Академический Документы
Профессиональный Документы
Культура Документы
Prepared By
MD. Shahinul Islam
ID No. : M-073752
Major: Finance
Program: MBA
This OCP Report is submitted for the partial fulfillment of the Degree
Masters of Business Administration (MBA) with major in Finance
Supervised By
Md. Shariful Haque
Associate Professor
Department of Business Administration, IIUC
Prepared By
MD. Shahinul Haque
ID No. : M-073752
Major: Finance
Program: MBA
LETTER OF SUBMISSION
November 22, 2013
Md. Shariful Haque
Associate Professor and Internship Supervisor
MBA Program
International Islamic university Chittagong, Dhaka Campus
Dear Sir,
It is my pleasure to submit my OCP report on Analysis on electricity crisis
and government steps toward the eradication of it and for your kind
consideration. This job is assigned to me to fulfill the partial requirement of
MBA program.
The report contains a comprehensive study on the Present Situation of Energy
of Bangladesh & Government Steps in eradicating the deficiency of Energy
crisis. It was a great pleasure for me to have the opportunity to work on the
above mentioned subject. I have tried my level best to come out with a good
one.
Please feel free to contact me if you have any inquiries. I would be very happy
to provide you with any clarification regarding this report.
Would you please kindly accept my paper and oblige me thereby.
Thank you.
Sincerely yours,
LETTER OF SUBMISSION
November 22, 2013
The Coordinator
MBA Program
International Islamic university Chittagong, Dhaka Campus
Sub: Submission of OCP report.
Dear Sir,
It is my pleasure to submit my OCP report on Analysis on electricity crisis
and government steps toward the eradication of it and for your kind
consideration. This job is assigned to me to fulfill the partial requirement of
MBA program.
The report contains a comprehensive study on the Present Situation of Energy
of Bangladesh & Government Steps in eradicating the deficiency of Energy
crisis. It was a great pleasure for me to have the opportunity to work on the
above mentioned subject. I have tried my level best to come out with a good
one.
Please feel free to contact me if you have any inquiries. I would be very happy
to provide you with any clarification regarding this report.
Would you please kindly accept my paper and oblige me thereby.
Thank you.
Sincerely yours,
Acknowledgement
I would like to thank The Almighty Allah for giving me the opportunity to
successfully complete my OCP report.
I have prepared my OCP report on Analysis on electricity crisis and
government steps toward the eradication of it. I tried my best to get this
paper ready to the required standard.
I would like to thank my OCP program supervisor Md Shariful Haque, Associate
Professor, IIUCDC for his prudent guidance and instruction that enabled me to
accomplish the internship report successfully.
Table of Content
Chapter 1
1.0
0
1.1
1.2
1.3
1.4
1.5
1.6
INTRODUCTION
Background of the Report
Objectives
Scope
Sources of Information
Methodology
Limitations:
Chapter 2
2.00
2.01
2.02
2.03
2.04
2.05
2.06
2.07
2.08
2.09
2.10
2.11
2.12
2.12.1
2.12.2
2.12.3
2.12.4
2.13
2.14
2.15
2.16
2.17
2.18
2.19
2.20
2.21
Page
Numb
er
10
10
11
11
11
12
13
Page
Numb
er
15
15
15
16
17
18
19
19
19
21
22
23
24
24
25
25
25
26
26
27
29
31
31
32
33
35
2.22
2.23
2.24
2.25
2.26
2.27
2.28
Chapter 3
41
42
42
50
53
54
55
Page
Numb
er
3.00
3.01
Recommendation
Perfect Estimation of future need
57
57
3.02
3.03
57
57
3.04
3.05
3.06
3.07
57
58
3.08
3.20
58
58
3.30
BIBLIOGRAPHY
60
57
57
ABSTRACT
Electricity, the most usable form of energy, is one of the most important
issues for the economic development of a country. The projection of demand
for electricity is an integral part of the planning process as it enables the
decisions-makers on the regarding matter. This study investigates the
possible pattern of electricity scenario in the near future.
A Developing nation like Bangladesh requires uninterruptable Energy Supply
for industrial, Agricultural growth. Without uninterruptable Electricity supply
we cannot even think of being Developed nation. Many parts of the country
did not get the Electricity coverage yet. Due to Load shedding our Irrigation is
been interrupted as a result it effect badly in production in agricultural sector
as well as in our GDP. We become badly dependent on import; it creates more
import pressure and deficit in foreign currency. In case of industry sector
heavy weight machine are being used, which requires uninterruptable
electricity supply for keeping production level up to the mark. Readymade
garments industry cannot meet there expected production which causes
delay in shipment. Country loses their export contract. Many Factories has
been closed due to insufficient supply of electricity.
Government has made successful record in Electricity generation in last five
years. Government has taken many steps in development of electricity
generation which is mainly based on temporary basis. Quick rental cannot be
the solution of electricity for long run. Government should take more
initiatives for long run and keep moving economic cycle towards the
developed nation. Government should have to take decision in such way that
the nation could meet the future demand of electricity.
