Академический Документы
Профессиональный Документы
Культура Документы
NAME OF PROJECT
LOCATION
MONTHS
PHASE 1
DRAWINGS
BASEMENT 2
EXCAVATION
WATER PROOFING
RCC RAFT
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
BASEMENT 1
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
GROUND FLOOR
RCC COL
RCC ROOF
APRIL
MARCH
FEBRUARY
2017
JANUARY
DECEMBER
NOVEMBER
OCTOBER
SEPTEMBER
AUGUST
JULY
JUNE
MAY
APRIL
2016
MARCH
JANUARY
DECEMBER
NOVEMBER
OCTOBER
SEPTEMBER
AUGUST
SR. NO.
JULY
DISCRIPTION OF ITEMS
MAY
LEVEL
JUNE
2015
FEBRUARY
WORK PROGRAME
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
FIRST FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
THIRD FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
PLUMBING WORK
FIRE FIGHTING WORK
HVAC WORK
MISS FINISHING WORKS
PHASE 2
DRAWINGS
BASEMENT 2
EXCAVATION
WATER PROOFING
RCC RAFT
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
BASEMENT 1
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
GROUND FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
FIRST FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
SECOUND FLOOR RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
THIRD FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
PLUMBING WORK
BOUNDRY WALL GUARD ROOM
SOLAR SYSTEM
LANDSCAPE
LIFT INSTALLATION
ERRECTION OF GRANITE SCULPTURE
FIRE FIGHTING WORK
HVAC WORK
NAME OF PROJECT
LOCATION
LEVEL
DISCRIPTION OF ITEMS
SR.
MONTHS
PHASE 1
DRAWINGS
BASEMENT 2
EXCAVATION
WATER PROOFING
RCC RAFT
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
BASEMENT 1
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
GROUND FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
FIRST FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
SECOUND FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
THIRD FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
PLUMBING WORK
FIRE FIGHTING WORK
HVAC WORK
MISS FINISHING WORKS
PHASE 2
DRAWINGS
BASEMENT 2
EXCAVATION
WATER PROOFING
RCC RAFT
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
BASEMENT 1
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
GROUND FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
FIRST FLOOR
RCC COL
RCC ROOF
BRICK WORK
5
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
SECOUND FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
THIRD FLOOR
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
PLUMBING WORK
BOUNDRY WALL GUARD ROOM
SOLAR SYSTEM
LANDSCAPE
LIFT INSTALLATION
ERRECTION OF GRANITE SCULPTURE
FIRE FIGHTING WORK
HVAC WORK
WORK PROGRAME
MONTHS
WATER PROOFING
RCC RAFT
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
PHASE 2
DRAWINGS
EXCAVATION
WATER PROOFING
RCC RAFT
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
DOOR WINDOW FRAME FIXING
PLASTERING
FLOORING
TILING WORK
PRE COAT OF PAINTING
SANITARY FIXTURE FIXING
ELECTRICAL FIXTURE FIXING
CULPTURE
FIRE FIGHTING WORK
HVAC WORK
May-15
8
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Jun-15
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Jul-15
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
10
Aug-15
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
10
11
Sep-15
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
O
28
29
30
31
10
11
12
Oct-15
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Nov
29
30
31
10
11
12
13
Nov-15
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Dec-1
30
31
Dec-15
Jan-16
Jan-16
Feb-16
Feb-16
Mar-16
r-16
Apr-16
16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
Jan-17
Feb-17
Ma
Mar-17
Apr-1
Apr-17
LEVEL
DISCRIPTION OF ITEMS
SR. NO.
