Вы находитесь на странице: 1из 326

BENGUET 2nd ENGINEERING DISTRICT

PROGRAMMING UNIT
Please fill up necessary data below:
Name of Project
:
Limits
:
Location
:
APPROPRIATION :
Prepared By
Position

BIG TANGO

Impvmt. Along Bayoyo-Yogo Road


Sta. 09+200- Sta. 16+825 (v.s.)
Bakun, Benguet
P1,000,000.00

Date Prepared
Length
Classification
Source of Fund
Starting Date

: ASTERIO D. AUSTRIA
: Draftsman II

Tax:
Det. Est. Mark -Up:
AAE Mark - up :

7-Jun-02

10%

Submitted By: EDGARDO M. GUNDRAN


Position
: Unit Head, Panning & Design
Item 102-A: Roadway Excavation (Earth)
Quantity :
5,200
cu.m.
If hauled out, volume =
cu.m.
Item 102-B Roadway Ecavation (S.R.)
Quantity :
70
cu.m.
Item
103 Structure Excavation
Quantity :
60
cu.m.
No. of Laborers:
5
Item
104 Embankment
Quantity :
1
cu.m.
No. of Laborers:
Item
105 Subgrade Preparation
Quantity :
sq.m.
No. of Laborers:
Item
201 Aggregate Base Course
L(m)=
W(m)=
T(m)=
No. of Laborers:
Item
311 Portland Cement Concrete Pavement
L(m)= 416 W(m)=
3
T(m)=
Dowels
20
Form lumbers
250
Template
3
Asphalt sealant
1
Hardwares
500
Item
404 Reinforcing Steel
16mm
12mm
10mm
Item
405 Structural Concrete
Quantity :
190
cu.m.
Form lumbers
200
Plywood
10
Hardwares
500
Item
500 RC Pipes
See Table
Quantity :
38
ln.m.
Size of RC pipes
24"
Laborers :
7
Capability :
Item
502 Catch Basin
Quantity :
1
unit
Form lumber
50
Plywood
3
Rebars
16
Hardwares
200
Item
504 Grouted Riprap
Quantity :
50
cu.m.
pcs. PVC pipes
15
Item
506 Handlaid Rock Embankment
Quantity :
290
cu.m.
Laborers :
5
Item
600 Curb & Gutter
Quantity :
416
l.m.

Length

Width

0.15

Enter Factor below !


Cement
Sand
0.70
0.038
6
/crew/day

SIZE
mm.
inches Cap. Of crew
610
24"
8 pcs./day
900
36"
6 pcs./day
1200
48"
3pcs./day

volume
1.2
1 Unit =
1.20 cu.m.
11 bags cement
0.60 cu.m. sand
1.0 cu.m. gravel

cu.m.

Thickness

0.2

16 pcs. 10 mm. Dia. RSB


3 pcs. 1/4" plywood
20 bd.ft. (10-2"x2"x6') form lumber

Form lumber
350
Hardwares
500
Item
601 Sidewalk
Quantity :
90
Form lumber
300
Hardwares
200
Item
611 Tree Planting
Quantity :
100
Item SPL-1 Reinforced Concrete Canal
Quantity :
100
Rebars (Longitudinal)
Form lumber
Plywood
Hardwares(amount)
Item SPL-2 Rockfill
Quantity :
Laborers :
5
Item SPL-3 Billboard
Quantity :
1
PRICES OF CONSTRUCTION MATERIALS

sq.m.

pcs.
ln.m.
Spacing
Thickness
Perimeter L

0.15
1.5

pcs. RSB
volume

cu.m.

pc.

TABLE1: Unit Prices of Construction Materials


TYPE OF MATERIALS
Cement
Sand
Gravel
Boulders
Filling Materials
Agg. Base Course
Agg. Sub-Base Course
Rockfill
Reinf. Bars(kilos)
1"dia.
3/4" dia.
5/8" dia.
1/2" dia.
3/8" dia.
Tie Wires
C.W. Nails
RC pipes Culverts
PVC pipes
Lumber (bd.ft.) 4" and below
Lumber (bd.ft.) 4" and above
Lumber (bd.ft.) 3" thick and above
Board Lumber
plywood, 4' x 8" x 1/4"
Dynamites
Blasting Caps
Fuse
Asphalt Sealant
Haul out Earth

#26 Corr. GI Sheet


#26 Plain GI Sheet x 8'
# 26 GI Flashing
# 26 GI Ridge Roll
Roof Fasteners
Flat Head GI Nails
VULCASEAL
Machine Bolts:
5/8" dia. x 7"
5/8" dia. x 8"
5/8" dia. x 9"
5/8" dia. x 10"
5/8" dia. x 12"

Perimeter
Length(a+b) 0.7
Volume
58.24
Length
75
Thickness
0.1
Width
1.2
Volume
9

COST
UNIT
P261.00 Per bag
P1,269.00 Per cu.m.
P0.00 Per cu.m.
P38.60 Per cu.m.
P150.00 Per cu.m.
P0.00 Per cu.m.
Per cu.m.
P250.00 Per cu.m.
P16.00 Per kgs.
P16.00 Per kgs.
P16.00 Per kgs.
P16.00 Per kgs.
P16.00 Per kgs.
P16.00 Per kgs.
P35.00 Per Kilogram
P30.00 Per kilogram
P1,500.00 Per Piece
P350.00 Per piece
P18.00 Per Bd.ft.
P26.00 Per Bd.ft.
P32.00 Per Bd.ft.
P30.00 Per Bd.ft.
P250.00 Per piece
P1,905.00 per case
P700.00 per box
P7.70 per meter
P3,200.00 per drum
P150.00 per cu.m.

P28.00 per Lin. m.


P260.00 per pc.
P150.00 per pc.
P150.00 per pc.
P50.00 per kilo
P80.00 per kilo
P225.00 per Li.
P24.50 per pc.
P27.00 per pc.
P31.50 per pc.
P35.00 per pc.
P42.00 per pc.

#VALUE!
22.5

Circular Washers
Fixed Hunges, 3" x3"
Loose Pin Dr Hinges, 4"x4"
Hook and Eye, 3"
Hook and Eye, 6"
Clear glass, 1/8" x 14" x 20"
Door Lock (yale)
Post Straps, 1/4" x 2" x 16"
Panel Door
Window Sash
5/8" dia. tension Rod X 1.50 m w/washer
1/4" x 2" x 12" Steel Strap w/ bolts, N & W
3/8" x 4" x 4" angle plate
1200 mm diameter
900 mm diameter
760 mm diameter
600 mm diameter
450 mm diameter
300 mm diameter
Emulsified Asphalt
Pre-mix Asphalt
WIRE MESH
6" X 8" X 16" CHB
2.80 m X 1.50 m Steel Window
1.40 m X 1.50 m Steel Window
.60 m X .40m Steel Window
1.00 m. X 2.10 m. Steel Door
.60 m. X 2.10 m. Steel Door
250mm X 350 mm X 3 mm Clear Glass
150mm X 400 mm X 3 mm Clear Glass
250mm X 700 mm X 3 mm Clear Glass
Glass Putty
Glass Pin
Barrel Bolt

P1.50 per pc.


P35.00 per pc.
P45.00 per pc.
P6.00 per pc.
P9.00 per pc.
P40.00 per pc.
P450.00 per pc.
P45.00 per pc.
P2,500.00 per pc.
P250.00 per pc.
P243.00 per pc.
per pc.
P67.00 per pc.
P95.00 per pc.
P2,200.00 per piece
P1,500.00 per piece
P1,300.00 per piece
P1,000.00 per piece
P800.00 per piece
P600.00 per piece
P2,600.00 per drum
P1,356.00 per ton
P80.00 per sq.m.
P12.00 per pc.
P1,200.00 per sq.m.
P1,200.00 per sq.m.
P1,200.00 per sq.m.
P3,500.00 per pc.
P1,000.00 per pc.
P55.00 per pc.
P30.00 per pc.
P105.00 per pc.
P45.00 per pair
P1.00 per pc.
P15.00 per pc.

Table 2: Daily Wage Rates of Personnel


PERSONNEL
Civil Engineer, Electrical Engineer, Materials
Engineer, Mech Engineer, Geodetic Engineer
Geologist
Construction Foreman
Laboratory Technician, Licensed Blaster
Painter, Instrumentman, construction capataz
Core drillers,or well driller
Steelman,Mason, carpenter
Skilled Laborers
Unskilled Laborers

Table 3: Equipment Rental Rates

DAILY RATE (P)


P625.55
P277.30
P277.30
P209.90
P231.15
P209.90
P209.90
P194.70

FACTOR per joint


Cement
Sand
Crew composition
0.35 bag
0.0196 cu.m.
6 laborers
0.70 bag
0.038 cu.m.
7 laborers
1.20 bag
0.065 cu.m.
7 laborers

rm lumber

UNIT COST DERIVATION OF CONSTRUCTION MATERIALS FOR


STO. TOMAS ROAD

UNIT COST DERIVATION OF CEMENT


A Hauling and Loading
Quantity:

#REF! bags

Assume Ave. Cap. of 1 CT

No. of bags/Cargotruck

5,000

kg.

5,000

kg.

40

kg. /bag

Loading Time :(Employing 5 Laborers)


125.00

bags x 1min./bag/man-day
5

B Handling
Total Hauling Dist.

60 km.

(From Baguio City to Project Site)

60 kms x

60

A) La Trinidad to Acop Junction, Hauling Distance =


Loaded Trip

Unloaded Trip

25

min/hr
kms/hr

60 kms x

60
30

min/hr
kms/hr

Loading Time
Unloading Time
Slack Time
Total Cycle Time
Utilizing
No. of days required

Cargotruck,
#REF!

bags

480.00 mins/day
320.00 mins./trip

CT x 125 bags
trip

1 Equipment Cost:
1 Cargotruck

1 CT x

P4,744.00 /day x

2 Labor Cost (@ 5 laborers/cargotruck, Total laborers required to load and unload the 1 Cargotruck = 5 laborers)
5 Laborers

Cost/bag at source

Total Cost of hauling

5 lab. x
216 /bag
#REF!
#REF!

Unit Cost of Hauling


Total Cost/bag

P258.51 /day x

#REF!
=

216

#REF!

UNIT COST DERIVATION OF RSB


Quantity:

#REF! kgs.

A Hauling and Loading


Source

Hauling Distance

La Trinidad
28 km.

(From La Trinidad to Project Site)

Assume Capacity of 1 Cargo Truck

5,000

Assume Capacity of 1 Laborer can carry 30 kgs. Of RSB


Loading Time :(Employing 6 Laborers)
5,000

kgs. X

30

1
kgs./man-day x

B Handling
A) La Trinidad to Acop Junction, Hauling Distance =
Loaded Trip

Unloaded Trip

8.8 kms.
8.8 kms x

60
25

min/hr
kms/hr

8.8 kms x

60
30

min/hr
kms/hr

B) Acop Junction to Project site, Hauling Distance =


Loaded Trip

Unloaded Trip

19.2 kms.
19.2 kms x

60
15

min/hr
kms/hr

19.2 kms x

60
20

min/hr
kms/hr

Loading Time
Unloading Time
Manuevering Time
Total Time

Utilizing
No. of days required

1
=

Cargotruck,
#REF!
480.00 mins/day
234.68 mins./trip

kgs
x

CT x 5000 kgs
trip

1 Equipment Cost:
1 Cargo Truck

CT x

P4,744

/day x

6 Laborers

Lab. x

P258.51

/day x

Cost/kg. at source

Total Cost of hauling

2 Labor Cost

58 /kg.
#REF!
#REF!

Unit Cost of Hauling

#REF!

Total Cost/kg

58.00

#REF!

UNIT COST DERIVATION OF RCPC


A Hauling, Loading and Unloading
Quantity
910 mm. Diam.

12.00 pcs.

14 pcs.

Source

(Baguio City, to Project Site)

Total Hauling Distance

32 km.

Assume Capacity of 1 Cargo Truck


910 mm. Diam.
Cycle Time

A) Baguio to Acop Junction, Hauling Distance =


Loaded Trip

Unloaded Trip

12.8 kms.
12.8 kms x

60
25

12.8 kms x

min/hr
kms/hr

60
30

min/hr
kms/hr

B) Acop Junction to Project site, Hauling Distance =


Loaded Trip

Unloaded Trip

19.2 kms.
19.2 kms x

60
15

19.2 kms x

min/hr
kms/hr

60
20

min/hr
kms/hr

Loading Time
Unloading Time
Manuevering Time
Total Time

No. of days Required

12.00
480.00

min/day x

ln.m.
14

pcs.

225.72 mins
1 Equipment Cost:
1 Cargotruck

P4,744

/day x

0.50 days

1 Chain Block

P500

/day x

0.50 days

2 Labor Cost (For Loading & Unloading)


6 Laborers

Lab. x

P258.51

/day x

Unit Cost Hauling


910 mm. Diam.

P3,397.53

total/

910 mm. Diam.

P3,000.00

/pc.

910 mm. Diam.

P3,000.00

12

pcs.

Cost/ln.m.@ source

Total Unit Cost


P283.13

UNIT COST DERIVATION OF COARSE & FINE AGGREGATES

A.)Coarse Aggregates
Volume

#REF!

cu.m.

Considering 15% Swell Factor, Total Vol. Req'd. =

#REF! cu.m.

a. Quarrying
Assume Quarry to Contain 30% Coarse Aggregate Materials
Volume of unprocessed materials

#REF!

Assumed Capacity/day of D4 bulldozer to quarry unprocessed aggregates =


No. of days

#REF!

/210

Quarrying Cost
1 D4 Bulldozer

D4 bulldozer x

P6,968

/day

b. Screening and Stockpiling


Assuming 2 mins cycle time for screening, stockpiling, and clearing of waste for a Loader of 1.20cu.m.-bucket ave. cap.

Loader Capacity/day

No. of days

6 hrs./day x

60 min.x 1.20 cu.m.

2 mins/cycle x

hr.

bucket

#REF!
216.00

#REF!

P6,728

/day x

cu.m.

Screening and Stockpilling Cost


1 Loader

Loader x

Materials Cost(2 Sets Screen - L.S.)

2. Hauling and Stockpilling


Volume required

#REF!

cu.m.

Cycle Time
Ave. Hauling Distance

70 kms.

Loading Time

5 min.

Unloading Time

2 min.

Slack Time

6 min.

(Naguilian Quarry to project site)

A) Source to Project Site, Hauling Distance =


Loaded Trip

Unloaded Trip

50.8 kms.
50.80 kms x

60
25

50.80 kms x

60
30

Unloaded Trip

Total Cycle Time

min/hr

kms/hr

B) Acop Junction to Project Ste, Hauling Distance =


Loaded Trip

min/hr

kms/hr

19.2 kms.
19.20 kms x

60
15

kms/hr

20

kms/hr

19.20 kms x

60

min/hr
min/hr

Utilizing 12 Dumptrucks with capacity of 5.00 cu.m.(Consider 15% Swell factor)


Capacity of 12 DT

No. of days Required

60 cu.m.
#REF!
8 x 60

cu.m.

mins./day x

370.920

60

cu.m.

mins.

Hauling Cost
12 Dumptrucks

12

CT x

P9,016

/day x

1 Loader

Loader x

P6,728

/day x

Total Direct Cost of Coarse Aggregates


Indirect Cost of Coarse Aggregates (12% Royalty Tax)
Total Cost of Coarse Aggregates

Unit Cost of Coarse Aggregates @ Project Site


B.)Fine Aggregates
- Treat Fine Aggregates as a by-product in the processing of Coarse Aggregates, therefore
Unit Cost can be reduced by as much as 10%.
Unit Cost

#REF!

0.90

UNIT COST DERIVATION OF BOULDERS


Source

Amburayan River, Kapangan

Total Hauling Dist.

Volume

167.00

1 Labor Cost
Picking, Hauling from the River and Stockpiling to the nearest Road.
Labor Capacity

1.5 cu.m./man-day

No. of Laborers

10

Total Output/day

15 cu.m.

km.
cu.m.

No. of days

Labor

167.00

cu.m./

10

15

Lab. X

=
11.00

days x

2 Equipment Cost:
Utilizing 2 Dumptrucks with capacity of 5.00 cu.m./DT.
Capacity of 4DT

10 cu.m.

Loading Time

6 min.

Unloading Time

2 min.

Slack Time

6 min.

Hauling Distance

6 kms

Loaded Trip

Unloaded Trip

6 kms x

60
10

kms/hr

6 kms x

min/hr

60
15

min/hr
kms/hr

Total Cycle Time


No. of days Required

167.00

8 x 60

cu.m.

mins./day x

74.000

10

cu.m.

mins.

2 Dumptrucks

DT x

P9,016

/day x

1 Loader

Loader x

P6,728

/day x

Total Direct Cost

Direct Unit Cost

Indirect Unit Cost

P102,716.10
P102,716.10
167.00
12% Royalty Tax

Total Unit Cost of Boulders @ Project Site

UNIT COST DERIVATION OF AGGREGATE BASE COARSE


Volume

349.80

cu.m.

Considering 15% Swell Factor, Total Vol. Req'd. =

402.27 cu.m.

Source

Amburayan River, Kapangan

Hauling Distance

4 km.

Loaded Trip

Unloaded Trip

4 kms x

60
10

4 kms x

min/hr
kms/hr

60
15

min/hr
kms/hr

Loading Time
Unloading Time
Slack Time
Total Time
a. Quarrying
Note: Backhoe is used to quarry because of limited space
Assume Quarry to Contain 30% Coarse Aggregate Materials
Volume of unprocessed materials

349.80

Assumed time elapse for a 0.70cu.m. Backhoe to quarry 1 bucket of unprocessed aggregates =
Effective working hours of Backhoe/day
Output of 1 Backhoe/day =

6 hrs. x
day

No. of days

60 mins x

1 cyle

hr.

2mins

1,166.00

0.70cu.m.
cycle
/126

Quarrying Cost
1 Backhoe

Backhoe x

P7,608

/day

b. Screening and Stockpiling


Assuming 2 mins cycle time for screening, stockpiling, and clearing of waste for a Loader of 1.20cu.m.-bucket ave. cap.
Loader Capacity/day

6 hrs./day x

No. of days

60 min.x 1.20 cu.m.

2 mins/cycle x

hr.

bucket

1,166.00
216.00

5.40

P6,728

/day x

cu.m.

Screening and Stockpiling Cost:


=

1 Loader

Loader x

Materials Cost(1 Set Screen - L.S.)


c. Hauling
Utilizing 4 Dumptrucks with capacity of 5 cu.m.(Consider 15% Swell Factor)
Capacity of 4 DT

No. of days Required

20 cu.m.
419.76
8 x 60

cu.m.

mins./day x

53.000

20

cu.m.

mins.

Hauling Cost
4 Dumptrucks

DT x

P9,016

/day x

1 Loader

Loader x

P6,728

/day x

Total Cost
Unit Cost

V)UNIT COST DERIVATION OF COARSE & FINE AGGREGATES


1. Canvassed Actual Prevailing Pick-up Price from a Crusher Plant for Processed Aggregates
Fine Aggregates
Coarse Aggregates
2. Hauling and Stockpilling
Volume required

4,935.70

cu.m.

Cycle Time
Ave. Hauling Distance

39.3 kms.

Loading Time

5 min.

Unloading Time

1 min.

Slack Time

Loaded Trip

Unloaded Trip

(From Amburayan River,Bulaga to Project Site)

6 min.
39.3 kms x

60
15

39.3 kms x

min/hr
kms/hr

60

min/hr

Unloaded Trip

20

kms/hr

Total Cycle Time


No. of Trips/day

8 hrs x

60

min/hr

287.10

mins

Utilizing 8 Dumptrucks with capacity of 5 cu.m.(Consider 15% Swell factor)


Capacity of 8 DT

40 cu.m.

No. of days Required

Equipment Cost
8 Dumptrucks

1 Loader

5,676.06
1.670

cu.m.

trips/day x

40

cu.m.

CT x

P9,016

/day x

Loader x

P6,728

/day x

Unit Cost of Hauling


3. Aggregate Tax
4. 2% Excise Tax for Fine Aggregates
5. 2% Excise Tax for Coarse Aggregates
6. Total Unit Cost of Fine Aggregates @ Construction Site
7. Total Unit Cost of Fine Aggregates @ Construction Site

UNIT COST DERIVATION OF COARSE & FINE AGGREGATES


A.)Coarse Aggregates
Volume

#REF!

cu.m.

Considering 15% Swell Factor, Total Vol. Req'd. =

#REF! cu.m.

a. Quarrying (Assume Quarry to Contain 30% Coarse Aggregate Materials)


Volume of unprocessed materials

#REF!

Capacity of D4 Bulldozer to quarry unproccesed materials in a day


No. of days
Equipment Cost
1 D4 Bulldozer

=
=

#REF!

D4 Bulldozer x

/210

P6,968

/day

#REF!

P6,728

/day x

b. Screening and Stockpiling(includes clearing of waste materials)


Utilizing 1 - Payloader with an average capability of 200 cu.m./day
No. of days

Equipment Cost
1 Loader

#REF!
200

cu.m.

Loader x

Materials Cost(2 Sets Screen - L.S.)


TOTAL PRODUCTION COST OF COARSE AGGREGATES
Production Unit Cost
2. Hauling and Stockpilling
Volume required

#REF!

cu.m.

Cycle Time
Ave. Hauling Distance

38 kms.

(From Amburayan River,Bulaga to Proposed Batching Plant)

Loading Time

5 min.

Unloading Time

1 min.

Slack Time

6 min.

Loaded Trip

Unloaded Trip

38.00 kms x

60
15

min/hr
kms/hr

38.00 kms x

60
20

min/hr
kms/hr

Total Cycle Time


No. of Trips/day

8 hrs x

60

min/hr

278.00

mins

Utilizing 12 Dumptrucks with capacity of 6.00 cu.m.(Consider 15% Swell factor)


Capacity of 12 DT

72 cu.m.

No. of days Required

Equipment Cost
12 Dumptrucks

12

1 Loader

#REF!
1.500

cu.m.

trips/day x

72

cu.m.

CT x

P9,016

/day x

Loader x

P6,728

/day x

Unit Cost of Hauling


3. Aggregate Tax
4. 2% Excise Tax
Unit Cost of Coarse Aggregates @ Batching Plant
B.)Fine Aggregates
- Treat Fine Aggregates as a by-product in the processing of Coarse Aggregates, therefore
Unit Cost can be reduced by as much as 10%.
Unit Cost

#REF!

0.90

UNIT COST DERIVATION OF COARSE & FINE AGGREGATES


A.)Coarse Aggregates
Volume

#REF!

cu.m.

Considering 15% Swell Factor, Total Vol. Req'd. =

#REF! cu.m.

a. Quarrying (Assume Quarry to Contain 30% Coarse Aggregate Materials)


Volume of unprocessed materials

#REF!

Capacity of D4 Bulldozer to quarry unproccesed materials in a day


No. of days
Equipment Cost
1 D4 Bulldozer

=
=

D4 Bulldozer x

#REF!

/210

P6,968

/day

#REF!

P6,728

/day x

b. Screening and Stockpiling(includes clearing of waste materials)


Utilizing 1 - Payloader with an average capability of 200 cu.m./day
No. of days

Equipment Cost
1 Loader

#REF!
200
1

cu.m.
Loader x

Materials Cost(2 Sets Screen - L.S.)


TOTAL PRODUCTION COST OF COARSE AGGREGATES
Production Unit Cost
2. Hauling and Stockpilling
Volume required

#REF!

cu.m.

Cycle Time
Ave. Hauling Distance

38 kms.

Loading Time

5 min.

Unloading Time

1 min.

Slack Time

6 min.

(From Amburayan River,Bulaga to Proposed Batching Plant)

a) From Quarry Site to Tadian (7-15% Slope Dirt Road) =


Loaded Trip
Unloaded Trip

18.50

18.50 kms x

60
10

kms/hr

18.50 kms x

min/hr

60
15

min/hr
kms/hr

b)Tadian to Maba-ay Junction (below 7% Slope Dirt Road) =


Loaded Trip

Unloaded Trip

19.50

19.50 kms x

60
15

min/hr
kms/hr

19.50 kms x

60
20

min/hr
kms/hr

Total Cycle Time


No. of Trips/day

8 hrs x

60

min/hr

333.50

mins

Utilizing 12 Dumptrucks with capacity of 6.00 cu.m.(Consider 15% Swell factor)


Capacity of 12 DT

72 cu.m.

No. of days Required

Equipment Cost
12 Dumptrucks

12

1 Loader

#REF!
1.000

cu.m.

trips/day x

72

cu.m.

CT x

P9,016

/day x

Loader x

P6,728

/day x

Unit Cost of Hauling


3. Aggregate Tax
4. 2% Excise Tax
Unit Cost of Coarse Aggregates @ Batching Plant
B.)Fine Aggregates
- Treat Fine Aggregates as a by-product in the processing of Coarse Aggregates, therefore
Unit Cost can be reduced by as much as 10%.
Unit Cost

#REF!

0.90

ION MATERIALS FOR

OF CEMENT

125.00

say

125.0

25

144.00

mins

120.00

min.

25.00

min.

25.00

min.

6.00

min.

320.00

min.

#REF!

days

#REF!

days

#REF!

