Chapter 3.

8 – System Development, Implementation, Management and


Applications

What is SSADM?

1. Structured Systems Analysis and Design Method is a set of standards developed in the early
1980s for systems analysis and application design widely used for government computing
projects in the United Kingdom.

2. SSADM uses a combination of text and diagrams throughout the whole life cycle of a system
design, from the initial design idea to the actual physical design of the application.

3. Unlike rapid application development, which conducts steps in parallel, SSADM builds each
step on the work that was prescribed in the previous step with no deviation from the model.
Because of the rigid structure of the methodology, SSADM is praised for its control over
projects and its ability to develop better quality systems.

What are the stages in SSADM?

SSADM application development projects are divided into five modules that are further broken
down into a hierarchy of stages, steps and tasks:

1. Feasibility study

The business area is analyzed to determine whether a system can cost effectively support the
business requirements.

2. Requirements analysis

The requirements of the system to be developed are identified and the current business
environment is modeled in terms of the processes carried out and the data structures involved.

3. Requirements specification

Detailed functional and non-functional requirements are identified and new techniques are
introduced to define the required processing and data structures.

4. Logical system specification

Technical systems options are produced and the logical design of update and enquiry processing
and system dialogues.

5. Physical design
2

A physical database design and a set of program specifications are created using the logical
system specification and technical system specification.

What are the advantages of using SSADM in designing a new system?

1. It is a standard approach to system analysis and design

2. User training is available in the methods used

3. It can be used for managing large scale software developing projects

4. It allows using teams on different tasks

5. It identifies precisely defined stages or modules

6. It enables standard documentation throughout

7. It enables a new manager to take over the project if necessary

8. It makes system maintenance easier

What are the graphical representations of system design that can be used to document a
system?

1. Data flow diagram (DFD)

2. Entity relationship diagram

3. Jackson structure diagram

What are the advantages of using DFDs?

1. It is a very useful design tool which models the system in terms of data, processes, data stores
and the sources from which the data input and output occurs

2. It clearly specifies the data communications in the system

3. It is easy to understand by users, analysts and programmers

What are the symbols used in DFDs?


3

Customer
External entity: This symbol represents the users or other systems which
put data to the system or get data out of the system

External entity duplicated in the DFD: The diagonal line shows that the
Customer symbol Customer, which is an
external entity occurs more than
once in the current DFD

1 Reception Process: This symbol represents data processing occur in the system such
as data validation, calculations, sorting data, merging data files
Data validation etc.

D1 Customer Details Data store: This symbol represents a data file or a database
table

Data store duplicated in the DFD: This symbol


M1 Customer Details
represents a data
store that occurs
more than once in
the current DFD

Data flow: This represents the transfer of a piece of data between


two processes or between a process and a data store or
between a process and an external entity

Advantages of employing a Team rather than an individual to carry out a Project

1. Can complete the task sooner by sharing the project tasks between team members

2. Can use specialist skills and talents of each team member for specific tasks

3. Reduce the problems arise when someone becomes ill or leaves the job

4. Easier to supervise the project

How can two or more members work together in a Software Development Project?

1. Programmers can be assigned to code different modules


4

2. One member can code while another member documents

3. One member can code while another member tests

4. One member can code while another member liaise with the client

5. All members can work together on agreed deadline

What are the Project Management Activities?

1. Planning the project

2. Analyzing tasks

3. Scheduling tasks

4. Identifying required resources

5. Allocating required resources

6. Identifying team members

7. Assigning tasks to team members

8. Team management

9. Gantt charting

10. Critical path analysis

11. Managing exceptional circumstances

What is a Gantt chart?


Summary 57 % complete
A Gantt chart is a graphical representation of the project schedule. It is a bar chart which shows
the duration of project tasks against the progression of time. Some Gantt charts show the
dependency
Task 1 or the relationship between the project tasks. It is a bar chart which shows the
75 % complete
proposed or actual progress of a project using horizontal bars. Gantt chart is a static time-
management chart useful for
Start-to-start the overall visualization of a project.
dependency

Gantt charts
Task 2 can be used to show current100
schedule status using percent-complete shadings and a
% complete
vertical "TODAY" line as shown here.
Finish-to-start dependency

Task 3 50 % complete

Finish-to-finish dependency

Task 4 0 % complete

TODAY

Week 1 2 3 4 5 6 7 8 9
5

Start-to-start dependency – Task 2 does not start before Task 1 is started

Finish-to-start dependency – Task 3 does not start before Task 2 is finished

Finish-to-finish dependency – Task 4 does not finish before Task 3 is finished

How Gantt charting is used for Project Management?

