Вы находитесь на странице: 1из 60

Dallas Water Utilities

Wastewater Treatment Facilities Strategic Plan


Improvements at CWWTP

Draft WWTFSP_App.G2-2.0
December 2010

Prepared by:
Carollo Engineers, Inc.
Registration No. F-882

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 4
Project:
White Rock Primary Clarifiers (no. 1-6) Rehabilitation
Location:
CWWTP
ELEMENT
White Rock Primary Clarifiers (no. 1-6)
Rehabilitation

$7,869,000

Total Direct Cost

$7,900,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$2,400,000
$10,300,000
$1,500,000
$1,500,000
$13,300,000
$2,000,000
$15,300,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 1 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 4
Project:
White Rock Primary Clarifiers (no. 1-6) Rehabilitation
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

White Rock Primary Clarifiers (no. 1-6) Rehabilitation


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Structural Wall Repair
Structural Floor Repair
Concrete Coatings
Aluminum Handrail
Subtotal Structure(s)
Major Equipment & Piping
Chain and Flight Replacement
Miscellaneous Mechanical Repair
Miscellaneous Expansion Joint Repair
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$0
33,450
57,600
91,050
3,600

SF
SF
SF
LF

$75
$50
$10
$62

$75 $2,508,750
$50 $2,880,000
$10 $910,500
$62 $223,200
$6,299,250

LS

$250,000

$250,000

$250,000

1
1

LS
LS

$50,000
$20,000

$50,000
$20,000

$50,000
$20,000
$320,000
$6,842,450

5%
5%
5%

December 2010

$342,123
$342,123
$342,123
$7,869,000

Page 2 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 6
Project:
WRRSPS Rehabilitation and Improvements
Location:
CWWTP
ELEMENT
WRRSPS Rehabilitation and Improvements
Total Direct Cost

$7,927,000
$7,900,000

Contingencies (20%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$1,600,000
$9,500,000
$1,400,000
$1,400,000
$12,300,000
$1,800,000
$14,100,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 3 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 6
WRRSPS Rehabilitation and Improvements
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

WRRSPS Rehabilitation and Improvements


Major Site Work
Relocation of Southerland & Septic Discharge Piping
Subtotal Major Site Work
Structure(s)
Structual and Architechural Improvements
Subtotal Structure(s)
Major Equipment & Piping
50 MGD Horizontal End Suction Centrifugal Pump
60 HP Ventillation Blowers (70,695 CFM)
VFDs
Misc. Pump Repair and Accessories

WWTFSP_App.G2-2.0

$400,000

$400,000

$400,000
$400,000

LS

$500,000

$500,000

$500,000
$500,000

Seal Water Pump Repair and Accessories


Ventilation System
Rooftop Ventilators
90" Slide Gate
Plug Valve Actuator Replacement
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

LS

2
2
3
1

EA
EA
EA
LS

$600,000
$150,000
$150,000
$25,000

$600,000 $1,200,000
$150,000
$300,000
$150,000
$450,000
$25,000
$25,000

1
1
2
2
6
1

LS
LS
EA
EA
EA
LS

$23,000
$75,300
$60,000
$35,000
$30,000
$1,611,218

$23,000
$23,000
$75,300
$75,300
$60,000
$120,000
$35,000
$70,000
$30,000
$180,000
$1,611,218 $1,611,218
$4,054,518
$4,954,518

20%
20%
20%

December 2010

$990,904
$990,904
$990,904
$7,927,000

Page 4 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 8
Project:
Existing Peak Flow Basins Rehabilitation
Location:
CWWTP
ELEMENT
Existing Basin Rehabilitation
Total-Direct Cost

$3,617,000
$3,600,000

Contingencies (10%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$400,000
$4,000,000
$600,000
$600,000
$5,200,000
$800,000
$6,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 5 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 8
Project:
Existing Peak Flow Basins Rehabilitation
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Existing Basin Rehabilitation


Major Site Work
Demolition
Berm Rehabilitation

112,580
1

Subtotal Major Site Work


Structure(s)
6" Concrete Slab On Grade
6" Sloped Slab On Grade
10" Wide Concrete Settling Walls
Grouting
Subtotal Structure(s)
Major Equipment & Piping

SF
LS

$8
$1,000,000

$8 $900,640
$1,000,000 $1,000,000
$1,900,640

2,167
1,333
200
2,000

CY
CY
CY
CY

$295
$306
$950
$75

$295
$306
$950
$75

$639,265
$407,898
$190,000
$150,000
$1,387,163

None
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Subtotal Direct Cost

WWTFSP_App.G2-2.0

December 2010

$0
$3,287,803
5%
5%
0%

$164,390
$164,390
$0
$3,617,000

Page 6 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 9
Project:
Space Utilization and Admin Facilities Improvements
Location:
CWWTP
ELEMENT
Space Utilization and Admin Facilities Improvements
Total Direct Cost

