post construction phases and continuing still in the operation period. The constructions of almost all
the major components of the project have met with stability challenges. The machine and transformer
caverns are still experiencing two main problems: i) the failure of rock bolts which fly out of caverns
walls and, ii) convergence of walls, since the construction period and are continuing during operational
phase too. These are serious problematic issues, creating hazardous situations and uncertain long
term stability may affect the operation of the plant. In this thesis, efforts have been made to study the
problems encountering in the machine hall of Tala Hydroelectric Project and finally determined the
main causes of the resulting instabilities of the case. After having addressed the problems in Tala, this
work started on reviewing the case based mainly on geology, rock mass quality, in-situ stresses,
geometry, and excavation & supports. Chukha Hydroelectric Project lying 2 km upstream of Intake for
Tala, along the same river basin (1974 1988), on the other hand, has not faced such problems
during operation period. A review study is conducted in a similar manner on Chukha project as well.
The works throughout are focused on machine halls of the two projects. Qualitative studies of the
machine halls of two projects have been carried out to compare and identify the most likely aspects of
stability problems. The work involves theoretical study and application of engineering geology and
rock engineering in reviewing of the cases. The engineering geological investigations of respective
phases have been reviewed and through evaluation of deviations, the causes of the instabilities are
ascertained. It is found that Tala Cavern is located in closer proximity to MCT and narrower valley than
Chukha powerhouse, which signifies high stress regime. Weak rocks such as phyllite & quartzitic
phyllite dominate the rock mass in Tala, while Chukha cavern constitutes better grade of metamorphic
rock like biotite gneisses. The joints are normally clean in Chukha but infilling materials prevail in Tala
with puckered and folded foliations. All the rock mass properties and classifications reveal weaker
rock mass quality in Tala than the later project. Based on the above studies, this thesis presents a
discussion on the probable reasons of stability problems being faced in Tala cavern. It is evaluated
that the powerhouse is constructed in a high stress regime influenced due to tectonic activity,
topography and overburden. Besides, the rock mass quality is found to be poor and deteriorated
further during excavation. The failures of rock bolts in sections are mainly due to excessive
overburden loads and existing weak rock mass conditions in folds enabling development of stresses
under compression and tension in varying depth. The creeping nature of the rock mass prevail due to
high horizontal stress, time-dependent behavior of highly jointed weak rock mass, reduced shear
strength and unfavorable orientation of the cavern with respect to discontinuities. Geometry for shape
and dimensions play important roles for the stability of the underground caverns. Beyond qualitative
analysis, Examine2D program has been used to investigate the influence of geometry and induced
stresses due to excavation. The analysis results indicated higher relative stress regime situation and
more relative deformations for Tala compared to Chukha, which has quite favorable stress regime with
negligible elastic deformation along the walls. The zones of influence of induced stresses and failure
trajectories expand in larger area and in fact they intersect between the two caverns of Tala. At the
end, some recommendations are put forth which may be used for successful construction and
implementation of future projects under similar conditions in the vicinity of tectonic thrusts. This study
has found that fixing location of underground cavity must be studied and options to be explored
through qualitative judgment of investigations. The results of the investigation phases show great
variations. These make the input parameters for any analysis unreliable and uncertain to a greater
extent. An attempt to improve the quality judgment through involvement of experienced and right
professional is mandatory for any future project. The designs pertaining to shapes and dimensioning
under such conditions need serious attention. Most importantly, proper sequential and careful
excavation must be incorporated at all times in such geology. Implementation of any future project
must be documented properly and experiences from such cases may be made available to achieve
successful tunneling in the Himalayan region.
b. Cast-inplace bolts
Cast-inplace anchor bolts are placed before setting of concrete. This ancor bolt may be
bolts, threaded rods having nuts or hooked bars.
Hooked bars:
Among these anchor bolts the hooked bars are suitable for base plates that are loaded
axially.
Bolts:
Bolts can be used either to anchor base plate subjected to moments or to anchor axially
loaded base plate.
Threaded rods:
Both axially loaded base plates and base plates subjected to moments and be anchored
by threaded rods with nuts. This system of anchoring are required when the size and
length obtained from design calculation for the specific design exceed those of standard
size bolts. This threaded nut system fails when stress in the rod is reached to tensile
capacities.