Академический Документы
Профессиональный Документы
Культура Документы
Summary Report
Discussed at the RICS Measurement Conference 30 September 2004
Preface
Recent changes in procurement routes have reduced the requirement for measurement to be
carried out on behalf of the client before a contractor is appointed. The responsibility for
measurement is, therefore, passed down the supply chain.
The Construction Faculty commissioned this research into who measures construction work to
establish:
The results show the continued importance of measurement to the procurement process and
highlight:
There is no doubt that the proliferation of procurement practices will continue, but in the
circumstances where there is a degree of design certainty before the contractor is appointed,
measurement based procurement will still be appropriate. Furthermore where design
decisions are being passed down the supply chain, measurement should be undertaken at the
level that the design is carried out in order to remove the need for duplication.
It is in the interest of the industry as a whole, including its clients, that measurement is carried
out consistently and there is therefore a continued need for a standard method of
measurement and by implication, a continued need for measurement skills.
The slow take up of electronic communication of documents, which are in the vast majority of
cases available in digital form, is interesting and the Construction Faculty have commissioned
research into why this should be. However the move towards integrated communication
systems is inevitable and will make the principles of Coordinated Project Information (CPI), of
which the Standard Method of Measurement forms part, more not less important.
The Construction Faculty will be reviewing the Standard Method of Measurement and would
welcome any further comments.
I would like to thank Theresa Burrows of BCIS Ltd who carried out this research.
Phil Shearer
Executive Summary
Many respondents have taken the opportunity to voice their opinions on all aspects of
measurement. Whilst most seem to recognise that accurate measurement is important,
not everyone agrees that SMM7 is the best way of achieving this.
Consultants estimate that they prepare measurement for tendering purposes on 55%
of projects compared to 23% of projects for which contractors believe that they receive
measurement. Even allowing for the fact that these are subjective opinions, there
seems to be some discrepancy over what constitutes measurement.
The Construction Facultys Contracts in Use survey tends to support the contractors
views as it shows that between 20 and 25% of projects are let on contracts requiring
quantities. This may indicate that the questionnaires were more likely to be returned by
consultants that carried out some measurement than those that did not.
At 31%, contractors are nearly twice as likely as consultants (17%) to regularly amend
SMM7. Some respondents felt that measurement under SMM7 does not necessarily
focus on those factors which influence price.
There is a perception that SMM7 and, therefore the Common Arrangement for Work
Sections, do not represent trades in the industry.
Where BQs are not prepared, 95% of contractors are likely to undertake their own
measurement, 86% preparing measurement in-house and 8% employing a private
quantity surveyor to carry out measurement on their behalf.
Some feel that SMM7 is open to interpretation and therefore often subject to
misunderstanding. In any event, some contractors were particularly vociferous in their
criticisms of the consultant QSs interpretation of SMM7.
Where BQs are prepared, consultants measure mechanical and electrical services only
15% of the time.
The proposal for a standard method of Approximate (Builders) Quantities met with
widespread approval: 56% of consultants, 61% of local authorities and 64% of
contractors agreed with this proposal in principle.
Some consultants feel that SMM7 is complex and perhaps unnecessarily complicated.
They also feel that current fee levels often do not support or justify the production of full
BQs.
Digital transmission of tenders remains relatively low (less than 10%) and experience
of e-commerce among survey respondents is negligible. Approximately half of
consultants utilise one of a wide variety of software billing systems.
Commentary
Purpose
The aim of this research was to establish the current practice in measurement-based
procurement in the UK.
In order to achieve this, the following objectives were set:
to confirm how measurement is being carried out for what purpose and in what context
Respondents
This report has been based on the 'Measurement Based Procurement of Buildings' survey
issued in July 2002 by BCIS Ltd on behalf of the RICS Construction Faculty that was sent to
consultants, contractors and local authority clients. The response was as follows:
462 questionnaires were received from consultants (20% response rate); these returns
represent approximately 8,739 projects.
160 questionnaires were completed and returned by contractors (12% response rate)
representing 19,540 projects tendered.
The organisational profile of the consultants responses was not dissimilar to the typical
structure of UK quantity surveying practices. The majority of consultants responses
(76%) were received from practices employing five or less surveying staff.
4%
39%
55%
Use of SMM7
Survey results indicate that SMM7 is used as the basis for measurement on over 66% of all
projects. Specifically, where BQs are prepared, 77% of consultants stated that they use the
current method of measurement. Thirty-three percent of contractors stated that they use
SMM7 as the basis for measurement where tender BQs are not provided.
Seventeen percent of consultants and 15% of contractors regularly amend the standard
method and 31% of contractors reported that there were areas where SMM7 did not match
their estimating conventions.
Interestingly 4% of consultants and 7% of contractors stated that they continue to use SMM6
for the measurement of BQs. This suggests that SMM6 continues to be used as the primary
method of measurement on approximately 7% of all projects.
