ATTACHMENT BASIC DRILLING PROGRAM

TABLE OF CONTENT
1 Field Introduction ............................................................................................................................ 1
1.1 Geographic location of the oilfield ............................................................................................... 1
1.2 Reservoir deposition characteristics and pay zone division ......................................................... 2
1.3 Predictions of reservoir pressure and temperature........................................................................ 4
2 Drilling wells Information ............................................................................................................... 4
3 Well Data Summary......................................................................................................................... 5
4 Drilling Risk Hint ............................................................................................................................ 5
5 Drilling Program .............................................................................................................................. 5
5.1 Principles For Finishing Drilling .................................................................................................. 5
5.2 Well Structure ............................................................................................................................... 5
5.3 Casing Program ............................................................................................................................ 6
5.4 Well Head and Well Control program .......................................................................................... 6
5.5 Preliminary Drilling Fluid Program ............................................................................................. 7
5.6 Preliminary Cement Program ....................................................................................................... 8
5.7 Estimate Drilling period ............................................................................................................... 9
5.8 Well bore Quality Requirement ...................................................................................................11

ATTACHMENT BASIC DRILLING PROGRAM

Field Introduction
1.1

Geographic location of the oilfield

Missan oilfield group is located in the Missan province in southeastern of Iraq and near the Iranian
border. It is about 175km south to Basra and about 350km northwest to Baghdad, (Figure 1-1). The
weather is hot and dry, with average temperature of 34 in July, the average temperature of 11 in
January, average annual rainfall of 165mm. Most of this area is desert and gobi, relatively flat, but
some hills in the north of Abu Ghirab.
Missan oilfield group consists of three producing oilfields, Abu Ghirab, Buzurgan and Fauqi oilfields,
of which Abu Ghirab and Fauqi oilfields across the border between Iraq and Iran. Abu Ghirab oilfield
contract area is 30km 6km, Buzurgan oilfield contract area is 40km 7km, and Fauqi oilfield
contract area is 23km 6km (Figure 1-2).
Figure 1-1

Page 1 of 13

ATTACHMENT BASIC DRILLING PROGRAM

Figure 1-2

Abu Ghirab

Buzurgan

Fauqi

1.2

Reservoir deposition characteristics and pay zone division

The formations penetrated from top to bottom in Mesopotamia region, where Missan oilfield group is
located, are respectively Tertiary Upper Fars, mainly consists of the sandstone and mudstone with
thickness of 2000m and more; Lower Fars, mainly consists of anhydrite and salt deposition with
thickness of about 800m, being the regional seal; Tertiary Jeribe to Cretaceous Nahr Umer, mainly
consists of carbonate with thickness of about 800m, with the late Cretaceous drilled through (Figure
1-3).
There are 4 sets of reservoirs developed in the oilfields: Tertiary Asmari, the lithology is limestone
and dolomite mainly and sandstone reservoir developed in some areas; Middle Cretaceous Mishrif
and Mauddud, lithology is the limestone mainly; Middle Cretaceous Nahr Umr, lithology is clastic
rocks mainly.
Fauqi oilfield has two sets of reservoir, Tertiary Asmari and Cretaceous Mishrif. 3 pay zones are
divided in the Asmari reservoir which is A, B and C. The main pay zone is B and A.
The pay zone A of Asmari consists mainly of dolomite. The pay zone B is dolomite intercalated with
sandstone, limestone and thin shale. The pay zone C is mainly the sandstone, intercalated with a few
dolomite, mudstone and limestone.
The main reservoir in Fauqi oilfield is cretaceous Mishrif. Seven pay zones can be divided in the
Mishrif reservoir which is MA, MB11, MB12, MB21, MB22, MC1 and MC2.