#REF!

days

#REF!

=
#REF!

say

bags

min.

#REF!
#REF!

N OF RSB

kgs.

min

6.00

laborers

21.12

17.60

76.80

57.60

min.

27.78

min.

27.78

min.

6.00

min.

234.68

min.

#REF!

27.78

min.

mins
min.

mins

say

0.5

day

#REF!

day

#REF!

day

#REF!

#REF!

#REF!

#REF!

F RCPC

30.72

25.60

76.80

57.60

min.

15.00

min.

15.00

min.

5.00

min.

225.72

min.

0.40

mins
min.

mins

say

0.50

2,372.00

day

2.1265284

250.00
2,622.00

0.50

days

FINE AGGREGATES

P3,283.13

P775.53

283.13

say

P3,283.00 /pc.

/30%

#REF!

cu.m.
210.00 cu.m.

#REF!

say

#REF!

#REF!

#REF!

216.00

c.m.

say

#REF!

days

#REF!

days

#REF!

P30,000.00
#REF!

121.92

mins

101.60

76.80

57.60

min.

370.92

min.

min.

mins

days

OULDERS

#REF!

say

#REF!

days

#REF!

days

#REF!

days

#REF!
#REF!

#REF!
#REF!
#REF!

#REF!

say

#REF! say

#REF!

/cu.m.

#REF! /cu.m.

#DIV/0!

11.13

say

11 days

258.51

/day

36.00

mins

24.00

min.

74.00

min.

2.57

say

3.00

days

P54,096.00

3.00

days

P20,184.00

P28,436.10

3.0

day

P74,280.00

P615.07 /cu.m.

73.81 /cu.m.

688.88

say

689.00

/cu.m.

6.49

TE BASE COARSE

24.00

16.00

min.

5.00

min.

2.00

min.

6.00

min.

53.00

min.

/30%

mins

1,166.00

=
=

=
x

126.00

9.25

mins

6.00

hrs.

cu.m./day of unprocess material

say
9.00

cu.m.

2.00

9.0
=

P68,472.00

days

216.00

c.m.

say

5.00

days

#REF!
5.00

days

P33,640.00
P16,000.00
P49,640.00

2.32

say

2.00

2.00

days

P72,128.00

2.00

days

P13,456.00
P85,584.00

P203,696.00

P506.37 /cu.m.
say

506.00 /cu.m.

475.00 /cu.m.
575.00 /cu.m.

Bulaga to Project Site)

157.20

117.90

mins
min.

days

9.06

#REF!

117.90

min.

=
=

287.10

min.

1.67

trips

84.97

say

85.00

days

P6,130,880.00

85.00

days

P571,880.00

1,358.02

/cu.m.

30.00

/cu.m.

9.50

/cu.m.

11.50

/cu.m.

1,872.52

/cu.m.

1,974.52

/cu.m.

85

days

P6,702,760.00

FINE AGGREGATES

/30%

=
=
=

#REF!

#REF!
210.00
say

cu.m.

cu.m./day
#REF!

#REF!

#REF!

say

#REF!

days

#REF!

days

#REF!

P30,000.00
#REF!

#REF!
=

Bulaga to Proposed Batching Plant)

#REF! /cu.m.

days

152.00

mins

114.00

min.

=
=

278.00

min.

1.73

say

1.50

trips

#REF!

say

#REF!

days

#REF!

days

#REF!

days

#REF!

/cu.m.

30.00

/cu.m.

#REF!

/cu.m.

#REF!

/cu.m.

#REF!
#REF!

#REF! /cu.m.

FINE AGGREGATES

/30%

=
=
=

#REF!

#REF!
210.00
say

cu.m.

cu.m./day
#REF!

#REF!

say

#REF!

days

#REF!

days

#REF!

#REF!

days

P30,000.00
#REF!

#REF!
=

#REF! /cu.m.

Bulaga to Proposed Batching Plant)

kms.
=

111.00

mins

74.00

78.00

58.50

min.

=
=

333.50

min.

1.44

say

1.00

trip

#REF!

say

#REF!

days

#REF!

days

#REF!

days

#REF!

/cu.m.

30.00

/cu.m.

#REF!

/cu.m.

#REF!

/cu.m.

min.

kms.
mins

#REF!
#REF!

#REF! /cu.m.

REGION
DISTRICT
PROJECT TITLE

: CAR
: BFDEO
: Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (N

WORK PROGRAM SCHEDULE


ITEM

DESCRIPTION

QUANTITY

B.4(10) Miscellaneous survey and staking

UNIT

1.00

l.s.

B.5

Project Billboard / Signboard

1.00

l.s.

B.7

Occupational Safety and Health Program

6.00

month

B.9

Mobilization / Demobilization

1.00

l.s.

B.13

Additional Geotechnical Investigation

1.00

l.s.

192.40

ln.m.

403 (4) Structural Steel, furnished, and fabricated - Purlins

3,844.20

kgs.

403 (5) Structural Steel, furnished, fabricated, and erected - Truss

6,998.50

kgs.

401 (1) Metal Railing

404 (1) a Reinforcing Steel


801(1) Removal of Actual Structures/Obstruction
803 (1) a Structure Excavation

ESTIMATED DAYS/WEEKS LOST DUE TO BAD WEATHER, ETC.

SUBMITTED BY :
ROMEO D. DULAY
Chief, Planning & Design Section

1.00

l.s.

630.04

cu.m.

10

20

30

40

oom-Tuba NHS (Nangalisan)

CALENDAR DAYS
40

50

60

70

80

90

APPROVED :
DAVID A. BULIYAT
District Engineer

100

#REF!

#REF!

NAME OF PROJECT

Construction of Three(3) Storey N

SOURCE OF FUND

Sub-Allotment No.: SR2016-04-0057

APPROPRIATION

P15,631,203.07
STRAIGHT LINE DIAGRAM

ITEM NO.

DESCRIPTION

QUANTITY

UNIT

TOTAL

B.4(10)

Miscellaneous survey and staking

1.00

l.s.

100%

B.5

Project Billboard / Signboard

1.00

l.s.

100%

B.7

Occupational Safety and Health Program

6.00

month

100%

B.9

Mobilization / Demobilization

1.00

l.s.

100%

B.13

Additional Geotechnical Investigation

1.00

l.s.

100%

401 (1)

Metal Railing

192.40

ln.m.

100%

403 (4) Structural Steel, furnished, and fabricated - Purlins 3,844.20

kgs.

100%

403 (5)
Structural Steel, furnished, fabricated, and erected - Truss
6,998.50

kgs.

100%

SPL2.A

Removal of Actual Structures/Obstruction

1.00

l.s.

100%

SPL2.B

Structure Excavation

630.04

cu.m.

100%

10

20

30

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Sub-Allotment No.: SR2016-04-005755

STRAIGHT LINE DIAGRAM


40

50

60

70

80

PREPARED BY:

ROMUALDO T. APALIAS
Engineer II

90

100

APPROVED BUDGET FOR THE CONTRACT


Construction of Virac MPB
Camp 5, Virac, Itogon
Stations:
Length:

ITEM NO.

(1)
B.4(10)
B.5
B.7
B.9
B.13
401 (1)
403 (4)
403 (5)
404 (1) a
801(1)
803 (1) a
803 (3)
804 (1) b
900(a)
900(b)
900 ( c )
900 ( d )
900 (e)
900 (f)
900 ( g )
902
1001 (1) a
1001 (1) a3
1001 (1) a4
1001 (1) b1
1002 (1) a1
1002 (1) a3
1002 (1) a4
1002 (1) b1
1002 (1) b3
1002 (1) c3
1002 (1) c4
1002 (1) e1

Contract Duration:

DESCRIPTION

(2)
Miscellaneous survey and staking
Project Billboard / Signboard
Occupational Safety and Health Program
Mobilization / Demobilization
Additional Geotechnical Investigation
Metal Railing
Structural Steel, furnished, and fabricated - Purlins
Structural Steel, furnished, fabricated, and erected - Truss
Reinforcing Steel
Removal of Actual Structures/Obstruction
Structure Excavation
Foundation Fill (Gravel Bedding)
Embankment (From Borrow)
Reinforced Concrete (Footing)
Reinforced Concrete (Columns)
Reinforced Concrete (Foundation Beams to Ground Floor Level)
Reinforced Concrete (Second Floor Beams to Roof Beams)
Reinforced Concrete (Concrete Slab on grade)
Reinforced Concrete (Concrete Slabs @ Second Floor and Third Floor )
Reinforced Concrete (Concrete Stairs, Ramp and Sunbreaker)
Lean Concrete
Pipe - 50mm diameter PVC
Pipe - 100mm diameter PVC
Pipe - 150mm diameter PVC
Pipe - 150mm diameter Concrete Pipe
Fittings- 63mm diameter PVC 45deg. Elbow
Fittings- 110mm diameter PVC 45deg. Elbow
Fittings- 150mm diameter PVC 45deg. Elbow
Fittings- 63mm diameter PVC 90deg. Elbow
Fittings- 110mm diameter PVC 90deg. Elbow
Fittings- 110mm diameter PVC Cleanout with Plug
Fittings- 150mm diameter PVC Cleanout with Plug
Fittings- 63mm diameter P-Trap

QUANTITY

UNIT

ESTIMATED
DIRECT COST

MARK-UPS IN
PERCENT

TOTAL - MARK-UPS

OCM PROFIT

VAT

(3)

(4)

(5)

(6)

(7)

(8)

1.00
1.00
6.00
1.00
1.00
192.40
3,844.20
6,998.50
99,301.25
1.00
630.04
33.00
520.21
146.52
27.24
29.37
79.68
36.03
34.86
18.28
20.65
114.00
153.00
42.00
95.60
12.00
12.00
4.00
30.00
24.00
19.00
4.00
19.00

l.s.
l.s.
month
l.s.
l.s.
ln.m.
kgs.
kgs.
kgs.
l.s.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
ln.m.
ln.m.
ln.m.
ln.m.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.

8,094.98
10,631.82
79,523.74
122,868.02
142,000.00
186,422.19
265,824.01
630,500.90
4,352,626.64
2,722.37
74,758.11
53,639.52
53,883.18
743,806.47
156,323.56
131,885.48
362,524.50
151,758.26
178,789.25
102,185.38
72,026.42
12,658.26
27,487.68
52,539.42
56,414.50
973.08
1,441.08
1,086.54
2,132.70
3,596.16
2,755.62
2,184.54
3,114.62

9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%

8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%

17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%

VALUE
(9)
(5) x (8)
1,376.15
1,807.41
13,519.04
20,887.56
24,140.00
31,691.77
45,190.08
107,185.15
739,946.53
462.80
12,708.88
9,118.72
9,160.14
126,447.10
26,575.01
22,420.53
61,629.16
25,798.90
30,394.17
17,371.51
12,244.49
2,151.90
4,672.91
8,931.70
9,590.47
165.42
244.98
184.71
362.56
611.35
468.46
371.37
529.49

(10)
5%[(5)+(9)]
473.56
621.96
4,652.14
7,187.78
8,307.00
10,905.70
15,550.70
36,884.30
254,628.66
159.26
4,373.35
3,137.91
3,152.17
43,512.68
9,144.93
7,715.30
21,207.68
8,877.86
10,459.17
5,977.84
4,213.55
740.51
1,608.03
3,073.56
3,300.25
56.93
84.30
63.56
124.76
210.38
161.20
127.80
182.21

1001 (2) i1
1001 (2) j2
1001 (6) b
1001 (8)
1002 (4) e3
1002 (5) a1
1002 (5) b1
1002 (5) c1
1002 (6) b1
1002 (6) b2
1002 (6) b3
1002 (6) c1
1002 (6) c2
1002 (6) d1
1002 (6) d2
1002 (4) e1
1002 (4) e2
1002(9)
1002(10)
1002(11)
1002(12)
1002(13)
1003(1) a
1003(3)a
1005 (1)a
1006 (1)
1010(1)
1010(1)b
1012 (1) f4
1013(1)
1013(2)a
1013(2) b
1013(2)c
1013(3)
1016(1)a
1018(1)
1018(2)
1021(1)a
1027(1)
1032(1)a
1032(1)b
1032(1)c
1035
1043(2) a
1043(2) b
1044(1)

Fittings- PVC 110mm dia. x 63mm dia. (2" x 2") Reducer - Sanitary Tee
Fittings- PVC 110mm dia. x 63mm dia. (4" x 2") Reducer - Sanitary Wye
Catch Basin - CHB
Three Chamber Septic Vault
Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 20mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 25mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 32mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 20mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 25mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 32mm PN10
Polyprophylene Random Copolymer (PPR-C) Tee -20mm PN10
Polyprophylene Random Copolymer (PPR-C) Tee -25mm PN10
Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -20mm PN10
Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -25mm PN10
Polyprophylene Random Copolymer (PPR-C) Coupling- 20mm PN10
Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Water Closet
Faucet, Plain Bibb, Brass 1/2"
Water Closet Flange
Tissue Holder
Concrete Counter Sink
Ceiling (4.5mm Fiber Cement Board)
Blackboard
Residential Casement
Hollow Steel Doors
Wooden Doors - Frames (Jambs, Sills, Head, Transoms and Mullions)
Wooden Doors - Flush
Glass and Glazzing
Corrugated Metal Roofing - Prepainted Long Span
Fabricated Metal Roofing Accessory -Ridge Roll
Fabricated Metal Roofing Accessory -Flashings
Fabricated Metal Roofing Accessory - Gutters
Roof Ventilators
Waterproofing-Cement Base
Glazed Tiles and Trims
Unglazed Tiles - Vitrified Floor Tile
Cement Floor Finish
Cement Plaster Finish
Painting Works - Masonry and Fiber Cement Painting
Painting Works - Metal Painting
Painting Works - Wood Paint
Furring Channel-Double Furring System
CHB Non Load Bearing Wall - 100mm
CHB Non Load Bearing Wall - 150mm
Forms and Falseworks

17.00
2.00
8.00
1.00
2.00
12.00
14.00
18.00
30.00
23.00
37.00
12.00
15.00
22.00
22.00
9.00
2.00
15.00
41.00
15.00
15.00
6.00
716.00
51.84
118.52
47.04
47.04
47.04
5.28
535.68
37.20
28.80
74.40
19.00
55.29
169.92
87.22
899.10
2,843.70
3,192.27
213.36
104.55
1,610.15
337.20
559.60
1.00

pcs.
pcs.
each
unit
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
set
pcs.
pcs.
pcs.
pc.
sq.m.
sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
sq.m
sq.m
ln.m.
ln.m.
each
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
ln.m.
sq.m.
sq.m.
l.s.

2,772.35
1,047.08
17,052.96
60,140.95
228.54
3,757.94
6,414.27
12,163.80
3,999.18
3,266.02
5,790.34
1,286.16
2,239.32
3,554.32
3,774.32
896.16
228.54
65,894.16
22,840.28
5,614.32
5,434.32
29,005.92
194,573.44
42,414.89
256,410.59
179,988.03
36,777.00
33,192.85
10,153.44
184,861.69
8,891.59
27,295.19
15,788.13
35,755.73
11,155.46
187,156.24
101,023.03
69,068.69
355,722.83
350,099.66
40,621.58
14,723.44
146,100.53
150,970.76
459,534.98
1,020,705.83

9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%

8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%

17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%

471.30
178.00
2,899.00
10,223.96
38.85
638.85
1,090.43
2,067.85
679.86
555.22
984.36
218.65
380.68
604.23
641.63
152.35
38.85
11,202.01
3,882.85
954.43
923.83
4,931.01
33,077.48
7,210.53
43,589.80
30,597.97
6,252.09
5,642.78
1,726.08
31,426.49
1,511.57
4,640.18
2,683.98
6,078.47
1,896.43
31,816.56
17,173.92
11,741.68
60,472.88
59,516.94
6,905.67
2,502.98
24,837.09
25,665.03
78,120.95
173,519.99

162.18
61.25
997.60
3,518.25
13.37
219.84
375.23
711.58
233.95
191.06
338.73
75.24
131.00
207.93
220.80
52.43
13.37
3,854.81
1,336.16
328.44
317.91
1,696.85
11,382.55
2,481.27
15,000.02
10,529.30
2,151.45
1,941.78
593.98
10,814.41
520.16
1,596.77
923.61
2,091.71
652.59
10,948.64
5,909.85
4,040.52
20,809.79
20,480.83
2,376.36
861.32
8,546.88
8,831.79
26,882.80
59,711.29

1100(1) h1
1100(1) h2
1100(7)a1
1100(4)d1
1100(4)d2
1100(7)a2
1100(7)a3
1100(7)b1
1100(7)b2
1100(8)b
1100(14)
1100(15)
1100(22)
1101(1)a2
1101(1)a3
1101(1)a4
1101(1)a5
1101(1)a8
1101(3)
1101(6)
1102(1)a
1102(1)b
1102(1)c
1103(1)a1
1103(1)a3
1103(1)a4
1201 (4)d
1201(4)e
1208 (2) a1
1209(1)

PVC Coupling 20mm diameter


PVC Coupling 25mm diameter
PVC Adapter 20mm diameter
PVC Elbow 20mmx90 deg.
PVC Elbow 25mmx90 deg.
PVC Adapter 20mm male diameter
PVC Adapter 25mm male diameter
Polyvinyl Chloride Pipes (PVC)-20mm
Polyvinyl Chloride Pipes (PVC)-25mm
GI Wire #16
Octagonal Junction Box PVC
Utility Boxes PVC
Grounding Rod Copperweld
Electrical Wire - 3.5mm TWG/THHN
Electrical Wire - 5.5mm TWG/THHN
Electrical Wire - 8.0mm TWG/THHN
Electrical Wire - 14 mm TWG/THHN
Electrical Wire - 38 mm TWG/THHN
Tumbler Switch Two-Gang
Duplex Convenience Receptacles
Panelboard Circuit Breaker Type - Main Distribution Panel (MDP)
Panelboard Circuit Breaker Type - LPA Flush Mounted, NEMA 1 Enclosure (Bolt-on Type)
Panelboard Circuit Breaker Type - LPB and LPC Flush Mounted, NEMA 1 Enclosure (Bolt-on Type)

Compact Flourescent Lamp (CFL)


Flourescent Lighting Fixture
Flourescent Lighting Fixture
Valves and Fittings
Floor Drain
Stainless Steel Railings
Fire Alarm System

416.00
8.00
4.00
52.00
4.00
496.00
149.00
208.00
4.00
12.00
124.00
91.00
2.00
18.00
0.24
0.11
0.10
0.20
15.00
36.00
1.00
1.00
2.00
6.00
58.00
90.00
6.00
16.00
2.00
1.00

pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
kgs.
pcs.
pcs.
length
roll
roll
roll
roll
roll
set
set
set
set
set
sets
sets
sets
pcs.
pcs.
set
l.s.

11,510.44
340.47
499.64
1,884.22
334.84
18,126.41
5,823.21
29,789.32
824.71
1,948.80
12,345.72
8,925.02
1,069.52
74,203.68
1,633.64
944.67
963.64
1,458.28
4,597.66
12,189.86
13,125.30
24,721.19
46,662.38
2,649.42
53,104.16
82,403.01
2,551.62
6,164.32
10,842.16
34,883.87

9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%
9%

8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%
8%

17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%
17%

1,956.77
57.88
84.94
320.32
56.92
3,081.49
989.95
5,064.18
140.20
331.30
2,098.77
1,517.25
181.82
12,614.63
277.72
160.59
163.82
247.91
781.60
2,072.28
2,231.30
4,202.60
7,932.61
450.40
9,027.71
14,008.51
433.78
1,047.93
1,843.17
5,930.26

673.36
19.92
29.23
110.23
19.59
1,060.39
340.66
1,742.68
48.25
114.00
722.22
522.11
62.57
4,340.92
95.57
55.26
56.37
85.31
268.96
713.11
767.83
1,446.19
2,729.75
154.99
3,106.59
4,820.58
149.27
360.61
634.27
2,040.71
-

TOTAL
Prepared/Submitted by:

ARNEL C. TANACIO
EngineerII
Member
Recommending Approval:

BENEDICTA C. MENDOZA
OIC - Asst. District Engineer

MARJORY B. BANAO
EngineerII
Member
Approved:

DAVID A. BULIYA
District Enginee

Contract Duration:
TOTAL
INDIRECT
COST
(11)
(9) + (10)
1,849.70
2,429.37
18,171.18
28,075.34
32,447.00
42,597.47
60,740.79
144,069.46
994,575.19
622.06
17,082.23
12,256.63
12,312.31
169,959.78
35,719.93
30,135.83
82,836.85
34,676.76
40,853.34
23,349.36
16,458.04
2,892.41
6,280.93
12,005.26
12,890.71
222.35
329.29
248.27
487.32
821.72
629.66
499.17
711.69

180

C.D.

TOTAL COST

UNIT COST

(12)
(5) + (11)
9,944.68
13,061.19
97,694.92
150,943.36
174,447.00
229,019.66
326,564.79
774,570.36
5,347,201.83
3,344.43
91,840.34
65,896.15
66,195.49
913,766.25
192,043.50
162,021.31
445,361.34
186,435.02
219,642.59
125,534.74
88,484.46
15,550.67
33,768.61
64,544.68
69,305.21
1,195.43
1,770.37
1,334.81
2,620.02
4,417.88
3,385.28
2,683.71
3,826.31

(13)
(12)/ (3)
9,944.68
13,061.19
16,282.49
150,943.36
174,447.00
1,190.33
84.95
110.68
53.85
3,344.43
145.77
1,996.85
127.25
6,236.46
7,050.06
5,516.56
5,589.37
5,174.44
6,300.71
6,867.33
4,284.96
136.41
220.71
1,536.78
724.95
99.62
147.53
333.70
87.33
184.08
178.17
670.93
201.38

ADJUSTED UNIT
COST
(14)
9,944.00
13,061.00
16,282.00
150,943.00
174,447.00
1,190.00
84.00
110.00
53.00
3,344.00
145.00
1,996.00
127.00
6,236.00
7,050.00
5,516.00
5,589.00
5,174.00
6,300.00
6,867.00
4,284.00
136.00
220.00
1,536.00
724.00
99.00
147.00
333.00
87.00
184.00
178.00
670.00
201.00

ADJUSTED TOTAL
COST
(15)
(14) x (3)
9,944.00
13,061.00
97,692.00
150,943.00
174,447.00
228,956.00
322,912.80
769,835.00
5,262,966.25
3,344.00
91,355.22
65,868.00
66,066.67
913,698.72
192,042.00
162,004.92
445,331.52
186,419.22
219,618.00
125,528.76
88,464.60
15,504.00
33,660.00
64,512.00
69,214.40
1,188.00
1,764.00
1,332.00
2,610.00
4,416.00
3,382.00
2,680.00
3,819.00

633.48
239.26
3,896.60
13,742.21
52.22
858.69
1,465.66
2,779.43
913.81
746.29
1,323.09
293.89
511.68
812.16
862.43
204.77
52.22
15,056.82
5,219.00
1,282.87
1,241.74
6,627.85
44,460.03
9,691.80
58,589.82
41,127.26
8,403.54
7,584.57
2,320.06
42,240.90
2,031.73
6,236.95
3,607.59
8,170.18
2,549.02
42,765.20
23,083.76
15,782.20
81,282.67
79,997.77
9,282.03
3,364.31
33,383.97
34,496.82
105,003.74
233,231.28

3,405.83
1,286.34
20,949.56
73,883.16
280.76
4,616.63
7,879.93
14,943.23
4,912.99
4,012.31
7,113.43
1,580.05
2,751.00
4,366.48
4,636.75
1,100.93
280.76
80,950.98
28,059.28
6,897.19
6,676.06
35,633.77
239,033.47
52,106.69
315,000.41
221,115.29
45,180.54
40,777.42
12,473.50
227,102.58
10,923.32
33,532.14
19,395.72
43,925.91
13,704.48
229,921.44
124,106.80
84,850.89
437,005.50
430,097.43
49,903.61
18,087.75
179,484.50
185,467.57
564,538.72
1,253,937.11

200.34
643.17
2,618.70
73,883.16
140.38
384.72
562.85
830.18
163.77
174.45
192.25
131.67
183.40
198.48
210.76
122.33
140.38
5,396.73
684.37
459.81
445.07
5,938.96
333.85
1,005.14
2,657.78
4,700.58
960.47
866.87
2,361.51
423.95
293.64
1,164.31
260.70
2,311.89
247.87
1,353.12
1,422.92
94.37
153.68
134.73
233.89
173.01
111.47
550.02
1,008.83
1,253,937.11

200.00
643.00
2,618.00
73,883.00
140.00
384.00
562.00
830.00
163.00
174.00
192.00
131.00
183.00
198.00
210.00
122.00
140.00
5,396.00
684.00
459.00
445.00
5,938.00
333.00
1,005.00
2,657.00
4,700.00
960.00
866.00
2,361.00
423.00
293.00
1,164.00
260.00
2,311.00
247.00
1,353.00
1,422.00
94.00
153.00
134.00
233.00
173.00
111.00
550.00
1,008.00
1,253,937.00

