Вы находитесь на странице: 1из 10

Ground Floor

Brick Work

Brick Work (4 1/2")

Cavity Wall

Volume (Cft)

100

Rate

Volume (Cft)

= 37.5

Area (sft)

Rate

Volume (Cft)

= 75

Mortar (Cft)

25

1:06

Mortar (Cft)

= 9.4

100

1:04

Mortar (Cft)

= 18.75

Dry Volume (Cft)

32.5

Dry Volume (Cft)

= 12.2

Dry Volume (Cft)

= 24.38

Plinth Protection

Area (sft)

Rate

100

1:04

C=1

210 Rs. /bag

C=1

210 Rs. /bag

C=1

210 Rs. /bag

S=6

5 Rs. /cft

S=4

5 Rs. /cft

S=4

5 Rs. /cft

Total = 7

Total = 5

1.5 Rs./No.

Cement

4.46 cft

Amount

3.71 bags

780.00

Sand

27.86 cft

139.00

Bricks

1350 Nos.

2,025.00

Total = 5

1.5 Rs./No.

Cement

2.44 cft

Amount

1.95 bags

410.00

Sand

9.75 cft

49.00

Bricks

506 Nos.

759.00

Area = 50'x3'

4.88 cft

18.75

31.00

Pcc (1:2:4) = 21.88

21.88

63.00

150.00

37.90

32.81

5.00

excavation = 150

150.00

1.00

filling = 250

250.00

4.00

brick work = 150


brick ballast = 32.81

1.6 Rs./No.

Cement

Pcc (1:4:8) = 18.75

Amount

3.90 bags

819.00

Sand

19.50 cft

98.00

Total =

Bricks

1013 Nos.

1,620.00

Area =
Rate / sft =

Amount / 100 cft=

2,944.00

Amount / 100 cft=

1,218.00

Amount / 100 cft=

2,537.00

Labour @ Rs. 6/cft=

600.00

Labour @ Rs. 4/cft=

400.00

Labour @ Rs. 8/cft=

800.00

Sub Total 1 =

6,488.00

Sub Total 1 =

2,836.00

Sub Total 1 =

5,874.00

Water charges @ 5%=

324.40

Water charges @ 5%=

141.80

Water charges @ 5%=

293.70

Scaffolding charges @ 5%=

324.40

Scaffolding charges @ 5%=

141.80

Scaffolding charges @ 5%=

293.70

Grand Total=

7,136.80

Grand Total=

3,119.60

Grand Total=

6,461.40

Grand Rs./ cft=

71.37

Grand Rs./ cft=

31.20

Grand Rs./ cft=

64.61

25.00

Marble Patti = 25

1.50

First Floor
Brick Work

Brick Work (4 1/2")

Cavity Wall

Volume (Cft)

100

Rate

Volume (Cft)

= 37.5

Area (sft)

Rate

Volume (Cft)

= 75

Mortar (Cft)

25

1:06

Mortar (Cft)

= 9.4

100

1:04

Mortar (Cft)

= 18.80

Dry Volume (Cft)

32.5

Dry Volume (Cft)

= 12.2

Dry Volume (Cft)

= 24.40

C=1

C=1

210 Rs. /bag

S=6
Cement

4.46 cft
3.71 bags

Amount

Cement

2.44 cft

Sand

27.86 cft

139.00

Bricks

1350 Nos.

2,025.00

1.95 bags

9.75 cft

49.00

Bricks

506 Nos.

759.00

Dry Volume (Cft)

= 11.00

4.88 cft

Amount

210 Rs. /bag


5 Rs. /cft

Total = 5

1.6 Rs./No.

Cement

2.19 cft

819.00

Sand

19.50 cft

98.00

Bricks

1013 Nos.

1,620.00

1:04

S=4

5 Rs. /cft

3.90 bags

Rate

100

C=1

1.6 Rs./No.

Cement

Area (sft)

8.40

1.76 bags

Amount
369.00

Sand

8.76 cft

44.00

Bricks

759 Nos.

1,139.00

Amount / 100 cft=

2,944.00

Amount / 100 cft=

12,218.00

Amount / 100 cft=

2,537.00

Amount / 100 cft=

1,551.00

700.00

Labour @ Rs. 5/cft=

500.00

Labour @ Rs. 9/cft=

900.00

Labour @ Rs. 7/cft=

394.00

Sub Total 1 =

3,644.00

Sub Total 1 =

1,718.00

Sub Total 1 =

3,437.00

Sub Total 1 =

1,945.00

Water charges @ 5%=

182.00

Water charges @ 5%=

86.00

Water charges @ 5%=

172.00

Water charges @ 5%=

97.00

Scaffolding charges @ 5%=

182.00

Scaffolding charges @ 5%=

86.00

Scaffolding charges @ 5%=

172.00

Scaffolding charges @ 5%=

97.00

Grand Total=

4,009.00

Grand Total=

1,889.00

Grand Total=

3,780.00

Grand Total=

2,140.00

Grand Rs./ cft=

40.09

Grand Rs./ cft=

18.89

Grand Rs./ cft=

37.80

Grand Rs./ cft=

21.40

Foundations

Mortar (cum)