Page 2 of 13

ATTACHMENT BASIC DRILLING PROGRAM

MA consists of mainly compact limestone while some packstone reservoir is developed in the south
dome area; MB11 mainly consists of mudstone interbeded with thin wackstone reservoir particularly
in the south dome; MB12 consists of mudstone; MB21 is mainly composed of grainstone, packstone
reservoir; MB22 consists of mainly compact mudstone; MC1 is mainly composed of packstone
reservoir in the upper part and lower part composed of compact mudstone; MC2 consists of mainly
packstone reservoir.
Figure 1-3
AGE

Depth R.T.
FORMATION LITHOLOGICAL
M
F
LOG

Page 3 of 13

LITHOLOGY

ATTACHMENT BASIC DRILLING PROGRAM

1.3

Predictions of reservoir pressure and temperature

1) Formation temperature
The Asmari reservoir in Abu Ghirab oilfield has the geothermal gradient of 2.3 /100m.
The Asmari reservoir in Fauqi oilfield has the geothermal gradient of 2.3 /100m.
The Mishrif reservoir in Buzurgan oilfield has the geothermal gradient of 2.4 /100m.
2) Formation pressure
Asmari reservoir in Abu Ghirab oilfield, the initial formation pressure for is 4630psi which is
equivalent to pressure co-efficient of 1.14; the reservoir pressure drop due to the production and
currently the pressure co-efficient is about 0.99-1.07.
Asmari reservoir in Fauqi oilfield, the initial formation pressure for is 4930psi which is equivalent to
pressure co-efficient of 1.14; the reservoir pressure drop due to the production and currently the
pressure co-efficient is about 0.97-1.09.
Mishrif reservoir in Buzurgan oilfield, the initial formation pressure for is 6300psi which is equivalent
to pressure co-efficient of 1.15; the reservoir pressure drop due to the production and currently the
pressure co-efficient is about 0.78-0.96 for MB21 in the south and about 0.92-1.01 for MB21 and
about 0.88-0.97 for MC1 in the north.
Asmari reservoir gas composition: CO2 content of 0.1-1.52%; H2S content of 0-0.4%.
Mishrif reservoir gas composition: CO2 content of 3.4-7.2%; H2S content of 0.6-2.5%.
It is necessary to guard against the risks of H2S and CO2.

Drilling wells Information

Based on the Missan Oilfield development plan, Company plans to drill twelve (12) vertical wells, by
three rigs in Abu Ghirab, Fauqi, and Buzurgan oilfield.
The construction specifications of the well-sites for the twelve (12) wells could be found in following
attachment.
Field

Abu
Ghirab

Fauqi

Total Depth
from RKB
m

Target

Vertical

3181

Asmari

Production

Vertical

3191

Asmari

AGCS-52

Production

Vertical

3186

Asmari

4th

AGCS-53

Production

Vertical

3158

Asmari

5th

AGCS-54

Production

Vertical

3232

Asmari

6th

AGCS-55

Production

Vertical

3170

Asmari

7th

AGCS-56

Production

Vertical

3226

Asmari

8th

AGCS-57

Production

Vertical

3190

Asmari

1st

FQCN-54

Production

Vertical

3235

Asmari

Well
Number

Well name

1st

AGCS-50

Production

2nd

AGCS-51

3rd

Well Type

Page 4 of 13

Layer

ATTACHMENT BASIC DRILLING PROGRAM

Buzurgan

1st

BUCN-58

2nd

BUCN-59

3rd

BUCS-61

Production and
Injector
Production and
Injector
Injector

Vertical

4092

Mishrif

Vertical

4092

Mishrif

Vertical

4080

Mishrif

Remark: The TD would be adjusted depending on actual Geological requirement.

Well Data Summary


Drilling rig Type
Well Quantity
Well Type
Geographic Location

8 wells in Abu Ghirab, 3 wells in Buzurgan and 1 well in Fauqi oilfield


Twelve (12) vertical wells
Missan province in southeastern of Iraq

G.L. Elevation

About 18~162m, it will be confirmed after wellsite survey and total depth
of these wells will update after this

Primary Target

Asmari formation for 9 wells


Mishrif formation for 3 wells

Drilling coring
Drillstem Testing
4

3 sets of 2000HP Land Rig

No drilling coring plan


No drill stem testing plan

Drilling Risk Hint

The high pressure layer exists in Lower Fars above Asmari reservoir. In addition, there are micro
fractures in reservoir.
Risk of Mud loss in MB1 in 12-1/4 hole.
During the drilling process, pay close attention to formation pressure changes, and adjust the mud
weight to prevent downhole accidents.
Gas formation may show in AALIJI, KHASIB and SADI formation.
Mishrif reservoir gas composition: CO2 content of 3.4-7.2%; H2S content of 0.6-2.5%. It is
necessary to guard against the risks of H2S and CO2. Bit balling may be occurred in 17-1/2 hole
section, sometimes POOH with back-reaming.
Mud loss and borehole collapse occurred in 8-1/4 hole section frequently during drilling and
cementing operation, high risk for running 6-5/8 liner, setting liner hanger and cementing.

