and sending the copy.
Rejected Invoices
If Finance Bureau receives an invoice that does not meet the requirements they
will send this back to the supplier with a note detailing the reasons for the
rejection. The main reasons that invoices are rejected are:
PO related problem (e.g. no PO number)
Invoice does not have a unique invoice number.
Invoice does not meet other minimum standards.
Late Payment
On a monthly basis, Cafcass generates reports on late payment of invoices.
Departments need to ensure that they use these reports to identify reasons for
delays in payment so that they can be avoided in the future.
Finance Bureau will pay an invoice as soon as there is a matching PO and GRN
for the invoice almost all delays in payment will be due to either the lack of a
PO number on the invoice leading to it being rejected or the lack of a GRN
evidencing receipt of the good or service.
(e) Credit Notes
From time to time a supplier may make a mistake when invoicing Cafcass or
goods may be returned or refunded. In this case the supplier will normally issue
Cafcass with a Credit Note. A Credit Note is, in effect, a negative invoice. If a
Credit Note is expected from a supplier for an invoice it is best to notify Finance
Bureau
of
this
as
early
as
possible
via
email
(Cafcass.finance@cafcass.gsi.gov.uk ) with details of the original Invoice so that
it is not paid.
If a Credit Note is received and the invoice to which it relates has not yet been
paid a PO will need to be raised for the Credit Note (this is done in exactly the
same way as an Invoice but with negative amounts see eBis User Guide). The
Invoice and Credit Note should be sent together to Finance Bureau who will
process them and make a Net payment to the supplier (zero if it is a full refund)
88
If a Credit Note is issued after an Invoice has been paid we should still raise the
PO as above. Finance Bureau will then process this and the resulting credit will
be netted off against any future payments. If we are not likely to use the supplier
again or we are approaching the end of the financial year, we would ask the
supplier to make a payment to us.
(f) AP1 Form
AP1 refers to a form to be completed when we need to make a payment to a
supplier where we do not have an invoice or where it is not appropriate to raise a
PO e.g. when we receive a Pro forma invoice or Subscription Notification.
(g) Payments
All payments are dealt with by the Finance Bureau. When Finance Bureau
receive an AP1 form or an invoice (and match it to a GRN), they will make a
payment to the supplier based on the information given when the supplier was
set up.
Cafcass can make payments to suppliers in three main ways:
Cheque
Some suppliers (usually individuals) still prefer to be paid by cheque.
When we need to make a payment to a supplier by cheque Finance
Bureau will raise the cheque on our behalf and send it to the supplier at
the address specified when they were set up.
89
CHAPS
payments
are
only made
in exceptional
For instruction on how to check if an invoice has been paid, please refer to
section 9.9 of the eBis User Guide .
Finance Bureau will send a remittance advice with every payment. A remittance
advice lists the invoices that have been paid and the total amount paid. This
enables suppliers to allocate the payment received from Cafcass against the
correct invoices.
90
that are sent to Finance Bureau for payment have been appropriately authorised
(see Copy Invoices).
91
Expense Codes
Expense Codes (sometimes called Natural Account Codes or NACs) are used to define the type of
expenditure e.g. Temporary Staff or Stationery. Each type of expenditure has an expense code
consisting of six numerical digits followed by a hyphen (-).
The Cost Centre Code and Expense Code are used to identify against which budget and what
expenditure type any expenditure should be coded. For example, when raising a PO for a temp
working in the Customer Services dept we would use the code the PO on eBis to cost code 008(Customer Services) and expense code 375000- (Temporary Staff).
Open Accounts
Open Accounts is the accounting software that Cafcass uses to maintain the Accounts Ledger. The
eBis PO system and GRN system links with Open Accounts.
92
Accruals
A simple definition of Accruals for AP purposes is that they are dummy transactions entered on the
ledger to represent expenditure for Goods/Services we have received in a particular financial month or
year that have not yet been paid for in that year.
6. Contact Information
Cafcass Finance
Cafcass Finance
Priestley House
Priestley Road
Basingstoke
Hampshire
RG24 9NW
DX 159050 Cafcass South
Basingstoke 25
Please note that all mail MUST be marked as Cafcass Finance
Telephone: 0844 353 1627
Fax: 0844 353 1621
Email: cafcass.finance@cafcass.gsi.gov.uk
E-mail: NOFinance@cafcass.gov.uk
Cafcass Payroll
Cafcass Payroll
Priestley House
Priestley Road
Basingstoke
Hampshire
RG24 9NW
DX 159050 Cafcass South
Basingstoke 25
93
Julie Brown
When Required
September 2013
Heather Jeffries
Introduction
Occasionally, Cafcass will need to pay for goods without receiving an invoice, for
example when paying for a publication subscription in advance. For these
payments, a Purchase Order is not appropriate and we need to complete an AP1
form to instruct CAFCASS FINANCE to make a payment to the supplier.
Process
Open the blank AP1 template. This can be downloaded from the intranet.
In Section A you will need to enter the Payees name and address details.
These should be taken from the suppliers supporting documentation.
Section B should be completed as follows: Invoice Date - This should be completed as the date on the
suppliers documentation e.g. the payment demand or subscription
notice.
Invoice Received Date - This is the date the document was
received
Invoice Number The document should have some form of
unique reference or subscription number you can use.
Cost Centre & Natural Account Code This is the Cost Code
and Natural Account Code to which the payment should be coded.
Please speak to Finance if you are unsure of the correct codes to
use.
Amount Exc VAT This will be the amount before VAT on the
documentation.
Amount of VAT This is the amount of VAT as on the
documentation.
Total Amount This will be automatically calculated from the
previous two items.
In Section C Part A the originator should type their name and the date
In Section C Part B the authoriser should type their name and the date
94
In the top right corner of the form is a section called Special Instructions,
for example instructions that the cheque be sent to an address other than
that of the supplier.
95
1.2
1.3
3.2
Contacts ........................................................................................................... 8
Version History
Version
1.0
1.1
Description
Process Guidance and policy
Document
Update of guidance
Author
J Wates / L Alade
Date
16.09.11
October 2013
1
Introduction
The purpose of this document is to provide guidance when setting up an
individual on eBIS as an Originator or Approver, as an Authorised Signatory, or
as an OpenAccounts user.