$2,400,000
$2,400,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$700,000
$3,100,000
$500,000
$500,000
$4,100,000
$600,000
$4,700,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 7 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 9
Space Utilization and Admin Facilities Improvements
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST

Space Utilization and Admin Facillites Improvements


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Adminstration Bldg Improvements
Subtotal Structure(s)
Major Equipment & Piping
None
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

December 2010

$0
1

LS

$2,000,000 $2,000,000
$2,000,000

$0
$2,000,000
0%

$0

10%
10%

$200,000
$200,000
$2,400,000

Page 8 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 11
Project:
Enhanced Biological Phosphorus Removal Improvements to Complex B
Location:
CWWTP
ELEMENT
Complex B Internal Selector
Complex B Aeration Basin Modifications
Total Direct Cost

$2,082,000
$3,593,000
$5,700,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$1,700,000
$7,400,000
$1,100,000
$1,100,000
$9,600,000
$1,400,000
$11,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 9 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 11
Enhanced Biological Phosphorus Removal Improvements to Complex B
Project:
CWWTP
Location:

QUANTITY UNIT UNIT COST UNIT COST

DESCRIPTION
Complex B Internal Selector
Major Site Work
None
Subtotal Major Site Work
Structure(s)
Interior Wall, 12" Thick

$0
889 CY

$954

$954

$848,106

Subtotal Structure(s)

$848,106

Major Equipment & Piping


Mixing Pumps
Mechanical Equipment
Internal Piping
Subtotal Major Equipment & Piping

2
1
1

Subtotal All Major Cost


Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

15%
15%
25%

Complex B Aeration Basin Modifications


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Interior Wall, 12" Thick
Subtotal Structure(s)
Major Equipment & Piping
Diffusers
Mechanical Equipment
Internal Piping
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

EA
LS
LS

$40,000
$237,040
$177,780

$40,000
$237,040
$177,780

$80,000
$237,040
$177,780
$494,820
$1,342,926
$201,439
$201,439
$335,732
$2,082,000

$0
443 CY

$954

$954

$422,622
$422,622

75,000
1
1

SF
LS
LS

$15
$440,280
$330,210

$15 $1,125,000
$440,280 $440,280
$330,210 $330,210
$1,895,490
$2,318,112

15%
15%
25%

December 2010

$347,717
$347,717
$579,528
$3,593,000

Page 10 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 12
SCADA MasterPlan and Replacement
Project:
CWWTP
Location:
ELEMENT
SCADA MasterPlan and Replacement
Total Direct Cost

$15,000,000
$15,000,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$4,500,000
$19,500,000
$2,900,000
$2,900,000
$25,300,000
$3,800,000
$29,100,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 11 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 12
Project:
SCADA MasterPlan and Replacement
Location:
CWWTP

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

SCADA MasterPlan and Replacement


Major Site Work
None
Subtotal Major Site Work

$0

Subtotal Structure(s)
Major Equipment & Piping
SCADA software
SCADA hardware
Instrumentation
Subtotal Major Equipment & Piping

$0

Structure(s)
None

Subtotal All Major Cost


Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

1
1
1

LS
LS
LS

$3,000,000
$7,000,000
$2,000,000

$3,000,000 $3,000,000
$7,000,000 $7,000,000
$2,000,000 $2,000,000
$12,000,000
$12,000,000

5%
0%
20%

December 2010

$600,000
$0
$2,400,000
$15,000,000

Page 12 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 13
Project:
Dallas Plant Headworks Rehabilitation
Location:
CWWTP
ELEMENT
Dallas Plant Headworks Rehabilitation
Total Direct Cost

$2,494,000
$2,500,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$800,000
$3,300,000
$500,000
$500,000
$4,300,000
$600,000
$4,900,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 13 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 13
Project:
Dallas Plant Headworks Rehabilitation
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Dallas Plant Headworks Rehabilitation


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Structural Repair
Concrete Coatings

12,000.00
12,000.00

Subtotal Structure(s)
Major Equipment & Piping
Odor Control Blowers
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$0
SF
SF

$150
$12

$150 $1,800,000
$12 $144,000
$1,944,000

3.00

EA

$75,000

$75,000

$225,000
$225,000
$2,169,000

5%
5%
5%

December 2010

$108,450
$108,450
$108,450
$2,494,000

Page 14 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 14
Project:
Odor Control MasterPlan Update
Location:
CWWTP & SWWTP
ELEMENT
Odor Control MasterPlan Update
Total Direct Cost

$0
$0

Contingencies (N/A)
Total Direct Cost + Contingencies
General Conditions (N/A)
Contractor OH & P (N/A)
Total Construction Cost
Engineering (N/A)
Total Project Cost (2010 Dollars)

