LIMET, Arielle U.
MAGALONG, Valerie Angel V.
A. Rationale
One of the citys major problems is vehicular traffic. As Baguio Citys
population continue to increase, its demand for public transportation also grows.
According to Philippine Statistics Authority, Baguio Citys population is now at
345,000 people, and its growth rate at 2.36. Saint Louis University, as one of the
biggest universities in Baguio City, consists of 25,000 students and employees, who
uses public transportation in order to come to school. It is located at Magsaysay Road,
one of the major roads at the central business district of Baguio City. This project aims
to reduce traffic along Magsaysay Road, and to improve circulation at the universitys
premises.
A. Proposal Properties
Drop-offs are constructed adjacent to roads, and functions as a station for
vehicles to drop-off or pick-up its passengers. Usually covered to protect it from direct
sunlight and strong rainfall, and directly connected to a public or private property. The
proposed drop-off will be constructed at the former bleacher area of the P.E Building,
just before the roundabout connecting Rimando Road and New Lucban Road. The
Drop-off will occupy 200 square meters, with two lanes, for drop-off and pick-up
stations. The proposed project will be constructed in a span of 3 months, under the
supervision of the Department of Public Works and Highways. It will occupy a part of
Saint Louis Universitys property, but the project will not only benefit the students and
employees of the university, but will also reduce vehicular traffic occurring along
Magsaysay and Bonifacio Road.
B. Objectives
This project seeks to attain the following:
1. Reduce traffic occurring along Magsaysay Bonifacio Road, as Aurora HillBaguio Plaza PUVs occupy one lane at Magsaysay Road in dropping off
and picking up commuters, affecting vehicular circulation. Magsaysay
Road has 4 active lanes, with different vehicles going to Rimando,
Bonifacio, and New Lucban are affected by the traffic.
2. Help the students going to Aurora Hill, Trancoville, Ambiong, and
Honeymoon Road, for they will have a direct access to the station, being
constructed just inside the schools property.
3. Create a station for private vehicles when dropping-off students and
employees, and not contribute to the traffic.
4. Help non-students and non-employees attending the mass at the new
cathedral of Saint Louis University every Sunday and its weekday mass.
C. Significance
This project will not only benefit students and employees, but will also help
in reducing the traffic occurring along Magsaysay Road. Being located at the
center of Magsaysay, New Lucban, and Rimando Road, it will have a major
effect in the vehicular circulation along the three roads.
1. Students and employees will have direct access to the station, so they
wont have to wait for PUVs in other areas, improving circulation inside the
university.
2. PUV drivers will not have to stop along Magsaysay Road, helping reduce
the traffic and not halt other vehicles from going forward.
3. Taxi drivers will also benefit from this project, for they will now have a
known station in picking up possible passengers.
4. Civilians residing in New Lucban, T. Alonzo, and Honeymoon, and other
near barangays will have a known station to wait for PUVs.
D. Schedule of Activities
Construction will be during the schools short term, June July 2017.
Activities
Duration / Schedule
June 1 June 3
Canvassing of Materials
June 4 June 5
Construction of Drop-off
June 6 June 20
Construction of Shed
June 20 June 27
June 28 July 1
E. Budget
Material
Quantity (Unit)
Price (Php/Unit)
Cost (Php)
Professional Fee
Architect
2000 / drawing
20,000.00
Engineer
5000 / visit
50,000.00
Supervisor
1000 / day
30,000.00
Manpower
10
450 / day
135,000.00
Concrete
150 Bags
200 / bag
30,000.00
Hollow Blocks
300 Blocks
50 / block
15,000.00
Aggregates
1 ton
10,000 / 200 kg
50,000
Reinforced Steel
100 Rebars
100 / rebar
10,000.00
Paint
10 Gallons
500 / gallon
5,000.00
Lighting Equipment
1000 / day
24,000.00
Construction
3000 / day
72,000.00
5000 / day
25,000
Total Cost of
466,000.00
Materials
Construction
Vehicles
Project