1.0
INTRODUCTION
Department of
1.2. OBJECTIVES
As a business expectative of future, we should have to gather experience
beside our survey. We should not concern our lesion only in classroom but to
implement it in practical life that will help us in our future life .A clear objective
help in preparation of well decorated report in which other take the right type of
decision .So, we identifying objectives is very much important.
1.3. SCOPE
The study would focus on the following areas:
1.4
SOURCES OF INFORMATION
Information collected to furnish this report is both from primary and secondary
sources.
The primary sources are:
1.5. METHODOLOGY
Type of Research:
This report is a descriptive type of research in nature and it administered by
collecting both primary and secondary data. The author has tried to use both
the primary and secondary sources of collecting information and some are to
make the report presentable with as fewer abstractions possible.
Sources of data:
In order to attain the objective of the study in this report all- necessary
information are prepared by collecting both primary & secondary sources of
data.
Primary sources:
Primary data collected directly to solve the customer problem through face-toface interaction. It is the systematic collection of information directly from
respondents using survey. Several sources of data collection are used to make
this report. The source of data are
Secondary sources:
Some secondary data collected to make the report more concrete. These data
has been collected from different books, web site, Annual report of BPDC and
combination of all these sources; such as
Books
Journals
1.6 LIMITATION:
Though I tried my level best to produce a comprehensive and well-organized
report on Analysis on electricity crisis and government steps toward
the eradication of It, some limitations were yet present there:
i.
ii.
iii.
iv.
2.01 INTRODUCTION
Bangladesh's energy infrastructure is quite small, insufficient and poorly
managed. The per capita energy consumption in Bangladesh is one of the
lowest (136 kWH) in the world. Noncommercial energy sources, such as wood
fuel, animal waste, and crop residues, are estimated to account for over half of
the country's energy consumption. Bangladesh has small reserves of oil and
coal, but very large natural gas resources. Commercial energy consumption is
mostly natural gas (around 66%), followed by oil, hydropower and coal.
Electricity is the major source of power for most of the country's economic
activities. Bangladesh's installed electric generation capacity was 8525 MW in
2013; only three-fourth of which is considered to be available. Only 40% of the
population has access to electricity with a per capita availability of 136 kWh per
annum. Problems in the Bangladesh's electric power sector include corruption
in administration, high system losses, and delays in completion of new plants,
low plant efficiencies, erratic power supply, electricity theft, blackouts, and
shortages of funds for power plant maintenance. Overall, the country's
generation plants have been unable to meet system demand over the past
decade.
remains the same, the average load shedding might be stood at 795 MW by
2015. The lower increasing rate of generation (5.37 percent) than that of the
demand (5.43 percent) has accelerated the rate of load shedding which has
increased at a rate of 6.72 percent per annum during the same period.
2.6 MAXIMUM DEMAND FOR ELECTRICITY BY
DIFFERENT ZONE
The scale of demand for electricity is going up. It varies according to
different zones of the country. The east zone is more developed and
industrial than the west zone. This causes the difference in the demand
between the two zones. The demand for electricity in east zone is much
higher (more than double) than that of the west zone. In east zone, the
demand for electricity has increased with a rate of 18.3 percent per year
between 2000-01 and 2008-09. However, in the west zone, this increasing
rate was 9.1 percent during the same time period.
Except 2005-2006, almost all the times after 2001-02, the consumption
pattern of electricity at the domestic level increased with a decreasing rate.
The same result is also found in the case of the commercial services.
However, in the industrial services and in other services, the consumption
pattern has also increased with a decreasing rate from 2003-04 except in
the year 2005-06. The consumption rate of electricity of all the service
categories was highest in the year 2005-06. The annual rate of increase
between 2000-01 and 2007-08 was highest at commercial services which
was 15.6 percent, followed by domestic services (13.8 percent),
industrial services (13.3 percent) and other services (6.4 percent).
R2 =
0.977
1
50
00
R2 = 0.9962
4000
3000
2000
R2 = 0.7187
10
00
0
2012*
2013*
It is also observed that the demand for electricity has been increased with a
rate of 5.43 percent per year whereas, the generation of electricity has been
increased with a rate of 5.37 percent per year between 2007 and 2011. The
lower increasing rate of generation (5.37 percent) than that of the demand
(5.43 percent) has accelerated the rate of load shedding which has been
increased at a rate of 6.72 percent per annum during the same period
(Figure 3).
7
6
5.43
5.37
Percent
5
4
3
2
1
0
Demand
Generation
Load Shed
9.1
West Zone
18.3
East Zone
10
15
20
Percentag
e
Authors calculation, based on BBS, 2011 data
10
0
12000
40
10000
30
Annual Growth Rate (%)
20
8000
6000
4000
-10
2000
-20
0
-30
2000-01
2001-02
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
Note: MKWH = Million
Kilowatt Hours
Source: Authors calculation, based
on BBS 2011 data
Percent
5
4
3
2
1
0
2006-07
2007-08
2008-09
2009-10
2010-11
2.12
Although the government has taken several initiatives for reducing the
crisis of electricity, yet the crisis persists. This is mainly due to the problems
associated with high gas dependency, improper privatization policy, lack
of satisfactory and timely implementation of allocated money, political
reasons and over population.