$0
$0
$0
$0
$0
$1,000,000
$1,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 15 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 16
Project:
Sodium Hypochlorite Disinfection Facilities
Location:
CWWTP
ELEMENT
Chemical Feed and Storage Facilities
Total Direct Cost

$4,039,000
$4,000,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$1,200,000
$5,200,000
$800,000
$800,000
$6,800,000
$1,000,000
$7,800,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 16 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 16
Sodium Hypochlorite Disinfection Facilities
Project:
CWWTP
Location:

DESCRIPTION
Total Direct Cost
Chemical Feed and Storage Facilities
Major Site Work
None

QUANTITY UNIT UNIT COST UNIT COST

Subtotal Major Site Work


Structure(s)
Base slab (assumes 24" thick)
Elevated Slab
Walls (assumes 18" thick)
Pre-fab Building
Rehab Building
Aluminum Handrails, Grating, Stairs, Ladders
Subtotal Structure(s)

$0
155 CY
725 CY
150 CY
1,800 SF
3,080 SF
1 LS

$460.92
$520.00
$605.07
$450.00
$150.00
$50,000.00

$461 $71,455
$520 $377,000
$605 $90,750
$450 $810,000
$150 $462,000
$50,000 $50,000
$1,861,205

Major Equipment and Piping


Chem. feed pumps (150 gph) - NaOCl
Chem. feed pumps (60 gph) - NaHSO3
Sump pumps
Chem. storage tanks (20,000 gal) - NaHSO3

10
2
4
1
1

Subtotal Major Equipment and Piping


Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical & Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

EA
EA
EA
EA
LS

$32,500.00
$32,500.00
$8,840.24
$40,000.00
$279,216

$32,500 $325,000
$32,500 $65,000
$8,840 $35,360
$40,000 $40,000
$279,216 $279,216
$744,576
$2,605,781

15%
15%
25%

December 2010

$390,867
$390,867
$651,445
$4,039,000

Page 17 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 18
Project:
ASIPS Rehabilitation and Improvements
Location:
CWWTP
ELEMENT
ASIPS Rehabilitation and Improvements
Total Direct Cost

$4,042,000
$4,000,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$1,200,000
$5,200,000
$800,000
$800,000
$6,800,000
$1,000,000
$7,800,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 18 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 18
Project:
ASIPS Rehabilitation and Improvements
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

ASIPS Rehabilitation and Improvements


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Structural Modifications
Subtotal Structure(s)
Major Equipment & Piping
Motors
VFD
Pumps
Flow Meters
Flow Meter Transmitter
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work

$0
1

$350,000

$350,000

$350,000
$350,000

3
3
3
10

EA
EA
EA
EA

$150,000
$150,000
$450,000
$8,500

10

EA

$950

$150,000 $450,000
$150,000 $450,000
$450,000 $1,350,000
$8,500
$85,000
$950

$9,500
$2,344,500
$2,694,500

15%
15%
20%

Subtotal Direct Cost

WWTFSP_App.G2-2.0

LS

December 2010

$404,175
$404,175
$538,900
$4,042,000

Page 19 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 19
Project:
84" Horseshoe Interceptor Rehabilitation
Location:
CWWTP
ELEMENT
84" Horseshoe Interceptor Rehabilitation
Total Direct Cost

$8,053,000
$8,100,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$2,400,000
$10,500,000
$1,600,000
$1,600,000
$13,700,000
$2,100,000
$15,800,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 20 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 19
84" Horseshoe Interceptor Rehabilitation
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

84" Horseshoe Interceptor Rehabilitation


Major Site Work
Utility Relocation and/or Flow Diversion
Dewatering
Site Restoration
Cleaning Existing Pipe
84" Pipe
Slip Lining and Grouting 84" Pipe
Sheet Piling
Backfill
Subtotal Major Site Work
Structure(s)

1 LS
1 LS
1 LS
4,300 LF
4,300 LF
4,300 LF
6,400 SF
10,667 CY

$2,000,000
$300,000
$300,000
$90
$510
$420
$29
$14

$2,000,000 $2,000,000
$300,000 $300,000
$300,000 $300,000
$90 $387,000
$510 $2,193,000
$420 $1,806,000
$29 $185,600
$14 $149,338
$7,320,938

None
Subtotal Structure(s)
Major Equipment & Piping
None
Subtotal Major Equipment & Piping
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$0

$0
$7,320,938
0%
10%
0%

December 2010

$0
$732,094
$0
$8,053,000

Page 21 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 20
Project:
Stormwater Facilities Plan and Improvements
Location:
CWWTP
ELEMENT
Stormwater Facilities Plan and Improvements
Total Direct Cost

$5,070,000
$5,100,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$1,500,000
$6,600,000
$1,000,000
$1,000,000
$8,600,000
$1,300,000
$9,900,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 22 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 20
Stormwater Facilities Plan and Improvements
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Stormwater Facilities Plan and Improvements


