Академический Документы
Профессиональный Документы
Культура Документы
A Case Study
Abstract: The case study seeks to highlight challenges of tunnel design vis--vis
environment impacts, mitigation and sustainability. It focuses on how innovative design
and mitigation measures address the challenge of collection, transportation and
disposal of huge quantity of excavated materials. It also captures application of
Environment Impact Assessment (EIA) and Environment Management Plan (EMP) in
addressing likely adverse impacts for sustainability of infrastructure development. It
covers the required safety measures in tunnel construction and operation. The project
illustrates unique features, being an eco-sensitive zone, located on a hilly terrain, the
only channel of connectivity to rest of the area and gets disconnected during landslides
and snow avalanches. The paper lays stress on the designing principles of the tunnel as
to how it has utilized the EIA and addressed the negative impacts of the environment in
the EMP, representing a climate-proof infrastructure and proving it to be a beneficial
exercise for the society.
Introduction
The road takes off from km 189.350, ends at km 204.600 of existing road thus making a
total length of 15.250 km. The road traverses through Doda and Anantnag district of
Jammu and Kashmir and comprises of two tunnels of 8.45 km and 0.865 km, 2.42 km
length of over-bridge and viaducts and balance road of 3.515 km on ground. The
alternate alignment is entirely a new 4-lane project which takes off from km 189.350,
where a junction has been proposed and runs parallel to the Bichleri river at most of the
locations between km 190.000 to km 195.000 traversing through villages Zeniha, Asar,
Lambar, Gund and Banihal town before traversing through one of the small ridges of the
main Pir Panjal Mountain ranges through a short tunnel of 674 m length.
The road serves as a critical route throughout the year for the movement of the
paramilitary forces, other food products and medicines. Above all, this is the only road
for maintaining connectivity to rest of the country from Srinagar.
The up-gradation of the stretch is required as it is deficient in road geometrics and has
sharp curves. It has 32 identified landslips locations and 15 Snow Avalanches zones
which are required to be avoided. The existing 2-lane road cannot be widened to 4-lane
requirement without hill cutting, which may accelerate the process of landslips, which is
common in the area of the present alignment. There are frequent closures of the road
during winter season due to heavy snowfall because the existing alignment lies above
1
the snow line. The necessity is to maintain an all weather flow on NH-1A and to design
the road as per latest IRC Standards and Specifications. The present road has outlived
its capacity and there is urgent need to upgrade it to 4-lane alignment. Hence, the
option considered appropriate is to construct road below snow line to maintain all
weather flow.
The existing road is 2-lane road traversing through Pir Panjal ranges covering a
distance of approximately 32 km through 2.4 km long Jawahar tunnel, which is approx.
2050 m above mean sea level and has two cubes one in each direction. It is a highly
eco-sensitive area with 32 identified landslips zone and 15 snow avalanches zone.
There are also steep gradients, Sharp curves and Poor Road Geometrics in the
alignment. Therefore, the overall challenge was to meet the environmental safeguards,
apply sound design principles and comply with the rules and policies of Government.
The case study has been structured to capture the key components of designing the
tunnel and lessons learned with reference to sustainability of infrastructure. The case
study includes (i) Introduction; (ii) EIA, EMP and Tunnel design; (iii) Monitoring plans;
and (iv) Conclusion.
EIA, EMP and Tunnel Design
Conducting EIA and accordingly preparing EMP have been two key elements which
contributed significantly in the tunnel design process. While possible impacts, both
positive and negative were studied in EIA, the EMP addressed mitigation measures for
the likely adverse environmental impacts of the tunnel.
Environment Impact Assessment (EIA)
Road projects particularly bring in adverse impacts on pollution load of different
environmental parameters like soil, water, air, noise, and ecological resources. There
may also be impact on the socio- economic parameters of the locality resulting in
displacement / dislocation / relocation for people and properties. This may also impact
sensitive areas as far as conservation of biological resources of a particular area is
concerned. Cultural properties / heritage sites may also be affected by such project
execution. The present project is distinctive to the extent that it has two tunnels one
small and the other long coupled with small stretches of the road providing access and
exit at the south and north portal of the long tunnel. Impacts on different parameters of
the environment for the stretches over ground and underground are likely to be different
both qualitatively and quantitatively.