PHASE 1
BASEMENT 2
BASEMENT 2
BASEMENT 2
BASEMENT 2
BASEMENT 2
BASEMENT 2
BASEMENT 2
BASEMENT 2
BASEMENT 2
BASEMENT 2
BASEMENT 1
RCC WALL
BASEMENT 1
RCC COL
BASEMENT 1
RCC ROOF
BASEMENT 1
BRICK WORK
BASEMENT 1
ELECTRICAL CONDUIT
BASEMENT 1
PLASTERING
BASEMENT 1
FLOORING
GROUND FLOOR
RCC COL
GROUND FLOOR
RCC ROOF
GROUND FLOOR
BRICK WORK
GROUND FLOOR
ELECTRICAL CONDUIT
GROUND FLOOR
GROUND FLOOR
PLASTERING
GROUND FLOOR
FLOORING
GROUND FLOOR
TILING WORK
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
ELECTRICAL FIXTURE
FIRST FLOOR
RCC COL
FIRST FLOOR
RCC ROOF
FIRST FLOOR
BRICK WORK
FIRST FLOOR
ELECTRICAL CONDUIT
FIRST FLOOR
FIRST FLOOR
PLASTERING
FIRST FLOOR
FLOORING
FIRST FLOOR
TILING WORK
FIRST FLOOR
FIRST FLOOR
FIRST FLOOR
ELECTRICAL FIXTURE
SECOUND FLOOR
RCC COL
SECOUND FLOOR
RCC ROOF
SECOUND FLOOR
BRICK WORK
SECOUND FLOOR
ELECTRICAL CONDUIT
SECOUND FLOOR
SECOUND FLOOR
PLASTERING
SECOUND FLOOR
FLOORING
SECOUND FLOOR
TILING WORK
SECOUND FLOOR
SECOUND FLOOR
SECOUND FLOOR
ELECTRICAL FIXTURE
THIRD FLOOR
RCC COL
THIRD FLOOR
RCC ROOF
THIRD FLOOR
BRICK WORK
THIRD FLOOR
ELECTRICAL CONDUIT
THIRD FLOOR
THIRD FLOOR
PLASTERING
THIRD FLOOR
FLOORING
THIRD FLOOR
TILING WORK
THIRD FLOOR
THIRD FLOOR
THIRD FLOOR
ELECTRICAL FIXTURE
ALL FLOORS
ALL FLOORS
ALL FLOORS
ALL FLOORS
PHASE 2
DRAWINGS
BASEMENT 2
EXCAVATION
BASEMENT 2
WATER PROOFING
BASEMENT 2
RCC RAFT
BASEMENT 2
RCC WALL
BASEMENT 2
RCC COL
BASEMENT 2
RCC ROOF
BASEMENT 2
BRICK WORK
BASEMENT 2
ELECTRICAL CONDUIT
BASEMENT 2
PLASTERING
BASEMENT 2
FLOORING
BASEMENT 1
RCC WALL
BASEMENT 1
RCC COL
BASEMENT 1
RCC ROOF
BASEMENT 1
BRICK WORK
BASEMENT 1
ELECTRICAL CONDUIT
BASEMENT 1
PLASTERING
BASEMENT 1
FLOORING
GROUND FLOOR
RCC COL
GROUND FLOOR
RCC ROOF
GROUND FLOOR
BRICK WORK
GROUND FLOOR
ELECTRICAL CONDUIT
GROUND FLOOR
GROUND FLOOR
PLASTERING
GROUND FLOOR
FLOORING
GROUND FLOOR
TILING WORK
GROUND FLOOR
GROUND FLOOR
GROUND FLOOR
ELECTRICAL FIXTURE
FIRST FLOOR
RCC COL
FIRST FLOOR
RCC ROOF
FIRST FLOOR
BRICK WORK
FIRST FLOOR
ELECTRICAL CONDUIT
FIRST FLOOR
FIRST FLOOR
PLASTERING
FIRST FLOOR
FLOORING
FIRST FLOOR
TILING WORK
FIRST FLOOR
FIRST FLOOR
FIRST FLOOR
ELECTRICAL FIXTURE
SECOUND FLOOR
RCC COL
SECOUND FLOOR
RCC ROOF
SECOUND FLOOR
BRICK WORK
SECOUND FLOOR
ELECTRICAL CONDUIT
SECOUND FLOOR
SECOUND FLOOR
PLASTERING
SECOUND FLOOR
FLOORING
SECOUND FLOOR
TILING WORK
SECOUND FLOOR
SECOUND FLOOR
SECOUND FLOOR
ELECTRICAL FIXTURE
THIRD FLOOR
RCC COL
THIRD FLOOR
RCC ROOF
THIRD FLOOR
BRICK WORK
THIRD FLOOR
ELECTRICAL CONDUIT
THIRD FLOOR
THIRD FLOOR
PLASTERING
THIRD FLOOR
FLOORING