When setup as a user on eBIS, an individual would be able to raise requests for
the expenditure of Cafcass funds (eBIS originator level) or authorise expenditure
of Cafcass funds (eBIS Approver level). Authorised signatories may sign off
various finance forms as indicated on their form, OpenAccounts access is used
by Finance staff for a range of purposes.
To setup an individual with the above access/authority, the Notification of
Signatory and eBIS user form needs to be completed. This can be found on the
Intranet via the following link and under Signatories
96
http://cafcassintranet/Intranet/departments/finance/finance_manual_new/supplier
s_and_ebisnew.aspx
Please note: Authorisation of T&S expenses is not assigned via this form as the
authorisation for T&S is done via iTrent and not Ebis.
1.1
General Policy - Financial Approval
Only the Budget holder of a specific cost centre (as well as Area Finance
Manager, Head of Service, and Operational Director) should be able to authorise
expenditure for that cost centre. However based on local circumstances and
business need additional approvers may be setup for a cost centre, this should
be controlled by each CAFCASS area and kept to a minimum where possible.
There are four levels of approval authority which are restricted to the roles as
follows:
Where these roles do not exist for a cost centre e.g. HQ or other non-standard
cost centres then appropriate managers may fill the roles below Head of Finance,
e.g. in the case of HQ the Operational Director level may be omitted and the
Department Head would fill the Head of Service role.
Purchase requisitions ought to be sent to the lowest level approver for approval
in the first instance, if the requisition is above 20k in value then it will progress
up the levels of approval automatically until it reaches the appropriate level, so a
purchase requisition for over 100k will be approved at all four of the approval
levels.
1.2
AP1 Payment Approval
Payments via AP1 form should be avoided where possible; when a payment via AP1 is
required the originator should email the completed AP1 form and supporting
documentation along with the appropriate statement to the authoriser, who must be a
signatory for the cost centre quoted, who should then forward the form with supporting
documentation and authorisation statement to Cafcass Finance.
1.3
eBIS Account Expiry
All eBIS users that have not used their account in 12 months or more will be
removed from the system. To enforce this policy a review of eBIS user accounts
97
will take place every 6-12 months and a list of all accounts unused for 12 months
will be sent to the Area Finance Manager and NO Finance, who will have the
opportunity to veto account closures if there is a valid reason for them remaining
open.
Payroll leavers will also be identified and their eBIS accounts (if any) will be
removed on a regular basis.
2
eBIS Originator Setup and Maintenance
In order to raise requests for the expenditure of Cafcass funds, individuals need
to be set up as an eBIS Originator. Complete the Notification of Signatory and
eBIS User form link above.
Please complete the following sections of the form:
Part 1: Details of individual
Enter the individuals surname, forename, employee number, email
address and direct telephone number.
Part 2: Action Required
Tick action required. I.e. to setup a new user, remove a user, or add to or
replace an individuals authorities.
Part 3: Type of Setup
Section a. Tick box:- eBIS Originator
Ignore section b.
Ignore Part 4
Part 5: Cost Centres and Expenses codes allowed
Enter cost centres and expense codes the individual is allowed to
originate purchase requisitions for.
Once the form has been correctly completed it needs to be emailed directly to the
Finance Bureau mailbox by the appropriate Signatory. Please note forms not
forwarded by the appropriate signatory will be rejected.
3
Signatory and eBIS Approver Setup and Maintenance
In order to authorise the expenditure of Cafcass funds, individuals need to be set
up as an eBIS Approver or an authorised signatory; by default, all eBIS
approvers are also authorised signatories. The Notification of Signatory and
eBIS user form needs to be completed.
http://cafcassintranet/Intranet/departments/finance/finance_manual_new/supplier
s_and_ebisnew.aspx
Please complete the following sections of the form:
Part 1: Details of individual
Enter the individuals surname, forename, employee number, email
address and direct telephone number.
98
A Specimen signature must be provided for a new setup, but is not necessary for
an amendment unless the signature has changed.
Part 2: Action Required
Tick action required. I.e. New setup, removal, or add to or replace
individuals current authorities.
Note: Remove Individual will remove the individuals eBIS system access and
all authority.
Part 3: Type of Setup
Section a. Tick box eBIS Approver or Signatory only as appropriate.
Note: There are restrictions on who can be setup to sign Supplier setup, Copy
invoices, and Notification of Signatory and eBIS user forms. Ask your area
finance team or the finance bureau if in doubt.
Part 4: Level of eBIS Approver (If Signatory only skip to part 5)
Tick relevant Level of eBIS Approver for the individual
Note the next level approver will be the approver with the next highest authority
level, e.g. for a Line Approver their next level approver will be their Head of
Service.
Part 5: Cost Centres and Expenses codes allowed
Enter cost centres and expense codes the individual will be entitled to
authorise expenditure for.
Note: These costs are applicable for non-staff; AP1 & AR1 form expenses only.
Staff costs such as T&S which are approved via iTrent are excluded.
Once the form has been correctly completed it needs to be authorised and
passed to the Finance Bureau for processing, please refer to section 5 of this
document for details.
3.1
Delegate amendments
Approvers will have their next level approver set as their eBIS delegate by default
when they are setup, if this needs changing e.g. to a covering manager, then an
email may be sent to the finance systems mailbox:
Finance_and_HR_Systems_Admin@flex-r.gsi.gov.uk with a request.
Alternatively an approver may modify their own delegate via the following
procedure:
Click the Menu button
necessary.
99
N.B. assigning a delegate will not confer any additional authority to that approver,
they must already have authority on the necessary GL codes or they will not be
able to approve the requisitions sent to them.
3.2
Routing amendments
If the next level approver for an approver changes the Finance Bureau should be
notified as soon as possible, this will help ensure the integrity of the workflow
routing within eBIS and help avoid misrouting of purchase requisitions and
resultant delays in approval.