2.12.1 HIGH GAS
DEPENDENCY
The most important reason at the moment is that the government is unable
to ensure the supply of natural gas, the main primary fuel which is used to
produce electricity. The Shortage of available gas supply creates a
struggling situation of electricity generation. Still, 83 percent of the total
electricity used to be generated by natural gas. Many power plants are idle
due to the shortage of gas supply. This has resulted in the lower
generation of electricity. On the other hand, unprecedented delay in
finalizing a coal policy makes it difficult to generate the expected level of
There has been an increase in the demand for electricity in the recent
years as a result of industrial development and population growth. One of
the common matters in the country is over population, which creates a lot of
problem in the various development sectors. More population means more
consumption of electricity. Population is increasing but the generation of
electricity is not increasing as required. After all, there is an improvement in
the life style of the citizen in the country. With the improvement of the
peoples life standard, the demand for electricity has also increased. As the
generation has increased with a slower rate than that of the demand for
electricity, the crisis of electricity is on the rise
in FY 2008-2009 which is still among the lowest in the world. About 47% of the
population has access to electricity which is also low compared to many
developing countries. This implies that there is a scope for significant growth in
power sector.
In the east zone, electricity generation was mainly done by indigenous gas
based power plants and a small percentage from hydro power plant. In the west
zone, imported liquid fuel, domestic coal and natural gas ware used for
generation of electricity. Law cost electricity generated in the east zone was
also transferred to the west zone through 230 kV East-West inter connector
(EWI). The energy transferred through EWI at the Ghorasal and Ashuganj end in
FY2009 was 2,548.99 GWh. The average feul cost per unit generation of
thermal power plants in the east and west zone under BPDB was BDT. 0.82/kWh
and BDT 3.87kWh respectively.
Bangladesh Government is committed affordable and reliable electricity to all
citizens by 2020 for the economic and social development. As per election
manifesto of the present government, electricity generation in the country
would be 7,000.00 MW by the year 2013, 8000 MW by the 2015 and 20,000
MW by the year 2021. Meanwhile, the government has declared its vision for
power sector to make the country free from load shedding beyond 2011 and to
make electricity available for all by the year 2020. In order to fulfill the vision,
additional 9,000 MW electricity will be required to be produced within nest 5
years under short, medium and long term out of which 5,400 MW would be
produced under private sector. Adequate transmission and distribution facilities
would also be developwd to get access to the electricity. Estimated total
investment US$ of 9.5 bilion would be required all together for generation ,
transmission and sictribution of power. In fact power sector reforms started in
late 70s through the creation of REB. However as part of reform programs,
following activities have been done so far.
Policies are as describe:
management issues within the power sector and visualize the improvement
against the measures taken up by the management.
Opportunities in the Power and LNG Sector:
2010 IPP round:
Bangladesh, with a history of successful IPP programmes, has announced plans
to install around 4000MW of new generating capacity on a build-ownoperate
(BOO) basis and one LNG terminal of around 3.5 MT near Chittagong on a buildown-operate-transfer (BOOT) basis by 2015. Towards this end, Bangladesh
Power Development Board (BPDB) has recently issued Pre Qualification
documents for several power projects.
YEAR (MW)
Sector
Public
Private
Quick
Rental
Total:
201
0
255
27
250
201
1
851
105
1238
201
2
838
1319
-
201
3
1040
1134
-
201
4
1270
1053
-
201
5
450
1900
-
201
6
1500
1300
-
Total
775
219
4
215
7
217
4
232
3
235
0
280
0
14,77
3
6204
7081
1488
on April 2012
Total(%)
3.74 %
1.64 %
75.99 %
5.01 %
10.19 %
3.44 %
100 %
Coal
F.Oil
Gas
HFO
HSD
Hydro
Total
200.00
85.00
4651.00
248.00
657.00
220.00
6061.00
MW
MW
MW
MW
MW
MW
MW
3.3 %
1.4 %
76.74 %
4.09 %
10.84 %
3.63 %
100 %
. Only deposit (Barapukuria) has been developed and coal in being extracted
mainly for one thermal power plants.
2.18 POWER SYSTEM RELIABILITY:
In Bangladesh today, the power system in unreliable. Often, not enough
generation is available to serve demand. BPDB sheds load by disconnection
distribution circuits on a rotating basis throughout the country. It is clear the
more generation must be built to supply customers demand. A key question is
how much generation is enough to supply customer demand with appropriate
reliability. In the demand forecast, we ignore the need for operating reserves
and the changes that some of the installed generation would not be available
due to schedule unscheduled maintenance outages. These outages keep any
individual unit out of service from 10-25% or more of the time. Thus, the power
system needs substantially more then projected demand to meet actual
demand. Units experience random forced outages at rates of 10-15% of the
time. Typically, power system operators do not schedule outages during times
when peak time demand is likely to occur. Thus, the forced outages become the
dominate factors.
