Академический Документы
Профессиональный Документы
Культура Документы
Draft WWTFSP_App.G2-2.0
December 2010
Prepared by:
Carollo Engineers, Inc.
Registration No. F-882
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 4
Project:
White Rock Primary Clarifiers (no. 1-6) Rehabilitation
Location:
CWWTP
ELEMENT
White Rock Primary Clarifiers (no. 1-6)
Rehabilitation
$7,869,000
$7,900,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$2,400,000
$10,300,000
$1,500,000
$1,500,000
$13,300,000
$2,000,000
$15,300,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 1 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
$0
33,450
57,600
91,050
3,600
SF
SF
SF
LF
$75
$50
$10
$62
$75 $2,508,750
$50 $2,880,000
$10 $910,500
$62 $223,200
$6,299,250
LS
$250,000
$250,000
$250,000
1
1
LS
LS
$50,000
$20,000
$50,000
$20,000
$50,000
$20,000
$320,000
$6,842,450
5%
5%
5%
December 2010
$342,123
$342,123
$342,123
$7,869,000
Page 2 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 6
Project:
WRRSPS Rehabilitation and Improvements
Location:
CWWTP
ELEMENT
WRRSPS Rehabilitation and Improvements
Total Direct Cost
$7,927,000
$7,900,000
Contingencies (20%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$1,600,000
$9,500,000
$1,400,000
$1,400,000
$12,300,000
$1,800,000
$14,100,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 3 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
$400,000
$400,000
$400,000
$400,000
LS
$500,000
$500,000
$500,000
$500,000
LS
2
2
3
1
EA
EA
EA
LS
$600,000
$150,000
$150,000
$25,000
$600,000 $1,200,000
$150,000
$300,000
$150,000
$450,000
$25,000
$25,000
1
1
2
2
6
1
LS
LS
EA
EA
EA
LS
$23,000
$75,300
$60,000
$35,000
$30,000
$1,611,218
$23,000
$23,000
$75,300
$75,300
$60,000
$120,000
$35,000
$70,000
$30,000
$180,000
$1,611,218 $1,611,218
$4,054,518
$4,954,518
20%
20%
20%
December 2010
$990,904
$990,904
$990,904
$7,927,000
Page 4 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 8
Project:
Existing Peak Flow Basins Rehabilitation
Location:
CWWTP
ELEMENT
Existing Basin Rehabilitation
Total-Direct Cost
$3,617,000
$3,600,000
Contingencies (10%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$400,000
$4,000,000
$600,000
$600,000
$5,200,000
$800,000
$6,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 5 of 59
Improvements at CWWTP
DESCRIPTION
112,580
1
SF
LS
$8
$1,000,000
$8 $900,640
$1,000,000 $1,000,000
$1,900,640
2,167
1,333
200
2,000
CY
CY
CY
CY
$295
$306
$950
$75
$295
$306
$950
$75
$639,265
$407,898
$190,000
$150,000
$1,387,163
None
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Subtotal Direct Cost
WWTFSP_App.G2-2.0
December 2010
$0
$3,287,803
5%
5%
0%
$164,390
$164,390
$0
$3,617,000
Page 6 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 9
Project:
Space Utilization and Admin Facilities Improvements
Location:
CWWTP
ELEMENT
Space Utilization and Admin Facilities Improvements
Total Direct Cost
$2,400,000
$2,400,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$700,000
$3,100,000
$500,000
$500,000
$4,100,000
$600,000
$4,700,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 7 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
December 2010
$0
1
LS
$2,000,000 $2,000,000
$2,000,000
$0
$2,000,000
0%
$0
10%
10%
$200,000
$200,000
$2,400,000
Page 8 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 11
Project:
Enhanced Biological Phosphorus Removal Improvements to Complex B
Location:
CWWTP
ELEMENT
Complex B Internal Selector
Complex B Aeration Basin Modifications
Total Direct Cost
$2,082,000
$3,593,000
$5,700,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$1,700,000
$7,400,000
$1,100,000
$1,100,000
$9,600,000
$1,400,000
$11,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 9 of 59