It is not necessary to complete a form to amend an approvers next level
approver as the routing does not confer any additional authority on either user, to
advise the Finance Bureau of a change in routing please email the finance
systems mailbox: Finance_and_HR_Systems_Admin@flex-r.gsi.gov.uk
N.B. An Approver may only have one next level approver and the next level
approver must have authority on all of the approvers GL codes. Requisitions that
exceed an approvers approval limit will automatically be escalated to their next
level approver, if their next level approver does not have permission on the GL
codes used in the requisition then the requisition will be stuck and a request to
redirect it will need to be emailed to the finance systems mailbox:
Finance_and_HR_Systems_Admin@flex-r.gsi.gov.uk
4
Adding and Amending Accounts OpenAccounts user
Finance staff may require access to OpenAccounts for system interrogation and
journaling. The Notification of Signatory and eBIS user form should be
completed to request this access. This access is generally restricted to relevant
finance staff.
Please note that for access to the OpenAccounts program within FLEX an email
request needs to be sent to FLEX by the users line manager requesting that they
be added to the necessary user group.
Please complete the following sections of the form:
100
101
102
Finance Procedure
Title
Department
Author
First Issued
Last Reviewed
Last Updated
Introduction:
Before a purchase order can be raised for a new supplier to Cafcass, a supplier
maintenance form must first be completed by a member of the Cafcass branch
and then authorised by the relevant Business Manager or 2 nd authoriser. The
form is then sent to Basingstoke Finance by post or by email.
Procedure:
Once received, supplier forms must be checked to ensure the authorising
signature is valid. Check this with the specimen signature held in the Authorised
Signatory log.
It is also necessary to check that the individual who has authorised the form is
set up to do so. Details of individuals who are set up to authorise supplier forms
can be found in Excel at G > Cafcass > HQ > FMS > Accounts> Authorisations.
Emailed forms can be accepted if scanned and received as a pdf.
Forms that contain any corrected mistakes either by correction fluid or crossings
out must be returned to the originating office with a request to re-submit the form.
Along with the supplier form, we should receive back-up documentation that has
been provided by the supplier. Check that the details provided on the supplier
form tally with those on the back-up document. Bank details must be provided
on the suppliers headed paper wherever possible. However, there may be
instances where the supplier is unable (or does not have the facility) to provide
headed paper, for example for Self-employed Contractors, Interpreters, and
some utility companies. Exceptions can be made in these instances
The back-up documents can be scanned and e-mailed. If it has not been
provided or if the details on the maintenance form differ from those on the backup then all documents should be returned to the originating office with an
accompanying note.
103
If the documents are satisfactory the information on the maintenance form must
then be entered on to the OpenAccounts system so that payments can be made
to the supplier accordingly.
To set up a new supplier:
1. Log into OpenAccounts
2. Select Payables > Maintenance Routines > Supplier Maintenance
3. Once in Supplier Maintenance it is necessary to check that the supplier you
will be logging is not already set up. To do this click on Query and then, in the
Short Name box
type the first part of the suppliers name. With some of the larger suppliers there
may be
more than one entry and a brief check through will be needed to ensure there will
be no
duplication of entries. Also check if its already set up by searching for the post
code.
4. In the main supplier selection screen click on Add.
You will notice that a supplier reference number has been allocated to the new
supplier. Write this number on the new supplier form.
Along the top of the next screen will be the following sections:
Supplier, Address, Payment, Codes, Tax, Pop, Mailmerge
All text should be in ordinary upper and lower case.
1. Click on Supplier
Enter the full Supplier Name (ensure that no pronunciation marks are used in
the Supplier
Name and Short Name).
The Short Name must be entered according to the suppliers name. For
example, a company
name such as British Gas will be entered as the same, but an individuals name
will be entered
104
with the surname first. A supplier name beginning with The, such as The
Royal Mail, will be
entered as Royal Mail The. This only applies to the Short Name section The
main Name
section must appear as normal.
The ledger defaults to Accounts Payable.
Enter the currency to be used when paying the supplier. This defaults to GBP.
If the supplier is
to be paid in a foreign currency the Currency Code, Invoice Currency and
Payment
Currency sections should be amended to the relevant currency. Click on Find
and select
accordingly.
Click on OK
2. Click on Address
Enter the address, including the postcode.
Click on OK
(If setting up a self-employed guardian the address should not be entered here
but instead
the word PRIVATE should be typed on the first line once the supplier set-up
has been
completed click on oasystem > Company > Guardian Address Maintenance.
Click on
Query to locate the guardian, click on Modify, enter the address and click on
OK)
3. Click on Contacts
Enter the contact details that have been provided including email address.
4. Click on Payment
Tab down to Payment Method
Click on Find to choose the appropriate payment method. If the payment is to be
made in a
foreign currency then D (direct debit) should be selected.
105
If BACS is selected as the appropriate method of payment enter the bank sort
code and
account number ensuring there are no gaps in the figures entered and that the
account number
has eight digits.
There is no need to enter any account details if payment by cheque is selected.
Once completed, click on OK
5. Click on Codes
Tab down to Supplier Type
Click on Find to choose the appropriate supplier type (VEND for vendor, GUA for
guardian
etc).
Once completed, click on OK
6. Click on Tax
Enter Supplier Tax Registration number (if available)
Payables > Maintenance Routines > Supplier Maintenance > Supplier File
Print
The supplier file print should then be attached to the original paperwork and
passed to another
member of staff on the section who will check that the details have been entered
correctly
before signing them off.
Once all the details have been checked as correct an email must be sent to the
originator of the
supplier form advising that the supplier has been set
106
****
107
The supplier file print should then be attached to the original paperwork and
passed to another member of staff on the section who will check that the details
have been amended correctly before signing them off.
The details should then be filed in the Change of Bank Details & Addresses file
in date order.
****
Guidance on Interpreters
Objective:
This guide is designed to clarify the following:
The process for booking an interpreter
Finance implications/requirements
Process:
Translation/interpreters services fall into 3 broad categories all of which are National
Contract awarded to Thebigword. These are as follows:
1. Telephone Interpreting
2. Written Translation
3. Face to Face interpreting
Please note before booking any of the above services listed the Service Manager
(SM) must be consulted so that they can consider whether there is a business need
and approve accordingly.
1) Telephone Interpreting
108
This type of interpreting is useful for unusual languages or for short notice when face
to face interpreters can be difficult to obtain.
