Академический Документы
Профессиональный Документы
Культура Документы
GEOTECHNICS
P V T . L T D.
24, Maruti Paradise, Sector 15, CBD Belapur, Navi Mumbai-400614. Tele.: 27570146, Fax: 27570147. e-mail: manoj@perfectgeotechnics.com
Table of Contents
Item
Page
1.0
INTRODUCTION
2.0
EXPLORATION PROGRAM
2.1
2.2
2.3
3.0
4.0
Exploration Scope
Subsurface Conditions
Groundwater Levels
FOUNDATION RECOMMENDATIONS
2
4
5
10
ANNEXURES
11
1.0 INTRODUCTION
Adhiraj Construction Pvt. Ltd. plans construction of a residential complex in Taloja, Navi
Mumbai. M/s. VMS Consultants is structural consultant and Edifice Consultants Pvt. Ltd.
is architect for the project. The proposed complex will consist of G+13, G+15, G+30 and
G+40 storied structures. The work of geotechnical investigation was awarded to Perfect
Geotechnics Pvt. Ltd.
Investigation were completed by Perfect Geotechnics Pvt. Ltd. in January 2011. This final
report presents results of the geotechnical investigation with foundation recommendations
for the proposed buildings.
1
Forty five Boreholes (BH-1 to BH-45) were completed for the project as illustrated on the
Borehole Location Plan in the Annexure. Borehole termination depths and structures are
summarized in table A below.
TABLE A
BOREHOLE TERMINATION DEPTHS & STRUCTURES
Structure
Depth of
Termination
BH. No
weathered
depth of borehole
bedrock
Below Ground
Surface
BH-1
0.7m
15.50m
BH-2
0.5m
10.40m
BH-3
1.0m
13.20m
BH-4
3.0m
12.20m
BH-5
1.0m
12.25m
BH-6
1.0m
7.90m
BH-7
3.0m
15.40m
BH-8
0.8m
15.40m
G+13
BH-9
0.9m
15.25m
BH-10
3.5m
10.80m
BH-11
2.0m
15.55m
BH-12
4.0m
9.60m
BH-13
4.0m
10.50m
BH-14
0.7m
14.55m
BH-15
2.5m
11.07m
BH-16
1.5m
9.73m
BH-17
G+40
1.5m
13.70m
BH-18
G+15
5.0m
11.60m
BH-19
G+40
1.5m
8.30m
BH-20
G+30
1.5m
12.60m
BH-21
G+40
4.5m
14.50m
BH-22
0.7m
10.90m
BH-23
0.7m
15.10m
BH-24
0.6m
10.20m
BH-25
1.0m
16.80m
BH-26
1.0m
10.00m
BH-27
G+40
0.7m
9.50m
BH-28
0.8m
10.00m
BH-29
1.0m
14.30m
BH-30
0.3m
15.20m
BH-31
0.0m
10.10m
BH-32
0.2m
15.10m
2
BH-33
BH-34
3.0m
9.00m
1.0m
17.18m
TABLE A (Contd)
BOREHOLE TERMINATION DEPTHS & STRUCTURES
Structure
BH. No
Depth of
weathered
bedrock
Termination
depth of borehole
Below Ground
Surface
BH-35
BH-36
BH-37
BH-38
BH-39
BH-40
BH-41
BH-42
BH-43
BH-44
BH-45
0.1m
0.5m
1.9m
1.5m
0.0m
2.0m
1.5m
1.0m
3.0m
1.0m
1.5m
9.85m
15.30m
7.70m
8.40m
9.20m
9.20m
9.70m
15.40m
8.50m
9.30m
15.85m
G+40
Subsurface profile at this site generally consists of black clay overlying completely
weathered bedrock underlain by hard bedrock.
described below;
refusals. Core recoveries were typically less than 35 percent. The lower boundary of this
layer was encountered at depths between 1.0m and 7.0m below ground surface.
and 801 kg/cm2. The boreholes were terminated in this bedrock layer at depths between
7.7m and 17.18m below ground surface.
can be designed for net allowable bearing capacity of 300 t/m2. Light rock breaking with
rock breakers will be required to complete excavations in the completely weathered rock.
Hard rock founding strata can be identified as it makes a ringing sound when struck with
crowbar or bucket excavators. Base of excavations should be manually cleaned of all
loose excavated soils/ materials.
