FOR
GSM/CDMA/
WIMAX
(CM SECTION)
BONGAIGAON
SSA
PLANNING
FOR NEW
PROPOSED
BTS (2G)
OF
BONGAIGAON
SSA
AT A GLANCE
-------- BTS proposed by considering NH coverage,
Railway Coverage, SH coverage with populated
Village having commercially strength.
(Detail in sheet)
---------- Proposed 2G BTS = 165 Nos.
(Details & summary in sheet)
---------- Media details with requirement of Battery &
Power plant available in sheet.
---------- District wise Map available with marking of
Proposed & existing 2G BTS.
AT A GLANCE
-------- 3G BTS proposed by considering NH coverage,
Railway Coverage, SH coverage & Urban, SemiUrban area.
(Detail in sheet)
--------
VISITING DOCUMENTS
(CM SECTION- BONGAIGAON SSA)
INCLUDUNG GSM/CDMA/WIMAX)
VISITED BY Honble
CGMT, Assam Circle & GM
(CM), CIRCLE OFFICE
GUWAHATI
SUMMARY OF CM SECTION
EQUIPMENTS OF CM SECTION
Sl. No
Total nos of
BSC
Total Nos
of RNCs
4 Nos
2 Nos.
Total
Nos of
2G BTS
224
Nos.
Total
Nos. of
Media
gateway
1
MPBN
Router
1+1
Total
nos. of
3G
BTS
129
Nos.
Total
Nos. of
CDMA
BSC
1 No.
Total
nos of
CDMA
BTS
41
Nos.
Total
Nos. of
WiMax
BTS
58 Nos.
Name of BSC
Total nos. of
Loaded BTS
Name RNCs
Total
nos.
Name of
CDMA
Total nos
Loaded
Total
Nos of
Loaded
BTSs
1
2
3
4
Bongaigaon
Barpeta
Road
Nalbari
Dhubri
86
Bongaigaon
Barpeta |
Road
89
64
BSC
Barpeta
Road
CDMA
BTS
41
Towers
224+15=
239
65
42
7
DET
SDE
JTO
TTA
=
=
=
=
One
Two
One
Two
4.
Gobardana
(i) BTS is avl. at site. Not installed due to water logging at site.
( ii) Media is not tested
(iii) Battery & P/P is not avl. at site.
(iv) Electricity is available.
(v) DG is not tested.
5.
Jaleswar
(i) BTS shifting & installation will be done before 20th August.
(ii) Media is not tested
(iii) Battery & P/P is not avl. at site.
(iv) Electricity is not available.
(v) DG is not tested.
(ii)
3.NEP Data:- Tender part completed. Agreement with is in progress. Then work order will be
issued. This will be done within this week.
4.IP fication of Node-Bs:- All Node-Bs have already been ip-fied. But, three Node-Bs are
integrated & tested in IPs. Due to non-availibilty of ETMFX cards, 3nos. Node-Bs areworking
in ATM. So, 3 nos. of ETMFX card are reuired for the same.
6. Addition of more E1s in data potential 2G BTS:- Five nos have already been done. Work is
progress for further. It is delayed due to allotment of PCMs from ETR section.
7. Conduction of inter SSA wise Drive test;8. AT of phase-VII BTS:- Installer i.e M/s ZTE is not coming to site for carrying out AT of 2G &
Node-Bs.
9. Tender work for redeployment work of BTS:- E-tender preparation is completed which will be
floated during this week.
IP SITE POSSESSION
BGN/CMTS/IP-Sites/15-16
WELCOME
VISIT of Honble
GM(CM), GM (CFA/Mktg.) &
DGM (CSC) Assam Circle.
SUMMARY OF CM SECTION
EQUIPMENTS OF CM SECTION
Sl. No
Total nos of
BSC
Total Nos
of RNCs
4 Nos
2 Nos.
Total
Nos of
2G BTS
229Nos.
Total
Nos. of
Media
gateway
1
MPBN
Router
1+1
Total
nos. of
3G
BTS
131
Nos.
Total
Nos. of
CDMA
BSC
1 No.
Total
nos of
CDMA
BTS
41
Nos.
Total
Nos. of
WiMax
BTS
58 Nos.
1
2
3
4
Name of BSC
Total nos. of
Loaded BTS
Bongaigaon
87
Barpeta
Road
Nalbari
Dhubri
Name RNCs
Bongaigaon
Barpeta |
Road
90
Total
nos.
Loaded
BTSs
65
Name of
CDMA
BSC
Barpeta
Road
Total nos
Total
Loaded
Nos of
CDMA
Towers
BTS
41
224+15=
239
66
44
8
DET
SDE
JTO
TTA
=
=
=
=
One
Two
One
Two
Cleanness of BTS.
Inspection of BTS
Target given to field SDEs for conversion of CAT-B
to CAT-A & CAT-C to CAT-B
Attending the hardware fault of BTS
Re-location of Node-Bs ( From low traffic site)
(Already two completed)
Completion/uploaded of all data in NEP Portal
Shifiting of BTS from closing USO sites
( 23 Completed out of 38 sites)
MAINTENACE ISSUES
Allotment of ETMFX Cards for IP (3 Nos.)
Addition of AMC of 40 sites
(For Both M/s ZTE & SSA)
Allotment of Power Plant (which are not supplied
since last 5years).
Requirement of at least 2 nos. of Trolly mounted
DG
Requirement of at least 2 nos. of Transformer (Low
Capacity) for keeping reserve.
Allotment of Drive test tools (mainly 3G) for RF
optimization.
Allotment of Transmission equipment( STM1CPE(DC Types)
Provisioning of DG in only ASEB sites( 14 sites)
Deletion of WEB docket before March-2014