Thebigword has set up access codes for each of the Cafcass Offices (These can be
viewed on the intranet, link shown below). This access code will need to be quoted
when a Translator is required.
A Telephone Translation Booking Form and instructions are available to use for this
process on the intranet.
Please note Dual Handsets are available for the purpose of telephone translation. If
required these can be purchase from Thebigword for 10 + VAT.
2) Written Translation
We also have a framework with Thebigword for written translation. A Written
translation booking form is available under the Procurement Section of the intranet; it
also contains information on pricing etc.
3) Face to Face Interpreting
As from 1st June 2012 Thebigword were awarded the National Contract for the
supply of Face to face interpreters. June 2012
109
All interpreting requests should now be booked on line and all documentation, the
booking website and guidance on how to use Thebigword is available on the
procurement section of the Intranet. Please click on the following link to access this:
http://cafcassintranet/Intranet/departments/procurement/national_supplier_informatio
n/interpreters__translation.aspx
Finance Implications/Requirements:
As mentioned earlier the Service Manager (SM) must be consulted so that they can
consider whether there is a business need and approve use accordingly.
The SM then must inform the Office Manager (OM) that the service has been
agreed. This is important as the OM hold the budgetary responsibility for
Interpretation costs and hence need to be aware of the forthcoming costs that will be
incurred.
The invoicing for all the different types of translation for Thebigword has been set up
on a consolidated basis. When the Booking Form on the intranet is used for
accessing Thebigword service, this will directly link in to the invoice received by
CAFCASS. Hence, it is vital that when completing the booking forms that the correct
cost centre is quoted. The Finance Bureau will receive and post the invoices into the
accounting system and the Area Finance teams will then receive a report with the
breakdown of jobs invoiced for that month, which will in turn be made available to
budget holders to review.
As we have a contract with Thebigword, their service must be used as they have
been selected as a preferred supplier as they offer quality service and competitive
pricing.
If Thebigword are unable to provide the services required then only in exceptional
circumstances should any other supplier be used. You must seek authorisation
first from the OM and provide the following details so that they can raise a PO in
advance and check that we have been charged correctly when the invoice comes in:
Date and time of the service to take place
Case details
Price per hour
Estimated time of use of service (including travel time if relevant)
If using a supplier for the first time that is not on our system, then again you must
seek authorisation from the OM as they must be informed that this is the case as
they will need to set the supplier up on the system first, before they can raise the PO
and pay the invoice.
It is imperative that a PO is raised in advance as this acts as the authorisation of
costs and helps OMs mange the translation/interpreters budget effectively.
110
111
4.3 Delivery and Collections from any UK mainland options are available and are
included in the daily charge.
5.0 Fuel and Accounting for Business Mileage
5.1 All cars should (usually) be provided with a full tank of petrol or diesel. Should a car
be provided with less than a full tank of fuel, take note of the level of fuel (inform
Leasedrive immediately upon receiving delivery of the car) and when the car is returned
refill the tank back to the level it was when delivered.
5.2 CAFCASS will reimburse the individual for all business mileage travelled in the hire
car. The reimbursement is as per the Expenses Reimbursement Policy and must be
claimed for via iTrent Travel and Subsistence (T&S) electronic submission.
5.3 CAFCASS does not pay towards the cost of fuel top ups or reimburse the actual
cost of fuel even when a receipt is produced. Where a vehicle is returned to Leasedrive
and it requires a fuel top up it is the responsibility of the individual to pay this.
5.4 It is the responsibility of the driver to ensure that the correct fuel type is used to refill
the car. If there is no visible proof of which type of fuel to use please contact Leasedrive
request it and to log a formal complaint, as this should be clearly indicated on the hire
car.
5.5 The driver will be liable for any traffic offence (i.e. parking, speeding fines etc)
committed in the hire car during the period of hire; this will also include any
administration fee charged by the hire company.
6.0 Definition of business mileage
6.1 Business mileage is defined as mileage carried out in the performance of CAFCASS
duties. This does not include home to work mileage.
6.2 If the vehicle is collected or returned by the individual, this counts as business
mileage.
7.0 Controls & Safeguards
7.1 The Account number and Cost Centre number must be quoted for all bookings:
The Cafcass account number is: ZC213
7.2 Car hire will be limited to three days. The driver should inform the Area Finance
Manager or National Office Department Heads if they plan to exceed the existing car
hire beyond 3 days.
7.3 Car keys MUST not be left in unsecured places e.g. under flowerpots, wheel bins,
etc. The keys must be handed over by an individual, as we are not insured for leaving
the keys unattended.
8.0 Options to consider before hiring a car via Leasedrive: Cafcass Car Hire Policy Full
Implementation July 2012 Page 3 of 4
112
113
YEAR END
TECHNICAL
GUIDANCE
2012-13
114
CONTENTS
Terms of reference
Page
1.
Introduction
04
2.
05
3.
Accruals
07
4.
General accrual
Travel and Subsistence and Time claim accrual
Government Procurement Cards (GPC)
Consolidated Invoices
Prepayments
07
10
12
12
13
5.
14
Journals
14
Operating Leases
14
Accrued Income
14
Capital Commitments
15
Provisions
Contingent Liabilities
15
16
17
Fixed Assets
17
17
6.
18
7.
21
115
Terms of reference
1.
Areas or Area refers to (1) Operational Service Area (OSA), (2) National
Business Centre (NBC), (3) National Office (NO) Departments which
includes National Improvement Service (NIS), Estates and
Accommodation (EST and ACC), and HQ departments.
2.
Finance teams refers to (1) Area Finance team for Operational Service
Areas and National Business Centre, (2) Estates and NIS Finance for
Estates projects and Accommodation and NIS; (3) HQ finance team for
HQ Departments.
116
1.