THIRD FLOOR
TILING WORK
THIRD FLOOR
THIRD FLOOR
THIRD FLOOR
ELECTRICAL FIXTURE
ALL FLOORS
ALL FLOORS
ALL FLOORS
ALL FLOORS
ALL FLOORS
ALL FLOORS
ALL FLOORS
ALL FLOORS
START DATE
END DATE
DRAWINGS
5/1/2015
7/31/2015
EXCAVATION
7/1/2015
31/08/2015
WATER PROOFING
7/1/2015
8/31/2015
RCC RAFT
7/1/2015
8/31/2015
RCC WALL
7/1/2015
8/31/2015
RCC COL
7/1/2015
8/31/2015
RCC ROOF
9/1/2015
10/2/2015
HVAC
WORK
9/1/2015
12/3/2015
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
RCC WALL
RCC COL
RCC ROOF
BRICK WORK
ELECTRICAL CONDUITING
PLASTERING
FLOORING
11/3/2015
12/3/2015
11/3/2015
1/3/2016
11/3/2015
1/3/2016
10/3/2015
11/2/2015
10/3/2015
11/2/2015
LIFT INSTALLATION
LANDSCAPE
11/3/2015
SOLAR12/5/2015
SYSTEM
12/4/2015
3/6/2016
2/4/2016
3/6/2016
1/5/2016
4/5/2016
PLUMBING WORK
2/4/2016
4/5/2016
RCC COL
11/3/2015
12/3/2015
RCC ROOF
12/4/2015
1/4/2016
BRICK WORK
1/5/2016
3/5/2016
ELECTRICAL CONDUITING
2/4/2016
3/5/2016
2/4/2016
4/5/2016
PLASTERING
2/4/2016
4/5/2016
FLOORING
3/6/2016
5/6/2016
TILING WORK
2/4/2016
4/5/2016
4/6/2016
6/7/2016
10/9/2016
11/8/2016
10/9/2016
11/8/2016
RCC COL
1/4/2016
2/3/2016
RCC ROOF
2/4/2016
3/5/2016
BRICK WORK
3/6/2016
5/6/2016
ELECTRICAL CONDUITING
4/6/2016
5/6/2016
4/6/2016
6/6/2016
PLASTERING
4/6/2016
6/6/2016
FLOORING
5/7/2016
7/7/2016
TILING WORK
4/6/2016
6/6/2016
5/7/2016
7/7/2016
10/9/2016
11/8/2016
10/9/2016
11/8/2016
RCC COL
3/6/2016
4/5/2016
RCC ROOF
4/6/2016
5/6/2016
BRICK WORK
5/7/2016
7/7/2016
ELECTRICAL CONDUITING
6/7/2016
7/7/2016
6/7/2016
8/7/2016
PLASTERING
7/8/2016
8/7/2016
FLOORING
7/8/2016
9/7/2016
TILING WORK
7/8/2016
9/7/2016
8/8/2016
10/8/2016
6/7/2016
9/7/2016
9/8/2016
11/8/2016
RCC COL
5/7/2016
6/6/2016
RCC ROOF
6/7/2016
7/7/2016
BRICK WORK
7/8/2016
9/7/2016
ELECTRICAL CONDUITING
8/8/2016
9/7/2016
8/8/2016
10/8/2016
PLASTERING
8/8/2016
10/8/2016
FLOORING
9/7/2016
11/8/2016
TILING WORK
8/8/2016
10/8/2016
10/9/2016
12/9/2016
2/10/2017
3/11/2017
2/10/2017
3/11/2017
PLUMBING WORK
9/2/2015
9/7/2016
2/4/2016
10/8/2016
HVAC WORK
3/6/2016
11/8/2016
10/9/2016
12/9/2016
PHASE 2
DRAWINGS
5/1/2015
8/1/2015
EXCAVATION
8/2/2015
11/2/2015
WATER PROOFING
10/3/2015
12/3/2015
RCC RAFT
10/3/2015
12/3/2015
RCC WALL
10/3/2015
12/3/2015
RCC COL
10/3/2015
12/3/2015
RCC ROOF
11/3/2015
1/3/2016
BRICK WORK
12/4/2015
1/3/2016
ELECTRICAL CONDUITING
12/4/2015
2/3/2016
PLASTERING
1/4/2016
3/5/2016
RCC WALL
12/4/2015
2/3/2016
RCC COL
1/4/2016
2/3/2016
RCC ROOF
2/4/2016
3/5/2016
BRICK WORK
3/6/2016
6/6/2016
ELECTRICAL CONDUITING
5/7/2016
6/6/2016
PLASTERING
4/6/2016
7/7/2016
FLOORING