Improvements at CWWTP
DESCRIPTION
Complex B Internal Selector
Major Site Work
None
Subtotal Major Site Work
Structure(s)
Interior Wall, 12" Thick
$0
889 CY
$954
$954
$848,106
Subtotal Structure(s)
$848,106
2
1
1
15%
15%
25%
WWTFSP_App.G2-2.0
EA
LS
LS
$40,000
$237,040
$177,780
$40,000
$237,040
$177,780
$80,000
$237,040
$177,780
$494,820
$1,342,926
$201,439
$201,439
$335,732
$2,082,000
$0
443 CY
$954
$954
$422,622
$422,622
75,000
1
1
SF
LS
LS
$15
$440,280
$330,210
$15 $1,125,000
$440,280 $440,280
$330,210 $330,210
$1,895,490
$2,318,112
15%
15%
25%
December 2010
$347,717
$347,717
$579,528
$3,593,000
Page 10 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 12
SCADA MasterPlan and Replacement
Project:
CWWTP
Location:
ELEMENT
SCADA MasterPlan and Replacement
Total Direct Cost
$15,000,000
$15,000,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$4,500,000
$19,500,000
$2,900,000
$2,900,000
$25,300,000
$3,800,000
$29,100,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 11 of 59
Improvements at CWWTP
DESCRIPTION
$0
Subtotal Structure(s)
Major Equipment & Piping
SCADA software
SCADA hardware
Instrumentation
Subtotal Major Equipment & Piping
$0
Structure(s)
None
WWTFSP_App.G2-2.0
1
1
1
LS
LS
LS
$3,000,000
$7,000,000
$2,000,000
$3,000,000 $3,000,000
$7,000,000 $7,000,000
$2,000,000 $2,000,000
$12,000,000
$12,000,000
5%
0%
20%
December 2010
$600,000
$0
$2,400,000
$15,000,000
Page 12 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 13
Project:
Dallas Plant Headworks Rehabilitation
Location:
CWWTP
ELEMENT
Dallas Plant Headworks Rehabilitation
Total Direct Cost
$2,494,000
$2,500,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$800,000
$3,300,000
$500,000
$500,000
$4,300,000
$600,000
$4,900,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 13 of 59
Improvements at CWWTP
DESCRIPTION
12,000.00
12,000.00
Subtotal Structure(s)
Major Equipment & Piping
Odor Control Blowers
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
WWTFSP_App.G2-2.0
$0
SF
SF
$150
$12
$150 $1,800,000
$12 $144,000
$1,944,000
3.00
EA
$75,000
$75,000
$225,000
$225,000
$2,169,000
5%
5%
5%
December 2010
$108,450
$108,450
$108,450
$2,494,000
Page 14 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 14
Project:
Odor Control MasterPlan Update
Location:
CWWTP & SWWTP
ELEMENT
Odor Control MasterPlan Update
Total Direct Cost
$0
$0
Contingencies (N/A)
Total Direct Cost + Contingencies
General Conditions (N/A)
Contractor OH & P (N/A)
Total Construction Cost
Engineering (N/A)
Total Project Cost (2010 Dollars)
$0
$0
$0
$0
$0
$1,000,000
$1,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 15 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 16
Project:
Sodium Hypochlorite Disinfection Facilities
Location:
CWWTP
ELEMENT
Chemical Feed and Storage Facilities
Total Direct Cost
$4,039,000
$4,000,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$1,200,000
$5,200,000
$800,000
$800,000
$6,800,000
$1,000,000
$7,800,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 16 of 59
Improvements at CWWTP
DESCRIPTION
Total Direct Cost
Chemical Feed and Storage Facilities
Major Site Work
None
$0
155 CY
725 CY
150 CY
1,800 SF
3,080 SF
1 LS
$460.92
$520.00
$605.07
$450.00
$150.00
$50,000.00
$461 $71,455
$520 $377,000
$605 $90,750
$450 $810,000
$150 $462,000
$50,000 $50,000
$1,861,205
10
2
4
1
1
WWTFSP_App.G2-2.0
EA
EA
EA
EA
LS
$32,500.00
$32,500.00
$8,840.24
$40,000.00
$279,216
$32,500 $325,000
$32,500 $65,000
$8,840 $35,360
$40,000 $40,000
$279,216 $279,216
$744,576
$2,605,781
15%
15%
25%
December 2010
$390,867
$390,867
$651,445
$4,039,000
Page 17 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 18
Project:
