Commissioning Guide

For a
New UPS System

This document is a detailed guide for Commissioning of a new Uninterruptible


Power Supply system (UPS). The commi ssioning is best performed by an
independent, third party, commissioning agent (CA) that is not employed by
either the equipment vendor or the installer. The equipment vendor's service
technician is expected to be part of the testing procedures, and the installer
should be on site to correct any in stallation issues should any arise.
1. Pre-installation
1.1. Client should schedule a pre-installation meeting between consultant
engineer, vendor, installer, and commissioning agent (CA) to review
equipment details, installation and startup plans, and commissioning.
1.2. CA will review vendor
1.3. Vendor's startup guide as purchased by client and make any
recommendations.
2. Installation Inspection
2.1. CA will perform one or more site visits during equipment installation to
inspect progress and provide any comments to client as appropriate
concerning general nature of equipment and installation.
2.2. Client's consulting engineer is responsible for any electrical code
requirements and any potential issues.
3. Vendor Startup of New UPS
3.1. CA will observe vendor's startup and review technician's FSR upon
completion.
4. Commissioning
4.1. The commission procedure may be incorporated into the vendor's startup
procedure, but activity will be supervised by CA.
4.2. Either at time of and part of initial startup or as separate procedure
following vendor startup, the SOW of final commissioning is as follows:
4.2.1. Observe and review vendor's startup procedure

Critical Power Resource, LLC 5868-A Faringdon Place Raleigh, NC 27609-3931


DUNS# 10-579-5418 (PH) 919-844-6447 (FX) 919-844-9845 www.cpr-nc.com

4.2.2. Instruct installer to connect load banks of the size as previously


decided by client (Load banks to be furnished by installer, CA, or
installer as previously decided).
4.2.3. Follow detailed SOW to insure all power is off at all connection
points prior to load bank hookup.
4.2.4. With UPS running, put load on UPS via load bank in steps and
observe UPS performance as load is increased to planned maximum.
4.2.5. Perform followi ng tests as detailed in commissioning SOW:
4.2.5.1. Check all UPS input and output voltage and currents for
accuracy with vendor's calibrated instrument.
4.2.5.2. With battery fully charged, perform a battery run down test for
the designed run time to verify battery performance.
4.2.5.2.1. Battery should initially
provide run time as purchased at
80% of designed load and will improve performance over time
after startup.
4.2.5.2.2. Take DC Tests of ba
ttery amperage and voltage
measurements every one minute to establish an initial
performance curve.
4.2.5.2.3. Perform IR scan on ba
ttery to detect heat and any
possible hot spots.
4.2.5.3. Vendor's startup procedur e should include the following at
minimum
4.2.5.3.1. Tests of alarm functions
4.2.5.3.2. Operation of transfer
s between by[pass and inverter
4.2.5.3.3. IR scan of UPS comp
onents during full load operation
4.2.5.3.4. Condition of room
environment at UPS location
4.2.5.3.5. Check of UPS and batte
ry input current limits if
applicable
4.2.5.3.6. Efficiency measureme
nt of UPS with battery fully
charged (or disconnected)
4.2.6. Inspect UPS room for proper cleanliness and removal of installation
materials by installer.
4.3. Provide final report to client noting any issues and recommendations.