INTRODUCTION
1.1
The Year End process is a series of accounting, financial and auditing tasks, which
st
st
are carried out at the end of the financial year for the period 1 April 2012 to 31
March 2013, to deliver the 2012/13 Annual Report and Accounts of Cafcass. The
publishing of an Annual Report and Accounts is a requirement of the Financial
Memorandum and Accounts Direction between the Department for Education (DfE)
and Cafcass; it is also a key target of the Public Accounts Committee, National
Audit Office (NAO) and Parliament to publish the Accounts before the summer
2013 Parliamentary recess.
1.2
Cafcass produces accounts on an accruals accounting basis, both during the year
and at Year End. This means we account for the goods and services used in the
period regardless of when the goods have been paid for.
1.3
The de minimus limit is the minimum value of the transaction to be included in the
returns. Each return will have its own de minimus limit.
Accruals are goods and services used but not paid for in the financial year ending
st
31 March 2013. An accrual is made when the amount to be accrued is 500.00 or
st
greater for goods and services received before 1 April 2013. Please see section 3
for examples of accruals.
1.5
Prepayments are expenses paid for but not yet consumed in the financial year
st
ending 31 March 2013. A prepayment is made when the amount prepaid is 500.00
st
or greater for goods or services not consumed before 1 April 2013. Please see
section 4 for examples of prepayments.
1.6
1.7
Operating Lease data represents property and equipment rentals such as land,
buildings etc. Details required are the values of the leases split into 12/13 spend
st
st
and the amounts Cafcass is committed to pay within one year (1 April 2013 to 31
st
st
st
March 14), within 2-5 years (1 April to 31 March 2018), and after 5 years (1 April
2018 onwards).
1.8
1.9
1.10
After collation of the above and other Finance schedules, the data on the
accounting system and returns will be subject to scrutiny by the NAO,
117
whose audit work will extend to visits to Operational Area offices. The
NAO will also examine and comment on the quality of Cafcass Internal
Controls at National Office, Finance Bureau and Operational Area offices.
1.11
Subject to the favourable outcome of Operational Area and corporate audits, the
objective is that the NAO will recommend an unqualified certification on the
Cafcass Annual Accounts. Cafcass would want to avoid a qualified
recommendation as that indicates significant weaknesses in Cafcass systems and
operations.
2.
2.1
The procedures that follow aim to deliver the information needed in the
most efficient way possible. The key to achieving this will be adequate
controls in local offices to ensure that accurate data is produced in a
timely manner. To enable Cafcass to meet its timetable electronic returns
should be sent to NO Finance. Please retain a copy for local and audit
purposes.
2.2
Prior to the Year End period, two electronic E-Learning Year End
packages will be made available via MySkills to train Office Managers/
budget holders as well as Business Support staff so that they fully
understand their role within the Year End process. Budget holders and
budget managers will be informed of the outcome of the training and of
any actions required as a result of the training. In addition, budget holders
and budget managers will be briefed about the Year End procedures and
processes during February/March 2013 and about the provisional Year
End outturns in April 2013 by the Area Finance Manager and NO Financial
Accountant/Finance Officer via Operational Management Meetings/HQ
team meetings. Minutes of such meetings must be kept and provided to
NO Finance when they are available. Together with the use of Budget
Delegation Letters and the Financial Manual, this serves as a control to
ensure the accuracy and completeness of the annual accounts.
2.3
2.4
2.5
The Year End adjustments for 2012/13 will affect the 12/13 Outturn i.e.
budget variances and the 13/14 Budgets as well. The timetable aims to
ensure that 2012/13 outturn is available in local cost centres by the end of
April 2013, and that brought forward balances are stable by June 2013.
2.6
As part of the Year End procedure, various returns (including Accruals and
Prepayments) need to be carried out. These are detailed in the schedule
below. Not all the returns are applicable to every cost centre, but where
returns are required these must be completed even if the return is NIL.
2.7
The AFM and NO FA/FO must collate and check each type of return for
their Areas. AFM and NO FA/FO should only submit their data in one
electronic consolidation by saving all Final Electronic Copies in the
Restricted Finance Folder and send a confirmation email to NO Finance.
Once NO Finance receives the return, they will lock the return to save a
copy of the original submission for auditing purposes.
2.8
2.9
Completion of these returns also allows local teams and their Finance
teams to monitor accruals posted against actual invoices processed post
March 2013.
2.10
All cost centres must keep Final Electronic Copies of all their returns as
well as the copies sent to the AFM and NO FA/FO.
2.11
AFM and NO FA/FO are responsible for ensuring that the returns are
completed correctly and that the figures look reasonable and are fully
backed up by appropriate backing documents.
119
Returns required
Applicable to
Prepayments
Operating Leases
Accrued
Debtors)
Income
(Deferred
Provisions
Area
NO
Area
NO
Area
NO
Area
NO
Area
NO
Area
Board Members
CMT.
ACCRUALS
General Accruals
04th April 2013: A single consolidated electronic copy received by NO
Finance.
05th April 2013: Supporting documents for items over 5000 received
by NO Finance.
08th April 2013 Midday 12 pm: Deadline for adjustments (only where
significant) submitted as additional returns
08th April 2013: Supporting documents for items under 5000 received
by Business Assurance Team
Where applicable nil Electronic Copy returns are required for control
& audit purposes.
The De minimus limit for Accruals is 500
120
3.1
This return applies to all Cafcass cost centres. An accrual is a liability (or a
commitment) to pay for goods or services after the goods or services have
been consumed e.g. the goods or services have been received or utilised
in the period 1st April 2012 to 31st March 2013, but the invoice has not
been paid before 31st March 2013. If there are accruals created prior to
12/13 that is still being re-accrued e.g. Accruals created during the 11/12
Year End or earlier, please discuss these with NO Finance before reaccruing.
3.2
3.3
The monthly outstanding purchase order report and the purchase order
report of items being GRNed without receiving invoices will be available
for use on 25th March 2013. This report can be used to identify which
purchase orders remain outstanding as at 31st March 2013 and whether
goods/services have been received by 31st March 2013 and which
commitments needs to be accrued. At the end of the financial year it is
important to make accruals as accurate as possible so that the outturn and
accounts accurately reflect the resources consumed during the financial
year.
3.4
3.5
121
Amount
122
3.6
3.7
The figure on the return should include VAT and split correctly between
actual amounts and estimated amounts (see Appendix 1 for example)
3.8
123
2
3
3.10
3.12
3.13
Please note that accruals data will be audited by the NAO for accuracy
and completeness as part of the Year End audit and that our published
accounts could be qualified e.g. considered materially inaccurate, if the
data viewed by the NAO is deemed to be significantly inaccurate.