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Stormwater Basin Improvements
Subtotal Structure(s)
Major Equipment & Piping
Stormwater Basin Improvements
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$0
1

LS

$1,950,000

$1,950,000 $1,950,000
$1,950,000

LS

$1,950,000

$1,950,000 $1,950,000
$1,950,000
$3,900,000

15%

$585,000

15%
0%

$585,000
$0

December 2010

$5,070,000

Page 23 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 22
Project:
New Peak Flow Basin D
Location:
CWWTP
ELEMENT
New Basin D Construction
Total-Direct Cost

$16,394,000
$16,400,000

Contingencies (10%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$1,600,000
$18,000,000
$2,700,000
$2,700,000
$23,400,000
$3,500,000
$26,900,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 24 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 22
Project:
New Peak Flow Basin D
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

New Basin D Construction


Major Site Work
Clear & Grub
Bentonite Slurry Trench
Excavation
Embankment for Levee
Haul Excess Excavation
New Perimeter Gravel Road
Cellular Grout for Annular Space
Vertical Shaft
Tunneling and Temporary Support
Subtotal Major Site Work
Structure(s)
6" Concrete Slab On Grade
6" Sloped Slab On Grade
Inlet Box Culvert
Outlet Control Structure

205
147,000
829,156
136,889
672,711
1
2,685
120
895

AC
SF
CY
CY
CY
LS
CY
LF
LF

$1,400
$5
$3
$3
$2
$170,000
$150
$3,000
$1,200

$1,400 $287,000
$5 $735,000
$3 $2,487,468
$3 $410,667
$2 $1,345,422
$170,000 $170,000
$150 $402,750
$3,000 $360,000
$1,200 $1,074,000
$7,272,307

13,167 CY
8,148 CY
342 LF
1 LS

$295
$306
$200
$190,000

$295 $3,884,265
$306 $2,493,288
$200
$68,400
$190,000 $190,000
$6,635,953

Major Equipment & Piping


66" Pipe
66" Sluice Gate
Junction Structure
Existing Junction Structure
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

1,765
2
2
1

LF
EA
EA
LS

$320
$20,000
$50,000
$1,000,000

$320 $564,800
$20,000
$40,000
$50,000 $100,000
$1,000,000 $1,000,000
$1,704,800
$15,613,060

5%
0%
0%

December 2010

$780,653
$0
$0
$16,394,000

Page 25 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 27
Project:
AB Blower Replacement and Automation
Location:
CWWTP
ELEMENT
AB Blower Replacement and Automation
Total Direct Cost

$10,465,000
$10,500,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$3,200,000
$13,700,000
$2,100,000
$2,100,000
$17,900,000
$2,700,000
$20,600,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 26 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 27
AB Blower Replacement and Automation
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT

AB Blower Replacement and Automation


Major Site Work
None
Subtotal Major Site Work
Structure(s)
None
Subtotal Structure(s)
Major Equipment & Piping
Blowers
Aeration Piping Improvements
Automation Instrumentation
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

UNIT COST

UNIT COST

$0

$0
5
1
1

EA
LS
LS

$1,200,000.00
$1,000,000
$2,100,000

$1,200,000 $6,000,000
$1,000,000 $1,000,000
$2,100,000 $2,100,000
$9,100,000
$9,100,000

10%
0%
5%

December 2010

$910,000
$0
$455,000
$10,465,000

Page 27 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 28
Project:
Major Maintenance/Repair 2015
Location:
CWWTP
ELEMENT
Major Maintenance/Repair 2015
Total Direct Cost

$7,700,000
$7,700,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$2,300,000
$10,000,000
$1,500,000
$1,500,000
$13,000,000
$2,000,000
$15,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 28 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 28
Major Maintenance/Repair 2015
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Major Maintenance/Repair 2015


Major Site Work
Major Maintenance/Repair

LS

$1,500,000

$1,500,000 $1,500,000

Subtotal Major Site Work

$1,500,000

Structure(s)
Major Maintenance/Repair

LS

$2,200,000

$2,200,000 $2,200,000

Subtotal Structure(s)
Major Equipment & Piping
Major Maintenance/Repair
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$2,200,000
1

LS

$4,000,000

$4,000,000 $4,000,000
$4,000,000
$7,700,000

0%

$0

0%
0%

$0
$0

December 2010

$7,700,000

Page 29 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 29
Project:
Security and Vulnerability Improvements 1
Location:
CWWTP & SSWWTP
ELEMENT
Security and Vulnerability Improvements 1
Total Direct Cost

$1,500,000
$1,500,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$500,000
$2,000,000
$300,000
$300,000
$2,600,000
$400,000
$3,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 30 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 29
Security and Vulnerability Improvements 1
Project:
CWWTP & SSWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Security and Vulnerability Improvements 1