1.54

C=1

Plinths Beams

Rate

Volume (cum)

.1:02:04

Mortar (cum)

1.54

C=1

210 Rs. /bag

Rate

Volume (cum)

.1:02:04

Mortar (cum)

1.54

C=1

210 Rs. /bag

Columns
Rate

Volume (cum)

.1:02:04

Mortar (cum)

1.54

C=1

210 Rs. /bag

Rate
.1:02:04
210 Rs. /bag

S=2

5 Rs. /cft

S=2

5 Rs. /cft

S=2

5 Rs. /cft

S=2

5 Rs. /cft

cr = 4

7 Rs./No.

cr = 4

7 Rs./No.

cr = 4

7 Rs./No.

cr = 4

7 Rs./No.

Total = 7

Total = 7

Cement

0.22 cum

Amount

Total = 7

Cement

0.22 cum

7.77 cft
6.22 bags

Sand

Crush

6.22 bags

Sand

Total = 7

Cement

0.22 cum

15.54 cft
Crush

31.08 cft

6.22 bags

Sand

Cement

0.22 cum

15.54 cft
Crush

31.08 cft

6.22 bags

Sand

1,305.00

0.44 cum
15.54 cft

78.00

Crush

0.88 cum

218.00

Amount

7.77 cft
1,305.00

0.44 cum

78.00

0.88 cum

218.00

Amount

7.77 cft
1,305.00

0.44 cum

78.00

0.88 cum
31.08 cft

Amount

7.77 cft
1,305.00

0.44 cum
15.54 cft

78.00

0.88 cum

218.00

31.08 cft

218.00

Amount / cum=

1,601.00

Amount / cum=

1,601.00

Amount / cum=

1,601.00

Amount / cum=

1,601.00

Labour @ Rs. 4/cft=

141.00

Labour @ Rs. 2/cft=

71.00

Labour @ Rs. 3/cft=

106.00

Labour @ Rs. 10cft=

424.00

Sub Total 1 =

1,742.00

Sub Total 1 =

1,671.00

Sub Total 1 =

1,707.00

Sub Total 1 =

2,025.00

Form Work @ 30% of ma. & lab. =

523.00

Form Work @ 5% of ma. & lab. =

84.00

Form Work @ 15% of ma. & lab. =

256.00

Form Work @ 30% of ma. & lab. =

607.00

Sub Total 1 =

2,265.00

Sub Total 1 =

1,755.00

Sub Total 1 =

1,963.00

Sub Total 1 =

2,632.00

Water charges @ 5%=

113.00

Water charges @ 5%=

88.00

Water charges @ 5%=

98.00

Water charges @ 5%=

132.00

Grand Total Rs. /cum =

2,378.00

Grand Total Rs. /cum =

1,843.00

Grand Total Rs. /cum =

2,061.00

Grand Total Rs. /cum =

2,764.00

Grand Total Rs./ cf t=

67.32

Grand Total Rs./ cf t=

52.17

Grand Total Rs./ cf t=

58.35

Grand Total Rs./ cf t=

78.24

Horizontal DPC
Area (sft)

= 100

Mortar (Cft)
Dry Volume (Cft)

Vertical DPC

Thickness

Ratio

Volume (sft)

= 100

= 16.67

.1:2:4

Mortar (Cft)

= 25.67

inch

Dry Volume (Cft)

Concrete PCC (1:4:8)

Thickness

Ratio

Volume (cum)

=1

= 6.25

0.75

1:04

Dry Volume (cum)

= 1.54

= 8.13

inch

Thickness
2

Terrazzo Topping
Ratio

Area (sft)

.1:2:4

Mortar (Cft)
Dry Volume (Cft)

C=1

210 Rs. /bag

= 100

Thickness

Ratio

= 6.25

0.75

1:02

= 9.63

inch

C=1

210 Rs. /bag

C=1

210 Rs. /bag

S=2

5 Rs. /cft

C=1

210 Rs. /bag

S=2

5 Rs. /cft

S=4

5 Rs. /cft

Cr=8

7 Rs./cft

Ch= 2

30 Rs. /cft

Cr=4

7 Rs./cft

Total = 7

Crush

Labour @ Rs. 7/cft=

Volume (cum)

Sand

= 56.30

Mortar (Cft)

210 Rs. /bag

410.00

Sand

Roof Slab

Cement

Amount

Volume (Cft)

1:04

Total = 5

1.5 Rs./No.

780.00

Rate

100

S=4

5 Rs. /cft

Total = 5

1.5 Rs./No.

Area (sft)