However , there is very small changes that all units will be out of services at
the time of peak demand., leaving the system unable to meet all demand. No
matter how many units are installed, there will always be some changes that
enough units will be forced out of service that the system is unable to meet all
demand. As more units are added, the changes of this occurring becomes very
small, but they are never zero. As such actual installed capacity should be
higher than the projected demand.
2.19 POWER GENERATION SCENARIO IN BANGLADESH:
To achieve this commitment, in spite of the major deterrents energy crisis and
gas supply shortage, government has taken several initiatives to generate
7,000 MW by 2013 and 13,000 MW by 2018, which are close to the
commitment in the election manifesto. 4432 MW of power (as of September,
2013) has already been added to the grid within three years time. The
government has already developed Power system Master Plan 2010. According
to the Master Plan the forecasted demand would be 19,000 MW in 2021 and
34,000 MW in 2030. To meet this demand the generation capacity should be
39,000 MW in 2030. The plan suggested to go for fuel-mixed option, which
should be domestic coal 30%, imported coal 20 %, natural gas (including LNG)
25%, liquid fuel 5%, nuclear, renewable energy and power import 20%. In line
with the Power system Master Plan 2010, an interim generation addition plan
up to 2018 has been prepared, which is as follows:
Plants Commissioned During 2009 September 2013
YEAR
2009
(MW)
Public
Private
356
Q. Rental
Total
356
2010
(MW)
255
270
250
775
2011
(MW)
800
125
838
1763
2012
(MW)
607
44
300
951
2013
(MW)
587
587
TOTAL
(MW)
2249
795
1388
4432
2013
(MW)
662
692
2014
(MW)
604
1366
2015
(MW)
1837
1097
2016
(MW)
1510
638
2017
(MW)
00
1271
2018
(MW)
1320
00
500
1854
TOTAL
(MW)
5933
5064
500
1970
2934
2138
1271
1320
11,497
Government has taken short, medium and long term plan. Under the short term
plan, Rental Power Plants will be installed using liquid fuels/gas and capable to
produce electricity within 12-24 months. Total 1653 MW was installed by this
time from rental power plants.
Under the medium term plan, initiatives have been taken to set up power
plants with a total generation capacity of 11,497 MW. The plants are mainly
coal based, some are gas and oil based. In the long term plan, some big coal
fired plants will be set up, one will be in Khulna and other will be in Chittagong,
each of having the capacity of 1300 MW. Some 300-450 MW gas based power
plants will be set up in Bibiana, Meghnaghat, Ashugonj, Sirangonj and in
Ghorashal. If the implementation of the plan goes smoothly, it will be possible
to minimize the demand-supply gap at the end of 2015
Government has already started implementation of this plan. Total 38,229
Million-kilowatt hour (MkWh) net energy was generated during 2012-13. Public
sector power plant generated 47% while private sector generated 53% of total
net generation. The share of gas, hydro, coal and oil based energy generation
was - 78.12%, 2.34%, 3.02% and 16.51% respectively. On the other hand, in
FY 2011-12 35,118 million-kilowatt hour (MkWh) net energy was generated i.e.
electricity growth rate in FY 2013 was 8.86% (In FY 2013
2.20 NEW GENERATION FUTURE PLAN OF THE GOVERNMENT:
In order to develop the Bangladesh power sector, a Power Sector Master Plan
(PSMP) was in place in 2005. The PSMP 2005 was mainly based on gas with the
perception that Bangladesh has abundance of gas reserve. But the reality is
reverse, as such even the existing gas based power plants could not be
operated due to the shortage of adequate gas pressure and gas reserve is
alarmingly depleting. Meanwhile, the government has declared its vision 2021
to provide electricity for all. To accommodate the changed scenario and the
govt.'s vision 2021, a new PSMP 2010 has been undertaken considering coal as
dominant primary fuel for the attainment of stable power supply up to the year
2030 in consideration of the diversification of fuel resources. The PSMP 2010
has been developed with the technical assistance of JICA and has been
approved by the government after a thorough sector experts review and
stakeholders consultations. The Study reveals that in order to attain a 8% GDP,
the electricity demand would be 34,000MW by the year 2030.
PSMP
(30%
LNG),
trade,
The PSMP 2010 is of the opinion that each of the aforementioned constraints
needs to be addressed and measures need to be implemented for
improvement, revision, and alleviation and strengthening for making an
investment decision by an investor.
2.21 TRANSMISSION PLAN:
Power Grid Company of Bangladesh Ltd. (PGCB) is responsible for operation,
maintenance and development of transmission system all over the country.
Presently power generated in various power plants in Bangladesh is transmitted
to the national grid through 230 kV and 132 kV transmission lines. In 1996
when PGCB was formed, the total lengths of 230 kV and 132 kV line was 8,500
ckt km. In FY 2011 length of 230 kV and 132 kV transmission lines stood at
8,662 ckt km. The total length of the OPGW installed in the transmission line
from 1996 to June, 2007 was 2200 km. This has been increased to 4200 km up
to June, 2010 after completing the NLDC project. This shows that the major
parts of the country are covered by the PGCB optical fiber network.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
On going Projects:
Sl
Name of the Project
No.
Three Transmission
Line.