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Vulnerability Improvements
Subtotal Structure(s)
Major Equipment & Piping
Vulnerability Improvements
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$0
1

LS

$750,000

$750,000 $750,000
$750,000

LS

$750,000

$750,000 $750,000
$750,000
$1,500,000

0%

$0

0%
0%

$0
$0

December 2010

$1,500,000

Page 31 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 30
Project:
Enhanced Biological Phosphorus Removal Improvements to Complex A
Location:
CWWTP
ELEMENT
Complex A Flow Splitter Structure
Complex A Internal Selector
Complex A Aeration Basin Modifications
Post-Aeration
Total Direct Cost

$1,524,000
$4,100,000
$4,181,000
$5,899,000
$15,700,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$4,700,000
$20,400,000
$3,100,000
$3,100,000
$26,600,000
$4,000,000
$30,600,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 32 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 30
Enhanced Biological Phosphorus Removal Improvements to Complex A
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Complex A Flow Splitter Structure


Major Site Work
None
Subtotal Major Site Work

$0

Structure(s)
Concrete Structures

LS

$146,449

$146,449

$146,449

Subtotal Structure(s)

$146,449

Major Equipment & Piping


Mechanical Equipment
Internal Piping
Subtotal Major Equipment & Piping
Subtotal All Major Cost

1
1

LS
LS

$400,000
$437,060

$400,000
$437,060

$400,000
$437,060
$837,060
$983,509

Other Misc. Yard Piping and Utilities


Other Site Work
Other Electrical and Instrumentation

15%
15%
25%

$147,526
$147,526
$245,877

Subtotal Direct Cost


Complex A Internal Selector
Major Site Work
Demolition

$1,524,000

9800

SF

$50

$50

$490,000

Subtotal Major Site Work


Structure(s)
Interior Wall, 12" Thick

$490,000
1698

CY

$954

$954 $1,620,201

Subtotal Structure(s)

$2,110,201

Major Equipment & Piping


Mixing Pumps
Mechanical Equipment
Internal Piping
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

3
1
1

EA
LS
LS

$40,000
$237,040
$177,780

$40,000
$237,040
$177,780

$120,000
$237,040
$177,780
$534,821
$2,645,022

15%
15%
25%

$396,753
$396,753
$661,255
$4,100,000

Complex A Aeration Basin Modifications


Major Site Work
None
Subtotal Major Site Work

$0

Subtotal Structure(s)
Major Equipment & Piping
Diffusers
Mechanical Equipment
Internal Piping
Mixers
Dissolved Oxygen Meter
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

$0

Structure(s)
None

WWTFSP_App.G2-2.0

75,000
1
1
24
12

December 2010

SF
LS
LS
EA
EA

$15
$440,280
$330,210
$30,000
$6,847

$15 $1,125,000
$440,280
$440,280
$330,210
$330,210
$30,000
$720,000
$6,847
$82,164
$2,697,655
$2,697,655

15%
15%
25%

$404,648
$404,648
$674,414
$4,181,000

Page 33 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 30
Enhanced Biological Phosphorus Removal Improvements to Complex A
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Post-Aeration
Major Site Work
Excavation, Class B, 0-20 depth
Truck Hauling & Disposal
Backfill

9,923
6,471
3,452

CY
CY
CY

$3
$3
$30

$3
$3
$30

$34,334
$18,831
$105,232

Subtotal Major Site Work


Structure(s)
Concrete Piers
Slab on Grade, 24" Thick
Exterior Wall, 18" Thick

1,731
1,067
347

Subtotal Structure(s)
Major Equipment & Piping
Diffusers
Mechanical Equipment
Blowers
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$158,396
CY
CY
CY

$709
$461
$605

$709 $1,227,279
$461
$491,802
$605
$209,959
$1,929,040

14,560
1
2

December 2010

SF
LS
EA

$15
$1,000,000
$250,000

$15
$218,400
$1,000,000 $1,000,000
$250,000
$500,000
$1,718,400
$3,805,836

15%
15%
25%

$570,875
$570,875
$951,459
$5,899,000

Page 34 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 32
Project:
Stage 2 IPS Improvements
Location:
CWWTP
ELEMENT
Stage 2 IPS Improvements
Total Direct Cost

$7,922,000
$7,900,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$2,400,000
$10,300,000
$1,500,000
$1,500,000
$13,300,000
$2,000,000
$15,300,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 35 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 32
Stage 2 IPS Improvements
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Stage 2 IPS Improvements


Major Site Work
Dewatering
Temporary Trench Support
Trenching at Backfill
Subtotal Major Site Work
Structure(s)
Junction Structures
Subtotal Structure(s)
Major Equipment & Piping
72" Pipe
72" Sluice Gate
VTSH Pumps (50 mgd)
Screen (150 mgd)
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