C=1

210 Rs. /bag

S=4

5 Rs. /cft

Total = 7

Honey Combed Wall

Total = 7
Cement

3.67 cft

Amount

Sand

Total = 13
1.63 cft

Amount

Cement

Total = 3
0.12 cumt

1.30 bags

273.00

4.18 cft

6.50 cft

33.00

3.35 bags

2.93 bags

616.00

7.33 cft

37.00

Amount / 100 cft=

150.00
456.00

306.00

Sand

Amount

7.30

Cement

Chips

3.21 cft

Amount

2.57 bags

539.00

6.42 cft

193.00

0.47 cum

Amount / 100 sft=

16.74 cft

Labour @ Rs. 8/cft=

800.00

Sub Total 1 =

1,532.00

732.00

103.00

Labour @ Rs. 1.50 /cft=

Amount / 100 cft=

755.00

Sub Total 1 =

Labour @ Rs. 2/cft=

200.00

Water charges @ 3%=

14.00

Sub Total 1 =

955.00

Sub Total 2 =

469.00

Amount / 100cum=

Water charges @ 1%=

10.00

Bitumen @ Rs. 1.50/sft =

150.00

Labour @ Rs. 2/cft=

70.00

Sub Total 2 =

965.00

Grand Total=

619.00

Sub Total 1 =

1,091.00

Grand Total=

1,697.00

Bitumen @ Rs. 1.50/sft =

150.00

Grand Total Rs./sft

6.19

Water charges @ 2%=

22.00

Grand Total Rs./sft

16.97

14.67 cft

Crush

84.00

0.95 cum
33.47 cft

234.00

Water charges @ 1%=

155.00

1,021.00

Sub Total 2 =

1,547.00

Polish @ Rs. 1.5 / sft =

150.00

Grand Total=

1,115.00

Rate Rs./sft

11.15

Grand Total=

1,113.00

Grand Total Rs./ cft =

31.52

PLASTER

PLASTER

PLASTER

PLASTER

Concrete Surfaces

Masonry Surface

Ceramic Tiles (Walls)

Terrazzo Skirting

Area (sft)

= 100

Thickness

Ratio

Area (sft)

= 100

Mortar (Cft)
Dry Volume (Cft)

= 4.17

0.5

1:04

Mortar (Cft)

= 5.42

inch

Dry Volume (Cft)

C=1

210 Rs. /bag

S=4

5 Rs. /cft

Total = 7

Thickness

Ratio

Area (sft)

= 100

= 6.25

0.75

1:05

Mortar (Cft)

= 8.13

inch

Dry Volume (Cft)

C=1

210 Rs. /bag

S=5

5 Rs. /cft

1.08 cft

Sand

Amount

0.87 bags

182.00

4.33 cft

22.00

Area (sft)

= 100

= 4.17

0.5

1:03

Mortar (Cft)

= 5.42

inch

Dry Volume (Cft)

S = 2.5

Cement

1.35 cft

Sand

Amount

1.08 bags

228.00

6.77 cft

34.00

Sand
Tiles

204.00

Amount / 100 sft=

162.00

Labour @ Rs. 2/sft=

180.00

Labour @ Rs. 1.5/sft=

Sub Total 1 =

384.00

Sub Total 1 =

Water charges @ 15%=

58.00

Grand Total=

441.00

1.55 cft

Amount

1.24 bags

260.00

3.87 cft

19.00

Ratio

= 4.17

0.5

1:02

= 6.42

inch
210 Rs. /bag

S=2

5 Rs. /cft

5 Rs. /cft

Total = 3

44 RS./ sft

Cement

Thickness

C=1

210 Rs. /bag

Total = 3.5

Amount / 100 sft=

Grand Total Rs./ sft =

Ratio

C=1

Total = 6

Cement

Thickness

44 RS./ sft

Cement

2.14 cft

Chips

Amount

1.71 bags

359.00

4.28 cft

128.00

110 sft

4,840.00

Amount / 100 sft=

150.00

Amount / 100 sft=

5,119.00

Labour @ Rs. 8/sft=

800.00

411.00

Labour @ Rs. 8/sft=

800.00

Sub Total 1 =

1,288.00

Water charges @ 10%=

41.00

Sub Total 1 =

5,919.00

Water charges @ 1%=

13.00

Grand Total=

452.00

Water charges @ 2%=

118.00

Sub Total 2 =

1,301.00

4.52

Grand Total=

6,038.00

Grand Total Rs./ sft =

4.41

Grand Total Rs./ sft =

Polish @ Rs. 1.5 / sft =

488.00

150.00

Grand Total=

1,451.00

Grand Total Rs./sft

14.51

60.38

Terrazzo Tiles Floor

PCC (1:2:4)

1/2" Levelling Curse

Terrazzo Tiles

Area (sft)

= 100

Thickness

Ratio

Area (sft)

= 100

Thickness

Ratio

Mortar (Cft)

= 12.5

1.5

1:02

Mortar (Cft)

= 4.2

0.5

1:03

= 19.25

inch

Dry Volume (Cft)

= 5.4

inch

Dry Volume (Cft)

S=3

5 Rs. /cft

Grinding

200

Plaster =

81

4.4

356.0

Total

2875

Rcc 1:2:4: =

11.32

63.0

713.0

Rate

= 28.75 sft

800.0

1.4 cft

Amount

1.1 bags

4.1 cft

228.00
20.00

28.00

Amount / 100 cum=

248.00

11.00 cft

77.00

Water charges @ 1%=

7.00

Grand Total=

255.00

567.00
6.00

Grand Total=

572.00

Sand

Grand Total Rs./ sft=

2.60

Area (sft)

= 100

Ratio

Area (sft)

= 100

= 6.25

0.75

1:02

Mortar (Cft)

= 9.63

inch

Dry Volume (Cft)

Mortar (Cft)