3,400.00
1,286.00
20,944.00
73,883.00
280.00
4,608.00
7,868.00
14,940.00
4,890.00
4,002.00
7,104.00
1,572.00
2,745.00
4,356.00
4,620.00
1,098.00
280.00
80,940.00
28,044.00
6,885.00
6,675.00
35,628.00
238,428.00
52,099.20
314,907.64
221,088.00
45,158.40
40,736.64
12,470.80
226,592.64
10,899.60
33,523.20
19,344.00
43,909.00
13,656.63
229,901.76
124,026.84
84,515.40
435,085.34
427,764.31
49,712.88
18,087.15
178,726.65
185,460.00
564,076.80
1,253,937.00

2,630.14
77.80
114.17
430.54
76.51
4,141.88
1,330.60
6,806.86
188.45
445.30
2,821.00
2,039.37
244.39
16,955.54
373.29
215.86
220.19
333.22
1,050.56
2,785.38
2,999.13
5,648.79
10,662.35
605.39
12,134.30
18,829.09
583.05
1,408.55
2,477.43
7,970.96
-

14,140.58
418.27
613.81
2,314.76
411.36
22,268.29
7,153.81
36,596.18
1,013.15
2,394.10
15,166.72
10,964.39
1,313.91
91,159.22
2,006.92
1,160.52
1,183.83
1,791.49
5,648.22
14,975.25
16,124.44
30,369.98
57,324.74
3,254.81
65,238.46
101,232.10
3,134.67
7,572.87
13,319.59
42,854.83
15,609,427.90

33.99
52.28
153.45
44.51
102.84
44.90
48.01
175.94
253.29
199.51
122.31
120.49
656.95
5,064.40
8,362.18
10,879.91
11,838.29
8,957.46
376.55
415.98
16,124.44
30,369.98
28,662.37
542.47
1,124.80
1,124.80
522.44
473.30
6,659.80
42,854.83

33.00
52.00
153.00
44.00
102.00
44.00
48.00
175.00
253.00
199.00
122.00
120.00
656.00
5,064.00
8,362.00
10,879.00
11,838.00
8,957.00
376.00
415.00
16,124.00
30,369.00
28,662.00
542.00
1,124.00
1,124.00
522.00
473.00
6,659.00
42,854.00

13,728.00
416.00
612.00
2,288.00
408.00
21,824.00
7,152.00
36,400.00
1,012.00
2,388.00
15,128.00
10,920.00
1,312.00
91,152.00
2,006.88
1,160.43
1,183.80
1,791.40
5,640.00
14,940.00
16,124.00
30,369.00
57,324.00
3,252.00
65,192.00
101,160.00
3,132.00
7,568.00
13,318.00
42,854.00
15,506,491.47

0.00
Err:509
102,936.43
15,552,866.92

Err:509
102,936.43

REAGAN G. PEDRO
Engineer II
Chairman

DAVID A. BULIYAT
District Engineer

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BENGUET 1st DISTRICT ENGINEERING OFFICE
Wangal, La Trinidad
Benguet
PROGRAM
Region
District
Name of Project
Road Section ID
Section
Location
Appropriation
Source of Fund
Classification
Station Limits
Net Length
Thickness
Width
Starting Date

OF WORK

: C.A.R.
: BED I
: Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS
(Nangalisan)
:
:
: Nangalisan, Tuba, Benguet
: P15,631,203.07
: Sub-Allotment No.: SR2016-04-005755
###
:
:
:

: Upon release of funds


ITEMS OF WORK
TO BE DONE
Miscellaneous survey and staking
Project Billboard / Signboard
Occupational Safety and Health Program
Mobilization / Demobilization
Additional Geotechnical Investigation
Metal Railing
Structural Steel, furnished, and fabricated - Purlins
Structural Steel, furnished, fabricated, and erected - Truss
Reinforcing Steel
Removal of Actual Structures/Obstruction
Structure Excavation
Foundation Fill (Gravel Bedding)
Embankment (From Borrow)
Reinforced Concrete (Footing)
Reinforced Concrete (Columns)
Reinforced Concrete (Foundation Beams to Ground Floor Level)
Reinforced Concrete (Second Floor Beams to Roof Beams)
Reinforced Concrete (Concrete Slab on grade)
Reinforced Concrete (Concrete Slabs @ Second Floor and Third Floor )
Reinforced Concrete (Concrete Stairs, Ramp and Sunbreaker)
Lean Concrete
Pipe - 50mm diameter PVC

Roadbed Width
Pavement Width
Bridge Width
Type of Structure
Type of Superstructure
Type of SubStructure
No. of Span : ____na____

:na
:na
:na
:School Building
:Reinforced Concrete
:Reinforced Concrete
No. of Piers :

Dimension
No. of Storeys
No. of Classrooms

:
:
:

No. of Days to Complete

%
0.064%
0.084%
0.628%
0.830%
0.959%
1.473%
2.100%
4.980%
34.381%
0.022%
0.591%
0.424%
0.426%
5.875%
1.235%
1.042%
2.864%
1.199%
1.412%
0.807%
0.569%
0.100%

9.50m x 36.00m
3
9
180

EQUIPMENT
DESCRIPTION
Backhoe (1.04 cu.m. Capacity)
Dumptruck (10 cu.m. Capacity)
Minor Tools 10% of Labor Cost
Plate Compactor
Concrete Vibrator
One Bagger Mixer
Welding Machine

Pipe - 100mm diameter PVC


Pipe - 150mm diameter PVC
Pipe - 150mm diameter Concrete Pipe
Fittings- 63mm diameter PVC 45deg. Elbow
Fittings- 110mm diameter PVC 45deg. Elbow
Fittings- 150mm diameter PVC 45deg. Elbow
Fittings- 63mm diameter PVC 90deg. Elbow
Fittings- 110mm diameter PVC 90deg. Elbow
Fittings- 110mm diameter PVC Cleanout with Plug
Fittings- 150mm diameter PVC Cleanout with Plug
Fittings- 63mm diameter P-Trap
Fittings- PVC 110mm dia. x 63mm dia. (2" x 2") Reducer - Sanitary Tee
Fittings- PVC 110mm dia. x 63mm dia. (4" x 2") Reducer - Sanitary Wye
Catch Basin - CHB
Three Chamber Septic Vault
Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 20mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 25mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 32mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 20mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 25mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 32mm PN10
Polyprophylene Random Copolymer (PPR-C) Tee -20mm PN10
Polyprophylene Random Copolymer (PPR-C) Tee -25mm PN10
Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -20mm PN10
Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -25mm PN10
Polyprophylene Random Copolymer (PPR-C) Coupling- 20mm PN10
Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Water Closet
Faucet, Plain Bibb, Brass 1/2"
Water Closet Flange
Tissue Holder
Concrete Counter Sink
Ceiling (4.5mm Fiber Cement Board)
Blackboard
Residential Casement
Hollow Steel Doors
Wooden Doors - Frames (Jambs, Sills, Head, Transoms and Mullions)
Wooden Doors - Flush
Glass and Glazzing
Corrugated Metal Roofing - Prepainted Long Span
Fabricated Metal Roofing Accessory -Ridge Roll
Fabricated Metal Roofing Accessory -Flashings
Fabricated Metal Roofing Accessory - Gutters
Roof Ventilators
Waterproofing-Cement Base
Glazed Tiles and Trims

0.217%
0.415%
0.446%
0.008%
0.011%
0.009%
0.017%
0.028%
0.022%
0.017%
0.025%
0.022%
0.008%
0.135%
0.475%
0.002%
0.030%
0.051%
0.096%
0.032%
0.026%
0.046%
0.010%
0.018%
0.028%
0.030%
0.007%
0.002%
0.520%
0.180%
0.044%
0.043%
0.229%
1.537%
0.335%
2.025%
1.422%
0.290%
0.262%
0.080%
1.460%
0.070%
0.216%
0.125%
0.282%
0.088%
1.478%

Unglazed Tiles - Vitrified Floor Tile


Cement Floor Finish
Cement Plaster Finish
Painting Works - Masonry and Fiber Cement Painting
Painting Works - Metal Painting
Painting Works - Wood Paint
Furring Channel-Double Furring System
CHB Non Load Bearing Wall - 100mm
CHB Non Load Bearing Wall - 150mm
Forms and Falseworks
PVC Coupling 20mm diameter
PVC Coupling 25mm diameter
PVC Adapter 20mm diameter
PVC Elbow 20mmx90 deg.
PVC Elbow 25mmx90 deg.
PVC Adapter 20mm male diameter
PVC Adapter 25mm male diameter
Polyvinyl Chloride Pipes (PVC)-20mm
Polyvinyl Chloride Pipes (PVC)-25mm
GI Wire #16
Octagonal Junction Box PVC
Utility Boxes PVC
Grounding Rod Copperweld
Electrical Wire - 3.5mm TWG/THHN
Electrical Wire - 5.5mm TWG/THHN
Electrical Wire - 8.0mm TWG/THHN
Electrical Wire - 14 mm TWG/THHN
Electrical Wire - 38 mm TWG/THHN
Tumbler Switch Two-Gang
Duplex Convenience Receptacles
Panelboard Circuit Breaker Type - Main Distribution Panel (MDP)
Panelboard Circuit Breaker Type - LPA Flush Mounted, NEMA 1 Enclosure (Bolt-on Type)
Panelboard Circuit Breaker Type - LPB and LPC Flush Mounted, NEMA 1 Enclosure (Bolt-on Type)

Compact Flourescent Lamp (CFL)


Flourescent Lighting Fixture
Flourescent Lighting Fixture
Valves and Fittings
Floor Drain
Stainless Steel Railings
Fire Alarm System

0.798%
0.546%
2.810%
2.765%
0.261%
0.116%
1.154%
1.192%
3.630%
8.062%
0.091%
0.003%
0.004%
0.015%
0.003%
0.143%
0.046%
0.235%
0.007%
0.015%
0.098%
0.070%
0.008%
0.586%
0.013%
0.007%
0.008%
0.012%
0.036%
0.096%
0.104%
0.195%
0.369%
0.021%
0.419%
0.651%
0.020%
0.049%
0.086%
0.276%
100.00%

ITEM
B.4(10)
B.5
B.7
B.9

DESCRIPTION
Miscellaneous survey and staking
Project Billboard / Signboard
Occupational Safety and Health Program
Mobilization / Demobilization

UNIT
l.s.
l.s.
month
l.s.

ESTIMATED COST OF PROPOSED WORK


QUANTITY
UNIT COST
9,944.68
1.00
13,061.19
1.00
16,282.49
6.00
129,011.42
1.00

B.13
401 (1)
403 (4)
403 (5)
404 (1) a
801(1)
803 (1) a
803 (3)
804 (1) b
900(a)
900(b)
900 ( c )
900 ( d )
900 (e)
900 (f)
900 ( g )
902
1001 (1) a
1001 (1) a3
1001 (1) a4
1001 (1) b1
1002 (1) a1
1002 (1) a3
1002 (1) a4
1002 (1) b1
1002 (1) b3
1002 (1) c3
1002 (1) c4
1002 (1) e1
1001 (2) i1
1001 (2) j2
1001 (6) b
1001 (8)
1002 (4) e3
1002 (5) a1
1002 (5) b1
1002 (5) c1
1002 (6) b1
1002 (6) b2
1002 (6) b3
1002 (6) c1
1002 (6) c2
1002 (6) d1
1002 (6) d2
1002 (4) e1
1002 (4) e2
1002(9)
1002(10)
1002(11)
1002(12)
1002(13)
1003(1) a

Additional Geotechnical Investigation


Metal Railing
Structural Steel, furnished, and fabricated - Purlins
Structural Steel, furnished, fabricated, and erected - Truss
Reinforcing Steel
Removal of Actual Structures/Obstruction
Structure Excavation
Foundation Fill (Gravel Bedding)
Embankment (From Borrow)
Reinforced Concrete (Footing)
Reinforced Concrete (Columns)
Reinforced Concrete (Foundation Beams to Ground Floor Level)
Reinforced Concrete (Second Floor Beams to Roof Beams)
Reinforced Concrete (Concrete Slab on grade)
Reinforced Concrete (Concrete Slabs @ Second Floor and Third Floor )
Reinforced Concrete (Concrete Stairs, Ramp and Sunbreaker)
Lean Concrete
Pipe - 50mm diameter PVC
Pipe - 100mm diameter PVC
Pipe - 150mm diameter PVC
Pipe - 150mm diameter Concrete Pipe
Fittings- 63mm diameter PVC 45deg. Elbow
Fittings- 110mm diameter PVC 45deg. Elbow
Fittings- 150mm diameter PVC 45deg. Elbow
Fittings- 63mm diameter PVC 90deg. Elbow
Fittings- 110mm diameter PVC 90deg. Elbow
Fittings- 110mm diameter PVC Cleanout with Plug
Fittings- 150mm diameter PVC Cleanout with Plug
Fittings- 63mm diameter P-Trap
Fittings- PVC 110mm dia. x 63mm dia. (2" x 2") Reducer - Sanitary Tee
Fittings- PVC 110mm dia. x 63mm dia. (4" x 2") Reducer - Sanitary Wye
Catch Basin - CHB
Three Chamber Septic Vault
Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 20mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 25mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 32mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 20mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 25mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 32mm PN10
Polyprophylene Random Copolymer (PPR-C) Tee -20mm PN10
Polyprophylene Random Copolymer (PPR-C) Tee -25mm PN10
Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -20mm PN10
Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -25mm PN10
Polyprophylene Random Copolymer (PPR-C) Coupling- 20mm PN10
Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10

Water Closet
Faucet, Plain Bibb, Brass 1/2"
Water Closet Flange
Tissue Holder
Concrete Counter Sink
Ceiling (4.5mm Fiber Cement Board)

l.s.
ln.m.
kgs.
kgs.
kgs.
l.s.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
ln.m.
ln.m.
ln.m.
ln.m.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
each
unit
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
set
pcs.
pcs.
pcs.
pc.
sq.m.

1.00
192.40
3,844.20
6,998.50
99,301.25
1.00
630.04
33.00
520.21
146.52
27.24
29.37
79.68
36.03
34.86
18.28
20.65
114.00
153.00
42.00
95.60
12.00
12.00
4.00
30.00
24.00
19.00
4.00
19.00
17.00
2.00
8.00
1.00
2.00
12.00
14.00
18.00
30.00
23.00
37.00
12.00
15.00
22.00
22.00
9.00
2.00
15.00
41.00
15.00
15.00
6.00
716.00

149,100.00
1,190.33
84.95
110.68
53.85
3,344.43
145.77
1,996.85
127.25
6,236.46
7,050.06
5,516.56
5,589.37
5,174.44
6,300.71
6,867.33
4,284.96
136.41
220.71
1,536.78
724.95
99.62
147.53
333.70
87.33
184.08
178.17
670.93
201.38
200.34
643.17
2,618.70
73,883.16
140.38
384.72
562.85
830.18
163.77
174.45
192.25
131.67
183.40
198.48
210.76
122.33
140.38
5,396.73
684.37
459.81
445.07
5,938.96
333.85

1003(3)a
1005 (1)a
1006 (1)
1010(1)
1010(1)b
1012 (1) f4
1013(1)
1013(2)a
1013(2) b
1013(2)c
1013(3)
1016(1)a
1018(1)
1018(2)
1021(1)a
1027(1)
1032(1)a
1032(1)b
1032(1)c
1035
1043(2) a
1043(2) b
1044(1)
1100(1) h1
1100(1) h2
1100(7)a1
1100(4)d1
1100(4)d2
1100(7)a2
1100(7)a3
1100(7)b1
1100(7)b2
1100(8)b
1100(14)
1100(15)
1100(22)
1101(1)a2
1101(1)a3
1101(1)a4
1101(1)a5
1101(1)a8
1101(3)
1101(6)
1102(1)a

Blackboard
Residential Casement
Hollow Steel Doors
Wooden Doors - Frames (Jambs, Sills, Head, Transoms and Mullions)

Wooden Doors - Flush


Glass and Glazzing
Corrugated Metal Roofing - Prepainted Long Span
Fabricated Metal Roofing Accessory -Ridge Roll
Fabricated Metal Roofing Accessory -Flashings
Fabricated Metal Roofing Accessory - Gutters
Roof Ventilators
Waterproofing-Cement Base
Glazed Tiles and Trims
Unglazed Tiles - Vitrified Floor Tile
Cement Floor Finish
Cement Plaster Finish
Painting Works - Masonry and Fiber Cement Painting
Painting Works - Metal Painting
Painting Works - Wood Paint
Furring Channel-Double Furring System
CHB Non Load Bearing Wall - 100mm
CHB Non Load Bearing Wall - 150mm
Forms and Falseworks
PVC Coupling 20mm diameter
PVC Coupling 25mm diameter
PVC Adapter 20mm diameter
PVC Elbow 20mmx90 deg.
PVC Elbow 25mmx90 deg.
PVC Adapter 20mm male diameter
PVC Adapter 25mm male diameter
Polyvinyl Chloride Pipes (PVC)-20mm
Polyvinyl Chloride Pipes (PVC)-25mm
GI Wire #16
Octagonal Junction Box PVC
Utility Boxes PVC
Grounding Rod Copperweld
Electrical Wire - 3.5mm TWG/THHN
Electrical Wire - 5.5mm TWG/THHN
Electrical Wire - 8.0mm TWG/THHN
Electrical Wire - 14 mm TWG/THHN
Electrical Wire - 38 mm TWG/THHN
Tumbler Switch Two-Gang
Duplex Convenience Receptacles
Panelboard Circuit Breaker Type - Main Distribution Panel (MDP)
Panelboard Circuit Breaker Type - LPA Flush Mounted, NEMA 1 Enclosure
1102(1)b
(Bolt-on Type)
Panelboard Circuit Breaker Type - LPB and LPC Flush Mounted, NEMA 1
1102(1)c
Enclosure (Bolt-on Type)
1103(1)a1 Compact Flourescent Lamp (CFL)
1103(1)a3 Flourescent Lighting Fixture
1103(1)a4 Flourescent Lighting Fixture
1201 (4)d Valves and Fittings

sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
sq.m
sq.m
ln.m.
ln.m.
each
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
ln.m.
sq.m.
sq.m.
l.s.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
kgs.
pcs.
pcs.
length
roll
roll
roll
roll
roll
set
set
set

51.84
118.52
47.04
47.04
47.04
5.28
535.68
37.20
28.80
74.40
19.00
55.29
169.92
87.22
899.10
2,843.70
3,192.27
213.36
104.55
1,610.15
337.20
559.60
1.00
416.00
8.00
4.00
52.00
4.00
496.00
149.00
208.00
4.00
12.00
124.00
91.00
2.00
18.00
0.24
0.11
0.10
0.20
15.00
36.00
1.00

1,005.14
2,657.78
4,700.58
960.47
866.87
2,361.51
423.95
293.64
1,164.31
260.70
2,311.89
247.87
1,353.12
1,422.92
94.37
153.68
134.73
190.39
173.01
111.47
550.02
1,008.83
1,253,937.11
33.99
52.28
153.45
44.51
102.84
44.90
48.01
175.94
253.29
199.51
122.31
120.49
656.95
5,064.40
8,362.18
10,879.91
11,838.29
8,957.46
376.55
415.98
16,124.44

set

1.00

30,369.98

set

2.00

28,662.37

sets
sets
sets
pcs.

6.00
58.00
90.00
6.00

542.47
1,124.80
1,124.80
522.44

1201(4)e Floor Drain


1208 (2) a1 Stainless Steel Railings
1209(1) Fire Alarm System

BREAKDOWN OF EXPENDITURES ( ESTIMATE )


1. LABOR
P
2. MATERIALS
3. EQUIPMENT EXPENSES
4. INDIRECT COST ( OCM,
PROFITS, TAX, VAT )
5. ENG'G. & ADM. OVERHEAD
6. CONST. CONTINGENCIES
7. GENDER & DEVELOPMENT
8. COST OF RIGHT OF WAY
9. RA 9206
10. YOUTH & INFRA DEVELOPMENT
11. BUDGET RESERVE
TOTAL P

Prepared By:

LOIDA B. PASCUA
Engineer ll
Recommending Approval:

BENEDICTA C. MENDOZA
OIC - Assist. District Engineer

pcs.
set
l.s.

16.00
2.00
1.00

473.30
6,659.80
42,854.83

%
12.649 A. TOTAL PROJECT COST
64.756 ( DIRECT / INDIRECT )
3.833 B. ENG'G. & ADMIN. OH
C. SURVEY PREPARATION
18.260 D. ROW /SITE ACQUISITION
0.500 SOIL EXPLORATION
0.001 E. CONST. CONTINGENCIES
F. GENDER & DEVELOPMENT
G. COST OF RIGHT OF WAY
H. RA 9206
I. BUDGET RESERVE
J. YOUTH & INFRA DEVELOPMENT
100.00 K. APPROPRIATION

1,977,184.52
10,122,173.85
599,173.06
2,854,335.49
78,156.02
180.13

15,631,203.07

Submitted By:

ROMEO D. DULAY
Chief, Planning & Design Section
Approved:

DAVID A. BULIYAT
District Engineer

ic of the Philippines
PUBLIC WORKS AND HIGHWAYS
STRICT ENGINEERING OFFICE
ngal, La Trinidad
Benguet
RAM

OF WORK

m.

,Steel
na
342 sq.m.

c.d.

EQUIPMENT
NEEDED
1
1
1
1
1
1
2

ESTIMATED COST OF PROPOSED WORK


TOTAL COST
9,944.68
13,061.19
97,694.92
129,011.42

149,100.00
229,019.66
326,564.79
774,570.36
5,347,201.83
3,344.43
91,840.34
65,896.15
66,195.49
913,766.25
192,043.50
162,021.31
445,361.34
186,435.02
219,642.59
125,534.74
88,484.46
15,550.67
33,768.61
64,544.68
69,305.21
1,195.43
1,770.37
1,334.81
2,620.02
4,417.88
3,385.28
2,683.71
3,826.31
3,405.83
1,286.34
20,949.56
73,883.16
280.76
4,616.63
7,879.93
14,943.23
4,912.99
4,012.31
7,113.43
1,580.05
2,751.00
4,366.48
4,636.75
1,100.93
280.76
80,950.98
28,059.28
6,897.19
6,676.06
35,633.77
239,033.47

52,106.69
315,000.41
221,115.29
45,180.54
40,777.42
12,473.50
227,102.58
10,923.32
33,532.14
19,395.72
43,925.91
13,704.48
229,921.44
124,106.80
84,850.89
437,005.50
430,097.43
40,621.58
18,087.75
179,484.50
185,467.57
564,538.72
1,253,937.11
14,140.58
418.27
613.81
2,314.76
411.36
22,268.29
7,153.81
36,596.18
1,013.15
2,394.10
15,166.72
10,964.39
1,313.91
91,159.22
2,006.92
1,160.52
1,183.83
1,791.49
5,648.22
14,975.25
16,124.44
30,369.98
57,324.74
3,254.81
65,238.46
101,232.10
3,134.67

7,572.87
13,319.59
42,854.83

15,552,866.92
78,156.02

180.13

15,631,203.07

page 2/2

SUMMARY OF ESTIMATES
ITEM
B.4(10)
B.5
B.7
B.9
B.13
401 (1)
403 (4)
403 (5)
404 (1) a
801(1)
803 (1) a
803 (3)
804 (1) b
900(a)
900(b)
900 ( c )
900 ( d )
900 (e)
900 (f)
900 ( g )
902
1001 (1) a
1001 (1) a3
1001 (1) a4
1001 (1) b1
1002 (1) a1
1002 (1) a3
1002 (1) a4
1002 (1) b1
1002 (1) b3
1002 (1) c3
1002 (1) c4
1002 (1) e1
1001 (2) i1
1001 (2) j2
1001 (6) b
1001 (8)
1002 (4) e3
1002 (5) a1
1002 (5) b1
1002 (5) c1

LABOR
2768.16
6,574.38
30,667.04
108,346.44
29,715.36
145,050.12
307,230.21
2,474.88
11,510.10
11,443.20
29,680.80
36,827.70
31,482.24
4,986.30
18,130.56
8,109.00
33,090.90
17,225.40
14,058.42
5,016.60
6,688.80
1,672.20
13,935.00
382.80
382.80
191.40
957.00
765.60
574.20
191.40
574.20
478.50
382.80
4,593.60
15,693.12
191.40
689.04
803.88
1,914.00

MATERIALS
5,050.00
3,400.00
45,790.00
142,000.00
57,731.78
230,064.39
458,184.07
3,878,706.25
41,052.00
16,129.80
703,296.00
115,157.10
124,336.55
337,076.88
138,413.36
133,866.51
73,749.98
52,421.00
7,140.00
20,130.00
50,700.00
41,086.00
552.00
1,020.00
876.00
1,080.00
2,754.00
2,124.00
1,974.00
2,483.00
2,246.00
626.00
12,000.00
42,878.52
18.00
3,000.00
5,530.00
10,058.40

EQ. RENTALS
276.82
657.44
3,066.70
122,868.02
20,343.97
6,044.26
27,266.71
166,690.18
247.49
63,248.01
1,144.32
8,072.58
3,682.77
9,684.22
2,562.63
7,317.06
5,235.90
11,831.84
11,210.00
5,547.00
501.66
668.88
167.22
1,393.50
38.28
38.28
19.14
95.70
76.56
57.42
19.14
57.42
47.85
38.28
459.36
1,569.31
19.14
68.90
80.39
191.40

