Вы находитесь на странице: 1из 40

Capacity Management

BUS 505 Production and Operations Management


Dilay elebi
25.01.2017

MBA 512E Production and Operations Management

Capacity Management

Capacity

The throughput, or the number of units a


facility can hold, receive, store, or produce in
a period of time
Determines
fixed costs
Determines if
demand will
be satisfied
Three time horizons
MBA 512E Production and Operations Management

Capacity Management

Planning Over a Time Horizon

Long-range
planning

Add facilities
Add long lead time equipment

Intermediaterange planning

Subcontract
Add equipment
Add shifts

Short-range
planning

*
Add personnel
Build or use inventory

Schedule jobs
Schedule personnel
Allocate machinery

Modify capacity

MBA 512E Production and Operations Management

Use capacity

Capacity Management

Design and Effective Capacity

Design capacity is the maximum theoretical


output of a system
Normally expressed as a rate

Effective capacity is the capacity a firm


expects to achieve given current operating
constraints
Often lower than design capacity

MBA 512E Production and Operations Management

Capacity Management

Utilization and Efficiency


Utilization is the percent of design capacity achieved
Utilization = Actual output/Design capacity

Efficiency is the percent of effective capacity


achieved
Efficiency = Actual output/Effective capacity

MBA 512E Production and Operations Management

Capacity Management

Example
Actual production last week = 148,000 rolls
Effective capacity = 175,000 rolls
Design capacity = 1,200 rolls per hour
Bakery operates 7 days/week,
3 - 8 hour shifts
Design capacity =

Utilization =

Efficiency =
Efficiency of new line = 75%
Expected Output =
MBA 512E Production and Operations Management

Capacity Management

Determining Capacity Requirements

1. Forecast sales
within each
individual product
line

MBA 512E Production and Operations Management

2. Calculate
equipment and
labor requirements
to meet the
forecasts

Capacity Management

3. Project
equipment and
labor availability
over the planning
horizon

Average unit cost


(dollars per room per night)

Economies and Diseconomies of Scale

25 - room
roadside motel

50 - room
roadside motel

Economies of
scale

25
MBA 512E Production and Operations Management

75 - room
roadside motel

Diseconomies of
scale

50
Number of Rooms
Capacity Management

75
8

Capacity Timing and Sizing


Forecast of
capacity required

Capacity

Planned unused
capacity

Capacity
increment
Time between
increments
Time

(a) Expansionist strategy


MBA 512E Production and Operations Management

Capacity Management

Capacity Timing and Sizing

Capacity

Planned use of
short-term options

Forecast of
capacity required
Capacity
increment

Time between
increments

Time

(b) Wait-and-see strategy


MBA 512E Production and Operations Management

Capacity Management

10

Managing Demand
Demand exceeds capacity
Curtail demand by raising prices, scheduling longer lead time
Long term solution is to increase capacity

Capacity exceeds demand


Stimulate market
Product changes

Adjusting to seasonal demands


Produce products with complementary demand patterns

MBA 512E Production and Operations Management

Capacity Management

11

Complementary Demand Patterns

Sales in units

4,000
3,000
2,000
Jet ski
engine
sales

1,000

JFMAMJJASONDJFMAMJJASONDJ
Time (months)
MBA 512E Production and Operations Management

Capacity Management

12

Complementary Demand Patterns

Sales in units

4,000
Snowmobile
motor sales

3,000
2,000

Jet ski
engine
sales

1,000

JFMAMJJASONDJFMAMJJASONDJ
Time (months)
MBA 512E Production and Operations Management

Capacity Management

13

Complementary Demand Patterns


Combining both
demand patterns
reduces the
variation

Sales in units

4,000

Snowmobile
motor sales

3,000
2,000

Jet ski
engine
sales

1,000

JFMAMJJASONDJFMAMJJASONDJ
Time (months)
MBA 512E Production and Operations Management

Capacity Management

14

Tactics for Matching Capacity to Demand


1. Making staffing changes
2. Adjusting equipment

Purchasing additional machinery


Selling or leasing out existing equipment
3. Improving processes to increase throughput

4. Redesigning products to facilitate more throughput


5. Adding process flexibility to meet changing product
preferences
6. Closing facilities
MBA 512E Production and Operations Management

Capacity Management

15

Tools for Capacity Planning

Waiting-line models
Useful in high customer-contact processes

Simulation
Useful when models are too complex for
waiting-line analysis

Decision trees
Useful when demand is uncertain and
sequential decisions are involved
MBA 512E Production and Operations Management

Capacity Management

16

Strategies for Capacity Planning


Level capacity strategy in an outpatients clinic

MBA 512E Production and Operations Management

Chase capacity strategy for a fast-food


restaurant

Capacity Management

17

Demand and Capacity Management in the


Service Sector
yield management
building exibility
reducing capacity
leakage
getting organisational
support for capacity
utilisation.
MBA 512E Production and Operations Management

Capacity Management

18

What happens when managers cant cope with demand?


