Вы находитесь на странице: 1из 17

Typical Exam

Production Technology

One Compulsory question from


Chapter 3 (40 Points)
Attempt three out of the following six
questions (each 20 Points), at least
one question from each category:
Three questions from Chapters 4 to 7,
12
Three questions from the remaining
Chapters

Wellbore Completion Concepts


Professor Bahman Tohidi
Institute of Petroleum Engineering
Heriot-Watt University
Edinburgh EH14 4AS
Scotland
Tel: +44 (0)131 451 3672
Fax: +44 (0)131 451 3127
Email: B.Tohidi@hw.ac.uk
January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

January 04

Introduction

The completion string has already been


designed and the required equipment
are generally in place by the rig site.

Drilling engineer will decide and co-ordinate


drilling programme, casing design, mud
programme, coring, various tests and logs,
cement job, etc.
6

January 04

Introduction

Optimum production/injection performance


Ensure safety
Maximise the integrity and reliability
Minimise the total cost
Others (sand control, corrosion, etc.)
Wellbore Completion Concepts
B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Principal decision areas are:


Bottom hole completion technique
Selection of Production Conduit
Completion String Facilities
Completion String Components

Objectives in the design and completion of


production and injection wells:

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Conceptual Design

Production engineers will take over when the


drilling operation is completed, though they
receive daily drilling reports.

Well completion will follow drilling


operations (though part of it is parallel to
drilling).

Rate of production
Number of wells, their locations, sequence and
depths
Production profile of each well

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Introduction

Reservoir engineering and economical


evaluation will determine:

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Uncertainty and alternative design


8

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

23-27 bit for drilling


18-5/8 casing
Cementing
17-1/2 bit for drilling
13-3/8 casing
Cementing
12-1/4 bit drilling
9-5/8 casing

30 conductor pipe

18-5/8 casing

Cementing
Drilling, if necessary

13-3/8 casing

7liner and cementing, or


9-5/8 casing

Bottomhole
Completion

7 liner
January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

10

10

January 04

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

12

12

Bottomhole Completion Techniques


Screen or pre-slotted completion

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

14

14

11

11

Open hole completion

Bottomhole Completion Techniques


Open hole completion

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Advantages

Disadvantages

No perforation,
production casing,
cementing, logging &
log interpretation
Less rig time
Full diameter hole

No selectivity for
production stimulation
and workover (new
alternatives)
Liable to sand out
Ability to isolate is
limited to the lower part
of the hole

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

13

13

Screen or pre-slotted completion


Advantages

Disadvantages

No perforation or
cementing for the
production casing,
logging & log
interpretation
Less rig time
Assists in preventing
sand production

No selectivity for production


stimulation and workover
Difficult to isolate zones for
production control purposes
Slightly longer completion
time compared to open hole
completions

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

15

15

Bottomhole Completion Techniques


Cemented and perforated casing/liner

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

16

16

Selection of Production Conduit

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Advantages

Disadvantages

Introduces
flexibility allowing
isolation of zones
and selection of
zones for
production and/or
injection

Requires logging & log


interpretation to specify
the actual perforation
zones
Cost of casing, cementing,
logging and perforating
Rig time

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Tubingless casing flow


Casing and tubing flow
Tubing flow without annular
isolation
Casing flow without annular
isolation?
Tubing flow with annular isolation
18

18

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

19

19

21

21

Casing and tubing flow

Advantages

Disadvantages

Advantages

Disadvantages

Larger flow area


Cost of tubing
and rig time
High flowrates
Simplicity
Ease of logging
and workover

Flow segregation
Difficulty in killing the
well (squeezing or volumetric)
Casing exposure to
high pressure
Corrosion and erosion

Larger flow area


Cost of packer
and rig time
High flowrates
Simplicity

Casing exposure
to high pressure
Corrosion and
erosion

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

17

Alternatives for a single zone


completion:

Tubingless casing flow

January 04

17

Selection of Production Conduit

Parameters in selecting:
Cost
Flow stability
Ability to control flow
Well safety

January 04

Cemented and perforated casing/liner

Ease of circulation
Kick-off
Gas lift
20

20

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Tubing flow without annular isolation

Annulus flow without annular isolation

Advantages

Disadvantages

Advantages

Disadvantages

Cost of packer
and rig time
Simplicity

Casing exposure
to high pressure
Corrosion
Annulus heading

Cost of packer
and rig time
Simplicity

Corrosion

Ease of circulation
Kick-off
Gas lift
January 04

Ease of circulation
Kick-off
Gas lift

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

22

22

January 04

Disadvantages

Flexibility

Cost

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

24

24

Completion String Facilities

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

25

25

The pressure and flow


are contained in:

Pressure and flow containment


Annulus isolation
Downhole closure of the flow string
Circulation capability
Tubing isolation