INDIRECT COST
1,849.70
2,429.37
18,171.18
6,143.40
7,100.00
42,597.47
60,740.79
144,069.46
994,575.19
622.06
17,082.23
12,256.63
12,312.31
169,959.78
35,719.93
30,135.83
82,836.85
34,676.76
40,853.34
23,349.36
16,458.04
2,892.41
6,280.93
12,005.26
12,890.71
222.35
329.29
248.27
487.32
821.72
629.66
499.17
711.69
633.48
239.26
3,896.60
13,742.21
52.22
858.69
1,465.66
2,779.43

TOTAL COST
9,944.68
13,061.19
97,694.92
129,011.42
149,100.00
229,019.66
326,564.79
774,570.36
5,347,201.83
3,344.43
91,840.34
65,896.15
66,195.49
913,766.25
192,043.50
162,021.31
445,361.34
186,435.02
219,642.59
125,534.74
88,484.46
15,550.67
33,768.61
64,544.68
69,305.21
1,195.43
1,770.37
1,334.81
2,620.02
4,417.88
3,385.28
2,683.71
3,826.31
3,405.83
1,286.34
20,949.56
73,883.16
280.76
4,616.63
7,879.93
14,943.23

1002 (6) b1
1002 (6) b2
1002 (6) b3
1002 (6) c1
1002 (6) c2
1002 (6) d1
1002 (6) d2
1002 (4) e1
1002 (4) e2
1002(9)
1002(10)
1002(11)
1002(12)
1002(13)
1003(1) a
1003(3)a
1005 (1)a
1006 (1)
1010(1)
1010(1)b
1012 (1) f4
1013(1)
1013(2)a
1013(2) b
1013(2)c
1013(3)
1016(1)a
1018(1)
1018(2)
1021(1)a
1027(1)
1032(1)a
1032(1)b
1032(1)c
1035
1043(2) a
1043(2) b
1044(1)
1100(1) h1
1100(1) h2
1100(7)a1
1100(4)d1
1100(4)d2
1100(7)a2
1100(7)a3

3,253.80
2,488.20
4,019.40
765.60
1,531.20
1,531.20
1,531.20
765.60
191.40
8,085.60
15,694.80
1,531.20
1,531.20
9,187.20
43,901.76
23,413.54
28,632.29
23,910.78
9,570.00
18,265.50
4,593.60
45,230.63
1,950.90
1,002.90
2,808.12
11,232.48
6,941.33
38,840.22
24,441.85
38,587.90
140,766.21
96,240.60
13,585.68
6,890.40
42,919.80
32,473.35
61,761.00
181,400.88
9,140.40
269.52
200.58
1,240.20
248.04
14,111.28
4,311.78

420.00
529.00
1,369.00
444.00
555.00
1,870.00
2,090.00
54.00
18.00
57,000.00
5,576.00
3,930.00
3,750.00
18,900.00
146,281.50
16,660.00
218,737.80
149,352.00
26,250.00
13,100.80
5,100.48
135,108.00
6,745.60
26,192.00
12,699.20
23,400.00
3,520.00
144,432.00
74,137.00
26,622.00
200,880.00
244,235.00
19,072.75
7,144.00
98,888.75
115,250.07
391,597.88
821,164.86
1,456.00
44.00
279.00
520.00
62.00
2,604.00
1,080.25

325.38
248.82
401.94
76.56
153.12
153.12
153.12
76.56
19.14
808.56
1,569.48
153.12
153.12
918.72
4,390.18
2,341.35
9,040.50
6,725.25
957.00
1,826.55
459.36
4,523.06
195.09
100.29
280.81
1,123.25
694.13
3,884.02
2,444.18
3,858.79
14,076.62
9,624.06
407.57
689.04
4,291.98
3,247.34
6,176.10
18,140.09
914.04
26.95
20.06
124.02
24.80
1,411.13
431.18

913.81
746.29
1,323.09
293.89
511.68
812.16
862.43
204.77
52.22
15,056.82
5,219.00
1,282.87
1,241.74
6,627.85
44,460.03
9,691.80
58,589.82
41,127.26
8,403.54
7,584.57
2,320.06
42,240.90
2,031.73
6,236.95
3,607.59
8,170.18
2,549.02
42,765.20
23,083.76
15,782.20
81,282.67
79,997.77
7,555.58
3,364.31
33,383.97
34,496.82
105,003.74
233,231.28
2,630.14
77.80
114.17
430.54
76.51
4,141.88
1,330.60

4,912.99
4,012.31
7,113.43
1,580.05
2,751.00
4,366.48
4,636.75
1,100.93
280.76
80,950.98
28,059.28
6,897.19
6,676.06
35,633.77
239,033.47
52,106.69
315,000.41
221,115.29
45,180.54
40,777.42
12,473.50
227,102.58
10,923.32
33,532.14
19,395.72
43,925.91
13,704.48
229,921.44
124,106.80
84,850.89
437,005.50
430,097.43
40,621.58
18,087.75
179,484.50
185,467.57
564,538.72
1,253,937.11
14,140.58
418.27
613.81
2,314.76
411.36
22,268.29
7,153.81

1100(7)b1
1100(7)b2

12,899.39
404.28

15,600.00
380.00

1,289.94
40.43

6,806.86
188.45

36,596.18
1,013.15

1100(8)b
1100(14)
1100(15)
1100(22)
1101(1)a2
1101(1)a3
1101(1)a4
1101(1)a5
1101(1)a8
1101(3)
1101(6)
1102(1)a
1102(1)b
1102(1)c
1103(1)a1
1103(1)a3
1103(1)a4
1201 (4)d
1201(4)e
1208 (2) a1
1209(1)
TOTAL

1,396.80
3,445.20
2,488.20
269.52
8,548.80
200.58
143.94
200.58
401.16
2,406.96
5,616.24
2,786.64
2,664.72
5,329.44
1,672.20
11,367.42
17,639.10
574.20
1,531.20
765.60
7,991.70

552.00
8,556.00
6,188.00
800.00
64,800.00
1,413.00
786.33
743.00
1,017.00
1,950.00
6,012.00
10,060.00
21,790.00
40,800.00
810.00
40,600.00
63,000.00
1,920.00
4,480.00
10,000.00
26,093.00

344.52
248.82
854.88
20.06
14.39
20.06
40.12
240.70
561.62
278.66
266.47
532.94
167.22
1,136.74
1,763.91
57.42
153.12
76.56
799.17

445.30
2,821.00
2,039.37
244.39
16,955.54
373.29
215.86
220.19
333.22
1,050.56
2,785.38
2,999.13
5,648.79
10,662.35
605.39
12,134.30
18,829.09
583.05
1,408.55
2,477.43
7,970.96

1,977,184.52 P

10,122,173.85 P

599,173.06 P

2,854,335.49 P

Total Project Cost = P


Contingencies=
( .5% ) Engineering Overhead Cost =

APPROPRIATION = P

Prepared by:

ROMUALDO T. APALIAS
Engineer II
Checked by:

LOIDA B. PASCUA
Engineer ll

Submitted by:

15,552,866.92
180.13
78,156.02
15,631,203.07

2,394.10
15,166.72
10,964.39
1,313.91
91,159.22
2,006.92
1,160.52
1,183.83
1,791.49
5,648.22
14,975.25
16,124.44
30,369.98
57,324.74
3,254.81
65,238.46
101,232.10
3,134.67
7,572.87
13,319.59
42,854.83
15,552,866.92

ROMEO D. DULAY
Chief, Planning & Design Section

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

401 (1)
: Metal Railing
Unit of Measurement=
ln.m.
Output=
0.625 ln.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
2

154
307
307

No. of Units

No. of Hours

1
1

154

Unit

Quantity

ln.m.
kgs.
kgs.
gal.
gal.
l.s.
gal.

192.40
124.00
13.00
4
10
1
3

192.40
307.84
307.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
Welding Machine

61.95

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
50mm (2") dia. GI Pipe
19mm (3/4") Square Bar
Welding Rod
Red Lead Primer
QDE Top Coat
Assorted Sizes Paint Brush
Thinner

216.66
48.60
110.00
400.00
599.00
1000.00
250.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 61

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

403 (4)
: Structural Steel, furnished, and fabricated - Purlins
Unit of Measurement=
kgs.
Output=
61.92 kgs./hr.

Designation

Quantity=
Duration=
Say
No. of Person

No. of Hours

1
4
4

62
62
62

No. of Units

No. of Hours

1
1

50

Unit

Quantity

kgs.
kgs.
kgs.
kgs.
gal.
kgs.

3,844.20
227.00
111.64
206.60
7
581.44

3,844.20
62.08
62.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
Welding Machine

61.95

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
50x100x1.2mm C-Purlins
Welding Rod
50x50x4.5 Angle Bar -Cleats
50x50x4.5 Angle Bar -End Flashing Support
Red Lead Primer
16mm Round Bar

48.60
110.00
48.60
48.60
400.00
48.60

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 62

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

403 (5)
: Structural Steel, furnished, fabricated, and erected - Truss
Unit of Measurement=
kgs.
Output=
17 kgs./hr.

Designation

Quantity=
Duration=
Say

No. of Person

No. of Hours

1
4
2

206
411
411

No. of Units

No. of Hours

1
1

206

Unit

Quantity

kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
gal.
gal.
l.s.
gal.
pc.
pc.
pc.
pc.
kgs.

1,810.98
698.18
4,295.90
183.44
57
350.00
8
20
1
5
36
2
2
64
389

6,998.50
411.68
411.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
Welding Machine

61.95

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
50x50x6mm Angle Bar
50x50x4.5mm Angle Bar
6mm thick Steel Plate
12mm thick Steel Plate
25x25x2mm Angle Bar (for stairs)
Welding Rod
Red Lead Primer
QDE Top Coat
Assorted Sizes Paint Brush
Thinner
16mmx450 A307 Anchor Bolt
Acetylene (Content only)
Oxygene(Content only)
16mm Turnbuckle
12mm dia. Sag Rod

48.60
48.60
48.60
48.60
48.60
110.00
400.00
599.00
1000.00
250.00
43.00
670.00
670.00
650.00
36.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST
Page 63

17%
5%

Page 64

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 404 (1) a : Reinforcing Steel
Unit of Measurement=
kgs.
Output= 179.5125 kgs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
6
6

415
553
332

No. of Units

No. of Hours

1
1
1
1

83
249
50

Unit

Quantity

kgs.
kgs.
kgs.
kgs.
kgs.
kgs.

28,173.91
33,537.22
7,678.76
12,662.65
17,248.71
993.00

99,301.25
553.17
553.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1-Grade 40


Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 5% of Labor Cost
Bar Cutter
Bar Bender
Cargo Truck

219.75
351.50
1,102.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
25mm dia. RSB
20mm dia. RSB
16mm dia. RSB
12mm dia. RSB
10mm dia. RSB
GI Wire #16

38.60
38.60
38.60
38.60
38.60
46.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 65

17%
5%

hours
hours
Amount

11,991.42
69,553.92
26,801.10

108,346.44
Amount

10,834.64
9,509.33

20,343.97
Amount

41,685.38
6,026.40
1,430.00
1,600.00
5,990.00
1,000.00
750.00
P
P
P
P
P
P

57,731.78
186,422.19
31,691.77
10,905.70
229,019.66
1,190.33

Page 66

hours
hours
Amount

4,843.44
14,046.72
10,825.20

29,715.36
Amount

2,971.54
3,072.72

6,044.26
Amount

186,828.12
24,970.00
5,425.70
10,040.57
2,800.00
28,257.98
P
P
P
P
P
P

230,064.39
265,824.01
45,190.08
15,550.70
326,564.79
84.95

Page 67

hours
hours
Amount

16,053.66
93,116.16
35,880.30

145,050.12
Amount

14,505.01
12,761.70

27,266.71
Amount

88,013.63
33,931.55
208,780.74
8,915.18
2,770.20
38,500.00
3,200.00
11,980.00
1,000.00
1,250.00
1,548.00
1,340.00
1,340.00
41,600.00
14,014.77
P
P
P
P
P
P

458,184.07
630,500.90
107,185.15
36,884.30
774,570.36
110.68
Page 68

Page 69

hours
hours
Amount

32,400.27
187,931.52
86,898.42
P

307,230.21
Amount

6,144.60
18,228.26
87,470.78
54,846.54
P

166,690.18
Amount
1,087,512.93
1,294,536.69
296,400.14
488,778.29
665,800.21
45,678.00

P 3,878,706.25
P 4,352,626.64
P 739,946.53
P 254,628.66
P 5,347,201.83
P
53.85

Page 70

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1001 (1) a : Pipe - 50mm diameter PVC
Unit of Measurement=
ln.m.
Output= 6.2625 ln.m./hr.

Quantity=
Duration=
Say

Designation

114.00
18.20
18.00

No. of Person

No. of Hours

Hourly Rate

1
2
2

18
18
18

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

ln.m.
cc

114.00
200.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
50mm PVC Pipe Series 600
Solvent Cement

60.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 71

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1001 (1) a3 : Pipe - 100mm diameter PVC
Unit of Measurement=
ln.m.
Output= 6.2625 ln.m./hr.

Quantity=
Duration=
Say

Designation

153.00
24.43
24.00

No. of Person

No. of Hours

Hourly Rate

1
2
2

24
24
24

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

ln.m.
cc

153.00
500.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
100mm PVC Pipe Series 600
Solvent Cement

126.67
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 72

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1001 (1) a4 : Pipe - 150mm diameter PVC
Unit of Measurement=
ln.m.
Output= 6.2625 ln.m./hr.

Quantity=
Duration=
Say

Designation

42.00
6.71
6.00

No. of Person

No. of Hours

Hourly Rate

1
2
2

6
6
6

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

ln.m.
cc

42.00
200.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
150mm PVC Pipe Series 600
Solvent Cement

1,200.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 73

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1001 (1) b1 : Pipe - 150mm diameter Concrete Pipe
Unit of Measurement=
ln.m.
Output= 1.9125 ln.m./hr.

Quantity=
Duration=
Say

Designation

95.60
50.00
50.00

No. of Person

No. of Hours

Hourly Rate

1
2
2

50
50
50

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

ln.m.
bags
cu.m.

95.60
4.00
1.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
150mm Concrete Pipe
40kg Portland Cement
Fine Sand

410.00
245.00
910.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 74

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (1) a1 : Fittings- 63mm diameter PVC 45deg. Elbow
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

12.00
2.00
2.00

No. of Person

No. of Hours

Hourly Rate

1
2

2
2

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

12.00
200.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
63mm 45deg. PVC elbow
Solvent Cement

21.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 75

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (1) a3 : Fittings- 110mm diameter PVC 45deg. Elbow
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

12.00
2.00

No. of Person

No. of Hours

Hourly Rate

1
2

2
2

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

12.00
200.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
110mm 45 deg. PVC elbow
Solvent Cement

60.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 76

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (1) a4 : Fittings- 150mm diameter PVC 45deg. Elbow
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

4.00
0.57
1.00

No. of Person

No. of Hours

Hourly Rate

1
2

1
1

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

4.00
200.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
150mm 45deg. PVC elbow
Solvent Cement

144.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 77

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (1) b1 : Fittings- 63mm diameter PVC 90deg. Elbow
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

30.00
5.00
5.00

No. of Person

No. of Hours

Hourly Rate

1
2

5
5

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

30.00
200.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
63mm 90 deg. PVC elbow
Solvent Cement

26.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 78

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (1) b3 : Fittings- 110mm diameter PVC 90deg. Elbow
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

24.00
4.00
4.00

No. of Person

No. of Hours

Hourly Rate

1
2

4
4

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

24.00
300.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
110mm 90 deg. PVC elbow
Solvent Cement

96.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 79

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (1) c3 : Fittings- 110mm diameter PVC Cleanout with Plug
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

19.00
3.00
3.00

No. of Person

No. of Hours

Hourly Rate

1
2

3
3

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

19.00
200.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
110mm diameter PVC Cleanout with Plug
Solvent Cement

96.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 80

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (1) c4 : Fittings- 150mm diameter PVC Cleanout with Plug
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

4.00
0.57
1.00

No. of Person

No. of Hours

Hourly Rate

1
2

1
1

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

19.00
100.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
150mm diameter PVC Cleanout with Plug
Solvent Cement

96.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 81

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (1) e1 : Fittings- 63mm diameter P-Trap
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Quantity=
Duration=
Say

Designation

19.00
3.00
3.00

No. of Person

No. of Hours

Hourly Rate

1
2

3
3

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

19.00
300.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
63mm 90 deg. PVC P-trap
Solvent Cement

107.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 82

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1001 (2) i1 : Fittings- PVC 110mm dia. x 63mm dia. (2" x 2") Reducer - Sanitary Tee
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

17.00
2.50

No. of Person

No. of Hours

Hourly Rate

1
2

2.50
2.50

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
cc

17.00
500.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
(2" x 2") Reducer - Sanitary Tee
Solvent Cement

88.00
1.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 83

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1001 (2) j2 : Fittings- PVC 110mm dia. x 63mm dia. (4" x 2") Reducer - Sanitary Wye
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Designation

Quantity=
Duration=
Say

2.00
0.29
2.00

No. of Person

No. of Hours

Hourly Rate

1
2

2
2

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

2.00

88.00

cc

300.00

1.50

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Fittings- PVC 110mm dia. x 63mm dia. (4" x 2") Reducer
- Sanitary Wye
Solvent Cement

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 84

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1001 (6) b : Catch Basin - CHB
Unit of Measurement=
each
Output=

Quantity=
Duration=
Say

Designation

8.00
24.00

No. of Person

No. of Hours

Hourly Rate

1
2

24
24

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

each

8.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
700x700x600 CHB Catch Basin

1,500.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 85

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1001 (8) : Three Chamber Septic Vault
Unit of Measurement=
unit
Output=

Quantity=
Duration=
Say

Designation

1.00
24.00

No. of Person

No. of Hours

Hourly Rate

1
2
4

24
48
48

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

unit

1.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Three Chamber Septic Vault

42,878.52

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 86

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (4) e3 : Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Unit of Measurement=
pcs.
Output=
3.40 pc./hr.

Designation

Quantity=
Duration=
Say

2.00
0.59
1.00

No. of Person

No. of Hours

Hourly Rate

1
2

1
1

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

2.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Coupling - 25mm PN10

9.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 87

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (5) a1 : Polyprophylene Random Copolymer (PPR-C) Pipes - 20mm PN10
Unit of Measurement=
pcs.
Output=
3.40 pc./hr.

Designation

Quantity=
Duration=
Say

12.00
3.60

No. of Person

No. of Hours

Hourly Rate

1
2

3.60
3.60

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

12.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
PPR Pipes - 20mmx3.00m PN10

250.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 88

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (5) b1 : Polyprophylene Random Copolymer (PPR-C) Pipes - 25mm PN10
Unit of Measurement=
pcs.
Output=
3.40 pc./hr.

Designation

Quantity=
Duration=
Say

14.00
4.20

No. of Person

No. of Hours

Hourly Rate

1
2

4.20
4.20

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

14.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
PPR Pipes - 25mmx3.00m PN10

395.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 89

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (5) c1 : Polyprophylene Random Copolymer (PPR-C) Pipes - 32mm PN10
Unit of Measurement=
pcs.
Output=
1.72 pc./hr.

Designation

Quantity=
Duration=
Say

18.00
10.47
10.00

No. of Person

No. of Hours

Hourly Rate

1
2

10
10

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

18.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
PPR Pipes - 32mmx3.00m PN10

558.80

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 90

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (6) b1 : Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 20mm PN10
Unit of Measurement=
pcs.
Quantity=
Output=
1.72 pc./hr.
Duration=
Say
Designation

30.00
17.44
17.00

No. of Person

No. of Hours

Hourly Rate

1
2

17
17

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

30.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
(PPR-C) (Elbow, 1/8 Bend (45 deg.)- 20mm PN10

14.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 91

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (6) b2 : Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 25mm PN10
Unit of Measurement=
pcs.
Quantity=
Output=
1.72 pc./hr.
Duration=
Say
Designation

23.00
13.37
13.00

No. of Person

No. of Hours

Hourly Rate

1
2

13
13

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

23.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
(PPR-C) (Elbow, 1/8 Bend (45 deg.)- 25mm PN10

23.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 92

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (6) b3 : Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 32mm PN10
Unit of Measurement=
pcs.
Quantity=
Output=
1.72 pc./hr.
Duration=
Say
Designation

37.00
21.51
21.00

No. of Person

No. of Hours

Hourly Rate

1
2

21
21

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

37.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
(PPR-C) (Elbow, 1/8 Bend (45 deg.)- 25mm PN10

37.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 93

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (6) c1 : Polyprophylene Random Copolymer (PPR-C) Tee -20mm PN10
Unit of Measurement=
pcs.
Output=
3.44 pc./hr.

Designation

Quantity=
Duration=
Say

12.00
3.49
3.00

No. of Person

No. of Hours

Hourly Rate

1
2

4
4

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

12.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
PPR Tee -20mm PN10

37.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 94

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (6) c2 : Polyprophylene Random Copolymer (PPR-C) Tee -25mm PN10
Unit of Measurement=
pcs.
Output=
3.44 pc./hr.

Designation

Quantity=
Duration=
Say

15.00
4.36
4.00

No. of Person

No. of Hours

Hourly Rate

1
2

8
8

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

15.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
PPR Tee -25mm PN10

37.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 95

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (6) d1 : Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -20mm PN10
Unit of Measurement=
pcs.
Quantity=
Output=
3.44 pc./hr.
Duration=
Say
Designation

22.00
6.40
6.00

No. of Person

No. of Hours

Hourly Rate

1
2

8
8

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

22.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Female Threaded Tee -20mm PN10

85.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 96

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (6) d2 : Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -25mm PN10
Unit of Measurement=
pcs.
Quantity=
Output=
3.44 pc./hr.
Duration=
Say
Designation

22.00
6.40
8.00

No. of Person

No. of Hours

Hourly Rate

1
2

8
8

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

22.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Female Threaded Tee -25mm PN10

95.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 97

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (4) e1 : Polyprophylene Random Copolymer (PPR-C) Coupling- 20mm PN10
Unit of Measurement=
pcs.
Output=
3.40 pc./hr.

Designation

Quantity=
Duration=
Say

9.00
2.65
4.00

No. of Person

No. of Hours

Hourly Rate

1
2

4
4

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

6.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Coupling - 20mm PN10

9.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 98

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002 (4) e2 : Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Unit of Measurement=
pcs.
Output=
3.40 pc./hr.

Designation

Quantity=
Duration=
Say

2.00
0.59
1.00

No. of Person

No. of Hours

Hourly Rate

1
2

1
1

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

2.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Coupling - 25mm PN10

9.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 99

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1002(9) : Water Closet


Unit of Measurement=
set
Output=
0.25 pc./hr.

Quantity=
Duration=
Say

Designation

15.00
60.00

No. of Person

No. of Hours

Hourly Rate

1
1

60
60

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

sets

15.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Water Closet 1.6gpf with accessories

3,800.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 100

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002(10) : Faucet, Plain Bibb, Brass 1/2"
Unit of Measurement=
pcs.
Output=
0.50 pc./hr.

Quantity=
Duration=
Say

Designation

41.00
82.00
82.00

No. of Person

No. of Hours

Hourly Rate

1
2

82
82

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

41.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Brass Faucet 1/2" diameter

136.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 101

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1002(11) : Water Closet Flange


Unit of Measurement=
pcs.
Output=
2.00 pc./hr.

Quantity=
Duration=
Say

Designation

15.00
7.50
8.00

No. of Person

No. of Hours

Hourly Rate

1
2

8
8

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

15.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Water Closet Flange

262.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 102

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002(12) : Tissue Holder
Unit of Measurement=
pcs.
Output=
2.00 pc./hr.

Quantity=
Duration=
Say

Designation

15.00
7.50
8.00

No. of Person

No. of Hours

Hourly Rate

1
2

8
8

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

15.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Ceramic Tissue Holder

250.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 103

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1002(13) : Concrete Counter Sink
Unit of Measurement=
pc.
Output=
0.13 pc./hr.

Quantity=
Duration=
Say

Designation

6.00
48.00
48.00

No. of Person

No. of Hours

Hourly Rate

1
2

48
48

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

6.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Concrete counter sink with Lever Type Faucet and
Stainless Drain

3,150.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 104

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1003(3)a : Blackboard
Unit of Measurement=
sq.m.
Output= 0.6375 sq.m/hr.

Quantity=
Duration=
Say

Designation

51.84
81.32
81.00

No. of Person

No. of Hours

Hourly Rate

1
4

65
81

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

bd.ft.
pc.
kg.
kg.
kg.

330.00
18.00
1
6
1

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Good Lumber, Sun Dried
1/4"thick Lawanit
Finishing Nails
Common Wire Nails
Concrete Nails

35.00
280.00
70.00
50.00
90.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 105

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1201 (4)d : Valves and Fittings
Unit of Measurement=
pcs.
Output=
2.00 pc./hr.

Quantity=
Duration=
Say

Designation

6.00
3.00
3.00

No. of Person

No. of Hours

Hourly Rate

1
2

3
3

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

6.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
3/4" Gate Valve

320.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 106

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1201(4)e : Floor Drain
Unit of Measurement=
pcs.
Output=
2.00 pc./hr.

