MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

To

Bombardier Global Rail Consortium

Date Reviewed

14 December 2016

Submittal Ref.

NOISE VIBRATION COMPLIANCE MANAGEMENT PLAN

Submittal Type

PLAN

Submittal Stage

Concept/Prelim/ Detailed/ Tender/ Construction/


As-built/Others

(Doc.No: SSP-BTGR-SS01-SYSW-PLN-00029-00)
Date of Dwg/ Doc Received

29th November 2016

Your Ref. : SSP-BTGR-TRANSMIT-000139


(WF-011980)

Our Ref.

SSP-PDP2-SS01-SYSW-DRR-00045 (Rev 00)

(* Please circle relevant item)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Reviewer

Systems

Approver

Name & Initial

Item

1.

Design/Document / Drawings No.

1.2 Scope

AMK

Final Approver

Name & Initial

Name & Initial

PDPs Comment
WPC does not need to repeat statement
on track work construction/ installation
does not form part of the work package in
this section. Please omit.

PAR

Reviewers
Name

CH2M

Status

Comment
Code

WPCs / Consultants Response

Omitted

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

PDPs Comment

2.

2.1 Abbreviations

WPC to clarify whether abbreviation for


PSD and APD are used for discussion in
this plan? If not, please remove from the
abbreviation section.

3.

3 REFERENCES

WPC to include The Planning Guidelines


for Vibration Limits and Control in the
Environment published by DOE.

Reviewers
Name

Status

Comment
Code

CH2M

CH2M

WPCs / Consultants Response

Included PSD/APG in discussion

Included The Planning Guidelines for Vibration


Limits and Control in the Environment
published by DOE

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

PDPs Comment

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

4.

Table 3: List of References ~ Standards

WPC to remove Ministry of Housing and


Local Government Malaysia from the list.

CH2M

Removed Ministry of Housing and Local


Government Malaysia

5.

5.3 Environmental Roles and


Responsibilities

Content in this section looks identical to


EMP without considerable discussion on
noise and vibration management.

CH2M

Rewritten the section

WPC to rewrite this section and elaborate


specific roles and responsibility in regards

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

PDPs Comment

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

to noise and vibration management for PD,


Site Manager, EM and EO.
6.

6 CONSTRUCTION NOISE AND


VIBRATION MONITORING

All subsections under section 6 are poorly


structured/ arranged and confuse to the
reviewer. WPC to rearrange and rewrite
the subsection with consideration on:

What are the source of noise or

CH2M

Rewritten and restructured Section 6

Please refer to Section 6

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

PDPs Comment

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

vibration expected from WPCs activities?


What are the proposed operation
control by WPC on these sources to
reduce impact to sensitive receptor?

Please refer to Section 1.2 on last paragraph


and Section 6

What are the proposed arrangement of


Baseline monitoring by WPC?

No monitoring will be done as the noise and


vibration generated from BT-GR Consortium not
that of concern level due to the nature of job

What are the propose arrangement on

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

Reviewers
Name

PDPs Comment

Status

Comment
Code

WPCs / Consultants Response

environment monitoring by WPC?

7.

6.1 Methodology

WPC to clarify methodology in this


subsection is refering to methodology to
control
the
noise/
vibration
or
methodology to monitor / measurement?
WPC to rewrite and elaborate
subsection with better clarity.

this

CH2M

Methodology to control the noise/vibration

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

8.

Design/Document / Drawings No.

6.2 Baseline Monitoring

PDPs Comment

Reviewers
Name

WPC
shall
elaborate
proposed
arrangement to fulfil the requirement under
GS 8.12 instead of copy and paste the
content.

CH2M

WPC to rewrite this subsection to propose


arrangement of baseline monitoring prior
start of site activities.

Status

Comment
Code

WPCs / Consultants Response

Rewritten the Section

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

9.

6.2 Baseline Monitoring 2)

10.

6.2 Baseline Monitoring - list of tools and


equipment that generate noise

PDPs Comment
In-situ instrument such as pH Meter,
Dissolved Oxygen Meter, Total Suspended
Solid, Turbidity has no relevancy to
NVCMP. Please remove these items from
the discussion.
WPC to list down the tools and equipment
used for baseline monitoring instead of the
grinder, low level noise generator set and

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

CH2M

Removed

CH2M

No monitoring will be done as the noise and


vibration generated from BT-GR Consortium not

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

PDPs Comment

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response


that of concern level due to the nature of job

drill. Please correct it.


11.