Travel and Subsistence (T&S) accruals and Time claim accruals (i.e.
Overtime & Bank and Sessional Staff claim accruals)
3.14
Staff should ensure that as far as possible that 12/13 T&S and time claims
are submitted and authorised by relevant managers via Itrent by the 7 th
March 2013, to ensure that they are processed and paid in the March
main payroll run. If this deadline is missed staff should ensure the April
main payroll run deadline is met i.e.T&S and time claims to be submitted
and authorised by relevant managers via Itrent by 7 th April 2013).
3.15
Unlike last year, NO Finance will NOT be using the T&S and time claim
data from the April pay run as the T&S and time claim accruals for 2012-
125
13. AFM and NO AF/FO for NO Departments must to accrue for ALL
unpaid claims and include them in the returns.
3.16
Any claims of 100.00 or greater relating to 2012-13 that miss the March
main cut-off e.g. be submitted and authorised by relevant managers via
Itrent after 7th March 2013 should be included on the T&S and time claim
accruals return by the finance teams. A claim history report will be issued
on 3rd April 2013 to identify all claims that are submitted and authorised
by 12pm on 3rd April 2013 but are not paid in March 2013 or earlier
months. The report will be the basis for accrual based on actual claims.
This T&S and time claim accruals made should be listed per employee.
Please note per Cafcass policy that in general T&S claims greater
than 3 months old are not accepted and therefore should not be
accrued unless being duly authorised.
3.17
Where T&S and time claims have not been authorised by relevant
managers via Itrent by 12pm on 3rd April 12 and hence not been
included in the Claim history report, an estimate should be made of the
amounts outstanding and entered onto the T&S and time claim accruals
return. The estimate for T&S accruals must be supported e.g. based on
known travel or an estimate based on the average of the previous 3 claims
with the workings clearly shown on the front sheet and backed up with the
appropriate supporting documentation. The estimate for time claim
accruals must be based on either (1) known overtime or (2) the volume of
work estimated by the authorising manager or (3) the average of the
previous 3 claims with the workings clearly shown on the front sheet and
backed up with the appropriate supporting documentation.
These
accruals made should be listed per employee. Please refer to section 6 for
details of backing documentation required.
Local teams/NO Departments have the responsibility to notify their
Finance teams about cases where T&S and time claim accruals are not
required such as the employee has been on sick leave, maternity leave or
they have confirmed no claims incurred during the month etc. AFM and
NO FA/FO will circulate internal deadlines for these activities of local
teams/NO Departments.
3.18
126
Post Year End Check: Please note that completion of this column does
not form part of your Year End return but may be used for ongoing checks .
Please enter the actual amount paid after 31st March 2013.
3.19
Natural Account Code: Please use the pull-down menu to enter the
appropriate Natural Account Code:
300112 Bank Staff.
300320 Misc. Allowances.
300400 Overtime.
300111 - Sessional staff
Employee/Bank Staff/Sessional staff Name: Please enter the name of
the individual to whom the overtime/bank/sessional hours relate.
Payroll No: Please enter the payroll number for the individual to whom the
overtime or bank/sessional hours relate.
Employee/Bank Staff/ Sessional staff Name: Please enter the name of
the individual to whom the overtime/bank/sessional hours relate.
Brief Description: Please enter the name of the staff, the month of
claim, number of hours worked by each employee and the estimated
hourly rate.
Amount Excluding Pension & NI: Please enter the total value of the
overtime / bank staff/sessional staff costs excluding pension and NI costs.
Amount Including Pension & NI: This is a formula-driven column adding
23.7% to your overtime / bank staff costs. Please do not input any data
in this column.
Post Year End Check: Please note that completion of this column does
not form part of your Year End return but may be used for ongoing checks .
Please enter the actual amount paid after 31st March 2013.
3.20 T&S accrual for Operational Service Area and NBC are completed by Area
Finance whereas the NO Financial Accountant and Finance Officer will
complete the return for HQ teams and NIS. Once your accruals return is
complete, save the electronic returns with supporting documentation for
any items included on it (including estimates) in the relevant folder as
directed by NO Finance by the required deadline and email the NO
finance mailbox confirming the submission.
3.21 Please note that accruals data will be audited by the NAO for accuracy
and completeness as part of the Year End audit and that our published
accounts could be qualified e.g. considered materially inaccurate, if the
data viewed by the NAO is deemed to be significantly inaccurate.
127
3.28
As per normal monthly procedures, NO Finance will accrue for all GPC
costs incurred on the March 28th 2013 GPC statements. Operational
Areas and NO departments should not accrue for these costs.
3.29
Consolidated invoices
3.30
Finance Bureau will post ALL monthly consolidated invoices into period 1
2013/14 and NO Finance will accrue for all consolidated invoices based
on the invoice break-down per cost centres provided by the suppliers.
3.31
4.
PREPAYMENTS
04th April 2013: A single consolidated electronic copy of each area
received by NO Finance.
05th April 2013: Supporting documents for items over 5000 received
by NO Finance.
08th April 2013 Midday 12 pm: Deadline for adjustments (only where
significant) submitted as separate returns
08th April 2013: Supporting documents for items under 5000 received
by Business Assurance Team
Where applicable nil Electronic Copy returns are required for control
& audit purposes.
The De minimus limit for Prepayment is 500
4.1
4.2
128
4.3
This return will be required from all cost centres, this may be in a form of a
nil return.
4.4
4.5
If the invoice paid has items that relate to two financial years, only the
element relating to the future period should be included on the return.
For example, an invoice paid in March 2013 for an alarm maintenance
service which pays for 1 March 2013 to 28 February 2014 and for a piece
of equipment replaced in March 2013. Only the prepayment element of
the payment should be recorded in the Prepayment return i.e the
alarm maintenance services costs. The cost of the equipment
replaced will not be entered on the prepayment return.