Quantity=
Duration=
Say

Designation

16.00
8.00
8.00

No. of Person

No. of Hours

Hourly Rate

1
2

8
8

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

16.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
4x4" Stainless Steel Floor Drain

280.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 107

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1208 (2) a1 : Stainless Steel Railings
Unit of Measurement=
set
Output=
0.50 pc./hr.

Quantity=
Duration=
Say

Designation

2.00
4.00
4.00

No. of Person

No. of Hours

Hourly Rate

1
2

4
4

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

set

2.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
1 1/2" Stainless Steel Grab Rail

5,000.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 108

17%
5%

Name of Project:
Location:

:
:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1012 (1) f4 : Glass and Glazzing
Unit of Measurement=
sq.m.
Output=

Quantity=
Duration=
Say

Designation

5.28
24.00
24.00

No. of Person

No. of Hours

Hourly Rate

1
2

24
24

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

sq.m.

5.28

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
3mm thick mirror with aluminum frame
( 6sets .55x1.60m)

966.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 109

17%
5%

hours
hours
Amount

1,406.16
2,039.04
1,571.40

5,016.60
Amount

501.66

501.66
Amount

6,840.00
300.00

P
P
P
P
P
P

7,140.00
12,658.26
2,151.90
740.51
15,550.67
136.41

Page 110

hours
hours
Amount

1,874.88
2,718.72
2,095.20

6,688.80
Amount

668.88

668.88
Amount

19,380.00
750.00

P
P
P
P
P
P

20,130.00
27,487.68
4,672.91
1,608.03
33,768.61
220.71

Page 111

hours
hours
Amount

468.72
679.68
523.80

1,672.20
Amount

167.22

167.22
Amount

50,400.00
300.00

P
P
P
P
P
P

50,700.00
52,539.42
8,931.70
3,073.56
64,544.68
1,536.78

Page 112

hours
hours
Amount

3,906.00
5,664.00
4,365.00

13,935.00
Amount

1,393.50

1,393.50
Amount

39,196.00
980.00
910.00

P
P
P
P
P
P

41,086.00
56,414.50
9,590.47
3,300.25
69,305.21
724.95

Page 113

hours
hours
Amount

156.24
226.56

382.80
Amount

38.28

38.28
Amount

252.00
300.00

P
P
P
P
P
P

552.00
973.08
165.42
56.93
1,195.43
99.62

Page 114

hours
hours
Amount

156.24
226.56

382.80
Amount

38.28

38.28
Amount

720.00
300.00

P
P
P
P
P
P

1,020.00
1,441.08
244.98
84.30
1,770.37
147.53

Page 115

hours
hours
Amount

78.12
113.28

191.40
Amount

19.14

19.14
Amount

576.00
300.00

P
P
P
P
P
P

876.00
1,086.54
184.71
63.56
1,334.81
333.70

Page 116

hours
hours
Amount

390.60
566.40

957.00
Amount

95.70

95.70
Amount

780.00
300.00

P
P
P
P
P
P

1,080.00
2,132.70
362.56
124.76
2,620.02
87.33

Page 117

hours
hours
Amount

312.48
453.12

765.60
Amount

76.56

76.56
Amount

2,304.00
450.00

P
P
P
P
P
P

2,754.00
3,596.16
611.35
210.38
4,417.88
184.08

Page 118

hours
hours
Amount

234.36
339.84

574.20
Amount

57.42

57.42
Amount

1,824.00
300.00

P
P
P
P
P
P

2,124.00
2,755.62
468.46
161.20
3,385.28
178.17

Page 119

hours
hours
Amount

78.12
113.28

191.40
Amount

19.14

19.14
Amount

1,824.00
150.00

P
P
P
P
P
P

1,974.00
2,184.54
371.37
127.80
2,683.71
670.93

Page 120

hours
hours
Amount

234.36
339.84

574.20
Amount

57.42

57.42
Amount

2,033.00
450.00

P
P
P
P
P
P

2,483.00
3,114.62
529.49
182.21
3,826.31
201.38

Page 121

hours
hours
Amount

195.30
283.20

478.50
Amount

47.85

47.85
Amount

1,496.00
750.00

P
P
P
P
P
P

2,246.00
2,772.35
471.30
162.18
3,405.83
200.34

Page 122

hours
hours
Amount

156.24
226.56

382.80
Amount

38.28

38.28
Amount

176.00
450.00

P
P
P
P
P
P

626.00
1,047.08
178.00
61.25
1,286.34
643.17

Page 123

hours
hours
Amount

1,874.88
2,718.72

4,593.60
Amount

459.36

459.36
Amount

12,000.00

P
P
P
P
P
P

12,000.00
17,052.96
2,899.00
997.60
20,949.56
2,618.70

Page 124

hours
hours
Amount

1,874.88
5,437.44
8,380.80
P

15,693.12
Amount

1,569.31

1,569.31
Amount

42,878.52

P
P
P
P
P
P

42,878.52
60,140.95
10,223.96
3,518.25
73,883.16
73,883.16

Page 125

hours
hours
Amount

78.12
113.28
P

191.40
Amount

19.14

19.14
Amount

18.00

P
P
P
P
P
P

18.00
228.54
38.85
13.37
280.76
140.38

Page 126

hours
hours
Amount

281.23
407.81
P

689.04
Amount

68.90

68.90
Amount

3,000.00

P
P
P
P
P
P

3,000.00
3,757.94
638.85
219.84
4,616.63
384.72

Page 127

hours
hours
Amount

328.10
475.78
P

803.88
Amount

80.39

80.39
Amount

5,530.00

P
P
P
P
P
P

5,530.00
6,414.27
1,090.43
375.23
7,879.93
562.85

Page 128

hours
hours
Amount

781.20
1,132.80
P

1,914.00
Amount

191.40

191.40
Amount

10,058.40

P
P
P
P
P
P

10,058.40
12,163.80
2,067.85
711.58
14,943.23
830.18

Page 129

hours
hours
Amount

1,328.04
1,925.76
P

3,253.80
Amount

325.38

325.38
Amount

420.00

P
P
P
P
P
P

420.00
3,999.18
679.86
233.95
4,912.99
163.77

Page 130

hours
hours
Amount

1,015.56
1,472.64
P

2,488.20
Amount

248.82

248.82
Amount

529.00

P
P
P
P
P
P

529.00
3,266.02
555.22
191.06
4,012.31
174.45

Page 131

hours
hours
Amount

1,640.52
2,378.88
P

4,019.40
Amount

401.94

401.94
Amount

1,369.00

P
P
P
P
P
P

1,369.00
5,790.34
984.36
338.73
7,113.43
192.25

Page 132

hours
hours
Amount

312.48
453.12
P

765.60
Amount

76.56

76.56
Amount

444.00

P
P
P
P
P
P

444.00
1,286.16
218.65
75.24
1,580.05
131.67

Page 133

hours
hours
Amount

624.96
906.24
P

1,531.20
Amount

153.12

153.12
Amount

555.00

P
P
P
P
P
P

555.00
2,239.32
380.68
131.00
2,751.00
183.40

Page 134

hours
hours
Amount

624.96
906.24
P

1,531.20
Amount

153.12

153.12
Amount

1,870.00

P
P
P
P
P
P

1,870.00
3,554.32
604.23
207.93
4,366.48
198.48

Page 135

hours
hours
Amount

624.96
906.24
P

1,531.20
Amount

153.12

153.12
Amount

2,090.00

P
P
P
P
P
P

2,090.00
3,774.32
641.63
220.80
4,636.75
210.76

Page 136

hours
hours
Amount

312.48
453.12
P

765.60
Amount

76.56

76.56
Amount

54.00

P
P
P
P
P
P

54.00
896.16
152.35
52.43
1,100.93
122.33

Page 137

hours
hours
Amount

78.12
113.28
P

191.40
Amount

19.14

19.14
Amount

18.00

P
P
P
P
P
P

18.00
228.54
38.85
13.37
280.76
140.38

Page 138

hours
hours
Amount

4,687.20
3,398.40
P

8,085.60
Amount

808.56

808.56
Amount

57,000.00

P
P
P
P
P
P

57,000.00
65,894.16
11,202.01
3,854.81
80,950.98
5,396.73

Page 139

hours
hours
Amount

6,405.84
9,288.96
P

15,694.80
Amount

1,569.48

1,569.48
Amount

5,576.00

P
P
P
P
P
P

5,576.00
22,840.28
3,882.85
1,336.16
28,059.28
684.37

Page 140

hours
hours
Amount

624.96
906.24
P

1,531.20
Amount

153.12

153.12
Amount

3,930.00

P
P
P
P
P
P

3,930.00
5,614.32
954.43
328.44
6,897.19
459.81

Page 141

hours
hours
Amount

624.96
906.24
P

1,531.20
Amount

153.12

153.12
Amount

3,750.00

P
P
P
P
P
P

3,750.00
5,434.32
923.83
317.91
6,676.06
445.07

Page 142

hours
hours
Amount

3,749.76
5,437.44
P

9,187.20
Amount

918.72

918.72
Amount

18,900.00

P
P
P
P
P
P

18,900.00
29,005.92
4,931.01
1,696.85
35,633.77
5,938.96

Page 143

hours
hours
Amount

5,062.18
18,351.36
P

23,413.54
Amount

2,341.35

2,341.35
Amount

11,550.00
5,040.00
70.00
300.00
90.00
P
P
P
P
P
P

16,660.00
42,414.89
7,210.53
2,481.27
52,106.69
1,005.14

Page 144

hours
hours
Amount

234.36
339.84
P

574.20
Amount

57.42

57.42
Amount

1,920.00

P
P
P
P
P
P

1,920.00
2,551.62
433.78
149.27
3,134.67
522.44

Page 145

hours
hours
Amount

624.96
906.24
P

1,531.20
Amount

153.12

153.12
Amount

4,480.00

P
P
P
P
P
P

4,480.00
6,164.32
1,047.93
360.61
7,572.87
473.30

Page 146

hours
hours
Amount

312.48
453.12
P

765.60
Amount

76.56

76.56
Amount

10,000.00

P
P
P
P
P
P

10,000.00
10,842.16
1,843.17
634.27
13,319.59
6,659.80

Page 147

hours
hours
Amount

1,874.88
2,718.72
P

4,593.60
Amount

459.36

459.36
Amount

5,100.48

P
P
P
P
P
P

5,100.48
10,153.44
1,726.08
593.98
12,473.50
2,361.51

Page 148

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

B.4(10) : Miscellaneous survey and staking


Unit of Measurement=
l.s.
Output=
-

Quantity=
Duration=
Say

Designation

1.00
12.00
12.00

No. of Person

No. of Hours

Hourly Rate

2
2

12
12

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

bd.ft.
kgs.

140.00
3.00

1. Labor:
Skilled
Unskilled

71.69
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
2x4 Good Lumber
Assorted Common Nails

35.00
50.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 149

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

B.5
: Project Billboard / Signboard
Unit of Measurement=
l.s.
Output=

Quantity=
Duration=
Say

Designation

1.00
57.88
57.00

No. of Person

No. of Hours

Hourly Rate

1
1

57
57

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

sq.ft.
bd.ft.
kg.
pcs.

64
54
2
2

30.00
25.00
65.00
595.00

sq.ft.
bd.ft.
kg.
pcs.

64
54
2
2

30.00
25.00
65.00
595.00

1. Labor:
Skilled
Unskilled

71.69
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
A.

B.

For DPWH Standard Billboard:


Computer generated tarpaulin signs
Coco Lumber
Common Nails Assorted
1/2" Ordinary Plywood
For COA Standard Billboard:
Computer generated tarpaulin signs
Coco Lumber
Common Nails Assorted
1/2" Ordinary Plywood
Sub-Total for 3

Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 150

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

B.7
: Occupational Safety and Health Program
Unit of Measurement=
month
Output=

Quantity=
Duration=

Designation

6.00

No. of Person

No. of Hours

Hourly Rate

2
2
4

180
8
8

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

sq.m.
bd.ft.
kg.
lot

298
222
5
1

30.00
50.00
50.00
1,000.00

set
pcs
pcs
pcs
pcs
pcs
pcs

1
15
15
5
15
15
15

2,000.00
750.00
150.00
600.00
100.00
250.00
50.00

1. Labor:
Safety Officer
Skilled
Unskilled

78.12
71.69
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
A.

B.

Temporary Facility (Perimeter Board up)


Corrugated Metal Sheet
Rough Lumber
Common Nails Assorted
Safety Warning Signs
Personal Protective Equipment (PPE)
Medical Kit
Safety Shoes
Hard Hat
Safety Harness
Reflectoriced Vest
Boots
Safety Gogles
Sub-Total for 3

Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 151

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

B.9
: Mobilization / Demobilization
Unit of Measurement=
l.s.
Output=

Quantity=
Duration=
Say

Designation

1.00
-

No. of Person

No. of Hours

Hourly Rate

No. of Units

No. of Hours

Hourly Rate

Quantity

Unit Cost

1. Labor:

Sub-Total for 1
Name and Capacity
2. Equipment:
1% of Total Direct Cost

Sub-Total for 2
Name and Specification

Unit

2. Materials:

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 152

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

B.13
: Additional Geotechnical Investigation
Unit of Measurement=
l.s.
Output=

Quantity=
Duration=
Say

Designation

1.00
-

No. of Person

No. of Hours

Hourly Rate

No. of Units

No. of Hours

Hourly Rate

Name and Specification

Unit

Quantity

Unit Cost

Soil Testing

l.s.

1.00

1. Labor:

Sub-Total for 1
Name and Capacity
2. Equipment:

Sub-Total for 2

2. Materials:
142,000.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 153

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

801(1) : Removal of Actual Structures/Obstruction


Unit of Measurement=
l.s.
Output=

Designation

Quantity=
Duration=
Say

1.00
8.00
8.00

No. of Person

No. of Hours

Hourly Rate

1
1
4

8
8
8

No. of Units

No. of Hours

Hourly Rate

Quantity

Unit Cost

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit

2. Materials:

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 154

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 803 (1) a : Structure Excavation
Unit of Measurement=
cu.m.
Output=
30 cu.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
6

21
21
21

No. of Units

No. of Hours

1
1
1.00

21
21

Unit

Quantity

630.04
21.00
21.00
Hourly Rate

1. Labor:
Foreman
Skilled (Equipment Operator)
Skilled (Mason)

78.12
65.07
56.64

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Backhoe (1.04 cu.m. Capacity)
Dumptruck (10 cu.m. Capacity)
Minor Tools 10% of Labor Cost

1,537.00
1,420.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 155

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

803 (3) : Foundation Fill (Gravel Bedding)


Unit of Measurement=
cu.m.
Output=
1.02 cu.m./hr.

Quantity=
Duration=
Say

Designation

33.00
32.35
32.00

No. of Person

No. of Hours

Hourly Rate

1
1
6

16
32
32

No. of Units

No. of Hours

Hourly Rate

Unit Cost

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit

Quantity

3/4 Gravel

cu.m.

33.00

2. Materials:
1,244.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 156

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 804 (1) b : Embankment (From Borrow)
Unit of Measurement=
cu.m.
Output=
6.225 cu.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
6

42
42
83

No. of Units

No. of Hours

1
1

42

Unit

Quantity

cu.m.

80.65

520.21
83.57
83.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
Plate Compactor

123.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
Additional Common Borrow

200.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 157

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

900(a) : Reinforced Concrete (Footing)


Unit of Measurement=
cu.m.
Output=
2.25 cu.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
6

65
65
65

No. of Units

No. of Hours

1
1

22

Name and Specification

Unit

Quantity

Ready Mix Concrete 4000 PSI @ 14 Days

cu.m.

146.52

146.52
65.12
65.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Concrete Vibrator
Minor Tools 10% of Labor Cost

545.00

Sub-Total for 2
Unit Cost

2. Materials:
4,800.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 158

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

900(b) : Reinforced Concrete (Columns)


Unit of Measurement=
cu.m.
Output= 0.3575 cu.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
6

38
76
76

No. of Units

No. of Hours

1
1

38

Unit

Quantity

bags
cu.m.
cu.m.

245.16
13.62
27.24

27.24
76.20
76.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
One Bager Mixer
Minor Tools 10% of Labor Cost

172.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40 Kgs. Portland Cement
Crashed Gravel (Sand)
3/4 Gravel

261.00
1,269.00
1,244.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 159

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 900 ( c ) : Reinforced Concrete (Foundation Beams to Ground Floor Level)
Unit of Measurement=
cu.m.
Output=
2.49 cu.m./hr.

Designation

Quantity=
Duration=
Say

No. of Person

No. of Hours

1
2
6

11
11
11

No. of Units

No. of Hours

1
1

12

Unit

Quantity

bags
cu.m.
cu.m.

265.00
14.69
29.37

29.37
11.80
11.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
One Bager Mixer

172.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40 Kgs. Portland Cement
Crashed Gravel (Sand)
3/4 Gravel

261.00
1,269.00
1,244.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 160

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 900 ( d ) : Reinforced Concrete (Second Floor Beams to Roof Beams)
Unit of Measurement=
cu.m.
Output=
2.49 cu.m./hr.

Designation

Quantity=
Duration=
Say

No. of Person

No. of Hours

1
4
6

32
32
32

No. of Units

No. of Hours

1
1

32

Unit

Quantity

bags
cu.m.
cu.m.

718.00
39.84
79.68

79.68
32.00
32.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
One Bager Mixer

172.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40 Kgs. Portland Cement
Crashed Gravel (Sand)
3/4 Gravel

261.00
1,269.00
1,244.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 161

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

900 (e) : Reinforced Concrete (Concrete Slab on grade)


Unit of Measurement=
cu.m.
Output=
2.363 cu.m./hr.

Designation

Quantity=
Duration=
Say
No. of Person

No. of Hours

1
2
8

15
15
15

No. of Units

No. of Hours

1
1
1

15
15

Unit

Quantity

bags
cu.m.
cu.m.

271.00
18.02
36.03

36.03
15.25
15.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
Concrete Vibrator
One Bager Mixer

123.00
172.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40 Kgs. Portland Cement
Fine Aggregate
3/4 Gravel

261.00
1,269.00
1,244.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 162

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

900 (f) : Reinforced Concrete (Concrete Slabs @ Second Floor and Third Floor )
Unit of Measurement=
cu.m.
Output= 0.4763 cu.m./hr.

Designation

Quantity=
Duration=
Say

No. of Person

No. of Hours

1
2
6

73
73
73

No. of Units

No. of Hours

1
1
1

18
37

Unit

Quantity

bags
cu.m.
cu.m.

262.00
17.43
34.86

34.86
73.19
73.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
Concrete Vibrator
One Bager Mixer

123.00
172.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40 Kgs. Portland Cement
Fine Aggregate
3/4 Gravel

261.00
1,269.00
1,244.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 163

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 900 ( g ) : Reinforced Concrete (Concrete Stairs, Ramp and Sunbreaker)
Unit of Measurement=
cu.m.
Output= 0.4763 cu.m./hr.

Designation

Quantity=
Duration=
Say

No. of Person

No. of Hours

1
2
6

38
38
38

No. of Units

No. of Hours

1
1
1

38
38

Unit

Quantity

bags
cu.m.
cu.m.

151.00
9.14
18.28

18.28
38.38
38.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost
Concrete Vibrator
One Bager Mixer

123.00
172.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40 Kgs. Portland Cement
Fine Aggregate
3/4 Gravel

261.00
1,269.00
1,244.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 164

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

902
: Lean Concrete
Unit of Measurement=
cu.m.
Output= 0.4763 cu.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
4

22
43
43

No. of Units

No. of Hours

32

Unit

Quantity

bags
cu.m.
cu.m.

114.00
11.00
7.00

20.65
43.36
43.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
One Bager Mixer

172.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40 Kgs. Portland Cement
Fine Aggregate
3/4 Gravel
mix: 1:12:14 (cement:gravel:sand)

261.00
1,269.00
1,244.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 165

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1003(1) a : Ceiling (4.5mm Fiber Cement Board)
Unit of Measurement=
sq.m.
Output=
5.1

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
4

112
112
56

No. of Units

No. of Hours

140

Unit

Quantity

pcs.
pcs.

288
28,770

716.00
140.39
140.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
10% of Labor Cost

4,390.18

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
4.5mm thick Fiber Cement Board
1" Metal Black Screw

433.00
0.75

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 166

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1005 (1)a : Residential Casement
Unit of Measurement=
sq.m.
Output=
0.72 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
1

82
165
82

No. of Units

No. of Hours

148

Unit

Quantity

sq.m.
sq.m.

108.00
10.52

118.52
164.61
164.00
Hourly Rate

1. Labor:
Foreman
Skilled (Welder)
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Welding Machine

61.25

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
Steel Casement Window (36)
Steel Awning Window (6)
note: complete accessories and glass

1,850.00
1,800.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 167

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1006 (1) : Hollow Steel Doors
Unit of Measurement=
sq.m.
Output=
0.384 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
2

61
122
61

No. of Units

No. of Hours

110

Unit

Quantity

sq.m.
sq.m.
sq.m.

34.02
10.08
2.94

47.04
122.50
122.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Welding Machine

61.25

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
.90x2.10 Steel Hollow Steel Door with Steel Jamb (18)
.80x2.10 Steel Hollow Steel Door with Steel Jamb (6)
.70x2.10 Steel Hollow Steel Door with Steel Jamb (2)

3,175.00
3,175.00
3,175.00

note: complete set (with hinges,barrel bolt, dead bolt,door knob and paint
finished)

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 168

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1010(1) : Wooden Doors - Frames (Jambs, Sills, Head, Transoms and Mullions)
Unit of Measurement=
set
Output= 0.9375 sq.m./hr.

Designation

Quantity=
Duration=
Say

No. of Person

No. of Hours

1
2

50
50

No. of Units

No. of Hours

50

Unit

Quantity

set
set
set
pairs

2
13
15
30

47.04
50.18
50.00
Hourly Rate

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

957.00

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
.90x2.10 Hollow Core Flush Type Door Jamb (D-2)
.70x1.20 Louvered Door(D-4)
Door Knobs
Door Higne (Loose Pine)

900.00
900.00
350.00
250.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 169

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1010(1)b : Wooden Doors - Flush
Unit of Measurement=
sq.m.
Output=
0.625 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

2
2

75
75

No. of Units

No. of Hours

75

Unit

Quantity

sq.m.
sq.m.
set

3.78
10.94
2

47.04
75.26
75.00
Hourly Rate

1. Labor:
Skilled
Unskilled

78.12
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

1,826.55

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
.90x2.10 Hollow Core Flush Type Door (D-2)
.70x1.20 Louvered Door (D-4)
.30x.80 Stainless Kickplate

890.00
890.00
500.00

note: doors with complete hardware accessories(hinge and


door knobs)

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 170

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1013(1) : Corrugated Metal Roofing - Prepainted Long Span


Unit of Measurement=
sq.m
Output=
4.15 sq.m./hr.

Designation

Quantity=
Duration=
Say
No. of Person

No. of Hours

1
4
2

97
129
97

No. of Units

No. of Hours

129

Unit

Quantity

sq.m
pcs.
pcs.

535.68
1,188.00
10

535.68
129.08
129.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

4,523.06

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
Gauge 26 Pre-painted Corrugated Metal Sheet(Long Span)

2"Self Drilling Screw (Tekscrew)


Roof Sealant

250.00
1.00
115.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 171

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1013(2)a : Fabricated Metal Roofing Accessory -Ridge Roll
Unit of Measurement=
ln.m.
Output= 5.3125 ln.m./hr.

Designation

Quantity=
Duration=
Say
No. of Person

No. of Hours

1
2
2

7
7
7

No. of Units

No. of Hours

Unit

Quantity

ln.m.
pcs.
pcs.

37.20
496.00
10

37.20
7.00
7.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

195.09

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
Gauge 24 Pre-painted Ridge Roll
2"Self Drilling Screw (Tekscrew)
Roof Sealant

168.00
1.00
115.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 172

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1013(2) b : Fabricated Metal Roofing Accessory -Flashings
Unit of Measurement=
ln.m.
Output= 5.3125 ln.m./hr.

Designation

Quantity=
Duration=
Say
No. of Person

No. of Hours

2
2

5
5

No. of Units

No. of Hours

Unit

Quantity

ln.m.
pcs.
lts.
lts.

28.80
200.00
2
1

28.80
5.42
5.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

100.29

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
Gauge 24 Pre-painted Gutter (2.44m)
1/8x1"Blind Revits
Marine Epoxy
Repaint

890.00
1.00
180.00
180.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 173

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1013(2)c : Fabricated Metal Roofing Accessory - Gutters
Unit of Measurement=
ln.m.
Output= 5.3125 ln.m./hr.

Designation

Quantity=
Duration=
Say
No. of Person

No. of Hours

2
2

14
14

No. of Units

No. of Hours

14

Unit

Quantity

ln.m.
pcs.

74.40
200.00

74.40
14.00
14.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

280.81

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
Gauge 24 Pre-painted End Flassing(2.44m)
1/8x1"Blind Revits

168.00
1.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 174

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1013(3) : Roof Ventilators


Unit of Measurement=
each
Output=

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

2
2

56
56

No. of Units

No. of Hours

56

Unit

Quantity

each

18.00

19.00
56.00

Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

1,123.25

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
300x1175mm Roof Ventilators

1,300.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 175

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1016(1)a : Waterproofing-Cement Base
Unit of Measurement=
sq.m.
Output=
1.25 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

2
1

44
44

No. of Units

No. of Hours

44

Unit

Quantity

gal
pcs.