6.2 Baseline Monitoring final paragraph

Statement by WPC on BT- GR


Consortium will not do the monitoring by
appointing consultant and others is not
compliance to GS 8.12 (2) and 8.25 (1).

CH2M

No monitoring will be done as the noise and


vibration generated from BT-GR Consortium not
that of concern level due to the nature of job

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

12.

Design/Document / Drawings No.

6.3.1 2) Sensitive Receptor.

PDPs Comment
WPC shall re-write this sentence to
elaborate arrangement for engaging
accredited laboratory to carry out
monitoring on noise and vibration stated in
the DEIA and associated approval
conditions.
Noise exposure to construction workers is
occupational health hazard and not

Reviewers
Name

CH2M

Status

Comment
Code

WPCs / Consultants Response

Removed

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

13.
14.

Design/Document / Drawings No.

PDPs Comment

6.3.1 4) Impacts to the Environment: first


bullet point

categorised under sensitive receptor in


environmental impact. Please remove this.
Disturbances and annoyance to workers is
not impact to environment. Please remove
this.
Possibility of hearing loss or impairment
particularly for workers who are exposed

6.3.1 4) Impacts to the Environment:


second bullet point

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

CH2M

Removed

CH2M

Removed

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

PDPs Comment

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

to high noise level over an extended


period is occupational health hazard and
not impact to environment. Please remove
this.
15.

6.3.2 1) Applicable Environmental


Regulations, Guidelines and DOE
Approval Conditions first bullet point

Do not understand this sentence. WPC to


rewrite with better clarity.

CH2M

Rewritten

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

16.

6.3.2 final paragraph

17.

7 OTHERS

PDPs Comment
This paragraph should read as vibration
related mitigation and noise. Please
amend sentence accordingly.
The elaboration of this paragraph is not
acceptable. WPC is not an authority to
establish guideline.
This NVCMP should read as working
document prepared by WPC to explain

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

CH2M

Amended

CH2M

Omitted and included in Section 1.1

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

PDPs Comment

18.

General

how to control and manage the noise and


vibration requirement required under GS
and legislation.
WPC to omit this section and include it
under section 1.1 purpose.
Comply to the guideline and format given.

19.

References

Item no.7 Local Authority Provisions. Detail

Reviewers
Name

PDP HSE
PDP HSE

Status

Comment
Code

WPCs / Consultants Response

Rewritten

Detailed out and included The Planning

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

5.2 Environmental Organization Chart


20.
21.

5.3 Roles and Responsibilities

PDPs Comment
out and include The Planning Guidelines
for Environmental Vibration Limits and
Control (2007).
The name in the org chart for EM is his full
time handling EM?
The roles and responsibilities listed for all

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

Guidelines for Environmental Vibration Limits


and Control (2007).
PDP HSE
3
PDP HSE

For this while, the EM appointed is Mr. B.


Nagavinotha. He is also a Safety & Health
Manager

Rewritten

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

22.
23.

Design/Document / Drawings No.

Section 6.2 Baseline Monitoring

Section 6.3.1 (4) Potential Impacts to the

PDPs Comment
does not link anything on this plan. It
should be how they are involved in
managing the noise and vibration control.
This section should not be copy paste from
GS. WPC to elaborate on the monitoring
locations if monitoring shall be carried out.
That line is not referring to the impact to

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

PDP HSE

PDP HSE

Monitoring shall not be carried out

Removed

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.


Environment

24.

Section 6.3.2 Proposed Vibration


Mitigation Measures Program

25.

General

PDPs Comment
environment but human which is more of a
safety
The para according to GS 8.25 (10) .
And last para contradicts. Rewrite the
statement.
to include the noise and vibration control
mitigation measure operation hour from

Reviewers
Name

Status

Comment
Code

WPCs / Consultants Response

PDP HSE

PDP

Rewritten the section

Included in Section 1.2 and Section 6

(Open/
Closed)

MMC CORPORATION BERHAD GAMUDA BERHAD JOINT VENTURE

Revision 01

PROJEK MASS RAPID TRANSIT LALUAN 2 SUNGAI BULOH SERDANG PUTRAJAYA (SSP)

D E S I G N / DOCUMENT R E V I E W REQUEST (DRR) S H E E T


R

Item

Design/Document / Drawings No.

PDPs Comment
8am to 7pm and no work for sunday and
public holiday

Note: Comment Code 1 Approved


Comment Code 2 Approved with Comment
Comment Code 3 Rejected

Reviewers
Name

Comment
Code

Status
WPCs / Consultants Response

(Open/
Closed)