5/7/2016
7/7/2016
RCC COL
2/4/2016
3/5/2016
RCC ROOF
3/6/2016
4/5/2016
BRICK WORK
4/6/2016
6/7/2016
ELECTRICAL CONDUITING
6/7/2016
8/7/2016
7/8/2016
8/7/2016
FLOORING
PLASTERING
7/8/2016
9/7/2016
FLOORING
7/8/2016
9/7/2016
TILING WORK
6/7/2016
8/7/2016
7/8/2016
9/7/2016
1/10/2017
2/9/2017
1/10/2017
2/9/2017
RCC COL
4/6/2016
5/6/2016
RCC ROOF
5/7/2016
6/6/2016
BRICK WORK
6/7/2016
8/7/2016
ELECTRICAL CONDUITING
7/8/2016
8/7/2016
7/8/2016
9/7/2016
PLASTERING
7/8/2016
9/7/2016
FLOORING
8/7/2016
10/7/2016
TILING WORK
7/8/2016
9/7/2016
9/8/2016
11/8/2016
1/10/2017
2/9/2017
1/10/2017
2/9/2017
RCC COL
RCC ROOF
BRICK WORK
6/7/2016
7/7/2016
7/8/2016
HVAC
WORK
8/7/2016
8/8/2016
10/8/2016
ELECTRICAL CONDUITING
9/8/2016
10/8/2016
PLUMBING
WORK
9/8/2016
11/8/2016
PLASTERING
9/8/2016
11/8/2016
FLOORING
10/9/2016
12/9/2016
TILING WORK
9/8/2016
11/8/2016
11/9/2016
1/9/2017
11/9/2016
1/9/2017
11/9/2016
1/9/2017
RCC COL
8/8/2016
9/7/2016
RCC ROOF
9/8/2016
10/8/2016
BRICK WORK
10/9/2016
12/9/2016
ELECTRICAL CONDUITING
11/9/2016
12/9/2016
11/9/2016
1/9/2017
PLASTERING
11/9/2016
1/9/2017
FLOORING
12/10/2016
2/9/2017
TILING WORK
11/9/2016
1/9/2017
1/10/2017
3/12/2017
3/13/2017
4/12/2017
3/13/2017
4/12/2017
PLUMBING WORK
3/6/2016
12/9/2016
5/7/2016
SOLAR SYSTEM
12/10/2016
3/12/2017
LANDSCAPE
2/10/2017
5/11/2017
LIFT INSTALLATION
12/10/2016
2/9/2017
12/10/2016
2/9/2017
9/7/2016
3/6/2016
12/9/2016
HVAC WORK
3/6/2016
12/9/2016
FLOORING
PLASTERING
ELECTRICAL CONDUITING
PLASTERING
ELECTRICAL CONDUITING
BRICK WORK
RCC ROOF
RCC COL
RCC WALL
RCC RAFT
WATER PROOFING
EXCAVATION
22/11/2013
91
61
61
61
61
61
31
93
30
61
61
30
30
31
92
31
91
61
30
31
5/13/2015
5/12/2015
5/11/2015
5/10/2015
5/9/2015
5/8/2015
5/7/2015
5/6/2015
5/5/2015
5/4/2015
5/3/2015
5/2/2015
5/1/2015
DURATION
60
30
61
61
61
61
62
30
30
30
30
61
30
61
61
61
61
61
30
30
30
30
61
30
61
30
61
61
61
92
61
30
30
61
30
61
61
62
61
61
29
29
371
247
247
61
92
92
61
61
61
61
61
30
61
61
61
30
30
92
30
92
61
30
30
62
61
30
61
61
61
61
30
30
30
30
61
30
61
61
61
61
61
30
30
30
30
61
30
61
61
61
61
61
61
61
30
30
61
30
61
61
61
61
61
30
30
278
123
92
90
61
61
278
278
5/29/2015
5/28/2015
5/27/2015
5/26/2015
5/25/2015
5/24/2015
5/23/2015
5/22/2015
5/21/2015
5/20/2015
5/19/2015
5/18/2015
5/17/2015
5/16/2015
5/15/2015
5/14/2015
6/14/2015
6/13/2015
6/12/2015
6/11/2015
6/10/2015
6/9/2015
6/8/2015
6/7/2015
6/6/2015
6/5/2015
6/4/2015
6/3/2015
6/2/2015
6/1/2015
5/31/2015
5/30/2015
6/30/2015
6/29/2015
6/28/2015
6/27/2015
6/26/2015
6/25/2015
6/24/2015
6/23/2015
6/22/2015
6/21/2015
6/20/2015