3.00
4.00

55.29
44.23
44.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

694.13

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
Cement Base Waterproof
4"Paint Brush

1,100.00
55.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 176

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1018(1) : Glazed Tiles and Trims


Unit of Measurement=
sq.m.
Output=
1.12 sq.m./hr.

Quantity=
Duration=
Say

Designation

169.92
151.71
151.00

No. of Person

No. of Hours

Hourly Rate

4
2

113
151

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

sq.m.

169.92

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools-10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
200x200mm Glazed Wall Tiles

850.00

note: with tile trim, adhesive and tile grout and cement base

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 177

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1018(2) : Unglazed Tiles - Vitrified Floor Tile


Unit of Measurement=
sq.m.
Output=
1.12 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

4
2

78
78

No. of Units

No. of Hours

78

Unit

Quantity

sq.m.

87.22

87.22
77.88
77.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

2,444.18

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
200x200mm Unglazed Vitrified Tiles

850.00

note: with tile trim, adhesive and tile grout and cement base

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 178

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1021(1)a : Cement Floor Finish
Unit of Measurement=
sq.m.
Output=
8.33 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

4
3

108
108

No. of Units

No. of Hours

108

Unit

Quantity

bags

102.00

899.10
107.94
107.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40kg.Portland Cement
(4mm thick plain cement finish)

261.00

Sub-Total for 3

Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 179

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1027(1) : Cement Plaster Finish


Unit of Measurement=
sq.m.
Output=
9.5 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

6
4

299
224

No. of Units

No. of Hours

299

Unit

Quantity

bags
cu.m.

546.00
46.00

2,843.70
299.34
299.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

14,076.62

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
40 kg. Cement
Fine sand
note:(16mm thick plaster average)

261.00
1,269.00

Sub-Total for 3

Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 180

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1032(1)a : Painting Works - Masonry and Fiber Cement Painting


Unit of Measurement=
sq.m.
Output= 12.5478 sq.m./hr.

Designation

Quantity=
Duration=
Say

3,192.27
254.41
254.00

No. of Person

No. of Hours

Hourly Rate

1
6

127
254

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

gal.
gal.
gal.
ls.
lts.
ls.
ls.
gal.
pcs.
gal.

107.00
213.00
107.00
1.00
71.00
1.00
1.00
10.00
10.00
27.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Flat Wall Primer - 1 coat
Semi-Gloss Latex - 2 coats
Penetrating Sealer
Tinting Color (latex)
Putty Filler
Paint Brush
Paint Roller (big)
Body Filler with Hardener
Extra Hardener
Paint Reducer (thinner)

581.00
581.00
545.00
1,230.00
275.00
1,200.00
675.00
550.00
120.00
250.00

Sub-Total for 3

Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 181

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1032(1)b : Painting Works - Metal Painting


Unit of Measurement=
sq.m.
Output= 4.1826 sq.m./hr.

Quantity=
Duration=
Say

Designation

213.36
51.01
51.00

No. of Person

No. of Hours

Hourly Rate

1
4

26
51

No. of Units

No. of Hours

Hourly Rate

Unit Cost

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit

Quantity

Red Oxide Primer/Rust-off Gray - 1 coat


Top Coat Quick Dry Enamel - 2 coats
Paint Brush
Lacquer Thinner

gals
gals
ls.
gal.

11
17
1.00
7.00

2. Materials:
581.00
581.00
1,200.00
250.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 182

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1032(1)c : Painting Works - Wood Paint


Unit of Measurement=
sq.m.
Output=
2.88 sq.m./hr.

Quantity=
Duration=
Say

Designation

104.55
36.30
36.00

No. of Person

No. of Hours

Hourly Rate

1
2

36
36

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

gals
ls.
ls.
gal.
lts.
ls.

4
1
1.00
3.00
7.00
1.00

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Quick Dry Enamel
Oil Tinting Color
Paint Brush
Paint Thinner
Wood Putty
Sand Paper

581.00
1,230.00
550.00
250.00
250.00
540.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 183

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1035
: Furring Channel-Double Furring System
Unit of Measurement=
ln.m.
Output=
10.5

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
4

154
154
77

No. of Units

No. of Hours

154

Unit

Quantity

pcs.
pcs.
pcs.
pcs.
kgs.
pcs.
pcs.
pairs
lot

186
256
104
82
3
425
868
450
1

1,610.15
153.35
154.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
L20x20 Wall Angle (2.44m)
Double Metal Furring (5.0m)
Carrying Channel (5.0m)
10mm Full Threaded Rod (3.0m)
1" Concrete Nail
1/8x1/2" Blind Revits
W-Clip
Nuts with Washer
Consumables (drill bit,screw bit,reviter,c-clamp etc.)

55.00
110.00
110.00
180.00
50.00
0.75
35.00
1.00
3,000.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 184

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1043(2) a : CHB Non Load Bearing Wall - 100mm
Unit of Measurement=
sq.m.
Output= 3.1875 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
2

53
105
53

No. of Units

No. of Hours

105

Unit

Quantity

337.20
105.79
105.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
100mm thick CHB Non-load Bearing
40 kg. Cement
Fine Sand

pcs.
bags
cu.m.

4,426
133
14.67

14.00
261.00
1,269.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 185

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1043(2) b : CHB Non Load Bearing Wall - 150mm
Unit of Measurement=
sq.m.
Output= 3.1875 sq.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
4

88
175
88

No. of Units

No. of Hours

175

Unit

Quantity

pcs.
bags
cu.m.

7,345
427
134

559.60
175.56
175.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
150mm thick CHB Non-load Bearing
40 kg. Cement
Fine Sand

15.00
261.00
1,269.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 186

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1044(1) : Forms and Falseworks
Unit of Measurement=
l.s.
Output=

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
4

257
514
257

No. of Units

No. of Hours

514

Unit

Quantity

pcs.
bd.ft.
bd.ft.

112
3,136
2,889

pcs.

96

bd.ft.
pcs.
pcs.

5,713
285
302

1.00
514.00
514.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
A. Forworks
1/2" Ordinary Plywood (4x8ft) - Two(2) Uses
2x3 Good Lumber (multiple uses)
2x2 Good Lumber (multiple uses)
B. Scaffolding
3/4" Ordinary Plywood (4x8ft) - Two(2) Uses for
Suspended Slabs
2x2 / 3/ 4/Good Lumber (multiple uses)
38mm GI Pipes GA 40
Swivel Clamp

Unit Cost

540.00
34.00
34.00
1,100.00
34.00
847.00
50.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 187

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(1) h1 : PVC Coupling 20mm diameter
Unit of Measurement=
pcs.
Output=
14 pcs./hr.

Quantity=
Duration=
Say

Designation

416.00
29.71
30.00

No. of Person

No. of Hours

Hourly Rate

1
4

30
30

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.

416

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools
30% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
20mm diameter PVC Conduit

3.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 188

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(1) h2 : PVC Coupling 25mm diameter
Unit of Measurement=
pcs.
Output=
3.5 pcs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
1

2
2

No. of Units

No. of Hours

Unit

Quantity

pcs.

8.00
2.29
2.00
Hourly Rate

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
20mm diameter PVC Coupling

5.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 189

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(7)a1 : PVC Adapter 20mm diameter
Unit of Measurement=
pcs.
Output=
18 pcs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

2
2

1
1

No. of Units

No. of Hours

Unit

Quantity

pcs.

4.00
0.22
1.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
20mm diameter PVC Conduit

69.75

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 190

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(4)d1 : PVC Elbow 20mmx90 deg.
Unit of Measurement=
pcs.
Output=
10.5 pcs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
3

5
5

No. of Units

No. of Hours

Unit

Quantity

pcs.

52

52.00
4.95
5.00
Hourly Rate

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
PVC Elbow 20mmx90 deg.

10.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 191

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(4)d2 : PVC Elbow 25mmx90 deg.
Unit of Measurement=
pcs.
Output=
10.5 pcs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
3

1
1

No. of Units

No. of Hours

Unit

Quantity

pcs.

4.00
0.38
1.00
Hourly Rate

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
PVC Elbow 20mmx90 deg.

15.50

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 192

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(7)a2 : PVC Adapter 20mm male diameter
Unit of Measurement=
pcs.
Output=
14 pcs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
2

36
36
36

No. of Units

No. of Hours

36

Unit

Quantity

pcs.

496

496.00
35.43
36.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
20mm diameter PVC Conduit

5.25

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 193

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(7)a3 : PVC Adapter 25mm male diameter
Unit of Measurement=
pcs.
Output=
14 pcs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
2

11
11
11

No. of Units

No. of Hours

11

Unit

Quantity

pcs.

149

149.00
10.64
11.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
PVC Adapter 25mm male diameter

7.25

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 194

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(7)b1 : Polyvinyl Chloride Pipes (PVC)-20mm
Unit of Measurement=
pcs.
Output=
13.5 ln.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
3
2

24
47
35

No. of Units

No. of Hours

47

Unit

Quantity

pcs.

208

208.00
46.22
47.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
20mm x 3m diameter PVC Pipe

75.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 195

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(7)b2 : Polyvinyl Chloride Pipes (PVC)-25mm
Unit of Measurement=
pcs.
Output=
4.5 ln.m./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
1

3
3

No. of Units

No. of Hours

Unit

Quantity

pcs.

4.00
2.67
3.00
Hourly Rate

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
25mm x 3m diameter PVC Pipe

95.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 196

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(8)b : GI Wire #16
Unit of Measurement=
kgs.
Output=

Quantity=
Duration=
Say

Designation

12.00
16.00
16.00

No. of Person

No. of Hours

Hourly Rate

16

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

kilo

12

1. Labor:
Unskilled

43.65

Sub-Total for 1
Name and Capacity
2. Equipment:

Sub-Total for 2
Name and Specification
2. Materials:
#16 GI Wire

46.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 197

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(14) : Octagonal Junction Box PVC
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2

18
18

No. of Units

No. of Hours

18

Unit

Quantity

pcs.
pcs.

124
496

124.00
17.71
18.00
Hourly Rate

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
4x4 Octagonal Junction Box
PVC Adapter

33.00
9.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 198

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(15) : Utility Boxes PVC
Unit of Measurement=
pcs.
Output=
7 pcs./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2

13
13

No. of Units

No. of Hours

13

Unit

Quantity

pcs.
pcs.

91
364

91.00
13.00
13.00
Hourly Rate

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
2x4 Utility Box
PVC Adapter

32.00
9.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 199

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1100(22) : Grounding Rod Copperweld
Unit of Measurement=
length
Output=

Quantity=
Duration=
Say

Designation

2.00
2.00
2.00

No. of Person

No. of Hours

Hourly Rate

1
1

2
2

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
pcs.

2
2

1. Labor:
Foreman
Skilled

78.12
56.64

Sub-Total for 1
Name and Capacity
2. Equipment:

Sub-Total for 2
Name and Specification
2. Materials:
16mm x 2.4 m Copperweld Grounding Rod
Clamp

250.00
150.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 200

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1101(1)a2 : Electrical Wire - 3.5mm TWG/THHN
Unit of Measurement=
roll
Output=
75 lm./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
4
2

20
26
13

No. of Units

No. of Hours

100

Unit

Quantity

rolls
rolls
pcs

13
5
3

18.00
25.75
26.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
3.5mm THHN Wire
3.5mm TWG Wire (for grounding)
Electrical Tape

3,600.00
3,600.00
31.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 201

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1101(1)a3 : Electrical Wire - 5.5mm TWG/THHN
Unit of Measurement=
roll
Output=
18.75 lm./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
1

2
2

No. of Units

No. of Hours

100

Unit

Quantity

rolls
pcs

0.24
3

0.24
1.92
2.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
5.5mm THHN Wire
Electrical Tape

5,500.00
31.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 202

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1101(1)a4 : Electrical Wire - 8.0mm TWG/THHN
Unit of Measurement=
roll
Output=
18.75 lm./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
1

1
2

No. of Units

No. of Hours

100

Unit

Quantity

rolls
pcs

0.11
3

0.11
0.85
1.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
8.0mm THHN Wire
Electrical Tape

6,500.00
31.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 203

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1101(1)a5 : Electrical Wire - 14 mm TWG/THHN
Unit of Measurement=
roll
Output=
lm./hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
1

2
2

No. of Units

No. of Hours

100

Unit

Quantity

rolls
pcs

0.10
3

0.10
2.00
2.00
Hourly Rate

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
14 mm THHN Wire
Electrical Tape

6,500.00
31.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 204

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1101(1)a8 : Electrical Wire - 38 mm TWG/THHN
Unit of Measurement=
roll
Output=

Quantity=
Duration=
Say

Designation

0.20
4.00
4.00

No. of Person

No. of Hours

Hourly Rate

1
1

4
4

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

rolls
pcs

0.11
3

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
38 mm THHN Wire
Electrical Tape

8,400.00
31.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 205

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1101(3) : Tumbler Switch Two-Gang


Unit of Measurement=
set
Output=
1.25 set/hr.

Quantity=
Duration=
Say

Designation

15.00
12.00
12.00

No. of Person

No. of Hours

Hourly Rate

2
2

12
12

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

set

15.00

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Tumbler Switch Two-Gang

130.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 206

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1101(6) : Duplex Convenience Receptacles


Unit of Measurement=
set
Output=
1.25 set/hr.

Quantity=
Duration=
Say

Designation

36.00
28.80
28.00

No. of Person

No. of Hours

Hourly Rate

2
2

28
28

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

set
set

18.00
18.00

1. Labor:
Skilled
Unskilled

56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
Duplex Convenience Outlet
Wall Fan Outlet

167.00
167.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 207

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1102(1)a : Panelboard Circuit Breaker Type - Main Distribution Panel (MDP)
Unit of Measurement=
set
Output=
0.3 set/hr.

Designation

Quantity=
Duration=
Say

1.00
16.00
16.00

No. of Person

No. of Hours

Hourly Rate

1
2
1

8
16
8

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
pcs.
set

1.00
3.00
1.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
125AMP Bolt-on Type Main Circuit Breaker
50AMP Bolt-on Type Branch Circuit Breaker
Panel Board Cabinet (Flush Type)
6-Knock Out Holes , 4-Branches and 1-Main,
grounding terninal, neutral bus bar

1,390.00
1,390.00
4,500.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 208

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1102(1)b : Panelboard Circuit Breaker Type - LPA Flush Mounted, NEMA 1 Enclosure (Bolt-on Type)
Unit of Measurement=
set
Quantity=
Output=
Duration=
Say
Designation

1.00
12.00

No. of Person

No. of Hours

Hourly Rate

1
1
2

12
12
12

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
pcs.
pcs.
set

1.00
3.00
7.00
1.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
50AMP Bolt-on Type Main Circuit Breaker
15AMP Bolt-on Type Branch Circuit Breaker
20AMP Bolt-on Type Main Circuit Breaker
Panel Board Cabinet (Flush Type)
14-Knock Out Holes , 10-Branches and 1-Main,
grounding terninal, neutral bus bar

1,390.00
1,390.00
1,390.00
6,500.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 209

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1102(1)c : Panelboard Circuit Breaker Type - LPB and LPC Flush Mounted, NEMA 1 Enclosure (Bolt-on Type)
Unit of Measurement=
set
Quantity=
2.00
Output=
Duration=
24.00
Say
Designation

No. of Person

No. of Hours

Hourly Rate

1
1
2

24
24
24

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

pcs.
pcs.
pcs.
set

2.00
6.00
12.00
2.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
50AMP Bolt-on Type Main Circuit Breaker
15AMP Bolt-on Type Branch Circuit Breaker
20AMP Bolt-on Type Main Circuit Breaker
Panel Board Cabinet (Flush Type)
14-Knock Out Holes , 10-Branches and 1-Main,
grounding terninal, neutral bus bar

1,390.00
1,390.00
1,390.00
6,500.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 210

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1103(1)a1 : Compact Flourescent Lamp (CFL)
Unit of Measurement=
sets
Output=
1.0 set/hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
2

6
6
6

No. of Units

No. of Hours

100

Unit

Quantity

sets
pcs.

6.00
6.00

6.00
6.00
6.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
1-18 Watts Compact Flourescent Lamp (CFL)
4"Plastic Receptacle

110.00
25.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 211

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1103(1)a3 : Flourescent Lighting Fixture
Unit of Measurement=
sets
Output=
1.0 set/hr.

Quantity=
Duration=
Say

Designation

No. of Person

No. of Hours

1
2
2

29
58
29

No. of Units

No. of Hours

100

Unit

Quantity

sets

58.00

58.00
58.00
58.00
Hourly Rate

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity

Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification

Unit Cost

2. Materials:
1-36 Watts Flourescent Lighting Fixture (FLF)

700.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 212

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM 1103(1)a4 : Flourescent Lighting Fixture
Unit of Measurement=
sets
Output=
1.0 set/hr.

Quantity=
Duration=
Say

Designation

90.00
90.00
90.00

No. of Person

No. of Hours

Hourly Rate

1
2
2

45
90
45

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

sets

90.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
2-36 Watts Flourescent Lighting Fixture (FLF)

700.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 213

17%
5%

Name of Project:
Location:

Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


Nangalisan, Tuba, Benguet

DETAILED UNIT PRICE ANALYSIS


ITEM

1209(1) : Fire Alarm System


Unit of Measurement=
l.s.
Output=

Quantity=
Duration=
Say

Designation

1.00
33.30
34.00

No. of Person

No. of Hours

Hourly Rate

1
2
1

34
34
34

No. of Units

No. of Hours

Hourly Rate

Unit

Quantity

Unit Cost

sets
pcs.
pcs.
pcs.
ln.m.
pcs.
pcs.
pcs.

1.00
3.00
1.00
3.00
117.00
10.00
4.00
6.00

1. Labor:
Foreman
Skilled
Unskilled

78.12
56.64
43.65

Sub-Total for 1
Name and Capacity
2. Equipment:
Minor Tools 10% of Labor Cost

Sub-Total for 2
Name and Specification
2. Materials:
FACP
Fire Alarm Bell 8"
Enlosed Air Circuit Breaker 20amp
Fire Alarm Station Outlet (Manual)
2.0mm TW Wire
20mm PVC Elec. Conduit
20mm PVC Elec. Elbow
PVC Utility Box

14,000.00
1,600.00
450.00
900.00
29.00
75.00
15.50
32.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT
ITEM COST
TOTAL UNIT COST

Page 214

17%
5%

hours
hours
Amount

1,720.56
1,047.60

2,768.16
Amount

276.82

276.82
Amount

4,900.00
150.00

P
P
P
P
P
P

5,050.00
8,094.98
1,376.15
473.56
9,944.68
9,944.68

Page 215

hours
hours
Amount

4,086.33
2,488.05
P

6,574.38
Amount

657.44
P

657.44
Amount

1,920.00
1,350.00
130.00
1,190.00
1,920.00
1,350.00
130.00
1,190.00
P
P
P
P
P
P

3,400.00
10,631.82
1,807.41
621.96
13,061.19
13,061.19

Page 216

Amount

28,123.20
1,147.04
1,396.80
P

30,667.04
Amount

3,066.70

3,066.70
Amount

8,940.00
11,100.00
250.00
1,000.00
2,000.00
11,250.00
2,250.00
3,000.00
1,500.00
3,750.00
750.00
P
P
P
P
P
P

45,790.00
79,523.74
13,519.04
4,652.14
97,694.92
16,282.49

Page 217

hours
hours
Amount

Amount

122,868.02

122,868.02
Amount

P
P

122,868.02

P
P
P

6,143.40
129,011.42
129,011.42

Page 218

Amount

Amount

Amount

142,000.00

P
P

142,000.00
142,000.00

P
P
P

7,100.00
149,100.00
149,100.00

Page 219

hours
hours
Amount

624.96
453.12
1,396.80

2,474.88
Amount

247.49

247.49
Amount

P
P
P
P
P
P

2,722.37
462.80
159.26
3,344.43
3,344.43

Page 220

hours
hours
Amount

1,640.52
2,732.94
7,136.64

11,510.10
Amount

32,277.00
29,820.00
1,151.01
P

63,248.01
Amount

P
P
P
P
P
P

74,758.11
12,708.88
4,373.35
91,840.34
145.77

Page 221

hours
hours
Amount

1,249.92
1,812.48
8,380.80

11,443.20
Amount

1,144.32

1,144.32
Amount

41,052.00

P
P
P
P
P
P

41,052.00
53,639.52
9,118.72
3,137.91
65,896.15
1,996.85

Page 222

hours
hours
Amount

3,241.98
4,701.12
21,737.70

29,680.80
Amount

2,968.08
5,104.50

8,072.58
Amount

16,129.80

P
P
P
P
P
P

16,129.80
53,883.18
9,160.14
3,152.17
66,195.49
127.25

Page 223

hours
hours
Amount

5,077.80
14,726.40
17,023.50

36,827.70
Amount

11,990.00
3,682.77
P

3,682.77
Amount

703,296.00

P
P
P
P
P
P

703,296.00
743,806.47
126,447.10
43,512.68
913,766.25
6,236.46

Page 224

hours
hours
Amount

2,968.56
8,609.28
19,904.40

31,482.24
Amount

6,536.00
3,148.22

9,684.22
Amount

63,986.76
17,283.78
33,886.56

P
P
P
P
P
P

115,157.10
156,323.56
26,575.01
9,144.93
192,043.50
7,050.06

Page 225

hours
hours
Amount

859.32
1,246.08
2,880.90

4,986.30
Amount

498.63
2,064.00

2,562.63
Amount

69,165.00
18,635.27
36,536.28

P
P
P
P
P
P

124,336.55
131,885.48
22,420.53
7,715.30
162,021.31
5,516.56

Page 226

hours
hours
Amount

2,499.84
7,249.92
8,380.80

18,130.56
Amount

1,813.06
5,504.00

7,317.06
Amount

187,398.00
50,556.96
99,121.92

P
P
P
P
P
P

337,076.88
362,524.50
61,629.16
21,207.68
445,361.34
5,589.37

Page 227

hours
hours
Amount

1,171.80
1,699.20
5,238.00

8,109.00
Amount

810.90
1,845.00
2,580.00
P

5,235.90
Amount

70,731.00
22,861.04
44,821.32

P
P
P
P
P
P

138,413.36
151,758.26
25,798.90
8,877.86
186,435.02
5,174.44

Page 228

hours
hours
Amount

5,702.76
8,269.44
19,118.70
P

33,090.90
Amount

3,309.09
2,244.75
6,278.00
P

11,831.84
Amount

68,382.00
22,118.67
43,365.84

P
P
P
P
P
P

133,866.51
178,789.25
30,394.17
10,459.17
219,642.59
6,300.71

Page 229

hours
hours
Amount

2,968.56
4,304.64
9,952.20
P

17,225.40
Amount

4,674.00
6,536.00
P

11,210.00
Amount

39,411.00
11,598.66
22,740.32

P
P
P
P
P
P

73,749.98
102,185.38
17,371.51
5,977.84
125,534.74
6,867.33

Page 230

hours
hours
Amount

1,679.58
4,871.04
7,507.80

14,058.42
Amount

5,547.00
-

5,547.00
Amount

29,754.00
13,959.00
8,708.00

P
P
P
P
P
P

52,421.00
72,026.42
12,244.49
4,213.55
88,484.46
4,284.96

Page 231

hours
hours
Amount

8,749.44
25,374.72
9,777.60

43,901.76
Amount

4,390.18

4,390.18
Amount

124,704.00
21,577.50

P
P
P
P
P
P

146,281.50
194,573.44
33,077.48
11,382.55
239,033.47
333.85

Page 232

hours
hours
Amount

6,405.84
18,647.15
3,579.30

28,632.29
Amount

9,040.50

9,040.50
Amount

199,800.00
18,937.80

P
P
P
P
P
P

218,737.80
256,410.59
43,589.80
15,000.02
315,000.41
2,657.78

Page 233

hours
hours
Amount

4,765.32
13,820.16
5,325.30

23,910.78
Amount

6,725.25

6,725.25
Amount

108,013.50
32,004.00
9,334.50

P
P
P
P
P
P

149,352.00
179,988.03
30,597.97
10,529.30
221,115.29
4,700.58

Page 234

hours
hours
Amount

3,906.00
5,664.00

9,570.00
Amount

957.00

957.00
Amount

1,800.00
11,700.00
5,250.00
7,500.00
P
P
P
P
P
P

26,250.00
36,777.00
6,252.09
2,151.45
45,180.54
960.47

Page 235

hours
hours
Amount

11,718.00
6,547.50
P

18,265.50
Amount

1,826.55

1,826.55
Amount

3,364.20
9,736.60
1,000.00

P
P
P
P
P
P

13,100.80
33,192.85
5,642.78
1,941.78
40,777.42
866.87

Page 236

hours
hours
Amount

7,558.11
29,226.24
8,446.28
P

45,230.63
Amount

4,523.06

4,523.06
Amount

133,920.00
1,188.00
1,150.00
P
P
P
P
P
P

135,108.00
184,861.69
31,426.49
10,814.41
227,102.58
423.95

Page 237

hours
hours
Amount

546.84
792.96
611.10
P

1,950.90
Amount

195.09

195.09
Amount

6,249.60
496.00
1,150.00
P
P
P
P
P
P

6,745.60
8,891.59
1,511.57
520.16
10,923.32
293.64

Page 238

hours
hours
Amount

566.40
436.50
P

1,002.90
Amount

100.29

100.29
Amount

25,632.00
200.00
360.00
180.00
P
P
P
P
P
P

26,192.00
27,295.19
4,640.18
1,596.77
33,532.14
1,164.31

Page 239

hours
hours
Amount

1,585.92
1,222.20
P

2,808.12
Amount

280.81

280.81
Amount

12,499.20
200.00
P
P
P
P
P
P

12,699.20
15,788.13
2,683.98
923.61
19,395.72
260.70

Page 240

hours
hours
Amount

6,343.68
4,888.80
P

11,232.48
Amount

1,123.25

1,123.25
Amount

23,400.00
P
P
P
P
P
P

23,400.00
35,755.73
6,078.47
2,091.71
43,925.91
2,311.89

Page 241

hours
hours
Amount

5,010.60
1,930.73
P

6,941.33
Amount

694.13

694.13
Amount

3,300.00
220.00
P
P
P
P
P
P

3,520.00
11,155.46
1,896.43
652.59
13,704.48
247.87

Page 242

hours
hours
Amount

25,657.92
13,182.30
P

38,840.22
Amount

3,884.02
Amount

144,432.00

P
P
P
P
P
P

144,432.00
187,156.24
31,816.56
10,948.64
229,921.44
1,353.12

Page 243

hours
hours
Amount

17,643.36
6,798.49
P

24,441.85
Amount

2,444.18

2,444.18
Amount

74,137.00

P
P
P
P
P
P

74,137.00
101,023.03
17,173.92
5,909.85
124,106.80
1,422.92

Page 244

hours
hours
Amount

24,453.79
14,134.11
P

38,587.90
Amount

3,858.79

3,858.79
Amount

26,622.00

P
P

26,622.00
69,068.69

P
P
P
P

11,741.68
4,040.52
84,850.89
94.37

Page 245

hours
hours
Amount

101,612.16
39,154.05
P

140,766.21
Amount

14,076.62

14,076.62
Amount

142,506.00
58,374.00

P
P

200,880.00
355,722.83

P
P
P
P

60,472.88
20,809.79
437,005.50
153.68

Page 246

hours
hours
Amount

9,921.24
86,319.36
P

96,240.60
Amount

9,624.06

9,624.06
Amount

62,167.00
123,753.00
58,315.00
1,230.00
19,525.00
1,200.00
675.00
5,500.00
1,200.00
6,750.00

