Академический Документы
Профессиональный Документы
Культура Документы
1.0
GENERAL
The following data shall be considered for the design of ash handling system:
1.1
Hourly worst coal firing rate at 100 % SGMCR condition per unit for worst coal shall be
400 T.
1.2
Ash content in worst coal considered for design shall be 34% considering that washed
coal will be available when domestic coal linkage is obtained.
1.3
: 90 %
1.4
1.5
Scraper conveyor system shall be provided for bottom ash removal from bottom ash
hopper. Fly ash removal system from the various fly ash hoppers shall be two stage
pneumatic conveying system.
1.6
Fly ash conveying and bottom ash shall be in dry form in view of the present
environment regulations. Provision of disposal in dry form and lean slurry form shall be
provided for bottom ash. Provision of disposal in dry form and high concentration slurry
form shall be provided for fly ash.
1.7
The water required for slurry formation shall be met from the outlet of the Central
Monitoring basin of the Effluent Treatment Plant. However, service water shall be used
for fly ash dust conditioners, jacket cooling of air compressors, etc.
2.0
45
pressure pneumatic system from the fly ash hoppers of the steam generator unit upto
89
ash storage silo at a rate of 125 TPH in continuous mode and at rate of 165 TPH in
emergency mode, i.e when ash collected in eight (8) hours in various hoppers due to
non availability of ash handling system shall be cleared in six (6) hours time after the ash
handling system is restored. The number of cycles of operation in continuous mode shall
be 20 cycles per hour and in emergency mode 30 cycles per hour. Bottom ash from the
bottom ash silo shall be disposed off either in dry form or in lean concentration slurry
form in about 4 hours in a shift of 8 hours. Fly ash from the fly ash silos shall be
disposed off either in dry form or in high concentration slurry form in about 4 hours in a
shift of 8 hours.
3.0
SYSTEM DESCRIPTION
3.1
The ash handling system shall include complete bottom ash (BA) evacuation system, fly
ash (FA) evacuation system, fly ash storage silos, and BA and FA disposal systems upto
the ash pond. The ash handling system shall be as per the system description and flow
diagrams enclosed.
Ash formed due to combustion of coal in the pulverised fuel steam generator (SG) shall
be collected as bottom ash in the bottom ash hopper and as fly ash in the fly ash
hoppers. The fly ash shall be collected in the economiser hoppers, air pre-heater
hoppers and electrostatic precipitator (ESP) hoppers provided along the flue gas path.
3.1.1
3.1.1.1
3.1.1.2
The bottom ash discharged onto the SCC in the water trough will be quenched and fed
to single / double roll type heavy duty clinker grinders provided at the head end of SCC.
In the clinker grinders, the bottom ash will be crushed to (-) 25 mm size.
90
3.1.1.3
The crushed bottom ash from the clinker grinders will be conveyed to the bottom ash silo
by belt conveyors. This system will be a continuous type of system.
3.1.1.4
The BAH gates shall be closed during the maintenance of SCC. Two (2) (1 working + 1
standby) SCCs shall be provided with long travel wheels and associated electro mechanical drives for shifting during maintenance. Long travel rails shall be provided for
the purpose.
Disposal of bottom ash from silo
3.1.1.5
There shall be one (1) No. BA silo with storage capacity of 1000 T which shall store
together BA generated in about 12 hours of operation for the three Units. Provision for
both truck disposal and lean slurry disposal system by will be made below the BA silo.
One (1) outlet below the silo for open truck unloading with rotary feeder & ash
conditioner, one (1) for closed truck unloading with rotary feeder & telescopic chute,
three (3) outlets for lean slurry disposal system and one (1) outlet for future shall be
provided. Provision of simultaneous unloading from two trucks shall be made.
When bottom ash has to be disposed off in lean slurry form from the designated outlets
below the bottom ash silo, bottom ash shall be discharged through three (3) (2 working +
1 standby) rotary feeders each of 100 TPH capacity and fed to three (3) (2 working + 1
standby) jet pumps each of 100 TPH capacity. The slurry from the jet pumps shall be
conveyed to a slurry sump from where it shall be pumped to ash disposal area by
horizontal centrifugal type slurry pumps. The capacity of the slurry pumps shall be 1000
cum/hr. There shall be two sets of slurry pumps (one (1) working + one (1) standby). The
total time required for clearing the silo shall be 4 hours in each shift of 8 hours. In the
balance four hours, flushing of lines, routine maintenance, etc. shall be carried out.
