Document
Course Tile
Date
CR Year
Lab Exercises
Backorder/Rescheduling/Factory Calendar
10/07/2013
2013
Pre requisites:
Ensure stock for material is available in the storage location.
Create a customer who is a prioritized customer for delivering goods.
Task 1:
Create a sales order for the normal customer & material. Ensure that the stock is
confirmed. Save the sales order.
Task2:
Create one more sales order for a priority customer & for the same material. Ensure
that the availability of the material is not confirmed. The confirmed delivery date is
set in future. Save the sales order.
Task 3:
Execute transaction V_RA (Back order processing). On the screen enter the Plant,
Material & Execute.
Task 4:
From the screen select the order for which the changes needs to be made & click on
change confirmation. Change the quantity & save.
Task 5:
From the screen select another order for which the changes needs to be made &
click on change confirmation. Change the quantity & Save.
Task 6:
Go to VA03 Display sales order & see whether the changes have been incorporated
in the sales orders where the back order processing has been executed. Check
whether the available to promise quantities have been updated.
Task 7: From the Easy access screen follow the path:
LogisticsSales & Distribution SalesBackordersReschedulingExecute
Page 1 of 2