6/19/2015
6/18/2015
6/17/2015
6/16/2015
6/15/2015
7/16/2015
7/15/2015
7/14/2015
7/13/2015
7/12/2015
7/11/2015
7/10/2015
7/9/2015
7/8/2015
7/7/2015
7/6/2015
7/5/2015
7/4/2015
7/3/2015
7/2/2015
7/1/2015
8/1/2015
7/31/2015
7/30/2015
7/29/2015
7/28/2015
7/27/2015
7/26/2015
7/25/2015
7/24/2015
7/23/2015
7/22/2015
7/21/2015
7/20/2015
7/19/2015
7/18/2015
7/17/2015
8/17/2015
8/16/2015
8/15/2015
8/14/2015
8/13/2015
8/12/2015
8/11/2015
8/10/2015
8/9/2015
8/8/2015
8/7/2015
8/6/2015
8/5/2015
8/4/2015
8/3/2015
8/2/2015
9/2/2015
9/1/2015
8/31/2015
8/30/2015
8/29/2015
8/28/2015
8/27/2015
8/26/2015
8/25/2015
8/24/2015
8/23/2015
8/22/2015
8/21/2015
8/20/2015
8/19/2015
8/18/2015
10/06/2014
9/18/2015
9/17/2015
9/16/2015
9/15/2015
9/14/2015
9/13/2015
9/12/2015
9/11/2015
9/10/2015
9/9/2015
9/8/2015
9/7/2015
9/6/2015
9/5/2015
9/4/2015
9/3/2015
10/4/2015
10/3/2015
10/2/2015
10/1/2015
9/30/2015
9/29/2015
9/28/2015
9/27/2015
9/26/2015
9/25/2015
9/24/2015
9/23/2015
9/22/2015
9/21/2015
9/20/2015
9/19/2015
10/20/2015
10/19/2015
10/18/2015
10/17/2015
10/16/2015
10/15/2015
10/14/2015
10/13/2015
10/12/2015
10/11/2015
10/10/2015
10/9/2015
10/8/2015
10/7/2015
10/6/2015
10/5/2015
11/5/2015
11/4/2015
11/3/2015
11/2/2015
11/1/2015
10/31/2015
10/30/2015
10/29/2015
10/28/2015
10/27/2015
10/26/2015
10/25/2015
10/24/2015
10/23/2015
10/22/2015
10/21/2015
11/21/2015
11/20/2015
11/19/2015
11/18/2015
11/17/2015
11/16/2015
11/15/2015
11/14/2015
11/13/2015
11/12/2015
11/11/2015
11/10/2015
11/9/2015
11/8/2015
11/7/2015
11/6/2015
12/7/2015
12/6/2015
12/5/2015
12/4/2015
12/3/2015
12/2/2015
12/1/2015
11/30/2015
11/29/2015
11/28/2015
11/27/2015
11/26/2015
11/25/2015
11/24/2015
11/23/2015
11/22/2015
12/23/2015
12/22/2015
12/21/2015
12/20/2015
12/19/2015
12/18/2015
12/17/2015
12/16/2015
12/15/2015
12/14/2015
12/13/2015
12/12/2015
12/11/2015
12/10/2015
12/9/2015
12/8/2015
1/8/2016
1/7/2016
1/6/2016
1/5/2016
1/4/2016
1/3/2016
1/2/2016
1/1/2016
12/31/2015
12/30/2015
12/29/2015
12/28/2015
12/27/2015
12/26/2015
12/25/2015
12/24/2015
27/12/2014
1/24/2016
1/23/2016
1/22/2016
1/21/2016
1/20/2016
1/19/2016
1/18/2016
1/17/2016
1/16/2016
1/15/2016
1/14/2016
1/13/2016
1/12/2016
1/11/2016
1/10/2016
1/9/2016
14
2/9/2016
2/8/2016
2/7/2016
2/6/2016
2/5/2016
2/4/2016
2/3/2016
2/2/2016
2/1/2016
1/31/2016
1/30/2016
1/29/2016
1/28/2016
1/27/2016
1/26/2016
1/25/2016
2/25/2016
2/24/2016
2/23/2016
2/22/2016
2/21/2016
2/20/2016
2/19/2016
2/18/2016
2/17/2016
2/16/2016
2/15/2016
2/14/2016
2/13/2016
2/12/2016
2/11/2016
2/10/2016
3/12/2016
3/11/2016
3/10/2016
3/9/2016
3/8/2016