3.1.2
3.1.2.1 The fly ash handling system shall be designed to collect fly ash in dry form in silo using
two stage pressure type dense phase pneumatic conveying system.
FA from ESP hoppers, APH hoppers and Economiser hoppers of each unit shall be
conveyed upto Intermediate Surge Hopper (ISH) by first stage pressure type dense
91
phase pneumatic conveying system and from ISH upto the fly ash silos by second stage
pressure type dense phase pneumatic conveying system.
The removal of fly ash from any particular hopper shall be initiated whenever the level in
the hopper reaches predetermined level and this shall continue cycle after cycle till the
level in the hopper reaches low level. Therefore, the removal and transfer of the fly ash
to the intermediate surge hopper shall be done in cyclic manner on a continuous basis.
Generally, the fly ash conveying system shall operate continuously but with time gaps
between cycles. The fly ash removal system shall be designed on a continuous basis
with 20 cycles of operation per hour and during emergency with 30 cycles of operation
per hour. The level probe shall be provided in each hopper in such a way that the ash
collected in the hopper shall be equal to the volume of the ash transmitter vessel. There
shall be one (1) manually operated isolation valve (knife gate type) below each fly ash
hopper which shall be used during maintenance of the ash transmitter vessel.
Disposal of fly ash from silo
3.1.2.2 Dry fly ash from the air pre-heater, economiser and ESP hoppers shall be collected in
the FA storage silos. The fly ash conveying air shall be vented to the atmosphere
through vent filter to mitigate the environmental pollution. Four (4) fly ash silos each of
1500 T capacity shall be provided which shall store together FA generated in about 16
hours of operation for the three Units. One (1) outlet for open truck unloading with rotary
feeder & ash conditioner, one (1) for closed truck unloading with rotary feeder &
telescopic chute, three (3) outlets for high concentration slurry disposal system and one
(1) outlet for future shall be provided below each silo.
Whenever fly ash has to be evacuated by high concentration slurry disposal system into
the disposal area, four (4) Nos. (3 working + 1 standby, each of capacity 125 TPH) of
weighing cum controlled feeding systems and ash conditioners below designated outlets
of each fly ash silo shall feed respective belt conveyors which shall in turn feed
respective mixing tanks located near the silos. The quantity of water depends upon the
rheology of the slurry to be achieved. The resultant high concentration slurry from the
mixing tanks shall be led to four (4) Nos. (three, one for each Unit + one common
92
standby) of high concentration slurry disposal pumps each of 450 cum/hr. These pumps
in turn pump high concentration slurry into the designated slurry disposal area.
4.0
4.1
Operation of complete ash evacuation and conveying upto storage silos (bottom ash as
well as fly ash) shall be controlled from the control panel (PLC) located in the control
room for control / sequential operation and monitoring.
4.2
The Bottom and Fly ash handling system operations such as operation of scraper
conveyors, belt conveyors, transmitters, water pumps, etc. can be operated from the
CRT keyboard. However local sump pumps, silo unloading into open or container trucks,
etc. shall be operated locally.
4.3
The silo unloading of both bottom ash and fly ash into trucks shall be controlled from
local control panels located on the operating floors of respective silos. This panel shall
be a conventional relay based panel. The slurry disposal control system also shall be
PLC based system which shall be from the main control system. Ash water recovery
system shall have its own local control system located near the ash pond.
4.4
The Bottom, Fly ash handling systems and the slurry disposal system shall be controlled
from one common PLC control system with CRT and keyboard. This PLC system is
common to bottom and fly ash handling system of both the units. This panel shall be
located in the control room.
4.5
The compressed air system also shall be controlled from same PLC control system
which is located in the control room.
4.6
The bottom and fly ash shall be evacuated from the respective hoppers and transported
to the silos (Bottom and fly ash) either in auto mode or in manual mode. In case of fly
ash handling systems, in auto mode, the operation shall be either in timer mode or in
level probe mode. However normal operation is in level probe mode. In manual mode,
the operation is hopper by hopper selectively. The system operation / initiation is by the
93
level probes provided either in the respective hoppers or in the vessel below the
respective hoppers.
4.7
Local push button stations with start/stop push buttons shall be provided near the drives
of all equipment to enable the local start/stop of the equipment or open/close of valves in
the de-interlock mode during testing and maintenance.