ASIPS Rehabilitation and Improvements
Location:
CWWTP
ELEMENT
ASIPS Rehabilitation and Improvements
Total Direct Cost
$4,042,000
$4,000,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$1,200,000
$5,200,000
$800,000
$800,000
$6,800,000
$1,000,000
$7,800,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 18 of 59
Improvements at CWWTP
DESCRIPTION
$0
1
$350,000
$350,000
$350,000
$350,000
3
3
3
10
EA
EA
EA
EA
$150,000
$150,000
$450,000
$8,500
10
EA
$950
$150,000 $450,000
$150,000 $450,000
$450,000 $1,350,000
$8,500
$85,000
$950
$9,500
$2,344,500
$2,694,500
15%
15%
20%
WWTFSP_App.G2-2.0
LS
December 2010
$404,175
$404,175
$538,900
$4,042,000
Page 19 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 19
Project:
84" Horseshoe Interceptor Rehabilitation
Location:
CWWTP
ELEMENT
84" Horseshoe Interceptor Rehabilitation
Total Direct Cost
$8,053,000
$8,100,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$2,400,000
$10,500,000
$1,600,000
$1,600,000
$13,700,000
$2,100,000
$15,800,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 20 of 59
Improvements at CWWTP
DESCRIPTION
1 LS
1 LS
1 LS
4,300 LF
4,300 LF
4,300 LF
6,400 SF
10,667 CY
$2,000,000
$300,000
$300,000
$90
$510
$420
$29
$14
$2,000,000 $2,000,000
$300,000 $300,000
$300,000 $300,000
$90 $387,000
$510 $2,193,000
$420 $1,806,000
$29 $185,600
$14 $149,338
$7,320,938
None
Subtotal Structure(s)
Major Equipment & Piping
None
Subtotal Major Equipment & Piping
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
WWTFSP_App.G2-2.0
$0
$0
$7,320,938
0%
10%
0%
December 2010
$0
$732,094
$0
$8,053,000
Page 21 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 20
Project:
Stormwater Facilities Plan and Improvements
Location:
CWWTP
ELEMENT
Stormwater Facilities Plan and Improvements
Total Direct Cost
$5,070,000
$5,100,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$1,500,000
$6,600,000
$1,000,000
$1,000,000
$8,600,000
$1,300,000
$9,900,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 22 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
$0
1
LS
$1,950,000
$1,950,000 $1,950,000
$1,950,000
LS
$1,950,000
$1,950,000 $1,950,000
$1,950,000
$3,900,000
15%
$585,000
15%
0%
$585,000
$0
December 2010
$5,070,000
Page 23 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 22
Project:
New Peak Flow Basin D
Location:
CWWTP
ELEMENT
New Basin D Construction
Total-Direct Cost
$16,394,000
$16,400,000
Contingencies (10%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$1,600,000
$18,000,000
$2,700,000
$2,700,000
$23,400,000
$3,500,000
$26,900,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 24 of 59
Improvements at CWWTP
DESCRIPTION
205
147,000
829,156
136,889
672,711
1
2,685
120
895
AC
SF
CY
CY
CY
LS
CY
LF
LF
$1,400
$5
$3
$3
$2
$170,000
$150
$3,000
$1,200
$1,400 $287,000
$5 $735,000
$3 $2,487,468
$3 $410,667
$2 $1,345,422
$170,000 $170,000
$150 $402,750
$3,000 $360,000
$1,200 $1,074,000
$7,272,307
13,167 CY
8,148 CY
342 LF
1 LS
$295
$306
$200
$190,000
$295 $3,884,265
$306 $2,493,288
$200
$68,400
$190,000 $190,000
$6,635,953
WWTFSP_App.G2-2.0
1,765
2
2
1
LF
EA
EA
LS
$320
$20,000
$50,000
$1,000,000
$320 $564,800
$20,000
$40,000
$50,000 $100,000
$1,000,000 $1,000,000
$1,704,800
$15,613,060
5%
0%
0%
December 2010
$780,653
$0
$0
$16,394,000
Page 25 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 27
Project:
AB Blower Replacement and Automation
Location:
CWWTP
ELEMENT
AB Blower Replacement and Automation
Total Direct Cost
$10,465,000
$10,500,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$3,200,000
$13,700,000
$2,100,000
$2,100,000
$17,900,000
$2,700,000
$20,600,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 26 of 59
Improvements at CWWTP