The coping zone in a high-quality restaurant

Customers have to wait a long time for service.


There is increasing likelihood of stock-outs (items removed from the menu).
Customers feel rushed and under pressure not to ask too much from busy
serving staff.
Staff feel under pressure and are less likely to give courteous responses or
the personalised service expected.
MBA 512E Production and Operations Management

Capacity Management

19

Bottleneck Analysis and Theory of Constraints


Each work area can have its own unique capacity
Capacity analysis determines the throughput
capacity of workstations in a system
A bottleneck is a limiting factor or constraint
A bottleneck has the lowest effective capacity in
a system

MBA 512E Production and Operations Management

Capacity Management

20

A Three-Station Assembly
Line

2 min/unit

4 min/unit

3 min/unit

MBA 512E Production and Operations Management

Capacity Management

21

Process Times for Stations, Systems, and Cycles


The system process time is the process
time of the bottleneck after dividing by the
number of parallel operations
The system capacity is the inverse of the
system process time

MBA 512E Production and Operations Management

Capacity Management

22

Process Performance Metrics


Throughput time = Average time for a unit to move
through the system
Cycle time = Average time between completion of units

1
Throughput rate
Cycle Time

MBA 512E Production and Operations Management

Capacity Management

23

Cycle Time Example

Suppose you had to produce 600 units in 80


hours to meet the demand requirements of a
product. What is the cycle time to meet this
demand requirement?

MBA 512E Production and Operations Management

Capacity Management

24

Capacity Analysis
Two identical sandwich lines
Lines have two workers and three operations
All completed sandwiches are wrapped

Bread
15 sec/sandwich

Fill

Toast

20 sec/sandwich

40 sec/sandwich

Order

Wrap

30 sec/sandwich

37.5 sec/sandwich

Bread
15 sec/sandwich

MBA 512E Production and Operations Management

Fill

Toast

20 sec/sandwich

40 sec/sandwich

Capacity Management

25

Capacity Analysis
Bread
15 sec

Fill
20 sec

Toast
40 sec

Order

Wrap

30 sec

37.5 sec
Bread
15 sec

Fill
20 sec

Toast
40 sec

Which station has the longest processing time?


What is the process time of the combined lines?
Which station is the bottleneck?
What is the capacity per hour?
What is process cycle time?

MBA 512E Production and Operations Management

Capacity Management

26

Theory of Constraints
Five-step process for recognizing and managing
limitations
Step 1: Identify the constraint
Step 2: Develop a plan for overcoming the
constraints
Step 3: Focus resources on accomplishing Step 2
Step 4: Reduce the effects of constraints by
offloading work or expanding capability
Step 5: Once overcome, go back to Step 1 and find
new constraints
MBA 512E Production and Operations Management

Capacity Management

27

Bottleneck Management
1. Release work orders to the system at the pace of
set by the bottleneck
2. Lost time at the bottleneck represents lost time
for the whole system
3. Increasing the capacity of a non-bottleneck
station is a mirage
4. Increasing the capacity of a bottleneck increases
the capacity of the whole system

MBA 512E Production and Operations Management

Capacity Management

28

Example : hammer production process


Description
1. Work begins at the machining center. Here two lines form
the heads of the hammers and place them in a buffer.
2. Handles are attached at the assembly step.
3. Finished hammers are sent to the next stage, where they
are packed and shipped.

machining

assembly
machining

MBA 512E Production and Operations Management

Capacity Management

pack and
ship

29

Example : hammer production process


machining

assembly
machining

pack and
ship

Process Data:
machining: Set up 80 min. 4 min per unit processing.
Batch size 200. Identical lines.
assembly: Manual by two workers (no set up). Each
hammer requires 40 min processing. 34 workers available.
pack and ship: 30 min set up, 2 min per unit processing.
Lot sizes of 100.
MBA 512E Production and Operations Management

Capacity Management

30

A very useful relationship


Littles Law:
WIP = (Throughput) x (Lead Time)

Littles Law is a fundamental law of system dynamics


Gives good results for a variety of scenarios
Throughput (Units/time).
Example: A facility has a cycle time of 2 minutes per unit, and
the average lead time is 20 minutes.