3/7/2016
3/6/2016
3/5/2016
3/4/2016
3/3/2016
3/2/2016
3/1/2016
2/29/2016
2/28/2016
2/27/2016
2/26/2016
3/28/2016
3/27/2016
3/26/2016
3/25/2016
3/24/2016
3/23/2016
3/22/2016
3/21/2016
3/20/2016
3/19/2016
3/18/2016
3/17/2016
3/16/2016
3/15/2016
3/14/2016
3/13/2016
4/13/2016
4/12/2016
4/11/2016
4/10/2016
4/9/2016
4/8/2016
4/7/2016
4/6/2016
4/5/2016
4/4/2016
4/3/2016
4/2/2016
4/1/2016
3/31/2016
3/30/2016
3/29/2016
4/29/2016
4/28/2016
4/27/2016
4/26/2016
4/25/2016
4/24/2016
4/23/2016
4/22/2016
4/21/2016
4/20/2016
4/19/2016
4/18/2016
4/17/2016
4/16/2016
4/15/2016
4/14/2016
92
91
5/15/2016
5/14/2016
5/13/2016
5/12/2016
5/11/2016
5/10/2016
5/9/2016
5/8/2016
5/7/2016
5/6/2016
5/5/2016
5/4/2016
5/3/2016
5/2/2016
5/1/2016
4/30/2016
15/07/2015
5/31/2016
5/30/2016
5/29/2016
5/28/2016
5/27/2016
5/26/2016
5/25/2016
5/24/2016
5/23/2016
5/22/2016
5/21/2016
5/20/2016
5/19/2016
5/18/2016
5/17/2016
5/16/2016
7/2015
61
61
61
61
61
6/16/2016
6/15/2016
6/14/2016
6/13/2016
6/12/2016
6/11/2016
6/10/2016
6/9/2016
6/8/2016
6/7/2016
6/6/2016
6/5/2016
6/4/2016
6/3/2016
6/2/2016
6/1/2016
7/2/2016
7/1/2016
6/30/2016
6/29/2016
6/28/2016
6/27/2016
6/26/2016
6/25/2016
6/24/2016
6/23/2016
6/22/2016
6/21/2016
6/20/2016
6/19/2016
6/18/2016
6/17/2016
92
31
7/18/2016
7/17/2016
7/16/2016
7/15/2016
7/14/2016
7/13/2016
7/12/2016
7/11/2016
7/10/2016
7/9/2016
7/8/2016
7/7/2016
7/6/2016
7/5/2016
7/4/2016
7/3/2016
30
30
93
93
8/3/2016
8/2/2016
8/1/2016
7/31/2016
7/30/2016
7/29/2016
7/28/2016
7/27/2016
7/26/2016
7/25/2016
7/24/2016
7/23/2016
7/22/2016
7/21/2016
7/20/2016
7/19/2016
61
61
61
61
30
31
30
30
8/19/2016
8/18/2016
8/17/2016
8/16/2016
8/15/2016
8/14/2016
8/13/2016
8/12/2016
8/11/2016
8/10/2016
8/9/2016
8/8/2016
8/7/2016
8/6/2016
8/5/2016
8/4/2016
61
30
31
61
61
30
30
9/4/2016
9/3/2016
9/2/2016
9/1/2016
8/31/2016
8/30/2016
8/29/2016
8/28/2016
8/27/2016
8/26/2016
8/25/2016
8/24/2016
8/23/2016
8/22/2016
8/21/2016
8/20/2016
61
61
61
30
31
9/20/2016
9/19/2016
9/18/2016
9/17/2016
9/16/2016
9/15/2016
9/14/2016
9/13/2016
9/12/2016
9/11/2016
9/10/2016
9/9/2016
9/8/2016
9/7/2016
9/6/2016
9/5/2016
30
61
61
30
60
92
31/01/2016
10/6/2016
10/5/2016
10/4/2016
10/3/2016
10/2/2016
10/1/2016
9/30/2016
9/29/2016
9/28/2016
9/27/2016
9/26/2016
9/25/2016
9/24/2016
9/23/2016
9/22/2016
9/21/2016
30
30
61
61
30
30
60
91
31
31/01/2016
10/22/2016
10/21/2016
10/20/2016
10/19/2016
10/18/2016
10/17/2016
10/16/2016
10/15/2016
10/14/2016
10/13/2016
10/12/2016
10/11/2016
10/10/2016
10/9/2016
10/8/2016
10/7/2016
30
371
30
61
61
61
61
61
11/7/2016
11/6/2016
11/5/2016
11/4/2016
