No.
DESCRIPTION
100
102a
Roadway Excavation
(Common)
UNIT
Ha.
cu.m.
LABOR
REQUIREMENT
PRODUCTION
OUTPUT (per
Hour)
MATERIAL REQUIREMENT
EQUIPMENT REQUIREMENT
(per Hour)
None
1 Foreman
2 Laborer
500 sq.m./hr.
None
1 Foreman
2 Laborer
60 cu.m./hr.
1 Foreman
2 Laborer
80 cu.m./hr.
102b
Roadway Excavation
(Surplus)
cu.m.
None
103a
Structure Excavation
(Soft Soil)
cu.m.
None
1 Foreman
3 Laborer
20 cu.m./hr.
1 Foreman
2 Unskilled
50 cu.m./hr.
1 Foreman
2 Unskilled
300 sq.m./hr.
104a
Embankment
cu.m.
105a
Subgrade Preparation
(in common excavation)
sq.m.
None
cu.m.
200
1 Foreman
2 Unskilled
50 cu.m./hr.
201
202
cu.m.
1 Foreman
2 Unskilled
50 cu.m./hr.
cu.m.
1 Foreman
2 Unskilled
50 cu.m./hr
cu.m.
1 Foreman
2 Unskilled
50 cu.m./hr
300
301
m.t
1 - Foreman
2-Unskilled
50 cu.m./hr
302
m.t
1-Foreman
3-Unskille
0.30 m.t./hr.
310(a)
310 (b)
Bituminous Concrete
Surface Course
Bituminous Concrete
Surface Course
Factor = 2.335 m.t./cu.m.
6.5% Asphalt Content
sq.m.
sq.m.
0.22 MT Bituminous
Concrete Surface Course (T50MM)
5% Wastage
50mm. thickness
0.00795MT/sq.m. Asphalt
Cement
0.00488 cu.m./sq.m.
Aggregates (93%)
0.0038 cu.m./sq.m. Mineral
Filler (7%)
1 Foreman
4 Skilled
8 Unskilled
171.30 sq.m./hr.
or
20 m.t./hr.
1 Foreman
6 Skilled
12 - Unskilled
171.30 sq.m./hr.
or
20 m.t./hr.
311 (a)
311 (b)
404 (1)
Portland Cement
Concrete Pavement
(Convention Method)
t 0.23 m
sq.m.
sq.m.
kg.
1 Foreman
4 Skilled
12 - Unskilled
70.00 sq.m./hr.
1 Foreman
4 Skilled
10 - Unskilled
174.00 sq.m./hr.
1 Foreman
2 Skilled
8 - unskilled
180 kg./hr.
0.15
0.15
0.50
0.50
404 (2)
405
500 (1)
500 (3)
505 b
1 Foreman
2 Skilled
8 - Unskilled
cu.m.
1 Foreman
4- Skilled
8 - Unskilled
l.m.
1 Foreman
2 Mason
4 - Laborer
1 Foreman
2 Mason
4 - Laborer
1 Foreman
2 Mason
8 - Unskilled
kg.
l.m.
cu.m.
Grouted Riprap
3 bags/cu.m.
0.25 cu.m. sand
0.30 l.m./cu.m. (Weep
Holes)
0.015 sq.m./cu.m.( Filter
Cloth)
1.05 cu.m./cu.m. ( Boulders)
0.015 cu.m./cu.m. (Gravel
Fill)
180 kg./hr.
1.40 cu.m./hr.
18 l.m./day
14 l.m./day
1 cu.m./man-day
506
Stone Masonry
509
511a
Gabions (2 x1 x1)
511b
Mattresses (6x2x0.3)
cu.m.
l.m.
cu.m.
cu.m.
600 (1)
600 (2)
Concrete Curb
l.m.
5.5 bags/cu.m.
0.30 cu.m. sand
0.30 l.m./cu.m. (Weep
Holes)
0.015 sq.m. (Filter Cloth)
0.02 cu.m./cu.m. (Gravel Fill)
1.05 cu.m./cu.m.(Boulders)
1 Foreman
2 Skilled
8 - Unskilled
1 Foreman
6 Skilled
12 - Unskilled
1 Foreman
2 Skilled
8 - Unskilled
2.0 cu.m./man-day
Mattress 6m x 2m x 0.3m
0.28 pc./cu.m.
1.05 Boulders
1 Foreman
2 Skilled
8 - Unskilled
2.5 cu.m./man-day
1 Concrete Vibrator
1 One Bagger Mixer
1 Water truck (500 1000
gals)
Minor Tools 5% of Labor)
1 Foreman
4 Skilled
8 - Unskilled
1 Concrete Vibrator
1 One Bagger Mixer
1 Foreman
4 Skilled
1.25 cu.m./man-day
0.15 cu.m./manhour
10 l.m./hr.
18.40 l.m./hr.
11.25 l.m./hr.
l.m.
8 - Unskilled