DESCRIPTION
QUANTITY UNIT
WWTFSP_App.G2-2.0
UNIT COST
UNIT COST
$0
$0
5
1
1
EA
LS
LS
$1,200,000.00
$1,000,000
$2,100,000
$1,200,000 $6,000,000
$1,000,000 $1,000,000
$2,100,000 $2,100,000
$9,100,000
$9,100,000
10%
0%
5%
December 2010
$910,000
$0
$455,000
$10,465,000
Page 27 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 28
Project:
Major Maintenance/Repair 2015
Location:
CWWTP
ELEMENT
Major Maintenance/Repair 2015
Total Direct Cost
$7,700,000
$7,700,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$2,300,000
$10,000,000
$1,500,000
$1,500,000
$13,000,000
$2,000,000
$15,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 28 of 59
Improvements at CWWTP
DESCRIPTION
LS
$1,500,000
$1,500,000 $1,500,000
$1,500,000
Structure(s)
Major Maintenance/Repair
LS
$2,200,000
$2,200,000 $2,200,000
Subtotal Structure(s)
Major Equipment & Piping
Major Maintenance/Repair
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
WWTFSP_App.G2-2.0
$2,200,000
1
LS
$4,000,000
$4,000,000 $4,000,000
$4,000,000
$7,700,000
0%
$0
0%
0%
$0
$0
December 2010
$7,700,000
Page 29 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 29
Project:
Security and Vulnerability Improvements 1
Location:
CWWTP & SSWWTP
ELEMENT
Security and Vulnerability Improvements 1
Total Direct Cost
$1,500,000
$1,500,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$500,000
$2,000,000
$300,000
$300,000
$2,600,000
$400,000
$3,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 30 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
$0
1
LS
$750,000
$750,000 $750,000
$750,000
LS
$750,000
$750,000 $750,000
$750,000
$1,500,000
0%
$0
0%
0%
$0
$0
December 2010
$1,500,000
Page 31 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 30
Project:
Enhanced Biological Phosphorus Removal Improvements to Complex A
Location:
CWWTP
ELEMENT
Complex A Flow Splitter Structure
Complex A Internal Selector
Complex A Aeration Basin Modifications
Post-Aeration
Total Direct Cost
$1,524,000
$4,100,000
$4,181,000
$5,899,000
$15,700,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$4,700,000
$20,400,000
$3,100,000
$3,100,000
$26,600,000
$4,000,000
$30,600,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 32 of 59
Improvements at CWWTP
DESCRIPTION
$0
Structure(s)
Concrete Structures
LS
$146,449
$146,449
$146,449
Subtotal Structure(s)
$146,449
1
1
LS
LS
$400,000
$437,060
$400,000
$437,060
$400,000
$437,060
$837,060
$983,509
15%
15%
25%
$147,526
$147,526
$245,877
$1,524,000
9800
SF
$50
$50
$490,000
$490,000
1698
CY
$954
$954 $1,620,201
Subtotal Structure(s)
$2,110,201
3
1
1
EA
LS
LS
$40,000
$237,040
$177,780
$40,000
$237,040
$177,780
$120,000
$237,040
$177,780
$534,821
$2,645,022
15%
15%
25%
$396,753
$396,753
$661,255
$4,100,000
$0
Subtotal Structure(s)
Major Equipment & Piping
Diffusers
Mechanical Equipment
Internal Piping
Mixers
Dissolved Oxygen Meter
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
$0
Structure(s)
None
WWTFSP_App.G2-2.0
75,000
1
1
24
12
December 2010
SF
LS
LS
EA
EA
$15
$440,280
$330,210
$30,000
$6,847
$15 $1,125,000
$440,280
$440,280
$330,210
$330,210
$30,000
$720,000
$6,847
$82,164
$2,697,655
$2,697,655
15%
15%
25%
$404,648
$404,648
$674,414
$4,181,000
Page 33 of 59
Improvements at CWWTP
DESCRIPTION
Post-Aeration
Major Site Work
Excavation, Class B, 0-20 depth
Truck Hauling & Disposal
Backfill
9,923
6,471
3,452
CY
CY
CY
$3
$3
$30
$3
$3
$30
$34,334
$18,831
$105,232
1,731
1,067
347
Subtotal Structure(s)
Major Equipment & Piping
Diffusers
Mechanical Equipment
Blowers
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
WWTFSP_App.G2-2.0
$158,396
CY
CY
CY
$709
$461
$605
$709 $1,227,279
$461
$491,802
$605
$209,959
$1,929,040
14,560
1
2
December 2010