= 12.5

1:04

.1:2:4

Excavation =

52

Dry Volume (Cft)

= 19.25

0.75

1.25

(1:4:8) =

Volume (cft)

= 6.25

Pcc (1:2:4) =

Dry Volume (Cft)

= 8.13

37.9

943.0

C=1

210 Rs. /bag

Plaster =

57

4.4

251.0

S=2

5 Rs. /cft

Rcc 1:2:4: =

6.25

63.0

394.0

Cr = 4

7 Rs./cft

Cl Cover =

800.0

800.0

2.29 cft

44 Rs. /sft
Amount

1.83 bags

385.00

1.63 bags

341.00

3211.0

PCC Floor

4.58 cft

23.00

Area (sft)

= 100

Thickness

Ratio

4.69 cft

23.00

Mortar (Cft)

= 16.67

.1:2:4

Crush

9.17 cft

64.00

Dry Volume (Cft)

= 25.67

inch

110 sft

4,840.00

Amount / 100 cum=

Tiles

Labour @ Rs. 8/sft =

Cement

Sand
Crush

Sub Total 1 =

C=1

210 Rs. /bag

5,677.00

S=2

5 Rs. /cft

800.00

Cr = 4

7 Rs. /cft

2.29 cft

Amount

1.83 bags

385.00

Water charges @ 2%=

130.00

4.58 cft

23.00

Grand Total=

6,606.00

9.17 cft

64.00

6.00

Amount / 100 cum=

472.00

Sub Total 1 =

572.00

Water Charges @ 1% =

Water Charges @ 2% =

572.00

Grand Total =

477.00

572.00

Grand Total Rs. /sft =

4.70

Polish @ Rs. 1.5/sft

24.87

Sand (2)

Labour @ Rs. 8/sft

567.00

Brick Work =

Sand (1)

7 Rs. /cft

77.00

595.0

.1:2:4

Cr = 4

28.00

177.0

63.0

inch

Total = 7

6.42 cft

31.0

9.45

1.25

5 Rs. /cft

Amount / 100 cum=

5.71

= 16.04

210 Rs. /bag

462.00

52.0

= 10.42

S=2

Amount

Mortar

1.0

Cement (2)

C=1

3.21 cft

Manhole (Small)

Ratio

Ratio

5 Rs. /cft

2.57 bags

800.0
4453.0

Thickness

210 Rs. /bag

Total = 7

Cl Cover =

Mortar

Total = 7
Cement (1)

PCC (1:2:4)

33.75

Ceramic Tiles Floors

Rate Rs. /sft = 37.00

5.72

Thickness

Sub Total 2 =

1279.0

Total = 4

5.5 cft

Glass Stirp =

952.0

37.9

7 Rs./cft

Marble Chips

Chips

63.0

5 Rs. /cft

Terrazzo Floor

Cement

15.11

Brick Work =

Amount
462.00

C=1

272.0

Pcc (1:2:4) =

2.75 cft
2.20 bags

Ch = 2

80.0

31.0

175

Amount / 100 cum=

Dry Volume (Cft)

1.0

8.78

800 1.75 Rs. /sft

Water charges @ 1%=

Mortar (Cft)

80

(1:4:8) =

Cement

= 100

Excavation =

Total = 7

Area (sft)

8 Rs./ sft

Labour

S=2

Grand Total Rs./ sft=

16 Rs. /sft

Carriage

Cr = 4

Crush

100
1600

210 Rs. /bag

210 Rs. /bag

Sand

=
=

C=1

C=1

Cement

Area (sft)
Tiles

Manhole (Big)

5.00

Grand Total Rs./ sft=

Total = 7

6,477.00

66.06

Cement

3.67 cft

Amount

2.93 bags

616.00

Sand

7.33 cft

37.00

Crush

14.67 cft

103.00

Glass Strip =

Terrazzo Tiles

Application of 1/16" layerof cement =


Area (sft) =

100

16 Rs./sft

105.00
150.00

Pgment =

572.00

Tiles =

1600

8 Rs./sft

Amount /cum =

1,010.00

Grand Total =

572.00

Labour =

800

1.75 Rs./sft

Labour @ Rs. 6/sft =

600.00

Grand Total Rs. /sft =

572.00

Carriage =

175

Sub Total 1 =

1,610.00

Grinding =

200

Water Charges @ 2% =

32.00

Total =

2875

Grand Total =

1,643.00

Rate =

28.75

Grand Total Rs./sft =

1,643.00

ESTIMATION
(0.450) Total Steel in KG.
%age of Steel =
Total Concrete in CFT
1.5
1.5 % Steel =

Concrete Volume in Cft


X

490

100

2.2046

1.25
1.25 % Steel =

Concrete Volume in Cft


X

490

100

2.2046

100 CFT Contains =

Steel Weight in
Kgs

17.6 Bags of Cement


1

The Formula is =

100
X

1.54

100*1.54/(7*1.25)

1.25

For 100 Cft Brick Work

For 100 Cft CONCRETE


RATIO

CEMENT %

CRUSH

SAND

RATIO

SAND

CEMENT
(BAGS)