Implementation Period : 2006-07 to
2010-11
Meghnaghat-Aminbazar 400 kV
Transmission Line (Phase1).
Implementation Period: 2006-07 to
2011-12
Physical
Physical
Target up Progress Financing
to June-11 up to June- Status
11
88.78%
100.00%
ADB &
Bangladesh
Govt.
39.58%
ADB &
Bangladesh
Govt.
60.30%
ADB &
Bangladesh
Govt.
63.60%
kfW &
87.46%
100.00%
33.08%
Bangladesh
Govt.
Siddhirganj-Maniknagar 230 kV
Transmission line with associated
30.57%
substations. August, 2009 -Dec, 2011
29.39%
ADB &
Bangladesh
Govt.
10.00%
EDCF &
Bangladesh
Govt.
15.00%
ADB &
Bangladesh
Govt.
32.25%
Bangladesh
Govt.
10.00%
Bank Loan
20.55%
8.00%
Barisal-Bhola-Borhanuddin 230kV
Transmission Line.
10
10.00%
Implementation Period: March, 2011
to Sep, 2012
The following projects are under active consideration of PGCB in the Govt.s
Prioritized Investment Plan as shown in.
Planned Project
Sl
No.
1
to Power Division
Construction of 230/132kV
Substation at Shyampur, Jhenaidah
Pre-DPP submitted
(Or Jessore), Bheramara and Sripur.
(2012-13 to 2014-15).
Ruppur-Bheramara-Zajira 400kV
12 Transmission line. (2014-15 to
2016-17)
Ashuganj-Joydebpur 400kV
13 Transmission line. (2014-15 to
2016-17)
2.23 ACHIVEMENTS
The government has been extremely successful to enhance and increase the
performance of the distribution entities due to continuous monitoring and
evaluation. The distribution entities have also taken various steps to improve
the electricity distribution system, heighten consumer satisfaction, and
decrease the overall system loss.
2.24 DISTRIBUTION PROJECT
To increase power generation as well as to improve customer service and bring
more people under electrification, integrated power distribution programs have
been undertaken. Up to June 2011, about 1.25 crore consumers are connected
with electricity by construction of 278,000 kilometer distribution lines. Nearly
80,000 new consumers will be connected through different projects within 3/4
years. However major power distribution expansion projects of five different
entities are mentioned below in Table.
Table: List of Projects
Name of Projects
Project
Completio cost
n Date
(Crore
Tk.)
Project objective
2013-14
637.76
1088.00
BPDB
1. Power Distribution
System Development,
Mymensingh Zone
2. Power Distribution
System Development,
Chittagong Zone
2013-14
3. Power Distribution
System Development,
Comilla Zone
2013-14
756.00
4. Power Distribution
2013-14
410.00
System Development,
Sylhet Zone
be provided by construction
and renovation of
distribution line &
substations
5. Power Distribution
System Development,
Rangpur Zone
710.00
693.00
6. Power Distribution
System Development,
Rajshahi Zone
2013-14
2013-14
Total (BPDB)
4295.00
REB
1. 10 lakh new connection 2012-13
348.00
2. RE upgradation
project(Rajshahi, Rangpur, 2012-13
Khulna & Barisal)
1322.00
3. RE Expansion Dhaka
Division-1
2012-13
498.00
4. RE Expansion
Chittagong-Sylhet Division- 2012-13
1
498.00
5. RE Expansion Rajshahi2012-13
Rangpur Division-1
407.00
6. RE Expansion Barisal
Division-1
268.00
2012-13
Total(REB)
2993.00
DPDC
1. Development of new
2011-12
434.00
Substation upgradation
Total(DPDC)
169.00
603.00
DESCO
1. Strengthening of
distribution network
2011-12
486.00
595.00
Total(DESC)
11081.00
Distribution network
upgradation
Distribution system
upgradation
WZPDC
1. 21 Districts Power
Distribution Projects
2012-13
Total(WZPDC)
Achievement at a glance:
469.00
Upgradation of distribution
network and substation
469.00
: 278,000 KM
Total Consumers
:12.5 million
Irrigation Consumer
: 2.77 Lac
Access to electricity
:50%
Distribution Loss