SF
LS
EA
$15
$1,000,000
$250,000
$15
$218,400
$1,000,000 $1,000,000
$250,000
$500,000
$1,718,400
$3,805,836
15%
15%
25%
$570,875
$570,875
$951,459
$5,899,000
Page 34 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 32
Project:
Stage 2 IPS Improvements
Location:
CWWTP
ELEMENT
Stage 2 IPS Improvements
Total Direct Cost
$7,922,000
$7,900,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$2,400,000
$10,300,000
$1,500,000
$1,500,000
$13,300,000
$2,000,000
$15,300,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will
not vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 35 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
3,700
3,700
3,700
LS
LS
LS
$75
$120
$240
$75
$120
$240
$277,500
$444,000
$888,000
$1,609,500
EA
$250,000
$250,000
$750,000
$750,000
3,700
1
LF
EA
$345
$23,000
$345 $1,276,500
$23,000
$23,000
2
1
EA
EA
$1,300,000
$630,000
$1,300,000 $2,600,000
$630,000 $630,000
$4,529,500
$6,889,000
5%
5%
5%
December 2010
$344,450
$344,450
$344,450
$7,922,000
Page 36 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 35
Project:
Strategic Plan Update 2020
Location:
CWWTP & SSWWTP
ELEMENT
Strategic Plan Update 2020
Total Direct Cost
$0
$0
Contingencies (N/A)
Total Direct Cost + Contingencies
General Conditions (N/A)
Contractor OH & P (N/A)
Total Construction Cost
Engineering (N/A)
Total Project Cost (2010 Dollars)
$0
$0
$0
$0
$0
$4,000,000
$4,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 37 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 36
Project:
Enhanced Biological Phosphorus Removal Chemical Feed Polishing Facilties
Location:
CWWTP
ELEMENT
Coagulation Basin Rehabilitation
Chemical Feed Facilities
New Coagulation Basin
Total Direct Cost
$1,550,000
$2,449,000
$5,458,000
$9,500,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$2,900,000
$12,400,000
$1,900,000
$1,900,000
$16,200,000
$2,400,000
$18,600,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 38 of 59
Improvements at CWWTP
DESCRIPTION
$0
1
LS
$1,000,000
$1,000,000 $1,000,000
$1,000,000
$0
$1,000,000
15%
$150,000
15%
25%
$150,000
$250,000
$1,550,000
$0
262
267
667
133
Subtotal Structure(s)
Major Equipment & Piping
Mechanical Equipment
Ortho-Phosphate Analyzers
Chemical Feed Tanks
Internal Piping
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
New Coagulation Basin
Major Site Work
Excavation
Hauling
Backfill
CY
CY
CY
CY
$709
$461
$605
$954
$709
$461
$605
$954
$185,758
$123,087
$403,535
$126,882
$839,262
1
1
4
1
LS
LS
EA
LS
$282,021
$84,000
$68,250
$211,516
$282,021
$84,000
$68,250
$211,516
$282,021
$84,000
$273,000
$211,516
$850,537
$1,380,954
15%
15%
25%
$207,143
$207,143
$345,239
$2,449,000
18,809 CY
9,404 CY
9,404 CY
$3
$3
$30
$3
$3
$30
$56,427
$28,212
$282,120
$366,759
1,896 CY
2,560 LF
436 CY
2,133 CY
Subtotal Structure(s)
Major Equipment & Piping
Mechanical Equipment Allowance
Subtotal Major Equipment & Piping
WWTFSP_App.G2-2.0
December 2010
$461
$16
$709
$605
$461 $874,056
$16
$40,960
$709 $309,124
$605 $1,290,465
$2,514,605
LS
$320,000
$320,000
$640,000
$640,000
Page 39 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
$3,521,364
15%
15%
25%
December 2010
$528,205
$528,205
$880,341
$5,458,000
Page 40 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 38
Project:
New WRRSPS Screening Facility
Location:
CWWTP
ELEMENT
New WRRSPS Screening Facility
Total Direct Cost
$7,345,000
$7,300,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$2,200,000
$9,500,000
$1,400,000
$1,400,000
$12,300,000
$1,800,000
$14,100,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 41 of 59
Improvements at CWWTP
DESCRIPTION
1
2
LS
LS
$250,000
$80,000
$250,000
$80,000
$250,000
$160,000
$410,000
698
185
556
89