Other Method
4%
SMM6
4%
SMM7
77%
SMM7
33%
SMM6
7%
Other Method
31%
Local Authorities
Consultants
31%
64%
No
35%
61%
Yes
39%
56%
Electronic communication
Whilst it is likely that all BQs have been initially created in an electronic format, the incidence
of digitally submitted measurement for the purpose of inviting and evaluating tenders remains
low.
Consultants stated that only 29% of bills were provided to the contractor in digital form (13%
on disk or CD-Rom, 15% by e-mail and 1% via a website). This is at odds with the contractors
view, which is that only 16% of projects are bills sent electronically. This difference of
viewpoints may result from the practice of sending both hardcopy and digital formats or
making the digital versions available on request only.
Figure 5 Method of distributing bills
BQ sent digitally:
by email
15%
BQ sent digitally:
via website
1%
BQ sent digitally:
by disc or CD
13%
The perceptions also diverge when the question relates to the return of priced bills in digital
form, which consultants believe they receive on 6% of projects sent electronically while
contractors believe that they return 17% of projects in this way.
Despite the differences of opinion it is clear that only between 2% and 3% of tenders make the
round trip electronically.
Word-processing files or spreadsheets are the most common formats for sending bills. Only
10% of projects sent electronically are sent in Construction Industry Trading Electronically
(CITE) format while 4% are sent as ASCII text files.
Overall, 55% of contractors had received bills electronically. Where digital bills were made
available, contractors reported that on 13% of projects this information could not be imported
into their estimating systems.
When receiving bills electronically, 43% of contractors who expressed a preference, preferred
the information in spreadsheet format, while 38% would prefer it in CITE format. Wordprocessing was held to be a useful format by 32% of contractors but slightly more classed it as
unhelpful.
Only 3% of consultants and 4% of contractors had experience of e-commerce systems.
Design and build tender sum analysis
Bills of Quantities are submitted with the tender sum analyses on 35% of Design and Build
contracts. There is a higher use of non-standard methods of measurement in this area.
Thirty-three percent of the tender sum analyses are elemental.
Figure 6 Format of Contract Sum Analyses on D&B contracts
No method stated
8%
BQ in SMM7
22%
BQ in SMM6
2%
Elements
33%
BQ in other
format
11%
Non Standard
Elements
24%
Over 10% of consultants were opposed to any changes to SMM7. This contrasts with only
4% of contractors and 3% of clients who agreed on this point.
Nearly 10% of consultants suggested that the current standard method should either revert
to SMM6 or trade order or generally proposed overall simplification of SMM7.
Approximately 3.2% of clients and 5.7% of contractors would appear to agree with these
proposals.
Perception that SMM7 and, therefore, Common Arrangement for Work Sections
(CAWS), do not represent trades in the industry. Some respondents seemed to think
that SMM7 is organised by building elements.
SMM7 does not necessarily focus on those factors which influence price or the way
work is carried out.
SMM6 continues to attract a small but committed following due in part to its perceived
relevance to construction industry trades.
Some respondents noted the detrimental effect inadequate design information has on
the competitive tendering process.
Some consultants feel that SMM7 is complex and perhaps unnecessarily complicated.
Some also feel that current fee levels do not necessarily support or justify the
production of full BQs.
Changes ought not to be made by those who use it. When QS's adapt the document to their
own use they negate the reason for having a standard method. It's a little like learning a foreign
language, then deciding to speak your own version of it and then wondering why nobody
understands you. Contractor, Greater London [584]
SMM7 created many arguments by leaving it to the individual surveyor to decide effectively if
further rules were required. This gave rise to the need for increasing numbers of
revisions/classifications being required each time QS in Local Authority, Humberside [3795]
We price tenders for a whole spectrum of clients.. in most cases quality of both the drawn
information and specification leaves much to be desired. In a bid to retain market
competitiveness, it seems as though the quality of tender documentation sent out by
consultants is certainly suffering. This without doubt is driving up the cost of tenders; I
personally would like to see contracts tendered under the traditional process based on SMM7
with quantities. When in private practice, I found that the spread of tender figures was much
smaller when tendered in the above manner rather than plan and spec. Should we receive a BQ
in the office, it's such a long time since I've seen one, I think I would probably frame it rather
than price it. Contractor, East Midlands. [839]
Clarifications are needed to remove the ambiguities and inconsistencies. Feedback from
estimators informs us that SMM7 is not clear or fully understood. Consultant, North West
[3317]
Numerous Q/S practices have their own interpretation of the rules of SMM7. We can be
presented with totally different bill descriptions for the same item of work. Contractor, Scotland
[947]
We note your observations on the recent changes to the procurement of projects and the
increasing practice of passing the responsibility for measurement down the supply chain. Being
at the sharp end of this change we have to comment that we find this practice very difficult to
bear financially, and it appears to be QS driven rather than client driven in many cases. As a
consequence the obvious drawback to the enquiry as far as we are concerned is the nonrecovery of fees incurred for quantities during the tender process if we are not successful. We
are unable to generate a great deal of interest from our sub-contractors to price without
quantities and the client probably does not received the most competitive tender. The client
pays for this service at the end of the day as contractors usually include the cost in their tender
submissions. Let us get back to the tried and tested ways of procuring tendered projects on bills
with assistance of course of the latest technology and everyone would be happy..