TABLE B
DEPTHS TO BEDROCK
BOREHOL
E NUMBER
STRUCTURE
DEPTHS TO CWR
CR<35%
BH-1
BH-2
BH-3
BH-4
BH-5
BH-6
BH-7
BH-8
BH-9
BH-10
BH-11
BH-12
BH-13
BH-14
BH-15
BH-16
BH-17
BH-18
BH-19
BH-20
BH-21
BH-22
G+13
0.2m
0.5m
0.15m
0.45m
0.3m
0.2m
0.25m
0.15m
0.15m
0.3m
0.3m
0.3m
0.2m
0.1m
0.3m
0.3m
0.3m
0.5m
0.3m
0.3m
0.25m
0.7m
G+40
G+15
G+40
G+30
G+40
6
DEPTHS TO
HARD ROCK
CR>35%
4.5m
4.5m
4.5m
6.0m
5.5m
1.0m
4.5m
4.0m
6.0m
5.0m
5.0m
4.0m
6.0m
4.5m
5.5m
4.5m
3.0m
6.5m
3.0m
6.0m
4.5m
4.5m
BH-23
BH-24
BH-25
BH-26
BH-27
BH-28
BH-29
0.7m
0.6m
1.0m
1.0m
0.2m
0.8m
1.0m
G+40
6.0m
4.5m
7.0m
5.0m
4.5m
3.0m
4.0m
TABLE B (Contd.)
DEPTHS TO BEDROCK
BOREHOL
E NUMBER
STRUCTURE
DEPTHS TO CWR
CR<35%
BH-30
BH-31
BH-32
BH-33
BH-34
BH-35
BH-36
BH-37
BH-38
BH-39
BH-40
BH-41
BH-42
BH-43
BH-44
BH-45
G+40
0.3m
0.0m
0.2m
0.3m
0.15m
0.1m
0.5m
1.65m
0.1m
0.0m
0.0m
1.0m
0.0m
2.1m
0.35m
0.3m
G+40
DEPTHS TO
HARD ROCK
CR>35%
4.5m
4.5m
4.5m
3.5m
5.5m
3.0m
5.0m
1.9m
3.0m
4.5m
3.5m
4.5m
5.0m
4.5m
3.4m
5.2m
Modulus of subgrade
reactions of 4500 t/m3 and 30,000 t/m3 can be utilized for design of foundations installed
on CWR and hard rock, respectively. Excavation sides should be sloped at a maximum
slope of 1:2 (horizontal: vertical) or flatter. Dewatering will be required in excavations.
3.1
Foundation Protection
Groundwater samples were collected for chemical analysis from the site.
Results of
Chemical analysis are enclosed in the Annexure. Based on chemical results, the site falls
under Class I for sulphates and chlorides (As per IS456-2000 and as per CIRIA Special
Publication No. 31). A moderate exposure condition was assigned to this site. Hence,
following precautions shall be taken to protect concrete and reinforcement in foundations;
Type of Cement:
OPC or PPC
M25
300 kg/m3
0.50
50mm
The sub-surface investigation was completed generally as per IS: 1892-1979. The field
investigation was carried out using a rotary machine. Casing was used to support sides of
borehole until sufficiently stiff strata was encountered. Standard Penetration Tests (i.e.
SPT) were carried out in soil in accordance with IS 2131-1981. Using this procedure, a 2
outside diameter split-barrel sampler is driven into the soil by 63.5 kg. weight falling
through 75 cm height. After an initial set of 15cm, the number of blows required to drive
the sampler an additional 30 cm, is known as the penetration resistance or N value.
When SPT refusal was obtained in hard strata, rock coring was done using diamond bit
and double tube core barrel to obtain rock samples. Percent Rock Core Recovery and
Rock Quality Designation (%RQD) were determined. % RQD = 100 x Sum of length of
rock pieces in cms, each having lengths greater than 10cms/Total length of core run.
Sincerely,
PERFECT GEOTECHNICS PVT. LTD.
__________________________________
Jaydeep Wagh
B.E., M.S., P.E. (Geotechnical)
10
REFERENCES
1) Foundation Analysis and Design, J.E. Bowles, McGraw Hill Publication, 5th Edition,
1996.
nd
3) Soil Mechanics in Engineering Practice, 2 Edition, Terzaghi K. and Peck R. B., John
Willey and Sons, 1967.