3,700
3,700
3,700

LS
LS
LS

$75
$120
$240

$75
$120
$240

$277,500
$444,000
$888,000
$1,609,500

EA

$250,000

$250,000

$750,000
$750,000

3,700
1

LF
EA

$345
$23,000

$345 $1,276,500
$23,000
$23,000

2
1

EA
EA

$1,300,000
$630,000

$1,300,000 $2,600,000
$630,000 $630,000
$4,529,500
$6,889,000

5%
5%
5%

December 2010

$344,450
$344,450
$344,450
$7,922,000

Page 36 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 35
Project:
Strategic Plan Update 2020
Location:
CWWTP & SSWWTP
ELEMENT
Strategic Plan Update 2020
Total Direct Cost

$0
$0

Contingencies (N/A)
Total Direct Cost + Contingencies
General Conditions (N/A)
Contractor OH & P (N/A)
Total Construction Cost
Engineering (N/A)
Total Project Cost (2010 Dollars)

$0
$0
$0
$0
$0
$4,000,000
$4,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 37 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 36
Project:
Enhanced Biological Phosphorus Removal Chemical Feed Polishing Facilties
Location:
CWWTP
ELEMENT
Coagulation Basin Rehabilitation
Chemical Feed Facilities
New Coagulation Basin
Total Direct Cost

$1,550,000
$2,449,000
$5,458,000
$9,500,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$2,900,000
$12,400,000
$1,900,000
$1,900,000
$16,200,000
$2,400,000
$18,600,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 38 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 36
Enhanced Biological Phosphorus Removal Chemical Feed Polishing Facilties
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Coagulation Basin Rehabilitation


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Coagulation Basin Rehab Allowance
Subtotal Structure(s)
Major Equipment & Piping
None
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

$0
1

LS

$1,000,000

$1,000,000 $1,000,000
$1,000,000

$0
$1,000,000
15%

$150,000

15%
25%

$150,000
$250,000
$1,550,000

Chemical Feed Facilities


None
Subtotal Major Site Work
Structure(s)
Concrete Piers
24" SOG
Ext Wall
Int Wall

$0
262
267
667
133

Subtotal Structure(s)
Major Equipment & Piping
Mechanical Equipment
Ortho-Phosphate Analyzers
Chemical Feed Tanks
Internal Piping
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
New Coagulation Basin
Major Site Work
Excavation
Hauling
Backfill

CY
CY
CY
CY

$709
$461
$605
$954

$709
$461
$605
$954

$185,758
$123,087
$403,535
$126,882
$839,262

1
1
4
1

LS
LS
EA
LS

$282,021
$84,000
$68,250
$211,516

$282,021
$84,000
$68,250
$211,516

$282,021
$84,000
$273,000
$211,516
$850,537
$1,380,954

15%
15%
25%

$207,143
$207,143
$345,239
$2,449,000

18,809 CY
9,404 CY
9,404 CY

$3
$3
$30

$3
$3
$30

$56,427
$28,212
$282,120

Subtotal Major Site Work


Structure(s)
24" SOG
24" Edge Forms for SOG
Concrete Piers
Ext Wall

$366,759
1,896 CY
2,560 LF
436 CY
2,133 CY

Subtotal Structure(s)
Major Equipment & Piping
Mechanical Equipment Allowance
Subtotal Major Equipment & Piping
WWTFSP_App.G2-2.0

December 2010

$461
$16
$709
$605

$461 $874,056
$16
$40,960
$709 $309,124
$605 $1,290,465
$2,514,605

LS

$320,000

$320,000

$640,000
$640,000
Page 39 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 36
Enhanced Biological Phosphorus Removal Chemical Feed Polishing Facilties
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Subtotal All Major Cost


Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$3,521,364
15%
15%
25%

December 2010

$528,205
$528,205
$880,341
$5,458,000

Page 40 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 38
Project:
New WRRSPS Screening Facility
Location:
CWWTP
ELEMENT
New WRRSPS Screening Facility
Total Direct Cost

$7,345,000
$7,300,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$2,200,000
$9,500,000
$1,400,000
$1,400,000
$12,300,000
$1,800,000
$14,100,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 41 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 38
New WRRSPS Screening Facility
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

New WRRSPS Screening Facility


Major Site Work
Utility Relocation
Demo Exisiting Screens

1
2

LS
LS

$250,000
$80,000

$250,000
$80,000

$250,000
$160,000

Subtotal Major Site Work


Structure(s)
Concrete Piers
24" SOG on Grade
Ext Wall
Channel Walls
Elevated Slab

$410,000
698
185
556
89
356

CY
CY
CY
CY
SF

$709
$461
$954
$954
$520

$709
$461
$954
$954
$520

$494,882
$85,285
$530,424
$84,906
$185,120

Subtotal Structure(s)

$1,380,617

Major Equipment & Piping


Mechanical Bar Screen System, 4" (LT)
Washer Compactor Units
Subtotal Major Equipment & Piping
Subtotal All Major Cost