BRICKS

1:02:04

17.6 Bags

98

44

1:02

20

1350

1:03:06

13 Bags

92

46

1:03

22.5

1350

1:04:08

9 Bags

96

48

1:04

24

4.8

1350

1:05:10

7.8 Bags

98

49

1:05

25

1350

1:06:10

6.6 Bags

98

49

1:06

25.7

3.44

1350

1:07

26.5

1350

1:08

26.67

2.66

1350

PLASTER ( 1/2" THICK)

POINTING
RATIO

SAND

CEMENT
(BAGS)

BRICKS

Bags

1:02

1.8

0.72

Bags

0.73

Bags

1:03

0.54

Bags

0.66

Bags

0.53

Bags

RATIO

SAND

CEMENT

1:03

3.4

0.88

1:04

3.6

1:05
1:06
1:02

Steel Weight in
Kgs

17.6 Bags

Ground Floor
Brick Work

Brick Work (4 1/2")

Cavity Wall

Volume (Cft)

100

Rate

Volume (Cft)

= 37.5

Area (sft)

Rate

Volume (Cft)

= 75

Mortar (Cft)

25

1:06

Mortar (Cft)

= 9.4

100

1:04

Mortar (Cft)

= 18.75

Dry Volume (Cft)

32.5

Dry Volume (Cft)

= 12.2

Dry Volume (Cft)

= 24.38

Plinth Protection

Area (sft)

Rate

100

1:04

C=1

210 Rs. /bag

C=1

210 Rs. /bag

C=1

210 Rs. /bag

S=6

5 Rs. /cft

S=4

5 Rs. /cft

S=4

5 Rs. /cft

Total = 7

Total = 5

1.5 Rs./No.

Cement

4.46 cft

Amount

Cement

2.44 cft

3.71 bags

780.00

27.86 cft

139.00

1350 Nos.

2,025.00

Amount / 100 cft=

2,944.00

Amount / 100 cft=

Labour @ Rs. 6/cft=

600.00

Sub Total 1 =

6,488.00

Sand
Bricks

Total = 5

1.5 Rs./No.

Sand
Bricks

Amount

1.95 bags

410.00

9.75 cft

49.00

506 Nos.

759.00

Area = 50'x3'

4.88 cft

Sand
Bricks

18.75

31.00

Pcc (1:2:4) = 21.88

21.88

63.00

150.00

37.90

32.81

5.00

excavation = 150

150.00

1.00

filling = 250

250.00

4.00

brick work = 150


brick ballast = 32.81

1.6 Rs./No.

Cement

Pcc (1:4:8) = 18.75

Amount

3.90 bags

819.00

19.50 cft

98.00

25.00

Marble Patti = 25

1.50
Total =

1013 Nos.

1,620.00

Area =

1,218.00

Amount / 100 cft=

2,537.00

Rate / sft =

Labour @ Rs. 4/cft=

400.00

Labour @ Rs. 8/cft=

800.00

Sub Total 1 =

2,836.00

Sub Total 1 =

5,874.00
293.70

Water charges @ 5%=

324.40

Water charges @ 5%=

141.80

Water charges @ 5%=

Scaffolding charges @ 5%=

324.40

Scaffolding charges @ 5%=

141.80

Scaffolding charges @ 5%=

293.70

Grand Total=

7,136.80

Grand Total=

3,119.60

Grand Total=

6,461.40

Grand Rs./ cft=

71.37

Grand Rs./ cft=

31.20

Grand Rs./ cft=

64.61

First Floor
Brick Work

Brick Work (4 1/2")

Cavity Wall

Volume (Cft)

100

Rate

Volume (Cft)

= 37.5

Area (sft)

Rate

Volume (Cft)

= 75

Mortar (Cft)

25

1:06

Mortar (Cft)

= 9.4

100

1:04

Mortar (Cft)

= 18.80

Dry Volume (Cft)

32.5

Dry Volume (Cft)

= 12.2

Dry Volume (Cft)

= 24.40

Rate

Volume (Cft)

= 56.30

100

1:04

Mortar (Cft)

Dry Volume (Cft)

= 11.00

C=1

210 Rs. /bag

C=1

210 Rs. /bag

C=1

210 Rs. /bag

C=1

S=6

5 Rs. /cft

S=4

5 Rs. /cft

S=4

5 Rs. /cft

S=4

Total = 7
Cement

Honey Combed Wall

Area (sft)

Total = 5

1.5 Rs./No.
4.46 cft

Amount

3.71 bags

780.00

Sand

27.86 cft

139.00

Bricks

1350 Nos.

2,025.00

Cement

Total = 5

1.5 Rs./No.
2.44 cft

Amount

1.95 bags

410.00

Sand

9.75 cft

49.00

Bricks

506 Nos.

759.00

Cement

4.88 cft

Amount
819.00

Sand

19.50 cft

98.00

Bricks

1013 Nos.

1,620.00

Area (sft)