4.8
Although above local operation of various systems / equipment are envisaged as above,
status indications of various equipment / systems will be provided on the main AHS
control system which is the main control system for bottom and fly ash handling system
and also in the control system CRT in the Unit Control Room.
5.0
MAJOR EQUIPMENT
5.1
BA HOPPER
The BA hopper shall have a capacity to store 4 hours of bottom ash generation. It shall
be made of MS welded construction having external supports. A seal trough shall be
provided around the top periphery of the BA hopper for furnace sealing and to prevent
ingress of air into the furnace. The hopper shall be lined with monolithic refractory.
5.2
5.3
CLINKER GRINDERS
Two (one working and one standby) single / double roll type clinker grinder housed in
steel enclosure with suitable liners shall be provided at the discharge end of scraper
chain conveyor. The grinders shall crush the ash clinkers to (-) 25mm size. Capacity of
clinker grinder shall be 45 TPH.
5.4
BELT CONVEYORS
Belt conveyors shall have Nylon-Nylon belts of 650mm width and a speed of 0.7 m/s.
The conveyors shall be provided with fully enclosed galleries to prevent dust nuisance
with 750 mm wide walkways on either side of the conveyors. The conveyors shall be
single stream considering the high reliability of belt conveyors. The conveyors shall be
94
provided with all standard accessories such as sprung blade and torsion arm type
external belt scrapers, internal belt scrapers, brakes, hold backs, etc.
5.5
5.6
JUNCTION TOWERS
Junction towers shall be of steel construction with concrete floors and side cladding of
either metal or brick work with GI roof and side cladding.
5.7
5.8
95
5.9
5.10
5.11
Retractable Chute
There shall be one retractable chute fitted with a limit switch for feeding fly ash / bottom
ash from fly ash / bottom ash silos to closed container trucks. There shall be one
retractable chute under each silo.
5.12
Rotary Feeder
Rotary feeder (air lock feeders) below bottom ash silo for slurry disposal will be provided
with a capacity of 100 TPH each and that provided for open / closed truck disposal will
be provided with a capacity of 200 TPH each. Rotary feeder (air lock feeders) below fly
ash silo for open / closed truck disposal will be provided with a capacity of 250 TPH
each. Rotary feeder mounted on outlet for feeding fly / bottom ash to open trucks feeds
fly / bottom ash to dust conditioner. The rotary feeder mounted on the outlet for
unloading fly / bottom ash into container trucks feeds fly / bottom ash to a retractable
chute which in turn unloads fly ash into container trucks.
5.13
96
with one standby shall be provided. The material of construction of the casing and
impeller shall be Alloy CI conforming to IS 4771 and shaft shall be of SS 316.
5.14
Bottom ash slurry disposal pipes, bends and fittings and valves
The bottom ash slurry disposal pipes shall be of MS ERW pipes with a thickness of
9.52mm. The bends and fittings shall be of Ni-Cr alloy cast iron having a hardness of
500 BHN.
Slurry line valves will be of knife gate or taper plug type. The knife gate valves will be bidirectional type to achieve tight shut-off.
5.15
5.16
HP water pumps
Three (3) Nos. of horizontal centrifugal high pressure (HP) water pumps (two operating +
one standby) shall be provided which shall take suction from the ash water tank in the
slurry pump house cum compressor room cum control room. HP water pumps shall
supply water to the jet pump/feeder ejector below the bottom ash silo and other bottom
ash requirements such as flushing of nozzles in BAH, inspection window cleaning, etc.
5.17
97
5.18
LP water pumps
Three (3) Nos. of horizontal centrifugal low pressure (LP) water pumps (two operating +
one standby) shall be provided which shall take suction from the ash water tank in the
Slurry pump house cum compressor room cum control room. LP water pumps shall
supply water to the agitation tank, ash mixer, for scraper conveyor cooling water make
up and bottom ash hopper requirements.
5.19
5.20
HCSD Pumps
Ash slurry in the agitation tank will be disposed to the ash disposal area by means of
HCSD pumps and transport piping. The pumps will be of non-clog, horizontal,
reciprocating and single stage type. Considering the distance of the disposal area
identified, four (4) (three for each Unit + one common standby) Nos. of high
concentration slurry disposal pumps each of 450 cum/hr will be required to pump the ash
slurry to the farthest point in the disposal area. Material of construction of the
components of the pumps will be selected so as to minimise the wear. Further, since fly
ash and bottom ash are not mixed and only fly ash is being disposed off by HCSD
system, the water requirement shall be marginally higher. However, the slurry
concentration shall be ascertained by the vendors after necessary rheology studies.
