Академический Документы
Профессиональный Документы
Культура Документы
ELL 303
By
Prof. Sukumar Mishra
Electrical Energy
Energy can be of any form such as heat, light, etc.
Electrical energy is opted as compared to other sources because
Transmission lines
220kV 1100kV
Tie lines
Control Power
Sub-Transmission lines
33kV 132kV
Control Power
Large loads
Primary(11kV)
/ Secondary(400V) Distribution System
Distributed
generation
Medium loads
Transmission lines
220kV 1100kV
Tie lines
Control Power
Renewable
sources
Sub-Transmission lines
33kV 132kV
Control Power
Large loads
Primary(11kV)
/ Secondary(400V) Distribution System
Renewable
sources
Distributed
generation
Bi-directional power
Medium loads
Generation
Total Electricity generation of world in 2014 is 23950 TWh [1]
Total installed capacity is 5,250 GW
Total worlds installed capacity
Coal-2100GW (40%)
Gas-262.5 GW (5%)
Hydro electric-17%
Nuclear -10%
Oil-5%
Others-7%
Total = 5,250GW
Total= 308.834GW
Transmission lines
Ultra High Voltage (UHV) Lines (1000kV, 1100kV and 1200kV).
Extra High voltage (EHV) Lines (345, 400, 500, and 765 kV).
High Voltage (HV) Lines (100, 138, 161, and 230 kV).
China as working line of 1000kV
1,200-kV ultra-high voltage (UHV) test station along with experimental
lines in Bina, Madhya Pradesh.
Power grid corp. has proposed worlds first 1,200-kV transmission line for
commercial purpose, which will be constructed between Wardha and
Aurangabad in Maharashtra.
Till now, the power is transmitted on maximum 765kV /800kV (DC) lines in
India.
Generating stations
Basic definitions to understand power plants:
=
( )
1.
The average load determines the energy consumption over the day, while
the peak load along with considerations of standby capacity determines
plant capacity for meeting the load.
High load factor helps in drawing more energy from a given installation.
max( )
1.
Generating stations
Conventional Sources:
Thermal coal
Nuclear
Hydro
Gas or Oil based
Unconventional sources:
solar,
wind
and tidal source
Alternator Rotor
Emergency lighting
Hydro
Gas
Paralleling
Division of load between a.c. generators operating in parallel is a function of the
power input to the generators.
So, the governor control switches are used to balance load. Adjusting the governor
control switch in the "raise" direction causes that generator to pick up load, and
"lower" causes it to shed load.
While turning the governor control switches, the wattmeter of both machines must
be observed until the load is balanced between the two generators.
Next balance the inductive load (amperes) using the voltage adjusting rheostat of
the generators.
If the load is balanced with rated voltage and frequency being generated, the
paralleling operation has been successfully completed.