11/3/2016
11/2/2016
11/1/2016
10/31/2016
10/30/2016
10/29/2016
10/28/2016
10/27/2016
10/26/2016
10/25/2016
10/24/2016
10/23/2016
30
30
61
61
61
11/23/2016
11/22/2016
11/21/2016
11/20/2016
11/19/2016
11/18/2016
11/17/2016
11/16/2016
11/15/2016
11/14/2016
11/13/2016
11/12/2016
11/11/2016
11/10/2016
11/9/2016
11/8/2016
30
62
92
30
30
61
61
61
30
62
62
12/9/2016
12/8/2016
12/7/2016
12/6/2016
12/5/2016
12/4/2016
12/3/2016
12/2/2016
12/1/2016
11/30/2016
11/29/2016
11/28/2016
11/27/2016
11/26/2016
11/25/2016
11/24/2016
30
61
92
30
247
30
61
61
61
61
12/25/2016
12/24/2016
12/23/2016
12/22/2016
12/21/2016
12/20/2016
12/19/2016
12/18/2016
12/17/2016
12/16/2016
12/15/2016
12/14/2016
12/13/2016
12/12/2016
12/11/2016
12/10/2016
30
61
247
30
30
61
30
61
61
61
278
278
123
278
1/10/2017
1/9/2017
1/8/2017
1/7/2017
1/6/2017
1/5/2017
1/4/2017
1/3/2017
1/2/2017
1/1/2017
12/31/2016
12/30/2016
12/29/2016
12/28/2016
12/27/2016
12/26/2016
30
30
30
61
61
61
30
61
247
92
30
61
278
278
278
1/26/2017
1/25/2017
1/24/2017
1/23/2017
1/22/2017
1/21/2017
1/20/2017
1/19/2017
1/18/2017
1/17/2017
1/16/2017
1/15/2017
1/14/2017
1/13/2017
1/12/2017
1/11/2017
30
30
61
61
61
30
61
61
61
61
61
30
61
92
61
61
30
18/08/2016
2/11/2017
2/10/2017
2/9/2017
2/8/2017
2/7/2017
2/6/2017
2/5/2017
2/4/2017
2/3/2017
2/2/2017
2/1/2017
1/31/2017
1/30/2017
1/29/2017
1/28/2017
1/27/2017
30
61
61
61
61
61
61
61
30
61
18/08/2016
2/27/2017
2/26/2017
2/25/2017
2/24/2017
2/23/2017
2/22/2017
2/21/2017
2/20/2017
2/19/2017
2/18/2017
2/17/2017
2/16/2017
2/15/2017
2/14/2017
2/13/2017
2/12/2017
30
61
61
61
30
30
61
62
61
3/15/2017
3/14/2017
3/13/2017
3/12/2017
3/11/2017
3/10/2017
3/9/2017
3/8/2017
3/7/2017
3/6/2017
3/5/2017
3/4/2017
3/3/2017
3/2/2017
3/1/2017
2/28/2017
61
61
61
61
62
61
30
30
30
30
3/31/2017
3/30/2017
3/29/2017
3/28/2017
3/27/2017
3/26/2017
3/25/2017
3/24/2017
3/23/2017
3/22/2017
3/21/2017
3/20/2017
3/19/2017
3/18/2017
3/17/2017
3/16/2017
30
61
61
61
61
61
61
4/16/2017
4/15/2017
4/14/2017
4/13/2017
4/12/2017
4/11/2017
4/10/2017
4/9/2017
4/8/2017
4/7/2017
4/6/2017
4/5/2017
4/4/2017
4/3/2017
4/2/2017
4/1/2017
61
61
61
30
61
61
61
61
61
5/2/2017
5/1/2017
4/30/2017
4/29/2017
4/28/2017
4/27/2017
4/26/2017
4/25/2017
4/24/2017
4/23/2017
4/22/2017
4/21/2017
4/20/2017
4/19/2017
4/18/2017
4/17/2017
61
92
61
5/11/2017
5/10/2017
5/9/2017
5/8/2017
5/7/2017
5/6/2017
5/5/2017
5/4/2017
5/3/2017
61
30
30
30
30
61
61
29
29
29
06/03/2017
90
30
30
30
06/03/2017
22/09/2017
DURATIO
START D
DURATION
START DATE
PHASE 1
START DATE
5/1/2015
MIESTONES
DRAWINGS
7/1/2015
EXCAVATION