Contractor, South East [999]
I would like to take the opportunity to state that a system of measurement based
procurement is in my opinion critical to the success of the construction industry in areas like
Argyll where small to medium local contractors depend heavily on good measurement practice
when pricing works for the vast majority of clients. It is of utmost importance that the ability to
produce accurate quantities is retained and strengthened if practices like my own are to provide
a high level of service to clients in remote areas like the West Highlands. I am strongly against
any move away from a robust standard method of measurement as in my opinion it will not be
in the best interest of our wide and varied client base Consultant, Scotland [2801]
More emphasis placed on need to highlight factors which influence price. Many of rules of
measurement are unclear in their coverage. Contractor, East Anglia [591]
TOTAL REVISION! It would be better just to give very basic quantities for the work involved with
each trade and let the contractors' Estimator assess associated items and labours etc that are
cost significant. SMM7 fails to identify many cost significant items Contractor, Wales [684]
Measurement is not of massive importance. However, a requirement to put more effort into
providing information in item descriptions would be helpful, particularly with elements like
foundations which cannot be see on a site visit. Contractor, Scotland [512]
PQ's often group work under headings where they don't understand the full content of work,
especially M and E. Contractor, Scotland [308]
I think there are a number of areas where the SMM7 is simply a way of measuring something,
rather than related to a practical method of building. I also think the way it groups large
elements together, for example a multitude of timber items grouped under P20 does not tell me
where they are, and therefore does not give me enough info to price adequately. Contractor,
East Midlands [698]
We believe the tendency of clients not to use BQs increases the industry costs by 2 to 2.5%.
Builders are tempted to shortcut the correct and prudent estimating processes. Tenders take
longer to prepare. Mistakes are more prevalent and the tendering process does not encourage
or identity value for money. Contractor, South West [86]
In all honesty SMM7 has to be viewed as a step backwards from SMM6. Therefore any
changes to SMM7 should represent a step towards the previously superior SMM6; but retaining
the elements of SMM7 that have proved to be beneficial. Contractor, Scotland [482]
Put it back in trades order. We send bills in tender sum analysis order for the pricing and resorted in trade order for the sub contract enquiries. Work group order is not used. Consultant,
South East [1799]
We would like bills to be prepared properly and adequately describe the work Supplemented by
Drawings, not Drawings replacing bill items. Contractor, Scotland [451]
In my time, not all that long really, I've seen SMM5, 6 and 7. Leave well alone!
Scotland [2396]
Architects should use NBS correctly placing materials in the right category so that the
appropriate SMM7 rules can be used for measurement
Consultant, Wales [1734]
SMM7 was designed for architects issuing detailed drawings for building. They invariably do
not; SMM7 is very difficult to follow even elementally. I find SMM6 more acceptable to
everyone.
Consultant, West Midlands [3390]
The standard information provided at pre-tender stage is worse than ever. The clauses in the
current SMM referring to providing preliminary or further information can never be completed.
Consultant, West Midlands [1447]
Consultant
No suggestion to change SMM7 but since it relies upon full working drawings being available at
tender stage which never happens these days. It is becoming increasingly difficult to make it
work as intended. Consultant East Midlands [2813]
Anything that simplifies it enabling less measurement to be undertaken and hence enhancing
fee income!! Consultant, South West [2834]
We find that producing BQ's for clients is becoming poor value for money and feel that the day
is fast approaching where standard methods of measurement are not required.
Consultant
Greater London [1968]]
Clients will not pay the fees for full bills of quantities. Consultant, Wales [2969]
I would suggest that if quantity surveyors try to NOT produce quantities in a manner that is
useful to other trades there will cease to be such a profession, and contract documents will end
up being produced by lawyers. Quantity surveyors have always had problems with justifying
their usefulness. I would suggest that the opinion of estimators who have to read their
documents be taken into account. Contractor, Scotland [397]
The SMM is dead. Killed off by foolish revisions and claims conscious contractors. Consultant,
Wales [2968]
I am surprised that the RICS is not more actively discouraging these changes in
procurement routes whereby these Quantity Surveying duties e.g. Bills of Quantities production,
is now being carried out by Contractors rather than the professional Quantity Surveyor. The
RICS should be promoting BQ production to clients as a way of saving money and obtaining
more competitive tenders. The pure Quantity Surveying profession would appear to be going
back to square one and the work is also being devalued at the same time! I shall be grateful for
the RICS's official stance on this. Consultant Greater London [2992]