Drilling Program

5.1 Principles For Finishing Drilling


The drilling can be finished when the anticipated TD is reached, geological and reservoir
requirements are met and the enough rate hole for logging tool.
5.2 Well Structure
The detail information of well trajectory for three horizontal wells is as following:
Well Structure
Producing
Oilfield

Sequence

Well name

st

36" (m)
Page 5 of 13

nd

26"(m)

3rd

4th

5th MD

17-1/2" (m)

12-1/4"

8-1/4" (m)

ATTACHMENT BASIC DRILLING PROGRAM


(m)
Vertical

Vertical

section

section

section

section

section

AGCS-50

30

130

2196

2886.8

3181

AGCS-51

30

130

2151

2911.8

3191

3rd

AGCS-52

30

130

2091

2906.8

3186

th

AGCS-53

30

130

2158

2868.8

3158

th

AGCS-54

30

130

2257

2952.8

3232

th

AGCS-55

30

130

2260

2895.8

3170

th

AGCS-56

30

130

2201

2926.8

3226

th

AGCN-57

30

130

2160

2915.8

3190

1st

FQCN-54

30

130

2180

2955.8

3235

st

BUCN-58

30

130

2052

2798.8

4092

nd

BUCN-59

30

130

2065

2797.8

4092

rd

BUCS-61

30

130

2161

2813.8

4080

4
5
6
7

1
Buzurgan

Vertical

nd

Fauqi

Vertical

st

Abu Ghirab

Vertical

Notes:
Company has the right to cancel the 36" section drilling operation and 30" conductor cementing.
5.3 Casing Program
Bit size

Casing size

Specifications of casing

Thread Type

36"

30"

196.1ppf,B or X52,

Square Cut

26"

20"

94ppf, K55, BTC

BTC

17-1/2"

13-3/8"

68ppf, N80, BTC

BTC

9-5/8"

47ppf, L80

VAM TOP

9-5/8"

58.4ppf, C95

VAM TOP

6-5/8"

28ppf, L80-13Cr

VAM TOP

12-1/4"
8-1/4"
1.
2.
3.
4.

Notes:
Contractor shall provide the same Connect Thread Type for their casing accessories according
to Companys casing specification.
Company has the right to cancel the 36" hole section drilling operation and the cementing of
30" conductor.
The torque indicator is required to use for all premium thread casings.
Contractor shall provide the specialized running tools for the liner of 6-5/8 L80-13Cr.

5.4 Well Head and Well Control program


Name

Rated Working Pressure


21-1/4" 2000PSI

Annular blowout preventer


13-5/8" 5000PSI
21-1/4" 2000PSI
Double Ram preventer
13-5/8" 10000PSI

Page 6 of 13

ATTACHMENT BASIC DRILLING PROGRAM

Ram preventer

13-5/8" 10000PSI
21-1/4" 2000PSI

Drilling spool
13-5/8" 10000PSI
Standpipe

5000PSI

Choke manifold

10000PSI

Kill manifold

10000PSI

21-1/4"casing head

2000PSI

13-5/8"casing head

5000PSI

11"casing head

5000PSI

5.5 Preliminary Drilling Fluid Program


36" & 26"

17.5"

12.25"

8.25"
(Asmari)

8.25"
(Mishrif)

1.05

1.10~1.30

2.2~2.30

1.15~1.28

1.15~1.30

35~40

45~55

45~70

45~60

45~60

Plastic Viscosity
(mPa.s)

35

70

30

30

Yield Point (Pa)

10~15

5~12

8~12

8~12

GEL 10 / 10 (Pa)

1~3/4~8

1~6/5~12

2~4/5~10

2~4/5~10

PH

9~10

9 ~10

9.5~10.5

9.5~10.5

API Fluid
Loss(ml/30 min)

5~10

2~4

2~5

2~5

Corrosion
inhibitor(H2S&CO2)

required

required

Properties
Mud Weight (g/cm3)
Viscosity (s/qt)

Note:
1. Contractor shall provide the proper drilling fluid formula for each section, the chemical
percentage such as KCL should be provided, and the properties could be adjusted according to the
down situation under the approval by Company.
2. The mud properties ofshall be recommended by Contractor.
3. The drilling fluid provided by Contractor shall be having the better properties to protect hole
stability for 17.5", 12.25", 8.25"holes.
4. The mud density for 12.25", 8.25" holes can be adjusted according to the actual situation.
5. 191000 mol/L CL- is recommended to use in 8.25" section in order to control borehole stability.