4.6
4.7
4.8
Please note that prepayments data will be audited by the NAO for
accuracy and completeness as part of the Year End audit and that our
published accounts could be qualified e.g. considered materially
inaccurate, if the data viewed by the NAO is deemed to be significantly
inaccurate.
Journals
Until 4th April 2013: Standard journals only may be posted by the Finance
teams until close of this date. Please check with your AFM or NO FA/FO for
the deadline for OMs.
129
5.1
Standard journals only may be posted by the AFM and NO FA/FO until the
close of the 4th April 2013. No reversing journals should be posted into
March 2013. After this date, only NO Finance will be allowed to post
journals to General Ledger.
5.2
Please note NO Finance will create and post all year end returns journals,
mainly the accruals, prepayments and accrued income.
Operating Leases:
28 March 2013: Single electronic consolidated return for each Area received
by NO Finance, consisting of a copy of the contract\Agreement\Invoice in
PDF format referenced to the consolidated electronic return.
5.3
This return applies to all cost centres for the 12 month period. The Finance
teams must collate these returns and ensure that NO Finance is in receipt
of electronic copies by the above deadline date. This is an update of the 9
month return which is due on the 21st December 2012.
5.4
The Finance teams will advise their local teams/NO Departments of the
deadline for the submission of team information
5.5
5.6
5.7
Details required are the values of the leases split into 2012-13 spend and
the total annual amounts Cafcass is committed to pay within one year (1st
April 2013 31st March 2014), within 2-5 years (1st April 2014 to 31st
March 2018) and after 5 years (1st April 2018 onwards). Please include
the date of expiry of the lease.
Example (as given on template): A photocopier is leased on the 1st April
2010 on a 9-year lease at a cost of 5,000.00 per annum with no annual
adjustment to the lease cost for inflation.
Lease Amount Due 2012-13: 5,000 x 1, therefore enter 5,000.
Date Lease Expires: A 9-year lease commencing 1st April 2010 would
expire 31st March 2019, therefore enter 31-03-19.
Lease Amount Due 13-14: 5,000 x 1, therefore enter 5,000.
Lease Amount Due 14-18: 5,000 x 4, therefore enter 20,000.
Lease Amount Due After 31-03-18: 5,000 x 1, therefore enter 5,000.
130
Accrued Income
04th April 2013: A single consolidated electronic copy received by NO
Finance.
05th April 2013: Supporting documents for items over 5000 received by NO
Finance.
08th April 2013 Midday 12 pm: Deadline for adjustments (only where
significant) submitted as separate returns
08th April 2013: Supporting documents for items under 5000 received by
Business Assurance Team
Where applicable nil Electronic Copy returns are required for control &
audit purposes.
The De minimus limit for Accrued Income is 500
.
5.8
This is income created during the period 1st April 2012 31st March 2013,
which has not been invoiced as at 31st March 2013.
5.9
The AFM or NO FA/FO should compile a total listing of all Accrued income
for their areas. Finance teams will advise their local teams/NO
Departments of the deadline for the submission of team information.
5.10
All team returns must be sent to and collated by their Finance teams.
Capital Commitments
Further guidance will be emailed to specific users on 1 March 2013 by NO
Finance for returns to be received by 22 March 2013.
5.11 In general this applies to NO Finance, NO IT and NO Estates and
Operational Areas.
5.12 Definition of Capital Commitments:
Fixed asset items are defined as laid out in the Fixed Asset section of the
Cafcass Intranet:
http://cafcassintranet/Intranet/departments/finance/finance_manual_new/a
sset_management_new.aspx
The commitment will be funded from the 2012-13 or post 2012-13 capital
expenditure budgets.
Payments in relation to the commitment have not been made by the 31st
March 2013.
Goods in relation to the commitment have not been received by the 31st
March 2013.
Any unsigned contracts for fixed asset purchases that have been
approved by the Board and for which the contract amount is certain.
Please note that (for these purposes) capital commitments do not include
capital items that has been received or paid for in 2012-13.
5.14
Provisions
Further guidance will be emailed to specific users on 1 March 2013 by NO
Finance for returns to be received by 22 March 2013
.
When reviewing provision details, the following will need to be considered:
5.15
5.16
Are there any new obligating events for which provisions need to be created as
at 31st March 2013? New provisions should only be created when all of the
following conditions can be met:
a. When the event in question has occurred by the 31st March 2013.
b. When payment by Cafcass for this event will only be decided by the
occurrence (or non-occurrence) of another event in the future (after the 31st
March 2013).
c. When that future event is not wholly within the control of Cafcass.
d. When payment by Cafcass for the event in question can be enforced by law.
OR
e. When based on the available evidence, experience, and / or the opinion of
experts there is a valid expectation of payment by Cafcass.
f. When a reliable estimate can be made as to the amount of the provision.
132
5.17
5.18
5.19
Contingent Liabilities
Further guidance will be emailed to specific users on 1 March 2013 by NO
Finance for returns to be received by 22 March 2013
5.20
A contingent liability should only be created when both of the following conditions
can be met:
a. When the event in question has occurred by the 31st March 2013.
b. When it is unlikely based on the available evidence, experience, and / or
the opinion of experts that there will be payment by Cafcass.
5.21
Please note that there is no financial impact with regards to contingent liabilities.
They are shown in the Accounts in narrative form only.
5.22
5.23
133
5.24
March 2013 electronic Petty cash returns are to be completed for all
cost centres holding a petty cash float, and forwarded to Finance
Bureau via the Area Finance team.
5.25
Reconciliations will be required at Year End for all petty cash floats, as per
the monthly returns requirements.
5.26
Returns should be submitted to the Area Finance team. The Area Finance
team should send all Petty Cash returns after checks and reviews to
FINANCE BUREAU by the above deadline.
Fixed Assets
Further guidance will be emailed to specific users on 1 March 2013 by NO
Finance for returns to be received by 22 March 2013
5.27
5.28
5.29
In order to complete this exercise, FMs and NO Dept Heads will need
to ensure that they are familiar with the Cafcass Fixed Asset Policy &
Procedures, a copy of which can be found on the Cafcass Intranet
under the following link:
http://cafcassintranet/Intranet/departments/finance/finance_manual_
new/asset_management_new.aspx
Please do not hesitate to contact NO Finance should you have any
queries relating to Fixed Assets.