P
P

244,235.00
350,099.66

P
P
P
P

59,516.94
20,480.83
430,097.43
134.73

Page 247

hours
hours
Amount

2,031.12
11,554.56
P

13,585.68
Amount

407.57

407.57
Amount

6,245.75
9,877.00
1,200.00
1,750.00
P
P
P
P
P
P

19,072.75
33,066.00
5,621.22
1,934.36
40,621.58
190.39

Page 248

hours
hours
Amount

2,812.32
4,078.08
P

6,890.40
Amount

689.04

689.04
Amount

2,324.00
1,230.00
550.00
750.00
1,750.00
540.00
P
P
P
P
P
P

7,144.00
14,723.44
2,502.98
861.32
18,087.75
173.01

Page 249

hours
hours
Amount

12,030.48
17,445.12
13,444.20

42,919.80
Amount

4,291.98

4,291.98
Amount

10,230.00
28,160.00
11,440.00
14,760.00
150.00
318.75
30,380.00
450.00
3,000.00
P
P
P
P
P
P

98,888.75
146,100.53
24,837.09
8,546.88
179,484.50
111.47

Page 250

hours
hours
Amount

4,101.30
23,788.80
4,583.25

32,473.35
Amount

3,247.34

3,247.34
Amount

61,960.50
34,675.62
18,613.95
P
P
P
P
P
P

115,250.07
150,970.76
25,665.03
8,831.79
185,467.57
550.02

Page 251

hours
hours
Amount

6,835.50
39,648.00
15,277.50

61,761.00
Amount

6,176.10

6,176.10
Amount

110,171.25
111,440.42
169,986.20
P
P
P
P
P
P

391,597.88
459,534.98
78,120.95
26,882.80
564,538.72
1,008.83

Page 252

hours
hours
Amount

20,076.84
116,451.84
44,872.20

181,400.88
Amount

18,140.09

18,140.09
Amount

60,480.00
106,624.00
98,226.00
105,105.00
194,234.86
241,395.00
15,100.00
P
P
P
P
P
P

821,164.86
1,020,705.83
173,519.99
59,711.29
1,253,937.11
1,253,937.11

Page 253

hours
hours
Amount

2,343.60
6,796.80

9,140.40
Amount

914.04

914.04
Amount

1,456.00
P
P
P
P
P
P

1,456.00
11,510.44
1,956.77
673.36
14,140.58
33.99

Page 254

hours
hours
Amount

156.24
113.28

269.52
Amount

26.95

26.95
Amount

44.00
P
P
P
P
P
P

44.00
340.47
57.88
19.92
418.27
52.28

Page 255

hours
hours
Amount

113.28
87.30

200.58
Amount

20.06

20.06
Amount

279.00
P
P
P
P
P
P

279.00
499.64
84.94
29.23
613.81
153.45

Page 256

hours
hours
Amount

390.60
849.60

1,240.20
Amount

124.02

124.02
Amount

520.00
P
P
P
P
P
P

520.00
1,884.22
320.32
110.23
2,314.76
44.51

Page 257

hours
hours
Amount

78.12
169.92

248.04
Amount

24.80

24.80
Amount

62.00
P
P
P
P
P
P

62.00
334.84
56.92
19.59
411.36
102.84

Page 258

hours
hours
Amount

2,812.32
8,156.16
3,142.80

14,111.28
Amount

1,411.13

1,411.13
Amount

2,604.00
P
P
P
P
P
P

2,604.00
18,126.41
3,081.49
1,060.39
22,268.29
44.90

Page 259

hours
hours
Amount

859.32
2,492.16
960.30

4,311.78
Amount

431.18

431.18
Amount

1,080.25
P
P
P
P
P
P

1,080.25
5,823.21
989.95
340.66
7,153.81
48.01

Page 260

hours
hours
Amount

1,835.82
7,986.24
3,077.33

12,899.39
Amount

1,289.94

1,289.94
Amount

15,600.00
P
P
P
P
P
P

15,600.00
29,789.32
5,064.18
1,742.68
36,596.18
175.94

Page 261

hours
hours
Amount

234.36
169.92

404.28
Amount

40.43

40.43
Amount

380.00
P
P
P
P
P
P

380.00
824.71
140.20
48.25
1,013.15
253.29

Page 262

hours
hours
Amount

1,396.80

1,396.80
Amount

Amount

552.00
P
P
P
P
P
P

552.00
1,948.80
331.30
114.00
2,394.10
199.51

Page 263

hours
hours
Amount

1,406.16
2,039.04

3,445.20
Amount

344.52

344.52
Amount

4,092.00
4,464.00
P
P
P
P
P
P

8,556.00
12,345.72
2,098.77
722.22
15,166.72
122.31

Page 264

hours
hours
Amount

1,015.56
1,472.64

2,488.20
Amount

248.82

248.82
Amount

2,912.00
3,276.00
P
P
P
P
P
P

6,188.00
8,925.02
1,517.25
522.11
10,964.39
120.49

Page 265

hours
hours
Amount

156.24
113.28

269.52
Amount

Amount

500.00
300.00
P
P
P
P
P
P

800.00
1,069.52
181.82
62.57
1,313.91
656.95

Page 266

hours
hours
Amount

1,523.34
5,890.56
1,134.90
P

8,548.80
Amount

854.88

854.88
Amount

46,800.00
18,000.00
93.00
P
P
P
P
P
P

64,800.00
74,203.68
12,614.63
4,340.92
91,159.22
5,064.40

Page 267

hours
hours
Amount

113.28
87.30
P

200.58
Amount

20.06

20.06
Amount

1,320.00
93.00
P
P
P
P
P
P

1,413.00
1,633.64
277.72
95.57
2,006.92
8,362.18

Page 268

hours
hours
Amount

56.64
87.30
P

143.94
Amount

14.39

14.39
Amount

693.33
93.00
P
P
P
P
P
P

786.33
944.67
160.59
55.26
1,160.52
10,879.91

Page 269

hours
hours
Amount

113.28
87.30
P

200.58
Amount

20.06

20.06
Amount

650.00
93.00
P
P
P
P
P
P

743.00
963.64
163.82
56.37
1,183.83
11,838.29

Page 270

hours
hours
Amount

226.56
174.60
P

401.16
Amount

40.12

40.12
Amount

924.00
93.00
P
P
P
P
P
P

1,017.00
1,458.28
247.91
85.31
1,791.49
8,957.46

Page 271

hours
hours
Amount

1,359.36
1,047.60
P

2,406.96
Amount

240.70

240.70
Amount

1,950.00
P
P
P
P
P
P

1,950.00
4,597.66
781.60
268.96
5,648.22
376.55

Page 272

hours
hours
Amount

3,171.84
2,444.40
P

5,616.24
Amount

561.62

561.62
Amount

3,006.00
3,006.00
P
P
P
P
P
P

6,012.00
12,189.86
2,072.28
713.11
14,975.25
415.98

Page 273

hours
hours
Amount

624.96
1,812.48
349.20
P

2,786.64
Amount

278.66

278.66
Amount

1,390.00
4,170.00
4,500.00

P
P
P
P
P
P

10,060.00
13,125.30
2,231.30
767.83
16,124.44
16,124.44

Page 274

hours
hours
Amount

937.44
679.68
1,047.60
P

2,664.72
Amount

266.47

266.47
Amount

1,390.00
4,170.00
9,730.00
6,500.00

P
P
P
P
P
P

21,790.00
24,721.19
4,202.60
1,446.19
30,369.98
30,369.98

Page 275

hours
hours
Amount

1,874.88
1,359.36
2,095.20
P

5,329.44
Amount

532.94

532.94
Amount

2,780.00
8,340.00
16,680.00
13,000.00

P
P
P
P
P
P

40,800.00
46,662.38
7,932.61
2,729.75
57,324.74
28,662.37

Page 276

hours
hours
Amount

468.72
679.68
523.80
P

1,672.20
Amount

167.22

167.22
Amount

660.00
150.00

P
P
P
P
P
P

810.00
2,649.42
450.40
154.99
3,254.81
542.47

Page 277

hours
hours
Amount

2,265.48
6,570.24
2,531.70
P

11,367.42
Amount

1,136.74

1,136.74
Amount

40,600.00

P
P
P
P
P
P

40,600.00
53,104.16
9,027.71
3,106.59
65,238.46
1,124.80

Page 278

hours
hours
Amount

3,515.40
10,195.20
3,928.50
P

17,639.10
Amount

1,763.91

1,763.91
Amount

63,000.00

P
P
P
P
P
P

63,000.00
82,403.01
14,008.51
4,820.58
101,232.10
1,124.80

Page 279

hours
hours
Amount

2,656.08
3,851.52
1,484.10
P

7,991.70
Amount

799.17

799.17
Amount

14,000.00
4,800.00
450.00
2,700.00
3,393.00
750.00
62.00
192.00
P
P
P
P
P
P

26,093.00
34,883.87
5,930.26
2,040.71
42,854.83
42,854.83

Page 280

ITEM OF WORKS IN BUILDING CONSTRUCTION


Item Number
B.4(10)
B.5
B.7
B.9
B.13
401 (1)
403 (4)
403 (5)
404 (1) a
801(1)
803 (1) a
803 (3)
804 (1) b
900(a)
900(b)
900 ( c )
900 ( d )
900 (e)
900 (f)
900 ( g )
902
1001 (1) a
1001 (1) a3
1001 (1) a4
1001 (1) b1
1002 (1) a1
1002 (1) a3
1002 (1) a4
1002 (1) b1
1002 (1) b3
1002 (1) c3
1002 (1) c4
1002 (1) e1
1001 (2) i1
1001 (2) j2
1001 (6) b
1001 (8)
1002 (4) e3
1002 (5) a1
1002 (5) b1
1002 (5) c1

1002 (6) b1
1002 (6) b2
1002 (6) b3
1002 (6) c1
1002 (6) c2
1002 (6) d1
1002 (6) d2
1002 (4) e1
1002 (4) e2
1002(9)
1002(10)
1002(11)
1002(12)
1002(13)
1003(1) a
1003(3)a
1005 (1)a
1006 (1)
1010(1)
1010(1)b
1012 (1) f4
1013(1)
1013(2)a
1013(2) b
1013(2)c
1013(3)
1016(1)a
1018(1)
1018(2)
1021(1)a
1027(1)
1032(1)a
1032(1)b
1032(1)c
1035
1043(2) a
1043(2) b
1044(1)
1100(1) h1
1100(1) h2
1100(7)a1
1100(4)d1
1100(4)d2
1100(7)a2

1100(7)a3
1100(7)b1
1100(7)b2
1100(8)b
1100(14)
1100(15)
1100(22)
1101(1)a2
1101(1)a3
1101(1)a4
1101(1)a5
1101(1)a8
1101(3)
1101(6)
1102(1)a
1102(1)b
1102(1)c
1103(1)a1
1103(1)a3
1103(1)a4
1201 (4)d
1201(4)e
1208 (2) a1
1209(1)

ITEM OF WORKS IN BUILDING CONSTRUCTION


Item Name
Miscellaneous survey and staking
Project Billboard / Signboard
Occupational Safety and Health Program
Mobilization / Demobilization
Additional Geotechnical Investigation
Metal Railing
Structural Steel, furnished, and fabricated - Purlins
Structural Steel, furnished, fabricated, and erected - Truss
Reinforcing Steel
Removal of Actual Structures/Obstruction
Structure Excavation
Foundation Fill (Gravel Bedding)
Embankment (From Borrow)
Reinforced Concrete (Footing)
Reinforced Concrete (Columns)
Reinforced Concrete (Foundation Beams to Ground Floor Level)
Reinforced Concrete (Second Floor Beams to Roof Beams)
Reinforced Concrete (Concrete Slab on grade)
Reinforced Concrete (Concrete Slabs @ Second Floor and Third Floor )
Reinforced Concrete (Concrete Stairs, Ramp and Sunbreaker)
Lean Concrete
Pipe - 50mm diameter PVC
Pipe - 100mm diameter PVC
Pipe - 150mm diameter PVC
Pipe - 150mm diameter Concrete Pipe
Fittings- 63mm diameter PVC 45deg. Elbow
Fittings- 110mm diameter PVC 45deg. Elbow
Fittings- 150mm diameter PVC 45deg. Elbow
Fittings- 63mm diameter PVC 90deg. Elbow
Fittings- 110mm diameter PVC 90deg. Elbow
Fittings- 110mm diameter PVC Cleanout with Plug
Fittings- 150mm diameter PVC Cleanout with Plug
Fittings- 63mm diameter P-Trap
Fittings- PVC 110mm dia. x 63mm dia. (2" x 2") Reducer - Sanitary Tee
Fittings- PVC 110mm dia. x 63mm dia. (4" x 2") Reducer - Sanitary Wye
Catch Basin - CHB
Three Chamber Septic Vault
Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 20mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 25mm PN10
Polyprophylene Random Copolymer (PPR-C) Pipes - 32mm PN10

Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 20mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 25mm PN10
Polyprophylene Random Copolymer (PPR-C) (Elbow, 1/8 Bend (90deg.)- 32mm PN10
Polyprophylene Random Copolymer (PPR-C) Tee -20mm PN10
Polyprophylene Random Copolymer (PPR-C) Tee -25mm PN10
Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -20mm PN10
Polyprophylene Random Copolymer (PPR-C) Female Threaded Tee -25mm PN10
Polyprophylene Random Copolymer (PPR-C) Coupling- 20mm PN10
Polyprophylene Random Copolymer (PPR-C) Coupling- 25mm PN10
Water Closet
Faucet, Plain Bibb, Brass 1/2"
Water Closet Flange
Tissue Holder
Concrete Counter Sink
Ceiling (4.5mm Fiber Cement Board)
Blackboard
Residential Casement
Hollow Steel Doors
Wooden Doors - Frames (Jambs, Sills, Head, Transoms and Mullions)
Wooden Doors - Flush
Glass and Glazzing
Corrugated Metal Roofing - Prepainted Long Span
Fabricated Metal Roofing Accessory -Ridge Roll
Fabricated Metal Roofing Accessory -Flashings
Fabricated Metal Roofing Accessory - Gutters
Roof Ventilators
Waterproofing-Cement Base
Glazed Tiles and Trims
Unglazed Tiles - Vitrified Floor Tile
Cement Floor Finish
Cement Plaster Finish
Painting Works - Masonry and Fiber Cement Painting
Painting Works - Metal Painting
Painting Works - Wood Paint
Furring Channel-Double Furring System
CHB Non Load Bearing Wall - 100mm
CHB Non Load Bearing Wall - 150mm
Forms and Falseworks
PVC Coupling 20mm diameter
PVC Coupling 25mm diameter
PVC Adapter 20mm diameter
PVC Elbow 20mmx90 deg.
PVC Elbow 25mmx90 deg.
PVC Adapter 20mm male diameter

PVC Adapter 25mm male diameter


Polyvinyl Chloride Pipes (PVC)-20mm
Polyvinyl Chloride Pipes (PVC)-25mm
GI Wire #16
Octagonal Junction Box PVC
Utility Boxes PVC
Grounding Rod Copperweld
Electrical Wire - 3.5mm TWG/THHN
Electrical Wire - 5.5mm TWG/THHN
Electrical Wire - 8.0mm TWG/THHN
Electrical Wire - 14 mm TWG/THHN
Electrical Wire - 38 mm TWG/THHN
Tumbler Switch Two-Gang
Duplex Convenience Receptacles
Panelboard Circuit Breaker Type - Main Distribution Panel (MDP)
Panelboard Circuit Breaker Type - LPA Flush Mounted, NEMA 1 Enclosure (Bolt-on Type)
Panelboard Circuit Breaker Type - LPB and LPC Flush Mounted, NEMA 1 Enclosure (Bolt-on Type)
Compact Flourescent Lamp (CFL)
Flourescent Lighting Fixture
Flourescent Lighting Fixture
Valves and Fittings
Floor Drain
Stainless Steel Railings
Fire Alarm System

Unit
l.s.
l.s.
month
l.s.
l.s.
ln.m.
kgs.
kgs.
kgs.
l.s.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
ln.m.
ln.m.
ln.m.
ln.m.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
each
unit
pcs.
pcs.
pcs.
pcs.

Qty
1.00
1.00
6.00
1.00
1.00
192.40
3,844.20
6,998.50
99,301.25
1.00
630.04
33.00
520.21
146.52
27.24
29.37
79.68
36.03
34.86
18.28
20.65
114.00
153.00
42.00
95.60
12.00
12.00
4.00
30.00
24.00
19.00
4.00
19.00
17.00
2.00
8.00
1.00
2.00
12.00
14.00
18.00

pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
set
pcs.
pcs.
pcs.
pc.
sq.m.
sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
sq.m
sq.m
ln.m.
ln.m.
each
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
ln.m.
sq.m.
sq.m.
l.s.
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.

30.00
23.00
37.00
12.00
15.00
22.00
22.00
9.00
2.00
15.00
41.00
15.00
15.00
6.00
716.00
51.84
118.52
47.04
47.04
47.04
5.28
535.68
37.20
28.80
74.40
19.00
55.29
169.92
87.22
899.10
2,843.70
3,192.27
213.36
104.55
1,610.15
337.20
559.60
1.00
416.00
8.00
4.00
52.00
4.00
496.00

16423.56+10054.59
23503.8
4867

pcs.
pcs.
pcs.
kgs.
pcs.
pcs.
length
roll
roll
roll
roll
roll
set
set
set
set
set
sets
sets
sets
pcs.
pcs.
set
l.s.

149.00
208.00
4.00
12.00
124.00
91.00
2.00
18.00
0.24
0.11
0.10
0.20
15.00
36.00
1.00
1.00
2.00
6.00
58.00
90.00
6.00
16.00
2.00
1.00

TIMESPOT SCHEDULE

Name of Project
Location
Type of Materials
Source of Materials
Ave. Hauling Distance

: Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


: Nangalisan, Tuba, Benguet
: Cement
: Baguio City
:
16 kms.
distance
speed
Time of Travel w/o Load:
16 x 60 / 20
=
48
mins.
Time of Travel w/ Load :
16 x 60 / 15
=
64
mins.
Time of Loading
:
Manual
=
60
mins.
Time of Unloading
:
Manual
=
60
mins.
Slack Time
:
=
5
mins.
Cycle Time
=
237
mins.
No. of Trips per day
Vehicle Used / Capacity of Truck
Volume Hauled per day

:
:
:

8*60/ 237
=
2.03
Dumptruck / 200 bags
2 trips x
200 bags

LABOR :

No. of Laborers
Rate per day
No. of Days

:
:
:

5
P317.84
1
P1,589.20

Equipment Used
Rate per day
No. of days

:
:
:

Dumptruck
P4,847.00
1
P4,847.00

RENTAL :

For Cement
Total Cost
Unit Cost
Cost at Source
Manual Hauling
Actual Cost

: P
:
: P
:
:
say P

6,436.20
16.09
245.00 /bag
261.09 /bag
261.00 /bag

trips say =
=

2
400

trip / day
bags

TIMESPOT SCHEDULE

Name of Project
Location
Type of Materials
Source of Materials
Ave. Hauling Distance

: Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


: Nangalisan, Tuba, Benguet
: Sand, Gravel
: Baguio City
23 km.
distance
speed
Time of Travel w/o Load:
23 x 60 / 20
=
69
mins.
Time of Travel w/ Load :
23 x 60 / 15
=
92
mins.
Time of Loading
:
Payloader
=
10
mins.
Time of Unloading
:
Dumptruck
=
2
mins.
Slack Time
:
=
5
mins.
Cycle Time
=
178
mins.
No. of Trips per day
Vehicle Used / Capacity of Truck
Volume Hauled per day

:
:
:

8*60/ 178
=
2.70
Dumptruck / 4.5 cu.m.
3 trips x
4.5 cu.m.

LABOR :

No. of Laborers
Rate per day
No. of Days

:
:
:

Equipment Used
Rate per day
No. of days

:
:
:

RENTAL :

:
:
:
:

SAND
P4,847.00
359.04
910.00
1,269.04
1,269.00 /cu.m.

:
:
:
:

GRAVEL
P4,847.00
359.04
885.00
1,244.04
1,244.00 /cu.m.

FOR AGGREGATES:

Total Cost
Unit Cost
Cost @ Source
Actual Cost
say

Total Cost
Unit Cost
Cost @ Source
Actual Cost
say

Dumptruck
P4,847.00
1
P4,847.00

trips say =

3.0

trip / day

13.5

cu.m.

TIMESPOT SCHEDULE

Name of Project
Location
Type of Materials
Source of Materials
Ave. Hauling Distance

: Construction of Three(3) Storey Nine(9) Classroom-Tuba NHS (Nangalisan)


: Nangalisan, Tuba, Benguet
: RSB, Structural Steel
: Baguio City
:
23 km.
distance
speed
Time of Travel w/o Load:
23 x 60 / 20
=
69
mins.
Time of Travel w/ Load :
23 x 60 / 15
=
92
mins.
Time of Loading
:
Manual
=
30
mins.
Time of Unloading
:
Manual
=
30
mins.
Slack Time
:
=
5
mins.
Cycle Time
=
226
mins.
No. of Trips per day
Vehicle Used / Capacity of Truck
Volume Hauled per day

:
:
:

8*60/ 226
=
2.12
Dumptruck / 5,000 kgs.
2 trips x
5,000 kgs.
RSB

LABOR :

CAPABILITY

No. of Laborers
Rate per day
No. of Days

:
:
:

5
P317.84
1
P1,589.20

Equipment Used
Rate per day
No. of days

:
:
:

Dumptruck
P4,847.00
1
P4,847.00

RENTAL :

Total Cost
Unit Cost
Cost @ Source
Actual Cost

Total Cost
Unit Cost
Cost @ Source
Actual Cost

:
:
###
:
say

RSB
P6,436.20
0.64
38.00 /kg.
38.64
38.60 /kg.

Structural Steel
:
P6,436.20
:
0.64
###
48.00 /kg.
:
48.64
say
48.60 /kg.

trips say =
=

2
10000

trip / day
kgs.

263
250
13

298
302
4

302
250
52

Name of Material

Unit

DepED Price

#REF! #REF!
Php
Php

150.00
850.00

Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php

41.03
50.00
209.00
800.00
850.00
13.00
60.00
354.75
9.50
30.00
31.00
900.00
70.00
50.00
49.00
280.00
70.00
352.50
245.00

#REF!

Php 8,444.00

#REF!

Php 4,222.00

#REF!

Php 6,257.50

#REF!

Php
39.86
Php
39.86
Php
34.34
Php
34.34
Php
107.00
Php 9,300.00
Php
45.00
Php
12.00
Php
67.00
Php
558.00
Php
34.34
Php
560.00

#REF!

