Академический Документы
Профессиональный Документы
Культура Документы
Prepared By:
Engr. Romen P. Real
Submitted to:
Dr. Antonio V. Sobrevias, Jr.
Solution:
1. We will build the previous information into a resource loading chart
Observation:
From the graph, we can immediately tell how many staff are needed at any one time. For
example, in week 10, we can identify that only 2 staff members are required. Whereas in
week 14, there are 5 staff members required. It is to note that the bottom row of the graph
could also be described as the critical path. Each of these items as Float = 0. This row can
be described as the Base Line. The method of creating this chart, by positioning one activity
at a time is called Serial Scheduling.
Resource Levelling
As identified, our chart contains extreme peaks. For example, weeks 1-5. Resource levelling
helps to avoid this. As we have several activities which contain float, we can try to move
these activities to level out the staff distribution:
Obviously, this still isnt ideal as we still have a peak during week 13. However, we have
levelled as much as possible, and in turn we have reduced costs.
Solution:
1. Have a go at plotting the chart with the strict resource limit of 4.
The result is:
References:
http://knowledge.apm.org.uk/bok/resource-scheduling-0
Harold Kerzner, 2009: Project Management, A System Approach to Planning, Scheduling and
Controlling 10th Edition. John Wiley & Sons Inc.
Field, M. & Keller, L., 1998: Project Management. The Open University and Thomson
Learning, London.