MBA 512E Production and Operations Management

Capacity Management

31

Littles law (a really quite useful law)

Throughput (TH) = Work In Process (WIP) / Cycle Time (CT)


Cycle time = 2 mins

WIP = 10
Lead time = 20 minutes
Throughput rate = 1 units/ 2 mins

MBA 512E Production and Operations Management

Capacity Management

32

Scenario 1: No Variability (Ideal World)


Data and Calculations
Planning Horizon
30 hours
Processing time
8 hour/unit
Inter-arrival time
10 hours
Utilization
80%
Average queue time
0 hours
Average lead time
8 hours
1st part
arrives

2nd part
arrives

1st part
processing

3rd part
arrives

2nd part
processing

10

1st part
departs
MBA 512E Production and Operations Management

3rd part
processing

18 20

2nd part
departs
Capacity Management

28

30

3rd part
departs
33

Scenario 2: Processing Variability


SCENARIO
Planning Horizon
Processing time
Inter-arrival time
Utilization
Average queue time
Average lead time

1st part
arrives

2nd part
arrives

1
30 hours
8 hour/unit
10 hours
80%
0 hours
8 hours

Parts waiting
in queue

2
same
12, 9, 3
same
same
1 hour
9 hours

3rd part
arrives

Same average !!!

Same utilization but ...


More queue time
More lead time

2nd part
processing

1st part processing

10

12

1st part
departs
MBA 512E Production and Operations Management

20

21 24

2nd part
departs

30

3rd part
departs

Capacity Management

34

Scenario 3: Arrival Variability


SCENARIO
Planning Horizon
Processing time
Inter-arrival time
Utilization
Average queue time
Average lead time

1
30 hours
8 hour/unit
10 hours
80%
0 hours
8 hours

1st part
arrives
13.5 hours

2
same as 1
12, 9, 3
same
same as 1
1 hours
9 hours

2nd part
arrives

3
same as 1
same as 1
13.5, 6.5 Same average !!!
same as 1
0.5 hours
Again, same
8.5 hours

utilization

but . . .

6.5 hours

More queue time

3rd part
arrives

More lead time

Part 3 waiting
in queue

1st part
processing

2nd part
processing

8 10

1st part
departs
MBA 512E Production and Operations Management

13.5

20

3rd part
processing

21.5

2nd part
departs
Capacity Management

29.5

3rd part
departs
35

Example Summary
SCENARIO
Planning Horizon
Processing time
Inter-arrival time
Utilization
Average queue time
Average lead time

1
30 hours
8 hour/unit
10 hours
80%
0 hours
8 hours

2
same as 1
12, 9, 3
same as 1
same as 1
1 hours
9 hours

3
same as 1
same as 1
13.5, 6.5
same as 1
0.5 hours
8.5 hours

Utilization alone is not sufficient to


estimate the lead-time performance
One must also consider the products arrival
and processing variability.
A mathematical model is needed to study
the system.
MBA 512E Production and Operations Management

Capacity Management

36

The impact of variability on queues

MBA 512E Production and Operations Management

Capacity Management

37

Arrival
Arrival
frequency
frequency
(demand)
(demand)

Throughput time
and capacity
utilisation

9 mins
30
20
10515 10515
Processing
time
Processing
time
minsmins mins
mins

Utilization
Utilization
33.33
50
100
%%
% %% QQQQ====0infinity
0>0
Utilization===100
<100%

High

time
Process throughput
length of queue
Average
(or inventory)

High utilization but long


throughput times

X
Low utilization but short
throughput times

X
Reduce process
variability

Low

20%

40%

60%

80%

100%

Capacity utilization
MBA 512E Production and Operations Management

Capacity Management

38

Decreasing
variability

10 20 30 40 50 60 70 80 90 100
Utilization

(a) Decreasing variability allows higher


utilization without long waiting times.

MBA 512E Production and Operations Management

Average number of units waiting


to be processed

Average number of units waiting


to be processed

Process utilization, waiting time and variability

High utilization but


long waiting time
Reduction in
process
variability

Short waiting
time but low
utilization
Y

10 20 30 40 50 60 70 80 90 100
Utilization
(b) Managing process capacity
variability.

Capacity Management

and/or

39

References
Operations Management for Competitive Advantage, 11th
Edition, by Chase, Jacobs, and Aquilano, 2005, N.Y.: McGrawHill/Irwin.
Heizer, J. and Render, B., Operations Management, 9/E,
Prentice Hall, 2009, ISBN-10: 0136073662
Krajewski, Lee J., Larry P. Ritzman; Manoj K. Malhotra,
Operations Management: Processes and Supply Chains, Tenth
Edition, Global Edition | 978-0-273-76683-4

MBA 512E Production and Operations Management

Capacity Management

40

Вам также может понравиться