Вы находитесь на странице: 1из 36

Beijing Blast Furnace Seminar March 11, 2009

Business Confidential

Beijing Blast Furnace Seminar March 11, 2009

Lecture Will Cover Two Topics


Drying Out the New Lining of a Blast
Furnace
Starting Up the New Furnace

Business Confidential

Drying Out the Blast Furnace Lining

Why to Do It
How to Do It

Business Confidential

Typical Blast Furnace Lining

Material

MT

Castable
Graphite
Carbon
Ram
Cement
Firebrick

115
72
757
25
66
664

TOTAL

~ 1700

Business Confidential

Drying Out the Blast Furnace Lining

Some People Suggest Not To Do It !


Not Up to Operating Temperature
Drying Only Affects About 50% of the
Material Volume
Takes a Lot of Time

Business Confidential

Drying Out the Blast Furnace Lining

Some People Suggest Not To Do It !


Not Up to Operating Temperature
Drying Only Affects About 50% of the
Material Volume
Takes a Lot of Time

Do Not Believe Them !


Business Confidential

Typical Blast Furnace Lining

Calculations Have Shown That


Between 150 and 250 MT of
Water and Volatiles Are
Contained in The Lining Materials

Business Confidential

Drying Out the Blast Furnace Lining

Not Removing the Water (and Volatiles)


Can and Does Lead Directly to

Gas Tracking
Overheating
Explosive Spalling
and
Sometime Liquid Breakout

Business Confidential

Options For Drying the Blast Furnace Lining

There Are Several Options


Hot Gas Generators on Casthouse
Contractor Company
The Stove System

The Stove System Is Preferred


Helps in Heating Stoves
Tests Operation of Stove System
More Even Heating of Entire Lining

Business Confidential

Procedure For Drying the Blast Furnace Lining

Bleeders CLOSED
Gas System Isolated After Dustcatcher
Furnace and Top Closed
Special Technique for Stove Changes
Warm Water on Staves, Cooling Plates,
Tuyeres, Etc.

Business Confidential

10

Drying Out the Blast Furnace Lining


Bleeders
Uptake

Downcomer

Dustcatcher
Measure Humidity
Hot Blast

Business Confidential

11

Procedure For Drying the Blast Furnace Lining


Blow Ambient Air Temperature for 24 Hrs

2000 m IV, use 30,000 m/Hr


4000 m IV, use 60,000 m/Hr

After 24 Hrs, Increase Temp +20 C / Hour Up to 350 C


Hold at 350 C for 24 Hrs
Then Increase to 400 C for Further 24 Hrs
Hold 400 C Until:

T/C Under Ceramic Arrestor > 100 C, and


T/C Mid Point of Refractory Lining Also > 100 C

Business Confidential

12

Procedure For Drying the Blast Furnace Lining


Measure The Humidity of the Blast Air
Time Estimate for Equalization of Incoming and
Outgoing Humidity = ~ 7 Days, But It Can Be Up to 10
or 12 Days.

Business Confidential

13

Special Procedure For Stove Changes


For Normal Stove Changes from Bottle Up to On
Blast. The Stove is First Pressurized, then the Cold
Blast Valve is Opened, then the Hot Blast Valve, and
Lastly the Mixing Air Valve. For Dryout, and
Considering the Low Pressure and Blast Volume, the
Hot Blast Valve is Opened First, and then The Mixing Air
Valve, and Lastly the Cold Blast Valve.
The Concept is to Never Allow Blast Air Temperature to
Exceed Target Level
Under No Circumstances Is Blast Temperature to
Approach 500 C, Due to Oxidation Potential

Business Confidential

14

Very Important Reminders

During the Dryout and Blow-In, Be Sure to Drain Water


from Hearth Drains Daily
About 2 Weeks After the Blow-In, Stop the Furnace and
Grout Between Hearth Bricks and Shell, to Restore and
Insure Good Contact for Heat Transfer

Business Confidential

15

Blowing In the Blast Furnace

Once the Dryout is Completed, and All


Equipment Is Ready for Service, It is
Time to Blow In the Blast Furnace
It Seems Every Plant Has Their Own
Peculiarities Regarding How To Do This,
and That Is a Great Problem

Business Confidential

16

Blowing In the Blast Furnace

It Is a Problem Because the Technology


Does Not Seem to be Transportable
The Following Is a Compilation of More
Than 150 Blow-Ins, and Has Been
Tested and Verified on BFs as Small as
6 m H.D. and as Large as 14 m H.D.

Business Confidential

17

Blowing In the Blast Furnace

Fundamentals
Burdening
Start Up Procedure

Business Confidential

18

Blowing In the Blast Furnace Fundamentals

Planning and Mental Discipline


Simplicity
High Slag Fluidity
Arrival at 110% of Normal Reductant
Consumption After 1.0 1.5 Times
Working Volume Charged After Initial Fill
Focus on Development of Connection
Between Tuyeres and Taphole

Business Confidential

19

Blowing In the Blast Furnace Burdening

Key Principles
Initial Fill
Subsequent Filling

Business Confidential

20

Blowing In the Blast Furnace Burdening

Key Principles
Optimize Coke Particle Size and Quality
50 mm Minimum Size For All Coke Portion
on Initial Fill. Best Quality Available
40 mm Bottom Size for Rest of Blow In
Optimize Melting Properties of Other
Materials Where Choice Exists
For Ex. Silicious Ore vs Silica Gravel