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Complexity and reliability


Identifying minimum requirement
Incremental complexity vs incremental benefit
Design factors in high operating cost areas

Pressure and Flow Containment

Essentials

January 04

23

Essentials: Those providing operational


security or safety
Non-essentials: Those providing improved
performance and flexibility

Packer close to the top of the


reservoir
Sliding Side Door or perforation for
circulation
Widely used

January 04

23

Completion String Facilities

Tubing flow with annular isolation


Advantages

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Production casing
Production tubing
Wellhead
Xmass tree
Packer

26

26

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

27

27

Annulus Isolation

Packer

Annulus isolation is required


in:
Production wells to avoid
annulus heading
Injection wells to protect
casing against injection
pressures
Production/injection wells to
minimise corrosion risks

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

28

28

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

29

29

Downhole Closure of the Flow String


Downhole closure is required for most wells,
in particular:

Gas wells
Offshore wells
Remote wells
High pressure wells

It is generally achieved by Sub-Surface


Safety Valve (SSSV)
Either remotely operated on fail safe principal
or by set-points.
January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

30

30

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

31

31

Circulation Capability
For hydraulic killing of a well:
Squeezing or volumetric
Coil tubing or snubbing units
Circulation port between the tubing and
annulus.
Sliding Side Door (SSD) or Sliding Sleeve (SS)
Side Pocket Mandrel (SPM)
Ported Nipple

Tubing Punch (normally prior to workover)

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

32

32

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

33

33

Tubing Isolation
In addition to SSSV a
secondary means of isolation
will be installed
Useful for removal of SSSV (it
can act as one safety factor)
Provision is normally provided
deep within the wellbore
Normally a wireline plug and
nipple combination is used
Sliding Side Door
January 04

Side Pocket Mandrel

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

34

34

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

35

35

Completion String Facilities

Basic Well Completion Schematic

Non-Essentials

(SSSV)

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

36

36

Downhole tubing detachment


Tubing stresses
Ability to suspend P & T monitoring equipment
Controlled fluid injection from annulus into tubing
Downhole pump system
Wireline entry guide

January 04

Downhole tubing detachment

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

37

37

39

39

Tubing stresses

Packer seal system

Variation in temperature and


pressure will result in expansion
or contraction of the tubing.
This could result in mechanical
failure or disengagement from the
packer or seal bore.
A concentric seal system is used

Which allows the tubing above


the packer to be disconnected
and retrieved

Downhole tubing hanger


Suspends the tubing downhole
Components which require
frequent replacement will be
above it

(called travel joint or seal assembly).

Tubing
Hanger

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

38

38

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

P & T monitoring

Downhole pump system

Ability to suspend P&T monitoring


equipment is generally achieved by
installing a wireline nipple as a
component of completion string
Perforated joint
Tubing isolation plug

Electrical or hydraulically
powered
Installation and retrieval
Access to the tubing or
wellbore beneath the
pump

Controlled fluid injection

Wireline entry guide


(WEG)

Corrosion inhibitor or pour point


depressant
Gas lift

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

To guide the wireline tool


string back to the tubing
40

40

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

41

41

43

43

General well
completion string

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

42

42

January 04

Wellhead and Xmas Tree

Completion String Components

Wellhead/Xmas Tree
Production Tubing
Provision of an Annular Pressure Seal
Seal between Packer and Tubing
Sub-Surface Safety Valves
Side Pocket Mandrel
Sliding Side Door
Landing Nipples
Perforated Joint

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Wellhead the basis for mechanical


construction of the well. It provides:
Suspension of all casings and tubings
Ability to install a surface closure device
A BOP stack whilst drilling
A Xmas Tree for production or injection

Hydraulic access to the annulus

44

44

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

45

45

Production Tubing
Xmas Tree

When selecting production tubing the


following data should be specified:
The grade of steel (e.g., N80, C75)
Wall thickness in weight/ft (e.g., 26, 29, 32
lb/ft for a 7 tubing)

The threaded coupling (e.g., Buttress BTC,


Extreme Line EL, Long Threaded Coupling LTC,
Hydril, VAM)

Well head

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

46

46

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

47

47

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

49

49

Provision of an Annular Pressure Seal


Annular seal is required for:
To improve flow stability and production
Protection of production casing and the
wealhead
To provide facility to select or isolate during
stimulation and production

Packer is most common method for


providing an annular seal.
January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

48

48

Types of Packer

Types of Packer
Packers can be divided according to:

Packers can be divided


according to:

Ability to Withstand Differential Pressure

Retrievability

Compression Packers
Tension Packers
Compression and Tension Set Packers

Retrievable Packer
Permanent Packer

Setting Mechanism

January 04

Packer Bore

Mechanical
Compression or Tension
Hydraulic
Electrical

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Single
Dual
Triple

50

50

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

51

51

Seal between Packer and Tubing

Seal between Packer and Tubing

It is not necessary for


Casing
Tubing
retrievable packers
Is divided into dynamic
or static seal assembly
Static seal assembly does
not provide any provision
Packer
Anchor Seal
for tubing movement