1. Used to identify project tasks

2. Helps to determine the length of each task

3. Helps to determine the order in which the project tasks are needed to be carried out

4. Helps to rearrange the project tasks or manage the dependencies between tasks

5. Helps to indicate or signal when resources are required

6. Helps to assess how long a project would take to complete

What information can be obtained from the Gantt chart?

1. Shows individual components of tasks

2. Shows earliest start times and latest end times

3. Shows relationships between components


6

4. Shows shortest time to finish the project

5. Shows percentage of tasks finished

Describe the features of a software tool that can be used to produce Gantt charts

1. Should include standard Gantt templates

2. Should be able to insert and edit duration of tasks

3. Should be able to identify parallel tasks automatically

4. Should be able to identify resource loads automatically

5. Should be able to superimpose and monitor project progress continually

What are the strengths of Gantt Charts?

1. Gantt chart shows whether the project is progressing on schedule.

2. Gantt charts are ideal for planning simple projects where there are not many tasks which
depend on each other.

What are the weaknesses of Gantt Charts?

1. Gantt charts are not sufficient for analyzing and monitoring the progress of complex projects
where many tasks depend on each other.

2. Gantt charts are not sufficient for analyzing projects where some tasks are dynamic in nature
(those tasks which may get delayed or change in their demand for resources).

What is a PERT (Project Evaluation and Review Technique)?

PERT is a method of analyzing the tasks involved in completing a given project, especially the
time needed to complete each task, and identifying the minimum time needed to complete the
total project.

What is Critical Path?

Critical path is the sequence of project network activities taken from the initial event to the
terminal event, which adds up to the longest overall duration. It determines the total calendar time
required for the project; and, therefore, any time delays along the critical path will delay the
reaching of the terminal event by at least the same amount.

What is a Network Diagram?


7

Complex projects require a series of activities, some of which must be performed sequentially
and others that can be performed in parallel with other tasks. This collection of sequential and
parallel activities can be modeled by a network diagram.
In a project, an activity is a task that must be performed and an event is a milestone marking the
completion of one or more activities. Before an activity can begin, all of its predecessor activities
must be completed. Project network diagrams represent activities by arc and milestones by nodes.

Example of a PERT Chart

4
0
t = 1wk t = 3wk
C F

t = 3wk t = 2wk
1 2 5
0 A 0 D 0

B E
t = 4wk t = 2wk
3
0

The milestones generally are numbered so that the ending node of an activity has a higher number
than the beginning node. Incrementing the numbers by 10 allows for new ones to be inserted
without modifying the numbering of the entire diagram. The activities in the above diagram are
labeled with letters along with the expected time required to complete the activity.

What information can be obtained from the PERT chart?

1. Different paths or tasks of the project are represented by different lines of different value

2. Direction of arrows shows the necessary order of completion

3. Longest journey along arrows shows shortest time for completion of the project

4. Resources can be allocated

5. Critical path can be found

6. Changes to the project can be implemented easily

7. “What If” analysis can be done

8. Gives duration of the project

Describe the features of a software tool that can be used to produce PERT charts
8

1. Should represent different tasks or paths by different lines

2. Should represent the order of completion of tasks by arrows pointing at different directions

3. Should contain tools to figure out the critical path

4. Should be able to identify deadlines and bottlenecks

What are the benefits of PERT

• Provides expected project completion time


• Provides the probability of completion before a specified date
• Shows the critical path activities that directly impact the completion time
• Indicates the activities that have slack time and that can lend resources to critical
path activities
• Indicates activity start and end dates

What are the weaknesses of PERT

1. The activity time estimates are somewhat subjective and guessed.

2. In other cases, if the person or group performing the task estimates the time, there may be bias
in the estimate.

Training requirements necessary to successfully implement a computerized system?

1. All the staff members must be trained relevant to their work

2. Many staff members may find the new system difficult to learn

3. Type of training provided:

(a) Training provided by the trainer


This restricts training times, can be intimidating, difficult to satisfy all the demands, needs
human contact for help

(b) Software based training


Can learn at times when the user is free, individual training eliminates intimidation, allows
for practice, allows repetition, the user can learn at his own pace

4. Age factor has to be considered


Young users may have preconceptions whereas older users may have worries about their
Abilities

5. Customers have to learn new procedures and may have problems in learning how to use the
new system
9

6. Upgrade of software and hardware makes training needs to be repeated

Advantages of providing computer based individual learning sessions rather than arranging
courses for the employees

1. Employees can get trained by taking their own time

2. Employees can get trained at their own speed

3. Employees can use virtual systems to learn

4. Training can be done outside working hours

5. Employees can learn on additional areas in order to advance their knowledge

6. Training programs can be individually tailored

7. Testing can be revisited as often as necessary

8. Employees can revisit testing areas as needed

9. Testing can be tailored automatically according to test results

10. Test results can be reported to the management through the system

11. Workers are not intimated by being in a group

What is technical documentation?