2
2

Grand Total

WWTFSP_App.G2-2.0

$935,000
$465,000

$935,000 $1,870,000
$465,000 $930,000
$2,800,000
$4,590,617

15%
20%
25%

Other Site Work


Other Electrical and Instrumentation

EA
EA

December 2010

$688,593
$918,123
$1,147,654
$7,345,000

Page 42 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 39
Project:
Major Maintenance/Repair 2020
Location:
CWWTP
ELEMENT
Major Maintenance/Repair 2020
Total Direct Cost

$7,700,000
$7,700,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$2,300,000
$10,000,000
$1,500,000
$1,500,000
$13,000,000
$2,000,000
$15,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 43 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 39
Major Maintenance/Repair 2020
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Major Maintenance/Repair 2020


Major Site Work
Major Maintenance/Repair

LS

$1,500,000

$1,500,000 $1,500,000

Subtotal Major Site Work

$1,500,000

Structure(s)
Major Maintenance/Repair

LS

$2,200,000

$2,200,000 $2,200,000

Subtotal Structure(s)
Major Equipment & Piping
Major Maintenance/Repair
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$2,200,000
1

LS

$4,000,000

$4,000,000 $4,000,000
$4,000,000
$7,700,000

0%

$0

0%
0%

$0
$0

December 2010

$7,700,000

Page 44 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 41
Project:
Security and Vulnerability Improvements 2
Location:
CWWTP & SSWWTP
ELEMENT
Security and Vulnerability Improvements 2
Total Direct Cost

$1,500,000
$1,500,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$500,000
$2,000,000
$300,000
$300,000
$2,600,000
$400,000
$3,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 45 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 41
Security and Vulnerability Improvements 2
Project:
CWWTP & SSWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Security and Vulnerability Improvements 2


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Vulnerability Improvements
Subtotal Structure(s)
Major Equipment & Piping
Vulnerability Improvements
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$0
1

LS

$750,000

$750,000 $750,000
$750,000

LS

$750,000

$750,000 $750,000
$750,000
$1,500,000

0%

$0

0%
0%

$0
$0

December 2010

$1,500,000

Page 46 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 42
Trickling Filter Demolition
Project:
Location:
CWWTP
ELEMENT
Trickling Filter Demolition
Total Direct Cost

$5,317,000
$5,300,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$1,600,000
$6,900,000
$1,000,000
$1,000,000
$8,900,000
$1,300,000
$10,200,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 47 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 42
Trickling Filter Demolition
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Trickling Filter Demolition


Major Site Work
Trickling Filter Demolition 1

LS

$3,430,000

$3,430,000 $3,430,000

Subtotal Major Site Work

$3,430,000

Subtotal Structure(s)
Major Equipment & Piping
None
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities

$0

Structure(s)
None

Other Site Work


Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$0
$3,430,000
15%

$514,500

15%
25%

$514,500
$857,500

December 2010

$5,317,000

Page 48 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 43
Dallas Plant Clarifiers Demolition
Project:
Location:
CWWTP
ELEMENT
Dallas Plant Clarifiers Demolition
Total Direct Cost

$1,868,000
$1,900,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$600,000
$2,500,000
$400,000
$400,000
$3,300,000
$500,000
$3,800,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 49 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 43
Dallas Plant Clarifiers Demolition
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Dallas Plant Clarifiers Demolition


Major Site Work
6" Ext Floor Slab Removal, Mesh Reinf Conc
Demo Concrete Walls, Heavy Rebar, 12"
Subtotal Major Site Work
Structure(s)
None
Subtotal Structure(s)
Major Equipment & Piping
None
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

55,007
46,510

SF
SF

$5.42
$20.46

$5 $275,035
$20 $930,200
$1,205,235

$0

$0
$1,205,235
15%
15%
25%

December 2010

$180,785
$180,785
$301,309
$1,868,000

Page 50 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 46
Project:
IPS Interconnect
Location:
CWWTP
ELEMENT
IPS Interconnect
Total Direct Cost

$4,745,000
$4,700,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$1,400,000
$6,100,000
$900,000
$900,000
$7,900,000
$1,200,000
$9,100,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 51 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 46
IPS Interconnect
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

IPS Interconnect
Major Site Work
Dewatering
Temporary Trench Support
Trenching at Backfill
Subtotal Major Site Work
Structure(s)
Junction Structure
Subtotal Structure(s)
Major Equipment & Piping
96" Pipe
96" Sluice Gate
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation

2,800
2,800
2,800

LF
LF
LF

$150
$240
$480

$150 $420,000
$240 $672,000
$480 $1,344,000
$2,436,000

LS

$200,000

$200,000

$200,000
$200,000

2,800
1

LF
EA

$460
$30,000

$460 $1,288,000
$30,000
$30,000
$1,318,000
$3,954,000

10%
10%
0%

$395,400
$395,400
$0
$4,745,000

WWTFSP_App.G2-2.0

December 2010

Page 52 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 48
Project:
Major Maintenance/Repair 2025
Location:
CWWTP
ELEMENT
Major Maintenance/Repair 2025
Total Direct Cost