11
Where,
q = Overburden Pressure (i.e. submerged unit weight x depth of
foundation)
c = Cohesion
B = Minimum Width of foundation = 1.5m
= submerged unit weight of soil = 0.80
Nc, Nq, N = Terzaghis Bearing capacity factors
Sc, sq, s = Shape factors = conservatively assumed as 1.2, 1.2, and 0.8
D = Minimum Depth of Footing = 1.0m
Minimum SPT N value obtained in boreholes = 50
o
Corresponding friction angle = 40 (Reference No. 5)
Corresponding Nc=75, Nq=64, N=109 (Reference 5, IS:6403-1981);
Substituting these values in the above equation;
q ultimate =qu =[0x75x1.2]+[1.0x0.8x(64-1)x1.2]+[0.5x1.5x0.8x109x0.8]= 0+60+52 = 112
2
t/m
q safe = qu/F.S. = 112/2.5 =45 t/m2
12
1 2
mI s I f
Es
Where,
q0 = Footing Pressure = 45 t/m2
B = B/2 (Where B is the width of pressure distribution
= Poissons ratio = 0.3
E = Modulus of Elasticity
Is = Influence Factor (Obtained from Table 5-2, Reference No. 1)
If = Depth Factor (Obtained from Figure 5-7, Reference No. 1)
m = 4 for center of footing
Very conservatively assuming weathered bedrock within the full influence zone of
footings:
E value for over-consolidated sand = 105(N)+4000 (Reference No. 1)
Therefore, for a SPT N value of 50, E=9,250 t/m2
L = 3/2 =1.50, B = 3/2 = 1.5, H=5.5m, and D=1m
Therefore, M=L/B=1; and N=H/B=3.67 and D/B=0.33
Corresponding, Is = 0.418, Conservative If = 1.0 (From Table 5-2, Reference 1)
Settlement of Layer =
1 0.3 2
S1 = 45 x1.5 x
x 4 x0.418x1.0 = 0.011m = 11mm
9250
13
1 2
mI s I f
Es
Where,
q0 = Footing Pressure = 45 t/m2 (after allowing for pressure dissipation)
B = B/2 (Where B is the width of pressure distribution
= Poissons ratio = 0.2
E = Modulus of Elasticity
Is = Influence Factor (Obtained from Table 5-2, Reference No. 1)
If = Depth Factor (Obtained from Figure 5-7, Reference No. 1)
m = 4 for center of footing
E value for Basalt Bedrock = 1700,000 t/m2
Using 1/10th of this value for Basalt Bedrock,
E = 0.1 x 17, 00,000 = 170,000 t/m2
Depth of top of layer below footing= 6.5m
Assuming a 30 degree pressure dissipation,
Width of pressure distribution at top of the layer = 3m + 6.5m = 9.5m
Length of pressure distribution at top of the layer = 3m + 6.5m = 9.5m
L = 9.5/2 =4.5, B = 9.5/2 = 4.5, H=6m, and D=6m
Therefore, M=L/B=1; and N=H/B=4 and D/B=0.66
Corresponding, Is = 0.255, Conservative If = 1.0 (From Table 5-2, Reference 1)
Settlement of Layer =
S2 = 45 x 4.5 x
1 0.25 2
x 4 x0.255x1.0 = 0.001m = 1mm
170,000
14
15
Settlement = S q0 B'
1 2
mI s I f
Es
Where,
q0 = Footing Pressure = 300 t/m2
B = B/2 (Where B is the width of pressure distribution
= Poissons ratio = 0.2
E = Modulus of Elasticity
Is = Influence Factor (Obtained from Table 5-2, Reference No. 1)
If = Depth Factor (Obtained from Figure 5-7, Reference No. 1)
m = 4 for center of footing
E value for Basalt bedrock = 17, 00,000 t/m2
th
2
Using 1/10 of this value for Basalt bedrock, E = 170,000 t/m (Reference 7)
L = 5/2 =2.5, B = 5/2 = 2.5, H=10m, and D=3m
Therefore, M=L/B=1; and N=H/B=4 and D/B=0.6
Corresponding, Is = 0.53, Conservative If = 1.0 (From Table 5-2, Reference 1)
Settlement of Layer =
S1 = 300 x2.5 x
1 0.2 2
x4 x0.43x1.0 = 0.007m = 7mm
170,000
16