Page 7 of 13

ATTACHMENT BASIC DRILLING PROGRAM

5.6 Preliminary Cement Program

(IN)

TYPE

WE
IG (#)
HT

SIZ E
(IN)

STAGE

DEPTH (m)

HOLE
SIZE

36"

X-52

196.1PPF

30"

30

26"

K-55

94PPF

20"

120

Cement Class G + Accelerator + Antifoam Agent + Others

1.90

800-2200

Cement Class G + Extender +Retarder + Dispersant + Fluid


loss agent + Antifoam Agent + Others

1.90

TO
800-1000m

800

Cement Class G + Extender +Accelerator + Antifoam Agent


+Others

1.90

TO
SURFACE

2900

Cement Class G + Retarder + Dispersant + Salt-Resisting


fluid loss agent + Antifoam Agent + Weighting agent + Silica
flour + NaCl + Others (anti migration additive)

2.3-2.35

TO
1500-1800m

2000

Cement Class G + Retarder + Dispersant + fluid loss agent


+Antifoam Agent + Others

2.3-2.35

TO
SURFACE

TD

Cement Class G + Retarder + Dispersant + Fluid loss agent


+Antifoam Agent + Silica Flour + Light weight material +
Others

1.90&1.50
(Asmari)
1.90&1.90
(Mishrif)

TO TOP OF
LINER
HANGER

17 1/2"

CASING

N-80

C95

68PPF

58.4PPF

12 1/4"

9 5/8"
L80

8 1/4"

13 3/8"

L80-13Cr

47PPF

28PPF

Liner
6-5/8"

CEMENT & Additives (REQUIRED)

Cement Class G + Accelerator + Antifoam Agent + Others

Remark:
1. The cement slurry density and the top of cement will be adjusted according to the actual downhole situation.
2. Single stage cementing technology for 13-3/8 casing could be as option to improve the cementing technique.
3. Liner hanger shall be 6-5/8" and not 7", and setting liner hanger after cementing job is recommended.

Page 8 of 13

SLURRY
DENSIT
Y (g/cm3)
1.90

TOP OF
CEMENT
TO
SURFACE
TO
SURFACE

ATTACHMENT BASIC DRILLING PROGRAM

5.7 Estimate Drilling period


CONTRACTOR should provide the preliminary drilling program.
1) The drilling period for vertical well of AGCS-50 is estimated 57 days.
Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

3rd spud in

17.50

2196

10~15

22

27

4th spud in

12.25

2886

5~12

20

47

5th spud in

8.25

3181

8~15

10

57

2) The drilling period for vertical well of AGCS-51 is estimated 57 days.


Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

3rd spud in

17.50

2151

10~15

22

27

4th spud in

12.25

2912

5~12

20

47

5th spud in

8.25

3191

8~15

10

57

3) The drilling period for vertical well of AGCS-52 is estimated 57 days.


Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

3rd spud in

17.50

2091

10~15

22

27

4th spud in

12.25

2907

5~12

20

47

5th spud in

8.25

3186

8~15

10

57

4) The drilling period for vertical well of AGCS-53 is estimated 57 days.


Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

3rd spud in

17.50

2158

10~15

22

27

4th spud in

12.25

2869

5~12

20

47

5th spud in

8.25

3158

8~15

10

57

5) The drilling period for vertical well of AGCS-54 is estimated 57 days.

Page 9 of 13

ATTACHMENT BASIC DRILLING PROGRAM

Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

3rd spud in

17.50

2257

10~15

22

27

4th spud in

12.25

2952

5~12

20

47

5th spud in

8.25

3232

8~15

10

57

6) The drilling period for vertical well of AGCS-55 is estimated 57 days.


Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

3rd spud in

17.50

2260

10~15

22

27

4th spud in

12.25

2896

5~12

20

47

5th spud in

8.25

3170

8~15

10

57

7) The drilling period for vertical well of AGCS-56 is estimated 57 days.


Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

3rd spud in

17.50

2201

10~15

22

27

4th spud in

12.25

2927

5~12

20

47

5th spud in

8.25

3226

8~15

10

57

8) The drilling period for vertical well of AGCN-57 is estimated 57 days.


Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

3rd spud in

17.50

2160

10~15

22

27

4th spud in

12.25

2916

5~12

20

47

5th spud in

8.25

3190

8~15

10

57

9) The drilling period for vertical well of FQCN-54 is estimated 57 days.


Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

130

8~15

3.5

Page 10 of 13

ATTACHMENT BASIC DRILLING PROGRAM

3rd spud in

17.50

2180

10~15

22

27

4th spud in

12.25

2956

5~12

20

47

5th spud in

8.25

3235

8~15

10

57

10) The drilling period for vertical well of BUCN-58 is estimated 77 days.
Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

120

8~15

3.5

3rd spud in

17.50

2052

10~15

21

26

4th spud in

12.25

2799

5~12

21

47

5th spud in

8.25

4092

8~15

30

77

11) The drilling period for vertical well of BUCN-59 is estimated 77 days.
Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

120

8~15

3.5

3rd spud in

17.50

2065

10~15

21

26

4th spud in

12.25

2798

5~12

21

47

5th spud in

8.25

4092

8~15

30

77

12) The drilling period for vertical well of BUCS-61 is estimated 77 days.
Bit size

Depth

ROP

Estimated
Item Time

Total Time

Item

(in)

(m)

(m/hr)

(Day)

(Day)

1st spud in

36.00

30

8~10

1.5

1.5

2nd spud in

26.00

120

8~15

3.5

3rd spud in

17.50

2162

10~15

21

26

4th spud in

12.25

2814

5~12

21

47

5th spud in

8.25

4080

8~15

30

77

Note:
The each section depth per well will be decided by site geological supervisor according to actual
geological condition and each casing/liner shoe depth & liner hang position will be adjusted
accordingly.
5.8 Well bore Quality Requirement
These wells bore quality should satisfy following requirements
Add short casing joint at 10-30m above pay zone; add radiation label at 70-100m above pay zone, the
details shall follow the requirement of geology.
Company has the right to evaluate the well after drilling operation, and Company has the right to
Page 11 of 13

ATTACHMENT BASIC DRILLING PROGRAM

refuse the well if the evaluation result is not acceptable.


Vertical section
No.

Item

Name

Quality standard

Well Depth (m)

Max Deviation()

0500

5001000

10002000

20003000

30004000
40005000

7
9

rate of over all


angle change

2
Wellbore
Quality

Bottom
Horizontal
Displacement(m)

Hole Diameter
Enlargement
Rate of Oil
Reservoir

Oil Reservoir

5
Drilling
fluild

Depth(m)

(o)/30m

1000

1.25

2000

1.75

3000

2.00

4000

2.50

5000

3.00

Depthm)

Bottom Horizontal
Displacement(m)

1000

30

2000

50

3000

75

4000

90

5000

120

Wellbore Diameter(")

Percentage

10

10
Bit Diameter 30%

8-1/4"

-0.03 g/cm3 +0.03 g/cm3

Water Base

10

6ml(API Filter Loss)

Water Base

10

Density
Oil Reservoir
Filter Loss

Score

Cement Slurry

-0.02 g/cm3 +0.02 g/cm3

Cement Slurry
Filter Loss

50ml

Cementing Bond
Logging(CBL)

5% Excellent; 5%CBL15% Good; 15%


CBL25% Acceptability

10

Cement Top
Incasing
Annulus

At Least 200m Above Oil Reservoir

11

Pressure Test in
Casing

Meet design requirement

Density

Cement
Job Quality

Page 12 of 13

ATTACHMENT BASIC DRILLING PROGRAM

12

Artificial Bottom
Hole in Casing

Satisfy the Design Requirements (50m)

13

Logging Item

Complete All the Logging Item of The Design

Logging Depth

Within 10m Far Away Bottom

Logging Quality

CNOOC Standard

10

14
15
16

Logging
Quality

Composite Score of Single Well

Page 13 of 13

100