Rate

100

1:04

210 Rs. /bag


5 Rs. /cft

Total = 5

1.6 Rs./No.

3.90 bags

8.40

Cement

1.6 Rs./No.
2.19 cft
1.76 bags

Amount
369.00

Sand

8.76 cft

44.00

Bricks

759 Nos.

1,139.00

Amount / 100 cft=

2,944.00

Amount / 100 cft=

12,218.00

Amount / 100 cft=

2,537.00

Amount / 100 cft=

Labour @ Rs. 7/cft=

700.00

Labour @ Rs. 5/cft=

500.00

Labour @ Rs. 9/cft=

900.00

Labour @ Rs. 7/cft=

394.00

Sub Total 1 =

3,644.00

Sub Total 1 =

1,718.00

Sub Total 1 =

3,437.00

Sub Total 1 =

1,945.00
97.00

1,551.00

Water charges @ 5%=

182.00

Water charges @ 5%=

86.00

Water charges @ 5%=

172.00

Water charges @ 5%=

Scaffolding charges @ 5%=

182.00

Scaffolding charges @ 5%=

86.00

Scaffolding charges @ 5%=

172.00

Scaffolding charges @ 5%=

97.00

Grand Total=

4,009.00

Grand Total=

1,889.00

Grand Total=

3,780.00

Grand Total=

2,140.00

Grand Rs./ cft=

40.09

Grand Rs./ cft=

18.89

Grand Rs./ cft=

37.80

Grand Rs./ cft=

21.40

Roof Slab

Foundations

Plinths Beams

Columns

Volume (cum)

Rate

Volume (cum)

Rate

Volume (cum)

Rate

Volume (cum)

Rate

Mortar (cum)

1.54

.1:02:04

Mortar (cum)

1.54

.1:02:04

Mortar (cum)

1.54

.1:02:04

Mortar (cum)

1.54

.1:02:04

C=1

210 Rs. /bag

C=1

210 Rs. /bag

C=1

210 Rs. /bag

C=1

S=2

5 Rs. /cft

S=2

5 Rs. /cft

S=2

5 Rs. /cft

S=2

5 Rs. /cft

cr = 4

7 Rs./No.

cr = 4

7 Rs./No.

cr = 4

7 Rs./No.

cr = 4

7 Rs./No.

Total = 7

Total = 7

Cement

0.22 cum

Amount

Total = 7

Cement

0.22 cum

7.77 cft
6.22 bags

Sand

15.54 cft

1,305.00

31.08 cft

6.22 bags

Sand

15.54 cft
Crush

218.00

31.08 cft

Amount / cum=

Labour @ Rs. 4/cft=

141.00

Sub Total 1 =

1,742.00

Sub Total 1 =

523.00

6.22 bags

Sand

15.54 cft

78.00

Crush
218.00

31.08 cft

Labour @ Rs. 2/cft=

71.00

Sub Total 1 =

1,671.00

Form Work @ 5% of ma. & lab. =


Sub Total 1 =

Cement

0.22 cum

84.00

Amount

7.77 cft
1,305.00

6.22 bags

Sand

1,305.00

0.44 cum
15.54 cft

78.00

Crush

0.88 cum

Amount / cum=

2,265.00

Amount

0.44 cum

1,601.00

78.00

0.88 cum

218.00

31.08 cft

218.00

1,601.00

Amount / cum=

Labour @ Rs. 3/cft=

106.00

Labour @ Rs. 10cft=

424.00

Sub Total 1 =

1,707.00

Sub Total 1 =

2,025.00

Form Work @ 15% of ma. & lab. =


Sub Total 1 =

1,755.00

256.00

Form Work @ 30% of ma. & lab. =


Sub Total 1 =

1,963.00

1,601.00

607.00
2,632.00

Water charges @ 5%=

113.00

Water charges @ 5%=

88.00

Water charges @ 5%=

98.00

Water charges @ 5%=

132.00

Grand Total Rs. /cum =

2,378.00

Grand Total Rs. /cum =

1,843.00

Grand Total Rs. /cum =

2,061.00

Grand Total Rs. /cum =

2,764.00

Grand Total Rs./ cf t=

67.32

Grand Total Rs./ cf t=

52.17

Grand Total Rs./ cf t=

58.35

Grand Total Rs./ cf t=

78.24

Horizontal DPC

Vertical DPC

Area (sft)

= 100

Thickness

Ratio

Volume (sft)

Thickness

Mortar (Cft)

= 16.67

.1:2:4

Mortar (Cft)

= 6.25

0.75

Dry Volume (Cft)

= 25.67

inch

Dry Volume (Cft)

= 8.13

inch

= 100

Concrete PCC (1:4:8)


Ratio

Volume (cum)

=1

1:04

Dry Volume (cum)

= 1.54

Terrazzo Topping

Thickness

Ratio

Area (sft)

Thickness

Ratio

.1:2:4

Mortar (Cft)

= 6.25

0.75

1:02

Dry Volume (Cft)