: 12.75%
Accounts Receivable
BPDB
4186
APSCL
777
EGCB
622
NWPGCL
300
RPCL
77
Subtotal
5,962(58%)
Private Sector
IPPs
1330
SIPPs(BPDB)
99
SIPPs(REB)
226
15 YR. Rental
167
1929
Power Import
500
Subtotal
4251(42%)
TOTAL
10,213
6675 MW
7525 MVA
12-07-2013
FY-2013
FY-2013
FY- 2013
11,717 MVA
34,827 K.M
CONSUMER NUMBER
26,53,946
FY- 2013
FY-2013
FY-2013
FUEL ACHIEVEMENT:
DAILY GENERATION:
Daily Generation 30/11/2013 to 30/11/2013 (All)
Power Station Name
Derated
Day Peak
Capacity(Unit)
Eve Peak
78.00
MW
95.00
MW 95.00
Ghorasal ST :Unit-3,
180.00
MW
110.00 MW 110.00 MW
Ghorashal ST 4
180.00
MW
180.00 MW 180.00 MW
Ghorashal 100
100.00
MW
35.00
MW 99.00
MW
Ghorrashal ST 5
190.00
MW
0.00
MW 0.00
MW
Ghorashal ST 6
190.00
MW
0.00
MW 0.00
MW
Ghorashal 45 MW
45.00
MW
46.00
MW 46.00
MW
Ghorashal MAX
78.00
MW
80.00
MW 80.00
MW
MW
0.00
MW 0.00
MW
Horipur NEPC
110.00
MW
47.00
MW 95.00
MW
360.00
MW
344.00 MW 355.00 MW
Meghnaghat P.Ltd
CCPP
450.00
MW
455.00 MW 453.00 MW
Meghnaghat IEL
100.00
MW
76.00
MW 76.00
MW
MW
Madanganj 102 MW
100.00
MW
81.00
MW 96.00
MW
Karanigonj
100.00
MW
45.00
MW 90.00
MW
Narshingdi
22.00
MW
16.00
MW 16.00
MW
Shiddirganj ST
150.00
MW
105.00 MW 95.00
MW
Siddirgonj GT 1,2
210.00
MW
0.00
MW 0.00
MW
Siddirgonj 100 MW
96.00
MW
0.00
MW 52.00
MW
100.00
MW
77.00
MW 100.00 MW
DPA Power 50 MW
50.00
MW
0.00
MW 47.00
MW
MW
0.00
MW 0.00
MW
Summit Power
(Dhaka)
146.00
MW
98.00
MW 95.00
MW
Gazipur RPCL
52.00
MW
0.00
MW 52.00
MW
Tongi GT
105.00
MW
0.00
MW 0.00
MW
Chittagong
180.00
RaozanST(Gas):Unit-1
MW
0.00
MW 0.00
MW
Raozan 25MW
MW
9.00
MW 26.00
MW
Chittagong
180.00
RaozanST(Gas):Unit-2
MW
0.00
MW 0.00
MW
Kaptai Hydro:Unit1,2,3,4,5
220.00
MW
28.00
MW 128.00 MW
Shikalbaha ST
40.00
MW
0.00
MW 0.00
MW
b) Shikalbaha
Peaking (GT)
150.00
MW
0.00
MW 0.00
MW
Hathazari
98.00
MW
0.00
MW 98.00
MW
Shikalbaha(Energis)
0.00
MW
0.00
MW 0.00
MW
Dohazari Sangu
102.00
MW
0.00
MW 102.00 MW
Julda
100.00
MW
90.00
MW 91.00
MW
0.00
MW
3.00
MW 4.00
MW
MW
8.00
MW 8.00
MW
a) Ashuganj ST Unit
-1,2
110.00
MW
0.00
MW 55.00
MW
b) Ashuganj ST 3
140.00
MW
100.00 MW 100.00 MW
Ashugonj ST 4
150.00
MW
150.00 MW 150.00 MW
Ashugonj ST 5
140.00
MW
100.00 MW 100.00 MW
c) Ashuganj CCPP-
91.00
MW
0.00
25.00
MW 0.00
MW
146MW
d) Ashuganj 50 MW
53.00
MW
15.00
MW 15.00
MW
Ashuganj (Precision)
55.00
MW
56.00
MW 57.00
MW
Ashuganj (Aggreko)
80.00
MW
78.00
MW 82.00
MW
Ashuganj Midland
0.00
MW
51.00
MW 28.00
MW
Ashugonj Up-53 MW
51.00
MW
49.00
MW 49.00
MW
Brahmanbaria
(Agrico) (Gas)
70.00
MW
70.00
MW 71.00
MW
Daudkandi 50 MW
52.00
MW
0.00
MW 50.00
MW
Chandpur CCPP
163.00
MW
0.00
MW 0.00
MW
Feni (Doreen)
22.00
MW
17.00
MW 0.00
MW
Feni, Mahipal
(Doreen)
11.00
MW
8.00
MW 8.00
MW
Jangalia (Summit)
33.00
MW
33.00
MW 34.00
MW
Summit Power,
Comilla
25.00
MW
22.00
MW 20.00
MW
RPCL,CCPP,
Mymensingh
197.00
MW
97.00
MW 149.00 MW
Tangail (Doreen)
22.00
MW
19.00
MW 20.00
MW
Fenchuganj CCPP-1
(Gas)
90.00
MW
73.00
MW 74.00
MW
Fenchuganj CCPP2(New)
104.00
MW
90.00
MW 90.00
MW
Fenchuganj (BEDL)
51.00
MW
39.00
MW 44.00
MW
Fenchuganj Prima 50
MW
44.00
MW
37.00
MW 40.00
MW
Hobiganj
(Confidence-EP)
11.00
MW
6.00
MW 7.00
MW
Shajibazar GT Unit-8,
66.00
9
MW
63.00
MW 63.00
MW
Shajibazar 86 MW
86.00
MW
75.00
MW 75.00
MW
Shajibazar - 50 MW
50.00
MW
46.00
MW 48.00
MW
Sylhet 150MW
142.00
MW
108.00 MW 137.00 MW
Sylhet GT (Gas)
20.00
MW
20.00
MW 20.00
MW
Sylhet 50 MW
50.00
MW
40.00
MW 41.00
MW
Sylhet 11 MW
10.00
MW
8.00
MW 8.00
MW
Bheramara GT (Unit-
46.00
MW
0.00
MW 0.00
MW
1,2,3)
Bheramara
105.00
MW
0.00
MW 12.00
MW
a)Khulna ST 110 MW
55.00
MW
55.00
MW 60.00
MW
HVDC C/B.