5.21
98
5.22
5.23
5.24
For fly ash conveying, MS black ERW heavy duty pipes as per IS 1239. Bends shall be
of alloy cast iron having a hardness of 500 BHN.
The fly ash hopper isolation valves which handle ash shall be of knife gate type with
plate made of stainless steel conforming to SS 304 stellited to minimum 1 mm thickness.
Body and seat shall be made of alloy cast iron with minimum hardness being 350 BHN.
The other ash handling valves shall be of proprietary nature and shall have
corresponding materials of construction. However it shall be specified that the minimum
life of the valves should not be less than one (1) year.
99
5.25
6.0
7.0
100
a.
: 400 TPH.
b.
Ash content
: 34%
c.
: 90%
d.
: 20%
e.
: 20m
f.
Height of ash bund considered for lean slurry : 3.5 m initial height.
disposal of bottom ash
Subsequent increase of
3.5m in two phases and
4.5m in last phase up to
ultimate height of 15 m.
g.
: About 35%
h.
j.
: 27 T
k.
: 125 T
l.
8.0
60 hectares
: 23 hectares
37 hectares
:
ASH UTILISATION
The environmental regulations are becoming stringent on the ash disposal aspect. The
present draft notification stipulates 100% ash utilization by the end of 3 rd year of
operation. The fly ash shall be collected in silos and most of it shall be utilized /
101
marketed in dry form. The fly ash which cannot be utilised / marketed shall be disposed
to the ash dump area in slurry form.
The fly ash generated in thermal power stations has commercial value because of its
usage in cement and construction industries. Fly ash generated from the plant shall be
commercially utilised in one or more of the following industries to the extent possible:
8.1
(a)
Cement industry
(b)
Brick industry
(c)
(d)
CEMENT INDUSTRY
Fly ash is used in the production of Pozzolona cement by intergrinding Portland cement
clinkers and fly ash or by blending intimately and uniformly Portland cement and fly ash.
Indian Standard specifications limit the Pozzolona (fly ash or similar material) component
up to 30% by weight whereas in other countries it varies from 15 to 50%.
The advantages of fly ash in the manufacture of Portland Pozzolona Cement (PPC) as
compared to other Pozzolonic materials are two-fold.
(d)
(e)
Cement retains its natural and accepted grey colour instead of becoming mudred in case bricks / tiles are used as Pozzolonic materials.
8.2
BRICK INDUSTRY
Fly ash produced in modern thermal power stations can be used in making bricks. The
Cement Association of India has conducted research and experiments for making hollow
bricks using fly ash. The Central Building Research Institute (CBRI), Roorkee has also
conducted experiments in making bricks by using fly ash as an admixture with black
cotton soil. In this project, bricks of minimum 105 kg/sq.cm strength were produced by
CBRI.
It is reported from Kolaghat thermal station that bricks are being manufactured by local
brick manufacturers with 70% fly ash and 30% clay which give higher strength than
conventional bricks.
102
8.3
8.4
ROADS / PAVING
It has been reported from the laboratory tests conducted by the Cement Association of
India that fly ash with other ingredients can be used for paving roads and airport
runways. Fly ash mixed with sand and hydrated lime is used as a base course of asphalt
pavement. The breaking strength of such a pavement is calculated to be as high as 68
kg/sq.cm (1000 psi). As a result of a series of experiments, the mixtures of ingredients
added in the following recommended proportions gave a good paving material with
adequate strength and reasonable setting time.
Ingredients
Fly ash
12 14
Lime
2.8 3.6
Portland Cement
0.7 0.9
Sand
80 84.5
The above mixture developed a strength from 54 to 95 kg/sq.cm (800-1400 psi) in about
90 days at a temperature of 18 deg. C to 21 deg. C. Further, the experiments have
shown that 30% of crushed stones (instead of sand) established a strength of 102 136
103
kg/sq.cm (1500-2000 psi). The total cost of manufacturing the paving mixture comes to
about one and half that of ordinary road stone which has much less strength and to less
than one third the cost of lime concrete which has good strength. Even the extra strength
obtained by using 30% crushed stones as a substitute for sand, the cost is not expected
to exceed that of conventional materials
8.5
104