The Environment Impact Assessment conducted for the proposed tunnels includes (i)
Collection of information on existing baseline conditions in order to identify the
2
features and their likely impact on the natural ecosystem. Potential significant impacts
were identified on the basis of: analytical review of baseline data; review of
environmental conditions at site; analytical review of the underlying socio-economic
conditions with the project influence area.
Environment Mitigation Plan (EMP)
Timely, planned and appropriate actions not only avoid adverse impacts, but also help
to capitalize on opportunities to mitigate environmental degradation or improve
environmental conditions. Environmental enhancement plans are prepared for
environmental features such as plantation and landscaping of the project corridor. An
Environment Mitigation Plan (EMP) for the project was prepared to specify the steps
required to ensure that the necessary measures have been and will be taken. This
includes the monitoring plan giving details of the resources budgeted and the
implementation arrangements. The mitigation measures are specified phase wise viz.,
preconstruction, construction and operation.
The EMP includes mitigation measures, implementation and monitoring arrangements
for various components which include: (i) Topography; (ii) Geology; (iii) Climatic
parameters; (iv) Air quality; (v) Noise and Vibration; (vi) Surface Water; (v) Ground
Water; (vi) Flora & Fauna; (vii) Archaeological and Socio-Cultural Properties; (viii) on
Public Health and Occupational Safety; and (ix) Road Safety. However, due to huge
volume of excavate material and complexity involved in appropriate disposal, the case
study focuses on this aspect.
Mitigation is defined as the elimination, reduction, control of adverse environmental
effects of the project and includes restitution for any damage to the environment caused
by such effects through replacement, restoration, compensation or any other means. A
variety of approaches have been considered for the purpose:
Operation strategies for control and minimization of waste streams and enhance
workers health and safety
Compensating for lost or degraded ecological values in the project area by
enhancing similar values elsewhere.
Mitigation measures in the present project for the tunnel environment have primarily
been built into the design features of both the tunnels with the requisite safeguards for
the construction and the implementation phase. Anticipated impacts over ground have
been proposed to be kept at acceptable levels through a combination of cost-effective
mitigation and management measures.
Topography
Impact has been assessed as low and permanent as such impacts will not affect
the drainage of watersheds in the project corridor. Therefore no mitigation measure has
been suggested.
The solid waste generated due to the construction of tunnel will be partly used in
the construction of embankment in the Banihal Side and around 1 million cubic meter of
muck will be disposed at identified site as per dump management plan.
Geology
In case of finding of mineralized zones along the tunnel alignment during excavation, it
will be brought to the notice of the Department of Geology and Mining of the State
Government for directions from their end. Some fossil finds in the sedimentaries
excavated from the tunnel which may generate some new information on the
stratigraphy of the Pir Panjal Range will also be brought to the notice of the said
Department. Appropriate blasting design will be opted which will consider safety, blast
geometry, free faces, burden, spacing, initiation pattern and angled holes. Specific
techniques used for minimizing the air overpressure and vibrations will include:
Delayed detonator initiation systems;
Reducing hole diameters;
Splitting of explosive charge columns into discrete charges fired on
separate delayed;
Avoiding use of exposed explosives;
Adequate confinement of explosives; and
Quantity and quality of stemming.
The boulders will be procured from the authorized suppliers and prevalent rules will be
followed for borrowing of soil. Hence, the impact on general geology of the region will be
insignificant.