356
CY
CY
CY
CY
SF
$709
$461
$954
$954
$520
$709
$461
$954
$954
$520
$494,882
$85,285
$530,424
$84,906
$185,120
Subtotal Structure(s)
$1,380,617
2
2
Grand Total
WWTFSP_App.G2-2.0
$935,000
$465,000
$935,000 $1,870,000
$465,000 $930,000
$2,800,000
$4,590,617
15%
20%
25%
EA
EA
December 2010
$688,593
$918,123
$1,147,654
$7,345,000
Page 42 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 39
Project:
Major Maintenance/Repair 2020
Location:
CWWTP
ELEMENT
Major Maintenance/Repair 2020
Total Direct Cost
$7,700,000
$7,700,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$2,300,000
$10,000,000
$1,500,000
$1,500,000
$13,000,000
$2,000,000
$15,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 43 of 59
Improvements at CWWTP
DESCRIPTION
LS
$1,500,000
$1,500,000 $1,500,000
$1,500,000
Structure(s)
Major Maintenance/Repair
LS
$2,200,000
$2,200,000 $2,200,000
Subtotal Structure(s)
Major Equipment & Piping
Major Maintenance/Repair
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
WWTFSP_App.G2-2.0
$2,200,000
1
LS
$4,000,000
$4,000,000 $4,000,000
$4,000,000
$7,700,000
0%
$0
0%
0%
$0
$0
December 2010
$7,700,000
Page 44 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 41
Project:
Security and Vulnerability Improvements 2
Location:
CWWTP & SSWWTP
ELEMENT
Security and Vulnerability Improvements 2
Total Direct Cost
$1,500,000
$1,500,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$500,000
$2,000,000
$300,000
$300,000
$2,600,000
$400,000
$3,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 45 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
$0
1
LS
$750,000
$750,000 $750,000
$750,000
LS
$750,000
$750,000 $750,000
$750,000
$1,500,000
0%
$0
0%
0%
$0
$0
December 2010
$1,500,000
Page 46 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 42
Trickling Filter Demolition
Project:
Location:
CWWTP
ELEMENT
Trickling Filter Demolition
Total Direct Cost
$5,317,000
$5,300,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$1,600,000
$6,900,000
$1,000,000
$1,000,000
$8,900,000
$1,300,000
$10,200,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 47 of 59
Improvements at CWWTP
DESCRIPTION
LS
$3,430,000
$3,430,000 $3,430,000
$3,430,000
Subtotal Structure(s)
Major Equipment & Piping
None
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
$0
Structure(s)
None
WWTFSP_App.G2-2.0
$0
$3,430,000
15%
$514,500
15%
25%
$514,500
$857,500
December 2010
$5,317,000
Page 48 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 43
Dallas Plant Clarifiers Demolition
Project:
Location:
CWWTP
ELEMENT
Dallas Plant Clarifiers Demolition
Total Direct Cost
$1,868,000
$1,900,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$600,000
$2,500,000
$400,000
$400,000
$3,300,000
$500,000
$3,800,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 49 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
55,007
46,510
SF
SF
$5.42
$20.46
$5 $275,035
$20 $930,200
$1,205,235
$0
$0
$1,205,235
15%
15%
25%
December 2010
$180,785
$180,785
$301,309
$1,868,000
Page 50 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 46
Project:
IPS Interconnect
Location:
CWWTP
ELEMENT
IPS Interconnect
Total Direct Cost
$4,745,000
$4,700,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$1,400,000
$6,100,000
$900,000
$900,000
$7,900,000
$1,200,000
$9,100,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 51 of 59
Improvements at CWWTP
DESCRIPTION
IPS Interconnect
Major Site Work
Dewatering
Temporary Trench Support
Trenching at Backfill
Subtotal Major Site Work
Structure(s)
Junction Structure
Subtotal Structure(s)
Major Equipment & Piping
96" Pipe
96" Sluice Gate
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
2,800
2,800
2,800
LF
LF
LF
$150