5.30
Fixed Asset returns (FAMFs & their supporting documents) will in the main
apply to NO IT, NO Estates and Operational Areas undertaking building
fit-out projects where the project has been classified as containing capital
costs.
5.31
In the event of there being no Fixed Assets costs, an emailed nil return is
required from specific user guidance recipients only.
5.32
As per the Policy & Procedures NO Finance will check all received
FAMFs. Further to this, NO Finance will also prepare and post all General
Ledger journals relating to Fixed Assets.
134
22nd March 2013: FINANCE BUREAU must receive all invoices and receipts
by this date to ensure that they are accounted for in the March 2013
accounting period (e.g. Paid for or receipted by 31st March 2013).
5.33
Please note that the 22nd March 2013 is the date by which FINANCE
BUREAU must receive all invoices and receipts to be accounted for in
March. Operational Area and NO departments will need to ensure that all
such invoices and receipts are posted/sent in good time in order to ensure
receipt by FINANCE BUREAU. Given the early closure of Accounts
Department for Year End, it is encouraged to email the invoices to
Cafcass Finance mailbox for processing with the GRN details and PO
number and Supplier number written on the invoices or in the body of the
email.
5.34
To enable both National Office Finance and the National Audit Office to
audit the Year End Accounts effectively all backing documents should
clearly show all workings clearly and the amount of each entry listed
on each return must match the figure/calculation shown on the
supporting documents.
6.2
6.3
5000
(including
all
supporting
documents
for
T&S
and
Overtime/Bank/Sessional accruals) must be saved in the following
directory: G:\CAFCASS\HQ\Finance\Restricted\Year end 2013.
Once all electronic returns and backing documents have been saved local
teams need to send an email to their Finance teams about the
submission. Similarly, AFM and NO AF/FO need to email NO Finance
mailbox about their submission once their consolidated electronic returns
and backing documents are saved.
6.4
Points to Note:
6.5
6.6
All back up sheets should be numbered, in the top right hand corner, with
the corresponding line number from the consolidated returns.
6.7
6.8
All officers responsible for collating year end returns should ensure that
invoices are chased in March, purchase orders and GRNs are raised and
T&S claims are submitted up to date.
6.9
6.10
6.11
General Accruals
6.12
If you have 2 or more invoices for one supplier and the amount entered in
the return is collective figure of all the invoices then this must be clearly
shown on the first invoice (please see Appendix 1 for an example)
6.13
136
knowledge of the invoice value expected, please adjust the amount on the
report and your template showing your workings/reasoning for the
adjustments. The GRN no invoice report should be attached as back up,
with the relevant items numbered on it, on the right hand side.
6.14
An approved and GRNd purchase order. (If necessary, amended and signed off
by the authoriser, for more up to date costs, preferably with correspondence from
the supplier). The relevant entries on the purchase order must be highlighted and
calculation of total accrued amount (VAT included) (if there is more than 1
entry on the purchase order to be accrued) must be clearly shown on the face of
the purchase order. And the accrued amounts on the return must match the
calculated figures shown on the backing documents (please see Appendix 1 for
an example)
6.15
Where it is not possible to obtain actual cost information for accrual, accrual can
be made on estimated basis using the last three months invoices. In this case,
copies of all previous three months invoices should be attached with calculations
shown clearly on the face of the first document. The average shown in the
calculation should match exactly with the amount accrued; the amount accrued
should not be adjusted/inflated unless there is evidence to show the need for
adjustment (please see Appendix 1 for an example).
6.16
For estimated accruals greater than 5,000.00 a purchase order alone will
not be sufficient, additional supporting evidence must be provided i.e. a
contract or an agreement where such contract or an agreement exist. This
could be in the form of an email from the supplier confirming the amount
etc. Please note the requirement for additional supporting documents to
the PO does not apply to Self Employed Contractor and Agency
practitioners/temporary staff costs.
6.17
6.18
137
the spreadsheet match with claim data stored in Itrent/Payroll system and claims
can be retrieved to back up those calculations if required. The average shown in
the calculation should match exactly with the amount accrued; the amount
accrued should not be adjusted/inflated unless there is evidence to show the
need for adjustment.
6.19
Prepayments
6.20 A copy of the relevant invoice, showing the dates entered into the return
template.
Accrued Income
6.21
6.22
Operating Leases
6.23
6.24
Where above is not available supply last paid invoice and state what the annual
cost is.
Only enter total annual cost in the return template.
6.25
6.26 Enter date in this format dd/mm/yy only; do not use dot or space as the
separator.
If you do not have the contract or agreement, as a minimum obtain an end date
from the supplier.
6.27
You must not leave the contract start and end dates blank. If the contract does
not have an end date then enter the end of the next financial year end date 31st
March 2014.
138
7.
7.1
Once each cost centre has completed each type of return, they will
provide you with a electronic copy with backing documentation in PDF
format, split in two files for each type of return (one file containing all items
over 5000 and one file containing items under 5000 if applicable).
7.2
All returns must be collated by type by the Finance teams for each Area
and once collated and reviewed; the PDF File should be saved in
G:\CAFCASS\HQ\Finance\Restricted\Year end 2013 (nil returns included).
7.3
Once you have received each type of return from local teams/NO
Departments, you are required to carry out accuracy and completeness
checks before you save them in the Restricted folder. This checking is
required to give NAO the assurance they need that returns are being
monitored thoroughly.
7.4
7.5
Completeness checks: you must check that all cost centres have
submitted a return, including NIL returns, for all returns that are
applicable to them. You must also ensure that all boxes and authorisation
sections of each form have been completed.
139
7.9
Further to this you must also ensure that all cost centres, natural account
codes and values have been entered in the correct format, as incorrect
entries can corrupt and distort the results produced as a whole.
7.10
Once you are content that both checks have been completed, you must
save the returns (by type) as mentioned in section 7.2 by the due date.
7.11
Please also retain copies of returns for information and for possible
checking by the NAO during the audit of the published accounts. NAO
may also require you to demonstrate what checks you have completed on
the returns to ensure they are accurate and complete.
140
141