= 9.63

inch

C=1

210 Rs. /bag

= 100

C=1

210 Rs. /bag

C=1

210 Rs. /bag

S=2

5 Rs. /cft

C=1

210 Rs. /bag

S=2

5 Rs. /cft

S=4

5 Rs. /cft

Cr=8

7 Rs./cft

Ch= 2

30 Rs. /cft

Cr=4

7 Rs./cft

Total = 7

Total = 7
Cement

1,305.00

0.88 cum

1,601.00

Form Work @ 30% of ma. & lab. =

0.22 cum
7.77 cft

0.44 cum

78.00

0.88 cum

Amount / cum=

Total = 7

Cement

7.77 cft

0.44 cum

Crush

Amount

210 Rs. /bag

Cement
3.67 cft

Amount

Sand

Total = 13
1.63 cft

Amount

Cement

Total = 3
0.12 cumt

1.30 bags

273.00

4.18 cft

6.50 cft

33.00

3.35 bags

Amount

Chips

3.21 cft

Amount

2.57 bags

539.00

6.42 cft

193.00

2.93 bags

616.00

Sand

7.33 cft

37.00

Amount / 100 cft=

306.00

Crush

14.67 cft

103.00

Labour @ Rs. 1.50 /cft=

150.00

Amount / 100 cft=

755.00

Sub Total 1 =

456.00

Labour @ Rs. 2/cft=

200.00

Water charges @ 3%=

14.00

Sub Total 1 =

955.00

Sub Total 2 =

469.00

Amount / 100cum=

Water charges @ 1%=

10.00

Bitumen @ Rs. 1.50/sft =

150.00

Labour @ Rs. 2/cft=

70.00

Sub Total 2 =

965.00

Grand Total=

619.00

Sub Total 1 =

1,091.00

Grand Total=

1,697.00

Bitumen @ Rs. 1.50/sft =

150.00

Grand Total Rs./sft

6.19

Water charges @ 2%=

22.00

Grand Total Rs./sft

16.97

Sand

Amount / 100 sft=

0.47 cum
16.74 cft

Crush

7.30

Cement

84.00

0.95 cum
33.47 cft

732.00

Labour @ Rs. 8/cft=

800.00

Sub Total 1 =

1,532.00

234.00

Water charges @ 1%=

155.00

1,021.00

Sub Total 2 =

1,547.00

Polish @ Rs. 1.5 / sft =

150.00

Grand Total=

1,115.00

Rate Rs./sft

11.15

Grand Total=
Grand Total Rs./ cft =

1,113.00
31.52

PLASTER

PLASTER

PLASTER

PLASTER

Concrete Surfaces

Masonry Surface

Ceramic Tiles (Walls)

Terrazzo Skirting

Area (sft)

= 100

Thickness

Ratio

Area (sft)

= 100

Thickness

Ratio

Area (sft)

= 100

Thickness

Ratio

Area (sft)

= 100

Thickness

Ratio

Mortar (Cft)

= 4.17

0.5

1:04

Mortar (Cft)

= 6.25

0.75

1:05

Mortar (Cft)

= 4.17

0.5

1:03

Mortar (Cft)

= 4.17

0.5

1:02

Dry Volume (Cft)

= 5.42

inch

Dry Volume (Cft)

= 8.13

inch

Dry Volume (Cft)

= 5.42

inch

Dry Volume (Cft)

= 6.42

inch

C=1

210 Rs. /bag

C=1

210 Rs. /bag

S=4

5 Rs. /cft

S=5

5 Rs. /cft

Total = 7
Cement

Sand

C=1
S = 2.5

Total = 6
1.08 cft

Amount

0.87 bags

182.00

4.33 cft

22.00

Cement

Sand

Total = 3.5
1.35 cft

Amount

1.08 bags

228.00

6.77 cft

34.00

Sand
Tiles

Amount / 100 sft=

204.00

Amount / 100 sft=

162.00

Labour @ Rs. 2/sft=

180.00

Labour @ Rs. 1.5/sft=

Sub Total 1 =

384.00

Sub Total 1 =

Water charges @ 15%=

58.00

Water charges @ 10%=

Grand Total=

441.00

Grand Total=

Grand Total Rs./ sft =

4.41

Cement

Grand Total Rs./ sft =

210 Rs. /bag

C=1

210 Rs. /bag

5 Rs. /cft

S=2

5 Rs. /cft

Total = 3

44 RS./ sft
1.55 cft

Amount

1.24 bags

260.00

3.87 cft

19.00

Cement

Chips

44 RS./ sft
2.14 cft

Amount

1.71 bags

359.00

4.28 cft

128.00

110 sft

4,840.00

Amount / 100 sft=

150.00

Amount / 100 sft=

5,119.00

Labour @ Rs. 8/sft=

800.00

411.00

Labour @ Rs. 8/sft=

800.00

Sub Total 1 =

1,288.00

41.00

Sub Total 1 =

5,919.00

Water charges @ 1%=

13.00

452.00

Water charges @ 2%=

118.00

Sub Total 2 =

1,301.00

Grand Total=

6,038.00

4.52

Grand Total Rs./ sft =

60.38

Polish @ Rs. 1.5 / sft =

488.00

150.00

Grand Total=

1,451.00

Grand Total Rs./sft

14.51

Terrazzo Tiles Floor

PCC (1:2:4)

1/2" Levelling Curse

Terrazzo Tiles

Area (sft)

= 100

Thickness

Ratio

Area (sft)

= 100

Thickness

Ratio

Mortar (Cft)

= 12.5

1.5

1:02

Mortar (Cft)

= 4.2

0.5

1:03

= 19.25

inch

Dry Volume (Cft)

= 5.4

inch

Dry Volume (Cft)