Interconnector
500.00
MW
0.00
MW 0.00
MW
b)Khulna ST 60MW
30.00
MW
0.00
MW 0.00
MW
KPC, Khulna
110.00
MW
5.00
MW 90.00
MW
115.00
MW
16.00
MW 115.00 MW
Khulna 150 MW
150.00
MW
0.00
MW 105.00 MW
Faridpur
54.00
MW
0.00
MW 41.00
MW
Gopalganj 110 MW
109.00
MW
0.00
MW 91.00
MW
Noapara (105MW)
Quantam
101.00
MW
0.00
MW 0.00
MW
MW
28.00
MW 40.00
MW
Khulna 40 MW
40.00
MW
0.00
MW 0.00
MW
Khulna 55 MW
55.00
MW
0.00
MW 31.00
MW
Barisal Diesel(HSD)
0.00
MW
0.00
MW 0.00
MW
Barisal GT 1& 2
32.00
MW
0.00
MW 0.00
MW
Bhola Venture
33.00
MW
0.00
MW 0.00
MW
a)Baghabari GT 1
71.00
MW
72.00
MW 72.00
MW
b)Baghabari GT 2
100.00
MW
95.00
MW 105.00 MW
Baghabari 50 MW
52.00
MW
0.00
MW 40.00
MW
Baghabari Westmont
70.00
MW
0.00
MW 0.00
MW
Bera 70 MW
71.00
MW
0.00
MW 63.00
MW
Amnura 50 MW
50.00
MW
0.00
MW 42.00
MW
50.00
MW
8.00
MW 50.00
MW
MW
0.00
MW 36.00
MW
Sirajganj 150 MW
150.00
MW
115.00 MW 116.00 MW
Santahar 50MW
50.00
MW
0.00
MW 46.00
MW
Bogra GBB
22.00
MW
21.00
MW 21.00
MW
Barupukuria ST 1
100.00
MW
0.00
MW 0.00
MW
Barupukuria ST 2
100.00
MW
80.00
MW 77.00
MW
Bogra 20 MW
20.00
MW
13.00
MW 13.00
MW
Summit
Powser(Ullapara)
11.00
MW
8.00
MW 8.00
MW
Rangpur GT (HSD)
20.00
MW
0.00
MW 0.00
MW
Syedpur GT
20MW(HSD)
20.00
MW
0.00
MW 0.00
MW
Thakurgaon 47
MW((RZ)
47.00
MW
0.00
MW 11.00
MW
Total
9599.00 MW
4014.0
5609.0
MW
MW
0
0
Owner Name
Derated Capacity
(MW)
Day Peak
(MW)
Eve. Peak
(MW)
3502.00
1016.00
1682.00
SBU,PDB
223.00
167.00
217.00
EGCB
622.00
0.00
0.00
APSCL
684.00
365.00
420.00
IPP
1464.00
1015.00
1337.00
SIPP,PDB
110.00
85.00
70.00
0.00
0.00
SIPP,REB
215.00
150.00
146.00
Q.Rental 3
Years
100.00
81.00
96.00
QRPP(5yrs)
200.00
153.00
176.00
Other
800.00
118.00
225.00
RPP (3 Yrs.)
1061.00
570.00
746.00
QRPP (3 Yrs.)
416.00
151.00
346.00
169.00
143.00
148.00
Total
9599.00
4014.00
5609.00
MAXIMUM GENERATION:
Maximum
Maximum
Maximum
Maximum
Maximum
Maximum
Maximum
generation
generation
generation
generation
generation
generation
generation
in
in
in
in
in
in
in
2013
2012
2011
2010
2009
2008
2007
:
:
:
:
:
:
:
6675.00 MW as on 12/07/2013
6350.00 MW as on 04/08/2012
5174.00 MW as on 23/11/2011
4698.5 MW as on 20/08/2010
4296 MW as on 18/09/2009
4036.7 MW as on 19/09/2008
4130 MW as on 17/09/2007
YEAR
2009
(MW)
Public
Private
Q. Rental
356
2010
(MW)
2011
(MW)
2012
(MW)
2013
(MW)
TOTAL
(MW)
255
800
607
587
2249
270
125
44
795
250
838
300
1388
Total
356
775
1763
951
587
4432
2013
(MW)
2014
(MW)
2015
(MW)
2016
(MW)
2017
(MW)
2018
(MW)
(MW)
Public
662
604
1837
1510
00
1320
5933
Private
692
1366
638
1271
00
5064
Power
Import
500
Total
1854
1097
500
1970
2934
2138
1271
1320
11,497
FY
BPDB REB
TRANSMISSIO
DESC WZPDC DISTRIBUTI N &
DPDC
O
O
ON
DISTRIBUTIO
N
2012-13
11.95 13.89
9.07% 8.44% 11.38% 12.03%
%
%
14.36%
2011-12
12.15 13.99
9.87% 8.52% 11.66% 12.26%
%
%
14.61%
2010-11
14.73%
2009-10
15.73%
2008-09
16.85%
2007-08
18.45%
2006-07
20.25%
2005-06
21.25%
2004-05
22.79%
2003-04
24.49%
2002-03
21.64%
25.69%
2001-02
23.92%
27.97%
2000-01
25.34%
28.43%
26.09%
31.60%
3.0 RECOMMENDATION:
After observation all information we can say Government has taken large
initiatives to eradicate the energy crisis of Bangladesh. Firstly, in past years
government was not concerned in the issue of Electricity which has created a
huge gap between the demand and supply in this area. This Gap creates load
shedding in for many years. On the other hand demand of electricity has rise
up in apex due to Socio Economic growth. Here is some recommendation to
strengthen more efficiency in energy generation.