7/1/2015
WATER PROOFING
7/1/2015
RCC RAFT
7/1/2015
RCC WALL
7/1/2015
RCC COL
9/1/2015
RCC ROOF
9/1/2015
BRICK WORK
11/3/2015
ELECTRICAL CONDUITING
11/3/2015
PLASTERING
11/3/2015
FLOORING
10/3/2015
RCC WALL
10/3/2015
RCC COL
11/3/2015
RCC ROOF
12/5/2015
BRICK WORK
2/4/2016
ELECTRICAL CONDUITING
1/5/2016
PLASTERING
2/4/2016
FLOORING
11/3/2015
RCC COL
12/4/2015
RCC ROOF
1/5/2016
BRICK WORK
2/4/2016
ELECTRICAL CONDUITING
2/4/2016
2/4/2016
PLASTERING
3/6/2016
FLOORING
2/4/2016
TILING WORK
4/6/2016
10/9/2016
10/9/2016
1/4/2016
RCC COL
2/4/2016
RCC ROOF
3/6/2016
BRICK WORK
4/6/2016
ELECTRICAL CONDUITING
4/6/2016
4/6/2016
PLASTERING
5/7/2016
FLOORING
4/6/2016
TILING WORK
5/7/2016
10/9/2016
10/9/2016
3/6/2016
RCC COL
4/6/2016
RCC ROOF
5/7/2016
BRICK WORK
6/7/2016
ELECTRICAL CONDUITING
6/7/2016
7/8/2016
PLASTERING
7/8/2016
FLOORING
7/8/2016
TILING WORK
8/8/2016
6/7/2016
9/8/2016
5/7/2016
RCC COL
6/7/2016
RCC ROOF
7/8/2016
BRICK WORK
8/8/2016
ELECTRICAL CONDUITING
8/8/2016
8/8/2016
PLASTERING
9/7/2016
FLOORING
8/8/2016
TILING WORK
10/9/2016
2/10/2017
2/10/2017
9/2/2015
PLUMBING WORK
2/4/2016
3/6/2016
HVAC WORK
10/9/2016
PHASE 2
5/1/2015
DRAWINGS
8/2/2015
EXCAVATION
10/3/2015
WATER PROOFING
10/3/2015
RCC RAFT
10/3/2015
RCC WALL
10/3/2015
RCC COL
11/3/2015
RCC ROOF
12/4/2015
BRICK WORK
12/4/2015
ELECTRICAL CONDUITING
1/4/2016
PLASTERING
FLOORING
12/4/2015
RCC WALL
1/4/2016
RCC COL
2/4/2016
RCC ROOF
3/6/2016
BRICK WORK
5/7/2016
ELECTRICAL CONDUITING
4/6/2016
PLASTERING
5/7/2016
FLOORING
2/4/2016
RCC COL
3/6/2016
RCC ROOF
4/6/2016
BRICK WORK
6/7/2016
ELECTRICAL CONDUITING
7/8/2016
7/8/2016
PLASTERING
7/8/2016
FLOORING
6/7/2016
TILING WORK
7/8/2016
1/10/2017
1/10/2017
4/6/2016
RCC COL
5/7/2016
RCC ROOF
6/7/2016
BRICK WORK
7/8/2016
ELECTRICAL CONDUITING
7/8/2016
7/8/2016
PLASTERING
8/7/2016
FLOORING
7/8/2016
TILING WORK
9/8/2016
1/10/2017
1/10/2017
6/7/2016
RCC COL
7/8/2016
RCC ROOF
8/8/2016
BRICK WORK
9/8/2016
ELECTRICAL CONDUITING
9/8/2016
9/8/2016
PLASTERING
10/9/2016
FLOORING
9/8/2016
TILING WORK
11/9/2016
11/9/2016
11/9/2016
8/8/2016
RCC COL
9/8/2016
RCC ROOF
10/9/2016
BRICK WORK
11/9/2016
ELECTRICAL CONDUITING
11/9/2016
11/9/2016
PLASTERING
12/10/2016
FLOORING
11/9/2016
TILING WORK
1/10/2017
3/13/2017
3/13/2017
3/6/2016
PLUMBING WORK
5/7/2016
12/10/2016
SOLAR SYSTEM
2/10/2017
LANDSCAPE
12/10/2016
LIFT INSTALLATION
12/10/2016
3/6/2016
3/6/2016
HVAC WORK
06 January 2015
05 January 2015
04 January 2015
03 January 2015
02 January 2015
01 January 2015
10 January 2015
09 January 2015
08 January 2015
07 January 2015