Dynamic Seal Assemblies


accommodate tubing movement
Locator Seal Assembly

shoulder
casing

Assembly
January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

53

53

January 04

Seal between Packer and Tubing


Extra Long Tubing Seal
Receptacle (ELTSR)
Travel Joint
Polished Bore Receptacle
(PBR)

Anchor
Seal
Assembly

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

54

54

Sub-Surface Safety Valves


Generally rely on hydraulic pressure
Ball type or a flapper device
Tubing or wireline retrievable

Direct Controlled SSSV (DCSSSV)


Rely on a pre-set differential pressure or a
minimum bottom hole pressure
Generally set in the tubing

PBR
casing

seal bore
extension

Remotely Controlled SSSV (RCSSSV)


ELTSR

Tubing

Travel
Joint

packer

Tubing

Production
liner

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

55

55

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

56

56

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

57

57

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

58

58

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

59

59

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

60

60

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

61

61

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

62

62

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

63

63

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

64

64

10

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

65

65

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

66

66

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

67

67

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

68

68

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

69

69

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

70

70

11

Surface Safety Valves

Side Pocket Mandrel (SPM)

SSVs are also used in some countries


They are cheaper and easier to service

Has offcentre pocket with ports


into the annulus
Using wireline or coiled tubing, a
valve can be installed in the
pocket. They are:

Onshore wells
Oil wells
Generally direct control
Minimum and maximum pressure set
points
Generally above top master valve

Gas lift valves


Chemical injection valves
Circulation

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

71

71

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

72

72

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

73

73

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

74

74

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

75

75

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

76

76

12

Sliding Side Door


Permits communication between tubing and
annulus
Consists of concentric sleeves with elastomer
seals between them and each with slots or
holes
Using wireline or coil tubing, the inner sleeve
can be moved upward or downward to align
the opening in both sleeves

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

77

77

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

78

78

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

79

79

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

80

80

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

81

81

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

82

82

13

Landing Nipples
Are short tubular devices
Accommodate and secure mandrel
Provide recess to mechanically lock the mandrel

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

83

83

January 04

Landing Nipples

Plugging the tubing for


Pressure testing
Setting hydraulic set packers
Isolating the tubing, safety factor
Zonal isolation

They can be classified into three basic designs:


Top No-go
Bottom No-go
Selective Nipples
Lock mandrel recess profile
Seal bore
No-go shoulder

Downhole chokes, regulators, SSSV


Bottom hole pressure recorders

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

85

85

January 04

Perforated Joint

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

86

86

Well Completion Designs

Located below packer


Allows fluid flow into the tubing, when
the base of the tubing string is plugged
by, say, pressure gauge
Another nipple above
perforated joint will be
required for tubing
isolation
January 04

84

Nipple profiles consist of the followings:

Installing flow control equipment

January 04

84

Landing Nipples

They are installed at various points in the string


to facilitate:

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

87

Depend on
Well characteristics
Pressure
Productivity or injectivity index
Fluid properties
Rock properties and geological data
Fluid temperature

87

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

88

88

14

Well Completion Designs

Well Completion Designs

Depend on
Geographical factors

Depend on
Operational design constraints

Location
Water depth for offshore wells
Weather conditions
Accessibility

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Environmental regulations
Safety aspects

Number of producing zones

89

89

Single Zone
Completion

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

90

90

92

92

94

94

Single Zone
Completion

with no provision for tubing


movement

January 04

January 04

with Locator Seal Assembly

91

91

Single Zone
Completion,
High Flowrate

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Single Zone,
High Flowrate
Injection/Production
Completion

with Extra Long Tubing Seal


Receptacle for Tubing
Movement

utilising a Polished Bore


Receptacle

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

93

93

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

15

Single Zone
Completion

Single Zone
Completion

utilising an Electrical
Submersible Pump (ESP)

utilising a Gas Lift Facility

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

95

95

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Dual Zone
Completion

Dual Zone
Completion

Allowing Segregated
Production

with Selective Production and


Gas Lift Facility

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

97

97

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

96

98

98

100

100

Single Zone
Subsea Completion
Serviced by
Through Flowline
Techniques (TFL)

Tubingless Dual
Zone Completion

January 04

January 04

96

99

99

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

16

Single Zone Subsea Completion


Serviced by Conventional Wireline Techniques from a Workboat or
Mobile Drilling Rig

January 04

Wellbore Completion Concepts


B Tohidi, Heriot-Watt Institute of Petroleum Engineering

101

101

17

Вам также может понравиться