Business Confidential

21

Blowing In the Blast Furnace Burdening


Initial Fill
Fill BF to Centerline of Tuyeres with Coke
Add +15% W.V. Coke
Add + 25% W.V. Fluxed Coke
Aim 1.27 B/S in Slag, H.M. Si 3.00%

Four Blocks of 12% W.V. each

Block 1 C.R. 1600 kg/tHM


Block 2 C.R. 1200 hg/tHM
Block 3 C. R. 1000 kg/tHM
Block 4 C. R. 900 kg/tHM

Slag Volume Results from B/S Calculation and


Fluidity Targets

Business Confidential

22

Blowing In the Blast Furnace Burdening


Subsequent Filling
10 Blocks of 10% - 15% W.V. each
Coke Rate
kg/tHM

Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10

900
860
815
770
725
680
635
590
545
500

Slag
B/S
1.27
1.27
1.27
1.27
1.27
1.27
1.27
1.27
1.27
1.27

Vol
1.5 x Normal
1.5 x Normal
1.25 x Normal
1.25 x Normal

Normal
Normal
Normal
Normal
Normal
Normal

Iron
% Si
2.50
2.50
2.00
2.00
1.75
1.75
1.50
1.50
1.25
1.00

Business Confidential

23

Blowing In the Blast Furnace Start Up Procedure

Key Principles
Drying the Burden
Light Off
Schedule for Blast Volume, Blast
Temperature, and Tuyere Opening
Casting

Business Confidential

24

Blowing In the Blast Furnace Start Up Procedure

Key Principles
Firmly Establish Gas and Liquid Connection
Between Tuyeres and Taphole(s)
Air Injection (Durfee Pipe)
Gas Burner
Allowing Long Time Blow

Gradual Increases in Blast Volume, Burden


Ratio, Hot Blast Temperature
Hot Metal Silicon Content <1.0% Within 36 48 Hours from First Cast
Business Confidential

25

Blowing In the Blast Furnace Start Up Procedure


Drying the Burden

Start at 300 C for 4 Hrs


Then to 400 C for 4 Hrs
Then to 500 C for 4 Hrs
Then + 50 C per Hour until Ignition

Light Off Occurs Automatically by the Hot Blast


~ 550 C
After Ignition, Move Immediately to 600 C Hot
Blast Temperature. Then Hold for 2 Hours

Business Confidential

26

Blowing In the Blast Furnace Start Up Procedure


Schedule for Blast Volume

Start Burden Drying at 33% of Normal Wind


At Ignition Move Immediately to 50%
+ 3% Every 2 Hrs, Means ~33 Hours Until Full Wind

Schedule for Blast Temperature

After 2 Hour Hold, +100 C Every 2 Hrs Until 80% of Normal


After 24 Hrs, +100 C Every 2 Hrs Until 90% of Normal
Reserve Last 10% HBT for Cold Furnace Issues. and Later
Blast Moisture for RAFT Control

Schedule for Tuyere Opening

Use Tuyere Inserts Equal to 50% Tuyere Cross Section


Break Inserts as Blast Volume Increases to Maintain Tuyere
Velocity
Keep Blast Balanced Around Furnace

Business Confidential

27

Blowing In the Blast Furnace Start Up Procedure

Business Confidential

28

Blowing In the Blast Furnace Start Up Procedure

Casting
During Burden Drying, Tapholes Are Open
After Ignition, Tapholes Are Kept Open as
Long as Possible, Even Using heavy
Equipment to Clean Main Trough

Business Confidential

29

Blowing In the Blast Furnace Start Up Procedure


Dog House

Business Confidential

30

Blowing In the Blast Furnace Start Up Procedure

Casting
Once Tapholes Are Closed, Wait 8 12
Hours to make First Cast
Then Finish Subsequent Casts Every 3
3.5 Hours

Business Confidential

31

Blowing In the Blast Furnace Start Up Procedure

The Procedure Review


Start All Tuyeres Open with Inserts, and
Dry Burden 12 Hrs. 1/3 Normal Blast
Volume, HBT 300 C, Increasing by
Schedule
After Drying Burden, Gradually Move to
Ignition
After Ignition, Allow the Taphole(s) to Blow
Hot Gas as Long as Possible

Business Confidential

32

Blowing In the Blast Furnace Start Up Procedure

The Procedure Review (Contd)


Close Taphole(s), and wait 8 12 Hrs to
Make First Cast
After First Cast, Subsequent Casts Finish at
3 3.5 Hr Intervals
Burden Ratio, Blast Volume, Hot Blast
Temperature Increase by Pre-arranged
Schedules

Business Confidential

33

Blowing In the Blast Furnace Start Up Procedure

The Procedure Review (Contd)


As Blast Volume Increases, Break Inserts
to Increase Tuyere Area by Calculation to
Maintain Tuyere Velocity

Business Confidential

34

Summary

Planning and Mental Discipline are the


Keys to Success
Pay Close Attention to Details

Business Confidential

35

This presentation and its guidelines are to be used for illustrative purposes only, and
are not intended to replace individual assessments. Each plant, blast furnace, and
operation is unique and adjustments need to be made to suit local conditions.
GrafTech makes no warranties, express or implied, as to these guidelines and
assumes no liability arising out of its use. The information contained in this
presentation should not be used as the sole basis of proper blast furnace procedures.
GrafTechs liability to purchasers is expressly limited to the terms and conditions of
sale.

Business Confidential

36

Вам также может понравиться