$240
$480
$150 $420,000
$240 $672,000
$480 $1,344,000
$2,436,000
LS
$200,000
$200,000
$200,000
$200,000
2,800
1
LF
EA
$460
$30,000
$460 $1,288,000
$30,000
$30,000
$1,318,000
$3,954,000
10%
10%
0%
$395,400
$395,400
$0
$4,745,000
WWTFSP_App.G2-2.0
December 2010
Page 52 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 48
Project:
Major Maintenance/Repair 2025
Location:
CWWTP
ELEMENT
Major Maintenance/Repair 2025
Total Direct Cost
$7,700,000
$7,700,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$2,300,000
$10,000,000
$1,500,000
$1,500,000
$13,000,000
$2,000,000
$15,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 53 of 59
Improvements at CWWTP
DESCRIPTION
LS
$1,500,000
$1,500,000 $1,500,000
$1,500,000
Structure(s)
Major Maintenance/Repair
LS
$2,200,000
$2,200,000 $2,200,000
Subtotal Structure(s)
Major Equipment & Piping
Major Maintenance/Repair
Subtotal Major Equipment & Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical and Instrumentation
Subtotal Direct Cost
WWTFSP_App.G2-2.0
$2,200,000
1
LS
$4,000,000
$4,000,000 $4,000,000
$4,000,000
$7,700,000
0%
$0
0%
0%
$0
$0
December 2010
$7,700,000
Page 54 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 49
Project:
Security and Vulnerability Improvements 3
Location:
CWWTP & SSWWTP
ELEMENT
Security and Vulnerability Improvements 3
Total Direct Cost
$1,500,000
$1,500,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$500,000
$2,000,000
$300,000
$300,000
$2,600,000
$400,000
$3,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 55 of 59
Improvements at CWWTP
DESCRIPTION
WWTFSP_App.G2-2.0
$0
1
LS
$750,000
$750,000 $750,000
$750,000
LS
$750,000
$750,000 $750,000
$750,000
$1,500,000
0%
$0
0%
0%
$0
$0
December 2010
$1,500,000
Page 56 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 50
Project:
Ozone Microconstiuents Removal Facilities
Location:
CWWTP
ELEMENT
Ozone Generation, LOX Facility & Reactor Pad
Total Direct Cost
$42,758,000
$42,800,000
Contingencies (30%)
Total Direct Cost + Contingencies
General Conditions (15%)
Contractor OH & P (15%)
Total Construction Cost
Engineering (15%)
Total Project Cost (2010 Dollars)
$12,800,000
$55,600,000
$8,300,000
$8,300,000
$72,200,000
$10,800,000
$83,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 57 of 59
Improvements at CWWTP
DESCRIPTION
QUANTITY UNIT
UNIT COST
UNIT COST
$0
1,888
2,222
74
93
20,866
20%
CY
CY
CY
CY
SF
$274.10
$460.92
$712.32
1,021.39
$1.20
$274
$461
$712
$1,021
$1
$517,312
$1,024,342
$52,688
$94,953
$20,866
$342,032
$2,052,193
1
4,000
50
1
1
10%
Mechanical
Subtotal Major Equipment and Piping
Subtotal All Major Cost
Other Misc. Yard Piping and Utilities
Other Site Work
Other Electrical & Instrumentation
Subtotal Direct Cost
WWTFSP_App.G2-2.0
LS
LF
EA
LS
LS
5%
0%
5%
December 2010
$1,943,535
$0
$1,943,535
$42,758,000
Page 58 of 59
Improvements at CWWTP
SUMMARY
Wastewater Treatment Facilities Strategic Plan
Project No.: 52
Project:
Strategic Plan Update 2030
Location:
CWWTP & SSWWTP
ELEMENT
Strategic Plan Update 2030
Total Direct Cost
$0
$0
Contingencies (N/A)
Total Direct Cost + Contingencies
General Conditions (N/A)
Contractor OH & P (N/A)
Total Construction Cost
Engineering (N/A)
Total Project Cost (2010 Dollars)
$0
$0
$0
$0
$0
$4,000,000
$4,000,000
The cost estimate herein is based on our perception of current conditions at the project location. This estimate reflects our professional opinion of accurate
costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials,
equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market
conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not
vary from the costs presented as shown.
WWTFSP_App.G2-2.0
December 2010
Page 59 of 59