This documentation describes anything that will be helpful for a technician to maintain the
system. Therefore it is also known as the system maintenance document.

Technical documentation contains:

(a) System design specifications and

(b) Program specifications

What is user documentation?

This documentation describes the things that would be helpful for a person who will be using or
operating the system.

Why technical documentation is necessary?

Because a technician can alter the system or correct the system when necessary
10

Why user documentation is necessary?

It provides instructions for users about how to use the system and what to do when something
goes wrong

What are the items to be included in the user manual?

1. Details of how to enter data

2. Details of how to use the system illustrated with screen shots

3. Help facilities and frequently asked questions

4. Troubleshooting guide for errors

What are the items to be included in the technical manual?

1. Details of installation and start up procedure

2. Minimum system specifications of the computer on which the software is to run

3. Algorithms

4. Database design

Testing and implementation planning

When implementing the new system, the analyst

1. Must ensure that the correct hardware is available

2. Must train the staff to use the new system

3. Must input the data to the data files, either manually or by importing them from the original
System

Describe the four system implementation (changeover) methods

1. Parallel running

The old and new systems are run side by side until it is made sure that the new system is fault
free. This method of implementation is adopted where a system failure is not affordable.

The advantages of this method are that


11

(a) The results of the two systems can be compared to ensure that there is no fault with the
new system

(b) The staff training on the new system can be carried out effectively

The disadvantage of this method is that it is very expensive as the things have to be done twice.

Examples of systems which are ideal for implementing with parallel running are:
Exam marks processing system

2. Pilot running

The new system is implemented initially only in a certain part of the company such as a
branch. The advantages of this method are that

(a) If there is a fault in the new system, it would affect the organization only in a relatively
small area of data processing.

(b) It allows the analyst to test how the system would perform with a smaller amount of data.

The disadvantage of this method is that it is not possible to check how the system would
perform with a large amount of data, which is the actual case when it is implemented at the
organization level.

3. Phased implementation

The system is implemented by replacing the parts of the old system gradually with the
corresponding parts of the new system while the rest of the system is still running with the old
system.

The advantages of this method are:

(a) Can repair a faulty module without affecting the other modules

(b) It allows staff to be trained gradually

The disadvantage of this method is that one or many part(s) of the old system and the part that
has been computerized may not be compatible. It would also take relatively a long time to fully
implement the new solution.
Examples of systems which are ideal for phased implementation are:

Example 1: Process control system of a chemical plant

1. One phase can be the computerization of the mixing of raw materials, monitoring and
controlling the conditions such as the temperature and pressure involved with one reaction

2. Another phase can be the computerization of the packing process of the final product

Example 2: ATM machine system


12

1. One phase can be the development of the withdrawing process of money

2. Another phase can be the development of the depositing process of money

Example 3: Computerized ticketing machine system

1. One phase can be the issuing of the printed ticket and returning the balance money only
when the coins are put into a till.

2. Another phase can be the capability of using a magnetic swipe card or smart card to pay the
bus fare

Example 4: Point of sale system

1. One phase can be the capability of using the barcode scanner as the device to input the
product ID

2. Another phase can be the capability of using magnetic swipe card or smart card facility to
pay the bill by a credit card or a debit card

Example 5: Pay phone system

1. One phase can be the capability of taking a call by inserting coins or bills to the system

2. Another phase can be the capability of using a prepaid phone card to pay and take the call

Example 6: Proximity card system

1. One phase can be the capability of taking a call by inserting coins or bills to the system

2. Another phase can be the capability of using a prepaid phone card to pay and take the call

4. Direct Conversion or “big bang”

The new system replaces the old system immediately and completely.

The advantages are that

(a) The cost of implementation is less.

(b) No confusion to the staff

The disadvantage is that it is risky. If the new system has a fault and malfunctions there will be
a loss of data and even the loss of customers. Allows no time for training and finding errors in
the system.

Explain what implementation method is suitable for a new POS system developed for a
supermarket
13

Parallel running is not feasible as customers would not put up with the delays

Pilot running can be done by implementing the new system only in some of the checkout
counters. It would cause no problems even if it fails because the customers can be moved to other
counters which run the old system. Also it is ideal for training the cashiers to the new system.

Direct conversion is risky because if the new system fails all the counters have to be closed which
means that the store must be shut down.

System maintenance and the software lifespan

The three kinds of system maintenance and the reasons for the system maintenance are:

1. Corrective maintenance

This kind of maintenance is performed to correct bugs found in the system after the system has
been commissioned.

2. Adaptive maintenance

This kind of maintenance is performed to make changes in the system because of the changes
that have taken place in way that the organization works (for example due to the changes in tax
rates, due to the changes in law etc.)

3. Perfective maintenance

This kind of maintenance is performed to improve the performance of the system.