3.01 Perfect Estimation of future need:
Perfect Forecasting is the key element in removal of the deficit of electricity
supply. A perfect estimation of demand will provide a target to set the perfect
supply plans to meet future possible need.
3.02 Alternative Source of Energy:
We should look for different other sources like solar, nuclear and windmill plants
which will diversify the energy supply and minimizes the risk of energy supply.
3.03 Effective long term plan to meet future Demand:
At present Government is concentrating on present need and trying heart and
soul to meet the demand. But the demand of electricity will rise soon as our
country is not yet been covered with electricity supply. Quick rental can meet
the present need but it cannot be useful for long run. It also creates import
pressure for foal. We have to take long term plan to future demand.
3.04 Government should go to other country for electricity Generation:
For electricity production Government can go neighboring country where water
resources are unused. Countries like Nepal, Bhutan have huge opportunity to
produce electricity plants. Government can go for negotiation to other country
regarding this issue.
3.05 Making Corruption free sector:
To ensure the efficiency in this sector, there is no option of being corruption free
because corruption is main element to destroy the Government initiatives.
3.06 Removing the system loss:
System loss also makes hamper in total production of electricity. Efficient work
force and efficient machines can ensure removal of system loss.
about the method of mining coal makes the problem thorny. In addition,
the time that would be inevitably needed to exploit and to use the
plentiful coal deposit will create an unacceptable time-gap in solving
the power crisis with desirable speed.
It is pertinent to mention that theoretically, many of the strategic
documents and policy papers are sound and seems implementable, but
in reality, fails to do so because of poor implementation rate of
allocated money, corruption, lack of funds, poor monitoring and
evaluation and so on. The government needs to be creative in
renewing and revising strategic approaches to reduce the power crisis.
Therefore, provisions must be formulated for programme evaluation
and also for understanding the impacts of programmes. Findings are
needed to be scientifically utilized in developing suitable programmes
addressing the case reducing the crisis of electricity in Bangladesh.
Otherwise, the target of ensuring electricity to all by 2021 may
remain an elusive and a distant dream.
Page 69of 70
BIBLIOGRAPH
Y
Bangladesh Power Development Board (BPDB). 2010. Annual Report
2008-09. Dhaka, Bangladesh.
International Energy Agency (IEA). 2011. IEA Guide to Reporting Energy
RD & D Budget/Expenditure Statistics. 9 rue de la Federation, 75739
Paris Cedex 15, France.
Ministry of Finance. 2010, Towards Revamping Power and Energy
Sector: A Road Map, June
2010, Finance Division, Government of the Peoples
Republic of Bangladesh.
Ministry of Finance. 2011, Bangladesh Economic Review 2011, Dhaka:
Advisers Wing. Finance
Division, Government of the Peoples
Republic of Bangladesh.
Ministry of Finance. 2011, Power and Energy Sector Road Map: An
Update, June 2011, Finance
Division, Government of the Peoples
Republic of Bangladesh.
Ministry of Planning. 2011, Population & Housing Census, Preliminary
Results, July 2011, Dhaka: Bangladesh Bureau of Statistics (BBS),
Planning Division, Government of the Peoples Republic of Bangladesh.
Ministry of Planning. 2011, Statistical Pocket Book of Bangladesh 2010,
Dhaka: Bangladesh Bureau of Statistics (BBS), Planning Division,
Government of the Peoples Republic of Bangladesh.
Power Cell. 2006. Bangladesh Power Sector Data Bank. Dhaka,
Bangladesh. Retrieved from http://www.powercell.gov.bd/indexphp?
pageid=245
Shuvra, M. A., Rahman, M. M., Ali, A. and Khan, S. I. 2011.
Modelling and Forecasting Demand for Electricity in Bangladesh:
Econometrics Model. International Conference on Economics, Trade and
Development (IPEDR), Vol. 7, IACSIT Press, Singapore
Page 70of 70