15.11

63.0

952.0

Brick Work =

33.75

37.9

1279.0

5 Rs. /cft

S=3

5 Rs. /cft

Grinding

200

Plaster =

81

4.4

356.0

7 Rs./cft

Total = 4

Total

2875

Rcc 1:2:4: =

11.32

63.0

713.0

Rate

= 28.75 sft

800.0

1.4 cft

Amount

1.1 bags

4.1 cft

5.5 cft

28.00

Amount / 100 cum=

248.00

11.00 cft

77.00

Water charges @ 1%=

7.00

Amount / 100 cum=

567.00

Grand Total=

255.00

Water charges @ 1%=

6.00

Grand Total=

572.00

Sand

Grand Total Rs./ sft=

2.60

Area (sft)

Marble Chips
Ratio

Area (sft)

1:02

Mortar (Cft)
Dry Volume (Cft)

0.75
inch

= 12.5

1:04

.1:2:4

Excavation =

52

1.0

52.0

= 19.25

0.75

1.25

(1:4:8) =

5.71

31.0

177.0

Volume (cft)

= 6.25

Pcc (1:2:4) =

9.45

63.0

595.0

Dry Volume (Cft)

= 8.13

Brick Work =

24.87

37.9

943.0

Plaster =

57

4.4

251.0

6.25

63.0

394.0

800.0

Chips

567.00

2.29 cft

44 Rs. /sft
Amount

1.83 bags

385.00

1.63 bags

341.00

800.0
3211.0

PCC Floor

23.00

Area (sft)

= 100

Thickness

Ratio

4.69 cft

23.00

Mortar (Cft)

= 16.67

.1:2:4

Crush

9.17 cft

64.00

Dry Volume (Cft)

= 25.67

inch

110 sft

4,840.00

C=1

210 Rs. /bag

Amount / 100 cum=

5,677.00

S=2

5 Rs. /cft

Labour @ Rs. 8/sft =

800.00

Cr = 4

7 Rs. /cft

Total = 7
Cement

Sand
Crush

Tiles

Sub Total 1 =

2.29 cft

Amount

1.83 bags

385.00

Water charges @ 2%=

130.00

4.58 cft

23.00

Grand Total=

6,606.00

9.17 cft

64.00
472.00

6.00

Amount / 100 cum=

Sub Total 1 =

572.00

Water Charges @ 1% =

Water Charges @ 2% =

572.00

Grand Total =

477.00

572.00

Grand Total Rs. /sft =

4.70

Polish @ Rs. 1.5/sft

Cl Cover =

4.58 cft

Labour @ Rs. 8/sft

Sub Total 2 =

7 Rs./cft

Sand (2)

7 Rs. /cft

Glass Stirp =

Cr = 4

Sand (1)

Cr = 4

77.00

Rcc 1:2:4: =

.1:2:4

5 Rs. /cft

28.00

5 Rs. /cft

inch
210 Rs. /bag

6.42 cft

S=2

1.25

S=2

Amount / 100 cum=

210 Rs. /bag

= 10.42

C=1

462.00

C=1

= 16.04

5 Rs. /cft

2.57 bags

Mortar

Cement (2)

210 Rs. /bag

Amount

Manhole (Small)

Ratio

C=1

3.21 cft

Ratio

Thickness

Ch = 2
Total = 7
Cement

= 100

Mortar

Dry Volume (Cft)

Total = 7
Cement (1)

PCC (1:2:4)

Thickness

= 100

800.0
4453.0

Mortar (Cft)

Rate Rs. /sft = 37.00

5.72

Cl Cover =

Ceramic Tiles Floors

Terrazzo Floor

= 6.25

272.0

Pcc (1:2:4) =

228.00
20.00

= 9.63

80.0

31.0

175

Amount
462.00

Dry Volume (Cft)

1.0

8.78

800 1.75 Rs. /sft

2.75 cft
2.20 bags

Mortar (Cft)

80

(1:4:8) =

Cement

= 100

Excavation =

Total = 7

Area (sft)

8 Rs./ sft

Labour

S=2

Grand Total Rs./ sft=

16 Rs. /sft

Carriage

Cr = 4

Crush

100
1600

210 Rs. /bag

210 Rs. /bag

Sand

=
=

C=1

C=1

Cement

Area (sft)
Tiles

Manhole (Big)

5.00

Grand Total Rs./ sft=

Total = 7

6,477.00

66.06

Cement

3.67 cft

Amount

2.93 bags

616.00

Sand

7.33 cft

37.00

Crush

14.67 cft

103.00

Glass Strip =

Terrazzo Tiles

Application of 1/16" layerof cement =


Area (sft) =

100

16 Rs./sft

105.00
150.00

Pgment =

572.00

Tiles =

1600

8 Rs./sft

Amount /cum =

Grand Total =

572.00

Labour =

800

1.75 Rs./sft

Labour @ Rs. 6/sft =

600.00

Grand Total Rs. /sft =

572.00

Carriage =

175

Sub Total 1 =

1,610.00

Grinding =

200

Water Charges @ 2% =

32.00

Total =

2875

Grand Total =

1,643.00

1,010.00

Rate =

28.75

Grand Total Rs./sft =

1,643.00

Вам также может понравиться