$7,700,000
$7,700,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$2,300,000
$10,000,000
$1,500,000
$1,500,000
$13,000,000
$2,000,000
$15,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 53 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 48
Major Maintenance/Repair 2025
Project:
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Major Maintenance/Repair 2025


Major Site Work
Major Maintenance/Repair

LS

$1,500,000

$1,500,000 $1,500,000

Subtotal Major Site Work

$1,500,000

Structure(s)
Major Maintenance/Repair

LS

$2,200,000

$2,200,000 $2,200,000

Subtotal Structure(s)
Major Equipment & Piping
Major Maintenance/Repair
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$2,200,000
1

LS

$4,000,000

$4,000,000 $4,000,000
$4,000,000
$7,700,000

0%

$0

0%
0%

$0
$0

December 2010

$7,700,000

Page 54 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 49
Project:
Security and Vulnerability Improvements 3
Location:
CWWTP & SSWWTP
ELEMENT
Security and Vulnerability Improvements 3
Total Direct Cost

$1,500,000
$1,500,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$500,000
$2,000,000
$300,000
$300,000
$2,600,000
$400,000
$3,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 55 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


Project No.: 49
Security and Vulnerability Improvements 3
Project:
CWWTP & SSWWTP
Location:

DESCRIPTION

QUANTITY UNIT UNIT COST UNIT COST

Security and Vulnerability Improvements 3


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Vulnerability Improvements
Subtotal Structure(s)
Major Equipment & Piping
Vulnerability Improvements
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

$0
1

LS

$750,000

$750,000 $750,000
$750,000

LS

$750,000

$750,000 $750,000
$750,000
$1,500,000

0%

$0

0%
0%

$0
$0

December 2010

$1,500,000

Page 56 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 50
Project:
Ozone Microconstiuents Removal Facilities
Location:
CWWTP
ELEMENT
Ozone Generation, LOX Facility & Reactor Pad
Total Direct Cost

$42,758,000
$42,800,000

Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)

$12,800,000
$55,600,000
$8,300,000
$8,300,000
$72,200,000
$10,800,000
$83,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 57 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

Wastewater Treatment Facilities Strategic Plan


50
Project No.:
Project:
Ozone Microconstiuents Removal Facilities
CWWTP
Location:

DESCRIPTION

QUANTITY UNIT

Ozone Generation, LOX Facility & Reactor Pad


Major Site Work
None
Subtotal Major Site Work
Structure(s)
Slab on grade (assumes 12-inch thick)
Slab on grade (assumes 24-inch thick)
Walls (assumes 12" thick, 15' high)
Exterior wall (assumes 8-inch thick, 6' high)
Metal roof
Doors & finishes
Subtotal Structure(s)

UNIT COST

UNIT COST

$0
1,888
2,222
74
93
20,866
20%

CY
CY
CY
CY
SF

$274.10
$460.92
$712.32
1,021.39
$1.20

$274
$461
$712
$1,021
$1

$517,312
$1,024,342
$52,688
$94,953
$20,866
$342,032
$2,052,193

Major Equipment and Piping


Ozone Generators
48" FLG CDPI Pipe in Trench
Adjustable Pipe Supports
230 MGD Low Lift Pump Equipment

1
4,000
50
1
1
10%

Mechanical
Subtotal Major Equipment and Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical & Instrumentation
Subtotal Direct Cost

WWTFSP_App.G2-2.0

LS
LF
EA
LS
LS

$20,915,371.00 $20,915,371 $20,915,371


$1,089.00
$1,089 $4,356,000
4,000.00
$4,000
$200,000
7,000,000.00 $7,000,000 $7,000,000
1,000,000.00 $1,000,000 $1,000,000
$3,347,137
$36,818,508
$38,870,701

5%
0%
5%

December 2010

$1,943,535
$0
$1,943,535
$42,758,000

Page 58 of 59

Dallas Water Utilities


Wastewater Treatment Facilities Strategic Plan

Improvements at CWWTP

SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 52
Project:
Strategic Plan Update 2030
Location:
CWWTP & SSWWTP
ELEMENT
Strategic Plan Update 2030
Total Direct Cost

$0
$0

Contingencies (N/A)
Total Direct Cost + Contingencies
General Conditions (N/A)
Contractor OH & P (N/A)
Total Construction Cost
Engineering (N/A)
Total Project Cost (2010 Dollars)

$0
$0
$0
$0
$0
$4,000,000
$4,000,000

The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.

WWTFSP_App.G2-2.0

December 2010

Page 59 of 59

Вам также может понравиться