Php
Php
Php

365.00
268.00
368.00

Unit

Php
1.25
Php
239.80
Php
132.00
Php
319.00
Php
425.00
Php
513.87
Php
165.00
Php
492.00
Php
470.00
Php
500.00
Php
260.00
Php
50.00
Php
112.50
Php
50.00
Php
15.00
Php
30.00
Php
150.00
Php
40.90
Php
263.80
Php
208.00
Php
97.68
Php 1,055.00
Php
600.00
Php
603.25
Php
37.50

DPWH BFDEO Price

PAY ITEM EQUIPMENT/MANPOWER REQUIREMENT AND PRODUCTION OUTPUT


ITEM NO. DESCRIPTION
100

UNIT

MATERIALS

Clearing and Grubbing


(with Stripping)

ha.

102(a)

Roadway Excavation (Common)

cu.m.

102(b)

Roadway Excavation (Surplus)

cu.m.

103a

Structure Excavation (Soft Soil)

cu.m.

104a

Embankment

cu.m.

105a

Subgrade Preparation
(in common excavation)

sq.m.

200

Aggregate Subbase Course

cu.m.

1.15

201

Aggregate Base Course

cu.m.

1.15

202

Crushed Aggregate Base Course

cu.m.

1.15

300

Aggregate Surface Course

cu.m.

1.15

301

Bituminous Prime Coat

m.t.

1.05

302

Bituminous tack Coat

m.t.

1.05

310a

Bituminous Concrete Surface


Course

sq.m.

310b

Bituminous Concrete Surface


Course
Facto r= 2.335 m.t./cu.m.
6.5% Asphalt Content

sq.m.

311a

Portland Cement Concrete Pavement (Conventional Method) sq.m.


Pavement (Conventional Method)

0.125

0.122

50 mm.
0.00795 MT/sq.m.
0.00488 cu.m./sq.m.
0.0038 cu.m./sq.m.

0.39 kgs.
0.285 liters
0.12 liters

0.45 l.m.
0.1265 cu.m.
0.23 cu.m.
9.5 bags
311b

Portland Cement Concrete


Pavement (Using Concrete
Paver)

sq.m.

404(1)

Reinforcing Steel Bar, Grade 40


(Bridge Structure & Other Major
Structure)

kg.

0.02 kgs.
1.05 kgs.

404(2)

Reinforcing Steel Bar, Grade 40


(Minor Structure)

kg.

0.02 kgs.
1.05 kgs.

Structural Concrete Class "A"

cu.m.

500(1)

Pipe Culverts and Storm Drains


(24") - 610 mm

l.m.

500(3)

Pipe Culverts and Storm Drains


(36") - 910 mm

l.m.

600(1)

Concrete Curb

l.m.

600(2)

Concrete Curb and Gutter


Type A

l.m.

405

603(3a) Metal Guardrail (Metal Beam)


Including Post

l.m.

603(b)

Guardrail (End Piece)

ea.

605(1)

Danger/Warning Signs, (60 cm.


Triangle)

ea.

0.39 kgs.
0.285 liters
0.12 liters
0.45 l.m.
0.1265 cu.m.
0.23 cu.m.
2.19 bags

9.50 bags
0.5 cu.m.
1 cu.m.
45 bd.ft./cu.m.
0.64 pc.
0.94 kg./cu.m.
0.78 kg./cu.m.
1.098 bags
0.061 cu.m.
1 pc.
0.061 cu.m.
1.80 bags
0.10 cu.m.
1 pc.
0.124 cu.m.
0.73 bags
0.004 cu.m.
0.0798 pc.
0.23 pc.
5.00 bd.ft.
1.20 bags
0.065 cu.m.
0.13 cu.m.
0.36 pc.
8.00 bd.ft.
0.136 cu.m.
16.542 kg.
0.678 pc.
24.49 bd.ft.
4.20 l.m.
0.331 kg.
1 ea.

0.48 bags
0.05 cu.m.

0.025 cu.m.
8.00 bd.ft.
3.10 m.
2 kgs.
1 pc.
12 pcs.
0.48 bags
0.05 cu.m.
0.025 cu.m.
8.00 bd.ft.
3.10 m.
2 kgs.
1 pc.
12 pcs.
0.48 bags
0.05 cu.m.
0.025 cu.m.
8.00 bd.ft.
3.10 m.
2 kgs.
1 pc.
12 pcs.
1.32 bags
0.145 cu.m.
0.073 cu.m.
8.00 bd.ft.
3.10 m.
2 kgs.
1 pc.
12 pcs.
1.32 bags
0.145 cu.m.
0.073 cu.m.
8.00 bd.ft.
3.10 m.
2 kgs.
1 pc.
12 pcs.
0.375 gal.

605(2)

Regulatory Signs
(60 cm. Triangle)

ea.

605(2)

Regulatory Signs
(60 cm. Octagon)

ea.

605(3)

Informative Signs
(12" x 24")

ea.

605(4)

Chevron Directional Signs


(18" x 24")

ea.

Pavement Marking

sq.m.

612(1)

Reflectorized Thermoplastic
Pavement Marking (white)

sq.m.

0.325 bags
0.033 bags
0.12 ltr.
0.004 cyl.
0.002 cyl.
0.125 kg.

612(2)

Reflectorized Thermoplastic
Pavement Marking (yellow)

sq.m.

0.325 bags
0.033 bags
0.12 ltr.
0.004 cyl.
0.002 cyl.
0.125 kg.

SPL 1

Project Billboard

pc.

606

32 ft.

42 bd.ft.
1 pc.

MATERIALS REQ.
None

None

None

None

Common Borrow
(w/ shrinkage factor)
None

Subbase Course
(w/ 15% shrinkage factor)
Aggregate Base Course
(w/ 15% shrinkage factor)
Crushed Aggregate Base Course
(w/ 15% shrinkage factor)
Aggregate Surface Course
(w/ 15% shrinkage factor)
MC-70 Cutback Asphalt
(Hot Laid)
Emulsified Asphalt SS-1
MT-Bituminous Concrete Surface
Course (T=50mm)
5% Wastage

thickness
Asphalt Cement
Aggregates (93%)
Mineral Filler (7%)

Reinforcing Steel Bars


Curing Compound
Asphalt Sealant

EQUIPMENT REQUIREMENT
1 Bulldozer (D65A-8-155 HP)
1 Payloader (1.50 cu.m.)
2 Dumptruck (10 cu.m.)
1 Bulldozer (D65A-8-155 HP)
1 Payloader (1.50 cu.m.)
2 Dumptruck (10 cu.m.)
1 Bulldozer (D65A-8-155 HP)
1 Payloader (1.50 cu.m.)
3 Dumptruck (10 cu.m.)
1 Backhoe (0.80 cu.m.)
2 Dumptruck (10 cu.m.)
1 Backhoe (0.80 cu.m.)
Minor Tools (10% of Labor)
1 Motorized Road Grader (140 HP)
1 Vibratory Road Roller (10MT)
0.25 Water Truck (1000 gals.)
1 Motorized Road Grader (140 HP)
1 Vibratory Road Roller (10MT)
0.25 Water Truck (1000 gals.)
1 Grader (140 HP)
1 Vibratory Road Roller (10MT)
0.25 Water Truck (1000 gals.)
1 Grader (140 HP)
1 Vibratory Road Roller (10MT)
0.25 Water Truck (1000 gals.)
1 Grader (140 HP)
1 Vibratory Road Roller (10MT)
0.25 Water Truck (1000 gals.)
1 Grader (140 HP)
1 Vibratory Road Roller (10MT)
0.25 Water Truck (1000 gals.)
1 Asphalt Distributor (5 Tons)
1 Power Broom (20 m. wide)
1 Asphalt Distributor (5 Tons)
1 Power Broom (20 m. wide)
1 Asphalt Paver (80 HP)
1 Pneumatic Roller (10 MT)
1 Tandem Steel Roller (10 MT)
1 Water Truck (1000 gals.)
Minor Tools (10% of Labor)
1 Asphalt Paver (88 HP, 10 ft. wide)
1 Pneumatic Roller (10 MT)
1 Tandem Steel Roller (10 MT)
2 Dumptruck (5 cu.m.)
1 Asphlat Batch Plant (60-80 TPH)
1 Water Truck (1000 gals.)
1 Payloader (1.50 cu.m.)
Minor Tools (10% of Labor)
4 Transit Mixer (5 cu.m. capacity)
2 Concrete Vibrator
1 Batching Plant (30 cu.m. capacity)

LABOR REQUIREMENT
1
2
1
2
1
2

1
3
1
2
1
2
1
2
1
2
1
2
1
2
1
3
1
3
1
4
8

1
6
12

1
4
12

Forms
Riversand
Gravel
Cement
(9.5 x volume of concrete)
Reinforcing Steel Bars
Curing Compound
Asphalt Sealant
Forms
Riversand
Gravel
Cement
#16 Tie Wire (2% of RSB)
RSB, Grade 40

#16 Tie Wire (2% of RSB)


RSB, Grade 40
Cement
Riversand
Gravel
Form Lumber
Plywood 1/2"x4'x8'
CWN (asstd)
#16 Tie Wire
Cement
Riversand
RCPC 24" - 610 mm
Sand Bedding
Cement
Riversand
RCPC 36" - 910 mm
Sand Bedding
Cement
Riversand
Gravel
1/2"x4'x8' Marine Plywood, 4 uses
Form Lumber, 4 uses
Cement
Riversand
Gravel
1/2"x4'x8' Marine Plywood, 4 uses
Form Lumber, 4 uses
Concrete Class "C"
Reinforcing Steel, Grade 40
Marine Plywood, 1/2"x4'x8' 4 uses
Form Lumber, 4 uses
Metal Beam Guardrail
Tie Wire, 2% of RSB
ea. Metal Guardrail End Piece

Cement
Gravel

1 Payloader (1.50 cu.m.)


1 Concrete Screeder
1 Water Truck (1000 gals.)
1 Concrete Saw
0.10 Bar Cutter
1 Batching Plant (50 cu.m./hr.)
1 Concrete Paver
5 Transit Mixer (8 cu.m. capacity)
1 Payloader (1.50 cu.m.)
1 Water Truck (1000 gals.)
1 Concrete Saw
0.10 Concrete Vibrator
0.10 Bar Cutter
0.15 Service Crane (25 Tons)
0.15 Service Truck (10 Tons)
0.50 Bar Cutter
0.50 Bar Bender
0.15 Service Truck (10 Tons)
0.50 Bar Cutter
0.50 Bar Bender
1 One Bagger Mixer
1 Concrete Vibrator
0.10 Water Truck (1000 gals.)

1
4
10

1
2
8
1
2
8
1
4
8

0.50 Backhoe (0.80 cu.m.)


0.50 Plate Compactor (5 HP)
Minor Tools (10% of Labor)

1
2
4

0.50 Backhoe (0.80 cu.m.)


0.50 Plate Compactor (5 HP)
Minor Tools (10% of Labor)

1
2
4

1 Concrete Vibrator
1 One Bagger Mixer
1 Water Truck (500-1000 gals.)
Minor Tools (5% of Labor)

1
4
8

1 Concrete Vibrator
1 One Bagger Mixer
0.05 Water Truck (500-1000 gals.)
Minor Tools (5% of Labor)

1
4
8

1 Concrete Vibrator
1 One Bagger Mixer
1 Water Truck (500-1000 gals.)
1 Cargo Truck (6-8 tons)
Minor Tools (5% of Labor)

1
2
4

1 Cargo Truck
Minor Tools (5% of Labor)

1
1
2
1
1

0.25 Stake Truck


Minor Tools 10% of Labor

Riversand
Form Lumber, good, 4 uses
3" G.I. Pipe
Plate
Sign Face, 3mm thick, Aluminum Sheet
Bolts, 5mm
bags Cement
cu.m Gravel
cu.m. Riversand
bd.ft. Form Lumber, good, 4 uses
3" G.I. Pipe
kgs. Plate
pc. Sign Face, 3mm thick, Aluminum Sheet
pcs. Bolts, 5mm
bags Cement
cu.m Gravel
cu.m. Riversand
bd.ft. Form Lumber, good, 4 uses
3" G.I. Pipe
kgs. Plate
pc. Sign Face, 3mm thick, Aluminum Sheet
pcs. Bolts, 5mm
bags Cement
cu.m Gravel
cu.m. Riversand
bd.ft. Form Lumber, good, 4 uses
3" G.I. Pipe
kgs. Plate
pc. Sign Face, 3mm thick, Aluminum Sheet
pcs. Bolts, 5mm
bags Cement
cu.m Gravel
cu.m. Riversand
bd.ft. Form Lumber, good, 4 uses
3" G.I. Pipe
kgs. Plate
pc. Sign Face, 3mm thick, Aluminum Sheet
pcs. Bolts, 5mm
Pavement Markings (white), 2 coats
Miscellaneous 5% of Above
Thermoplastic Paint (yellow)
Glass Beads
Primer
LPG (50 kg.)
LPG (12 kg.)
Calsumine
Miscellaneous 5% of Above
Thermoplastic Paint (yellow)
Glass Beads
Primer
LPG (50 kg.)
LPG (12 kg.)
Calsumine
Miscellaneous 5% of Above
Tarpaulin (4'x8')

0.25 Stake Truck


Minor Tools 10% of Labor

1
1
2

0.25 Stake Truck


Minor Tools 10% of Labor

1
1
2

0.25 Stake Truck


Minor Tools 10% of Labor

1
1
2

0.25 Stake Truck


Minor Tools 10% of Labor

1
1
2

0.05 Stake Truck


Minor Tools 10% of Labor

1
1
2
1
2
6

1 Stake Truck/Delivery Truck


1 Applicator Machine
1 Kneading Machine
1 Traffic Safety Device
Minor Tools 10% of Labor

1 Stake Truck/Delivery Truck


1 Applicator Machine
1 Kneading Machine
1 Traffic Safety Device
Minor Tools 10% of Labor

1
2
6

Minor Tools 10% of Labor

Good Lumber
Plywood Marine, 1/2"x4'x8'

1
4

LABOR REQUIREMENT

PRODUCTION OUTPUT/HR.

Foreman
Laborer

500 sq.m./hr.

Foreman
Laborer

60 cu.m./hr.

Foreman
Laborer

80 cu.m./hr.

Foreman
Laborer

20 cu.m./hr.

Foreman
Unskilled

50 cu.m./hr.

Foreman
Unskilled

300 sq.m./hr.

Foreman
Unskilled

50 cu.m./hr.

Foreman
Unskilled

50 cu.m./hr.

Foreman
Unskilled

50 cu.m./hr.

Foreman
Unskilled

50 cu.m./hr.

Foreman
Unskilled
Foreman
Unskilled
Foreman
Skilled
Unskilled

6.30 m.t./hr.

171.30 sq.m./hr.
or
20 m.t./hr.

Foreman
Skilled
Unskilled

171.30 sq.m./hr.
or
20 m.t./hr.

Foreman
Skilled
Unskilled

70.00 sq.m./hr.

0.30 m.t./hr.

Foreman
Skilled
Unskilled

174.00 sq.m./hr.

Foreman
Skilled
Unskilled

180.00 kg./hr.

Foreman
Skilled
Unskilled
Foreman
Skilled
Unskilled

180.00 kg./hr.

1.40 cu.m./hr.

Foreman
Mason
Laborer

18.00 l.m./day

Foreman
Mason
Laborer

14.00 l.m./day

Foreman
Skilled
Unskilled

18.40 l.m./hr.

Foreman
Skilled
Unskilled

11.25 l.m./hr.

Foreman
Skilled
Unskilled

4.20 l.m./hr.

Foreman
Skilled
Unskilled
Foreman
Skilled

6.00 ea./hr.

1.00 ea./hr.

Unskilled

Foreman
Skilled
Unskilled

1.00 ea./hr.

Foreman
Skilled
Unskilled

1.00 ea./hr.

Foreman
Skilled
Unskilled

1.00 ea./hr.

Foreman
Skilled
Unskilled

1.00 ea./hr.

Foreman
Skilled
Unskilled
Foreman
Skilled
Unskilled

10.00 sq.m./hr.

Foreman
Skilled
Unskilled

25.00 sq.m./hr.

Foreman

1.00 pc./hr.

25.00 sq.m./hr.

Skilled
Unskilled

UNIT COST DERIVATION FOR CONSTRUCTION MATERIALS FOR


Construction of Daclan E/S Open Gym
UNIT COST DERIVATION OF CEMENT
Source: La Trinidad, Benguet
Distance of Paved Road = 65 kms.
Distance of Unpaved Road = 6 kms.
Toatal Distance from Source to Site = 71 kms.
Volume
=
Volume required =

48.00
48.00 bags

Cycle Time
Ave. Hauling Distance =

90.00 kms.

cu.m.

Distance from Source to Project Site


paved road
unpaved road (National)
unpaved road (Local)
Capacity of Cargo Truck =
No. of Laborers =

=
=
=
=

90.00
72.00
18.00
-

150.00 bags
6.00 Laborers

A) Paved Road
Loaded Trip

Unloaded Trip

72.00 kms x
20
72.00 kms x
30

60
kms/hr
60
kms/hr

min/hr

18.00 kms x
15
18.00 kms x
25

60
kms/hr
60
kms/hr
18.00
60
kms/hr
60
kms/hr

min/hr

min/hr

216.00

mins

144.00

mins

72.00

mins

43.20

0.00

0.00

min.

B) UnPaved Road (National)


Loaded Trip

Unloaded Trip

C) UnPaved Road (Local)


0.00 kms x
5
0.00 kms x
10

min/hr
kms.
min/hr

min.

Loaded Trip

Unloaded Trip

D) Loading Time

150.00 bags X 1min./bag/man-day


6

25.00

min.

E) Unloading Time

150.00 bags X 1min./bag/man-day


6

25.00

min.

6.00

min.

531.20

min.

0.90

trips/day

150.00

bags/trip

0.40

days

0.40
0.40

days
days

=
=

min/hr

F) Slack Time
Total Cycle Time
No. of Trips/day

480

Utilizing 1 Cargo Truck w/ capacity of

=
=

1
6

531.20

150 bags

150.00

48.00
x

Cargo Truck
Laborers

x
x

No. of days Required =

Hauling Cost
Equipment Cost
Labor Cost

0.90

6,248.00
312.24

/day x
/day x

mins

Unit Cost of Hauling


Cost at Source

67.68 /bag
215.00

Unit Cost of CEMENT .


say

282.68
283.00 /bag

UNIT COST DERIVATION FOR CONSTRUCTION MATERIALS FOR


Construction of Road along Ambangeg Junction National Road to Mt. Pulag
UNIT COST DERIVATION OF COARSE AGGREGATES
Source: Gurel, Bokod, Benguet
Distance of Paved Road = 13 kms.
Distance of Unpaved Road = 18 kms.
Toatal Distance from Source to Site = 31 kms.
Volume
=
Volume required =

8.00
9.20 cum.

Cycle Time
Ave. Hauling Distance =

31.00 kms.

cum.

Distance from Source to Project Site


paved road
unpaved road (National)
unpaved road (Local)
Capacity of Dump Truck =

=
=
=
=

31.00
13.00
18.00
-

3.00 cum.

A) Paved Road
Loaded Trip

Unloaded Trip

13.00 kms x
20
13.00 kms x
30

60
kms/hr
60
kms/hr

min/hr

18.00 kms x
15
18.00 kms x
25

60
min/hr
kms/hr
60
min/hr
kms/hr
(31.00) kms.
60
min/hr
kms/hr
60
min/hr
kms/hr

min/hr

39.00

mins

26.00

mins

72.00

mins

43.20

0.00

0.00

min.

6.00

min.

3.00

min.

6.00

min.

195.20

min.

2.46

trips/day

3.00

cum./trip

1.25

days

1.25
1.25

days
days

=
=

B) UnPaved Road (National)


Loaded Trip

Unloaded Trip

C) UnPaved Road (Local)


Loaded Trip

Unloaded Trip

0.00 kms x
5
0.00 kms x
10

D) Loading Time
E) Unloading Time
F) Slack Time
Total Cycle Time
No. of Trips/day

480

Utilizing 1 Dump Truck w/ capacity of

1
1

3 cum.

3.00

9.20
x

Dump Truck
Payloader

x
x

No. of days Required =

Hauling Cost
Equipment Cost

195.20

2.46

5,944.00
7,464.00

/day x
/day x

min.

mins

Unit Cost of Hauling 1,821.74 /cum.


Cost at Source 450.00
Unit Cost of COARSE AGGREGATES ...
say

2,271.74
2,272.00 /cum.

UNIT COST DERIVATION FOR CONSTRUCTION MATERIALS FOR


Construction of Road along Ambangeg Junction National Road to Mt. Pulag
UNIT COST DERIVATION OF FINE AGGREGATES
Source: Gurel, Bokod, Benguet
Distance of Paved Road = 13 kms.
Distance of Unpaved Road = 18 kms.
Toatal Distance from Source to Site = 31 kms.
Volume
=
Volume required =

3.00
3.45 cum.

Cycle Time
Ave. Hauling Distance =

31.00 kms.

cum.

Distance from Source to Project Site


paved road
unpaved road (National)
unpaved road (Local)
Capacity of Dump Truck =

=
=
=
=

31.00
13.00
18.00
-

3.00 cum.

A) Paved Road
Loaded Trip

Unloaded Trip

13.00 kms x
20
13.00 kms x
30

60
kms/hr
60
kms/hr

min/hr

18.00 kms x
15
18.00 kms x
25

60
min/hr
kms/hr
60
min/hr
kms/hr
(31.00) kms.
60
min/hr
kms/hr
60
min/hr
kms/hr

min/hr

39.00

mins

26.00

mins

72.00

mins

43.20

0.00

0.00

min.

6.00

min.

3.00

min.

6.00

min.

195.20

min.

2.46

trips/day

3.00

cum./trip

0.47

days

0.47
0.47

days
days

=
=

B) UnPaved Road (National)


Loaded Trip

Unloaded Trip

C) UnPaved Road (Local)


Loaded Trip

Unloaded Trip

0.00 kms x
5
0.00 kms x
10

D) Loading Time
E) Unloading Time
F) Slack Time
Total Cycle Time
No. of Trips/day

480

Utilizing 1 Dump Truck w/ capacity of

1
1

3 cum.

3.00

3.45
x

Dump Truck
Payloader

x
x

No. of days Required =

Hauling Cost
Equipment Cost

195.20

2.46

5,944.00
7,464.00

/day x
/day x

min.

mins

Unit Cost of Hauling 1,826.60 /cum.


Cost at Source 400.00
Unit Cost of FINE AGGREGATES ...
say

2,226.60
2,227.00 /cum.

UNIT COST DERIVATION FOR CONSTRUCTION MATERIALS FOR


Construction of Road along Ambangeg Junction National Road to Mt. Pulag
UNIT COST DERIVATION OF ABC
Source: Gurel, Bokod, Benguet
Distance of Paved Road = 13 kms.
Distance of Unpaved Road = 18 kms.
Toatal Distance from Source to Site = 31 kms.
Volume
=
Volume required =

3.35
3.85 cum.

Cycle Time
Ave. Hauling Distance =

31.00 kms.

cum.

Distance from Source to Project Site


paved road
unpaved road (National)
unpaved road (Local)
Capacity of Dump Truck =

=
=
=
=

31.00
13.00
18.00
-

3.00 cum.

A) Paved Road
Loaded Trip

Unloaded Trip

13.00 kms x
20
13.00 kms x
30

60
kms/hr
60
kms/hr

min/hr

18.00 kms x
15
18.00 kms x
25

60
min/hr
kms/hr
60
min/hr
kms/hr
(31.00) kms.
60
min/hr
kms/hr
60
min/hr
kms/hr

min/hr

39.00

mins

26.00

mins

72.00

mins

43.20

0.00

0.00

min.

6.00

min.

3.00

min.

6.00

min.

195.20

min.

B) UnPaved Road (National)


Loaded Trip

Unloaded Trip

C) UnPaved Road (Local)


Loaded Trip

Unloaded Trip

D) Loading Time
E) Unloading Time
F) Slack Time
Total Cycle Time

0.00 kms x
5
0.00 kms x
10

min.

mins

No. of Trips/day

480

Utilizing 1 Dump Truck w/ capacity of

1
1

3 cum.

3.00

3.85
x

Dump Truck
Payloader

x
x

No. of days Required =

Hauling Cost
Equipment Cost

195.20

2.46

5,944.00
7,464.00

/day x
/day x

2.46

trips/day

3.00

cum./trip

0.52

days

0.52
0.52

days
days

=
=

Unit Cost of Hauling 1,809.78 /cum.


Cost at Source 190.00
Unit Cost of ABC ....
say

1,999.78
2,000.00 /cum.

trips/day
bags/trip

2,499.20
749.38
3,248.58

trips/day
cum./trip

7,430.00
9,330.00
16,760.00
/cum.

/cum.

trips/day
cum./trip

2,793.68
3,508.08

6,301.76
/cum.

/cum.

trips/day
cum./trip

3,090.88
3,881.28
6,972.16
/cum.

/cum.

Tuba NHS (Nangalisan)


Hauling Cost
509,875.15

Soil Testing
150,000.00

Building Cost
14,971,327.92

Total
15,631,203.07

5.25
5.65
29.6625

4
7.06
28.24

Вам также может понравиться