Land Environment
During design phase the alignment has been chosen in such manner that acquisition of
agriculture land is kept to the minimum. Construction camps, offices, plants, stockyards,
traffic detours will not be located on fertile land unless and otherwise unavoidable. If
these are to be located on fertile land topsoil should be stripped, stored and such areas
will be restored after completion of work. Best work period will be chosen in order to
limit erosion i.e. rainy season will be avoided. District authorities have been approached
for identification and handing over of dump disposal sites. The solid waste generated
from the worker camps would be dumped in locally identified site. The liquid discharge
from the workers camp will be disposed to the existing drainage system in order to
prevent soil pollution. Solid waste dumps will be re-vegetated through use of stock piled
top soil obtained from areas of construction of embankments. Local quarries and borrow
areas can be landscaped and developed for a variety of recreational and economic
uses. Engineering structures like toe-walls will be constructed to prevent debris flow
from dumping as well as storage sites. Slope embankments will be provided with the
grass turf and run off from the roads will be safely disposed of to the existing drainage
system to prevent any possibility of soil erosion. Movement of construction machinery
will be restricted to designated paths which will not pass through agriculture fields in
order to avoid compaction and physical disruption of agricultural soil. Maintenance work
of the construction machinery will be done on pre-designed cemented platforms which
will be further provided with oil drains/ oil segregators. The vegetal cover that will come
up gradually with time through compensatory afforestation will also hold the soil firmly
through their root system and also by cutting down on quantum of precipitation reaching
the ground through canopy interceptions and evaporation through canopy foliage. The
excavations from tunnel sites can be specifically used in following way:
All structures like retaining walls etc. required will be constructed to retain the spoil. The
spoil / debris will be carried in trucks / dumpers covered with tarpaulin and will be kept
moist to avoid spill of material. The loading and unloading will be carried in such a
manner, so as not to cause discomfort to the workers/ residents. The disposal site will
be covered from all the four sides up to a sufficient height to avoid spill of material. The
spoil/debris will be kept moist by sprinkling water regularly. After filling of Spoil/ debris
the site will be developed as agreed initially with the owner of site before handing over
of site.
7
Global CCTV network: Video cameras will be installed all along the tunnel
roadway and in the transit rooms of the emergency exits. All video pictures from
the video cameras will be transmitted in real time to the Tunnel Control Centre
and continuously recorded on HDD digital recording system.
Tunnel SCADA system: This system will conform to the best standards and
codes of practice. Such a system will provide the traffic operators a large number
of tools, both in practical and functional terms to operate the tunnel installations,
to obtain information and to avoid taking wrong decisions. All equipment will be
manually controlled from the Tunnel Control Centre via the SCADA system.
Monitoring Plans
The intent of the monitoring programme is to ensure that the envisaged purpose of the
project are achieved and result in desired benefits to the target population. To ensure
the effective implementation of the EMP, it is essential that an effective monitoring
programme has to be designed and carried out. The broad objectives are:
Noise levels (Leq and Maximum Noise level) around sensitive locations;
The monitoring plan during construction and operation stages has been described in
detail in the respective EMP document. For each of the environmental components, the
monitoring plan specifies the parameters to be monitored; location of monitoring sites;
frequency and duration of monitoring. The monitoring plan also specifies the applicable
standards, implementation and supervising responsibilities.
Visual observations;
(ii)
(iii)
The contingency and action plans methodology covers (i) Components to be monitored;
(ii) Parameters for monitoring of the above components; (iii) Monitoring frequency; (iv)
Monitoring standards; (v) Responsibilities for monitoring; (vi) Direct responsibility, (vii)
Overall responsibility; and (viii) Monitoring costs.
Conclusion
The case study has captured the tunnel designing process with environmental
assessment and mitigation as the key focus. A major challenge is appropriate disposal
of the estimated quantity of Excavated Material (Debris) which is 1565000 cum.
Preparation of EIA, EMP and monitoring plans have been crucial elements which
contributed significantly to the designing process. The study also includes the required
safety features in tunnel construction and operation. The project signifies unique
10
features, being an eco-sensitive zone, located on a hilly terrain, the only channel of
connectivity to rest of the country and gets disconnected during landslides and snow
avalanches. The paper lays stress on the designing principles of the tunnel as to how it
has utilized the EIA and addressed the negative impacts of the environment in the EMP,
representing a climate-proof infrastructure and proving it to be a beneficial exercise for
the society.
11