Академический Документы
Профессиональный Документы
Культура Документы
183
These configurations are based on a serie of activities that are listed below. The engineering firm,
the pipe support supplier, the contractor or pipe fabricator performs each activity according to the
configuration that is being studied.
Activities
1. Route Pipe
2. Locate Pipe Supports
3. Identify Preliminary Pipe Support Loads
4. Get Preliminary Pipe Support Loads
5. Perform Pipe Flexibility Analysis
6. Define Pipe Diameters and Schedules, Valve Weights and Lengths, etc.
7. Refine Pipe Support Loads
8. Get Final Pipe Support Loads
9. Perform Pipe Stress Analysis
10. Select Supplier in Advance
11. Select from Catalog
12. Special Pipe Support Design
13. Check Interference
14. Check Loads Structural Steel
15. Coordinate Reinforcement
16. Reinforce Structure
17. Issue New Detail Drawings for Structural Steel
18. Prepare Pipe Support Detail Drawings
19. Investigate Potential Suppliers
20. Prepare Information for Pipe Support Supplier
21. Issue Request for Quotation
22. Analyze Information from Engineering Firm
23. Advise Suppliers
24. Convert Specifications to Supplier Standards
25. Prepare Budget for Approval
26. Approve Budget & Conversions
27. Check Schedule Priority
28. Issue Pipe Support Detail Drawings for Fabrication
29. Approve Drawings
30. Fabricate Pipe Supports
31. Ship to Shop Fabricator
32. Ship to Site
33. Advise Contractor/Pipe Fabricator
34. Release price
35. Ok Price
36. Analyze Information from Contractor
184
Decision Nodes
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
First Analysis?
Stress Analysis OK?
Can Supports be Relocated?
Special Design or Catalog?
Design Support Feasible?
Support Available in Catalog?
Interference Check OK?
Are Loads OK?
Is Structural Reinforcement Possible?
Is Engineering Firm Information OK?
Are Conversions Needed?
Is Contractor Information Ok?
Basically, the configurations require the same activities involved in the design, procurement and
fabrication processes but different parties perform them (supplier, engineering firm, contractor or
pipe fabricator). As a convention, each activity box in the maps has been numbered in order to
identify who has to perform that activity and what activity it is. Engineering-firm activities start
with the code 1, pipe support supplier activities with code 2, contractor activities with code
3 and fabricator activities with code 4. For example, if an activity has code 1-5, it means
that it is performed by the engineering firm and it is the fifth activity on the overall list. The
activity description is as follows:
1. Route Pipe (1-1)
The configurations assume that the Piping Engineer (in other words, the engineering firm)
always performs the task of routing pipes.
2. Locate Pipe Supports (1-2, 2-2)
The engineering firm (or the supplier) has to decide on locations of pipe supports throughout
the pipeline. Those locations have to be shown in a working isometric or piping drawing.
3. Identify Preliminary Pipe Support Loads (1-3, 2-3)
The engineering firm (or the supplier) has to decide on preliminary pipe support loads that
will be imposed on the structure in order to perform the flexibility analysis.
4. Get Preliminary Pipe Support Loads (1-4)
The structural engineer requests the preliminary pipe support loads that will be used in the
flexibility analysis. The structural engineer gets an order of magnitude of these loads.
185
188
28. Issue New Pipe Support Detail Drawings for Fabrication (2-28, 3-28, 4-28)
Supplier, contractor or pipe fabricator prepares a new set of drawings that include
conversions in order to start fabrication.
29. Approve Pipe Support Drawings (1-29)
The engineering firm approves support-detail drawings before fabrication starts.
30. Fabricate Pipe Supports (2-30)
Supplier starts fabrication according with schedule priority.
31. Ship to Shop Fabricator (2-31)
Supplier delivers supports to the pipe fabricators shop according with schedule. Some pipe
supports or some attachments need to be welded to the pipeline before to be sent to site.
32. Ship to Site (2-32)
Supplier delivers pipe supports to the site according with schedule priority.
33. Advise Contractor/Pipe Fabricator (1-33)
The engineering firm advises contractor or pipe fabricator during the interpretation of the
information provided to start the design and fabrication of pipe supports.
34. Release Price (2-34)
Supplier releases the final price of pipe supports to the engineering firm, contactor or pipe
fabricator for approval.
35. Ok Price (1-35, 3-35)
The procurement department of the engineering firm, contractor or pipe fabricator verifies
the final price.
36. Analyze Information from Contractor (3-36)
Supplier analyzes documentation in order to evaluate price, lead times and possible
conversions.
The decision nodes as well as probabilistic forks for both configurations are described as
follows:
a. First Analysis OK?
Used only in configuration 3. The engineering firm performs the activity Route Pipe many
times until admissible results will be obtained in the pipe stress analysis. If this is the first
analysis, the engineering firm starts investigating potential suppliers.
b. Stress Analysis OK?
The engineering firm (or the supplier) evaluates pipe stress analysis results. The process
continues with relocation of pipe supports, if possible, or design of pipe support.
190
191
The following table shows the different symbols used to map the different supply chain
configurations.
Table I.1: Symbols used in Detailed Supply Chain Configuration Maps
SYMBOL
Truck to Site
Procedure
te
Proceed
with
Project?
No
Yes
Repair
Needed?
OTHER SYMBOLS
2
192
Detailed Functional Maps for Pipe Support Case Study (following pages)
Configuration 1: Engineering firm designs pipe supports
Configuration 2: Supplier designs pipe supports, engineering firm does pipe stress analysis
Configuration 3: Supplier fully designs pipe supports
Configuration 4: Contractor takes responsibility for pipe support design and fabrication
Configuration 5: Pipe Fabricator takes responsibility for pipe support design and fabrication
193